Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd & Anor

England and Wales High Court (Technology & Construction Court)
Sep 29, 2008
Smart Summary (Beta)

Factual and Procedural Background

This opinion concerns protracted litigation between Company A and Company B relating to a subcontract for steelwork on the new National Stadium at Wembley. Company A was the main contractor and Company B the steelwork subcontractor. Following mutual loss of confidence, Company B's role under the subcontract was substantially reduced by agreement in early and mid-2004, culminating in Company B's repudiation of the subcontract on 2nd August 2004. Company A then engaged Company C and its sister company to complete the outstanding fabrication and erection work. The present litigation seeks to establish the final account between Company A and Company B, including sums owed for work done and damages for defects and repudiation.

The litigation history includes two rounds of preliminary issues, heard by this court and the Court of Appeal, addressing questions of principle. The main trial commenced in March 2008 and concluded in May 2008, with a vast volume of evidence and extensive witness testimony. Post-trial hearings addressed unresolved matters and assisted in finalizing calculations for claims and counterclaims. The court’s judgment references extensive documentary and transcript material.

Legal Issues Presented

  1. What sums are owed by Company A to Company B for work done and materials supplied under the subcontract and purchase order as of key dates?
  2. What damages are owed by Company B to Company A for defects in steelwork and for repudiation of the subcontract?
  3. How should the court assess damages given the interplay of repudiation, substitution of contractors, and changes in scope and methodology?
  4. What is the proper valuation methodology for work in progress, variations, and provisional sums under the subcontract and Supplemental Agreement?
  5. What is the impact of Company B’s repudiation on delay and disruption to the project, and consequent damages?
  6. What credit or set-off should be given to Company A for gains arising from Company B’s repudiation?
  7. What are the entitlement and valuation principles for retention monies and interest?

Arguments of the Parties

Company A's Arguments

  • Company A contends that Company B repudiated the subcontract and that damages should be assessed for defects and repudiation based on actual costs incurred by Company A and its substitute contractors.
  • Company A asserts that work in progress should not be paid for unless completed, and that valuations must be based on completed stages.
  • Company A maintains that delay and disruption caused by Company B’s repudiation should be compensated, but contends that certain delays were due to other factors such as industrial relations and design changes by third parties.
  • Company A claims entitlement to set off gains resulting from Company B’s repudiation against damages claims.
  • Company A argues that retention monies were properly withheld and should be released only after practical completion and defects liability periods.

Company B's Arguments

  • Company B disputes the extent of damages claimed by Company A and argues for payment of sums based on valuations that include work in progress and partial fabrication.
  • Company B contends that they completed a substantial proportion of design and drafting work and should be paid accordingly.
  • Company B asserts that certain alleged defects were not their responsibility or were the result of variations and changes beyond their control.
  • Company B challenges Company A’s claim for delay damages, emphasizing other causes such as design changes and industrial relations problems.
  • Company B claims entitlement to payment for temporary steel and equipment left on site and seeks interest on sums awarded for non-return.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd [2006] EWHC 1341 (TCC) Determination of preliminary issues on repudiation and contractual interpretation. Used as foundation for procedural and substantive rulings on repudiation and valuation methodology.
Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd (No. 2) [2007] EWHC 145 (TCC) Clarification of responsibility for design and fabrication of temporary works. Applied to determine scope of Company B’s obligations at repudiation date.
Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd [2007] EWCA Civ 1372 Court of Appeal ruling on design responsibility and repudiation. Used to confirm that Company B remained responsible for design of roof temporary works.
Lusty v Finsbury Securities Ltd (1991) 58 BLR 66 Admissibility of opinion evidence by factual witnesses with expertise. Guided the court in admitting technical opinions from factual witnesses.
DN v LB Greenwich [2004] EWCA Civ 1659 Admissibility of professional opinion evidence by defendants in negligence cases. Supported court’s approach to technical evidence from factual witnesses.
Sumpter v Hedges [1898] 1 QB 673 Principle that payment entitlement arises when instalments are earned and certified. Applied to reject entitlement to payment for lump sum work after repudiation without certification.
Abbey Developments Ltd v PP Brickwork Ltd [2003] CILL 2033 Interpretation of variation clauses and limits on employer’s rights to omit work. Applied to reject argument that employer could omit work to give to another contractor without adjustment.
Trustees of the Stratfield Saye Estate v AHL Construction Ltd [2004] EWHC 3286 (TCC) Similar principles on variation and contractual rights. Supported conclusions on variation and omission of erection engineering work.
The Mihalis Angelos [1971] 1 QB 164 Damages for anticipatory breach must reflect actual loss, considering mitigation and predestined events. Applied by analogy to assess damages for repudiation, considering removal of obligations.
Fairchild v Glenhaven Funeral Services Ltd [2003] 1 AC 32 Relaxation of causation rules in exceptional tort cases; policy considerations. Distinguished as inapplicable to contractual repudiation damages.
Six Continents Retail Ltd v Carford Catering Ltd [2003] EWCA Civ 1790 Evaluative approach to causation and duty to mitigate. Supported court’s approach to causation and mitigation in repudiation damages.
The Golden Victory [2007] UKHL 12 Damages for anticipatory breach must consider subsequent events that would have terminated contract. Applied to conclude damages should disregard obligations removed before repudiation.

Court's Reasoning and Analysis

The court undertook a detailed and methodical analysis of the complex factual matrix, contractual provisions, and evidential material. It commenced by establishing the factual background and procedural history, including the parties’ respective roles, the subcontract and its amendments, and the repudiation by Company B.

The court examined the valuation of work done and materials supplied at key dates (15th February 2004, 30th June 2004, and 2nd August 2004), applying the subcontract conditions, the Supplemental Agreement, and the purchase order. It rejected claims for payment of partial fabrication or painting, holding that payment was due only for completed stages, consistent with the contract scheme and the operation of the Go Data system.

The court found that Company B’s repudiation occurred after Company A had resolved to remove certain obligations and had engaged Company C to perform them, including erection engineering and design of temporary works. The court held that damages for repudiation must be assessed by disregarding obligations which Company A had already allocated to Company C, applying principles analogous to those in anticipatory breach cases such as The Mihalis Angelos and The Golden Victory. It concluded that Company A did not suffer loss from Company B’s failure to perform those obligations and was not entitled to damages for them.

Regarding defects claims, the court undertook a granular assessment of multiple groups of claims relating to paintwork, remedial works, and design and drafting defects. It accepted certain claims for remedial painting and defects but rejected others where evidence was insufficient or where damage resulted from actions of Company A or its subcontractors.

In relation to delay claims, the court identified multiple causes of delay during the relevant periods, including industrial relations issues, accidents, weather, and design changes by third parties. It found no causal link between Company B’s repudiation and delay or loss of production during the period after repudiation, especially given that Company C was already engaged and the workforce was on strike for part of the period.

The court also addressed the valuation of temporary steel and equipment left on site by Company B and retained by Company A. It awarded damages for non-return of certain items at assessed values, rejecting speculative or unproven claims.

In relation to retention monies and interest, the court held that retention was properly withheld during the project and was due for release only after practical completion and defects liability periods. It rejected late attempts by parties to alter their positions on retention and interest, holding them to admissions made during trial.

Throughout, the court emphasized the contractual terms, the factual evidence, and the necessity of applying established legal principles on repudiation, valuation, causation, and mitigation. It declined to make arbitrary deductions or adjustments unsupported by evidence and rejected attempts to reframe claims or defenses at late stages.

Finally, the court lamented the excessive costs and complexity of the litigation, encouraging parties in future to use dispute resolution mechanisms more effectively and to settle disputes on the basis of resolved principles rather than protracted trial.

Holding and Implications

DISPOSED OF

The court ordered that Company B pay Company A the total sum of £6,154,246.79, representing overpayments previously made, damages for breach of contract, and interest. Company A’s claims for damages for repudiation were dismissed except for nominal damages. Claims for defects and remedial painting were allowed in limited amounts. Claims for delay damages were dismissed due to lack of causation. Company A’s gains from Company B’s repudiation exceeded losses, resulting in no net damages for repudiation.

The court’s decision directly affects the financial entitlements and liabilities of the parties in respect of the subcontract and related contracts. No new legal precedent is established beyond applying existing principles of contract law, valuation, and damages to a complex construction dispute. The judgment underscores the importance of clear contractual terms, proper valuation procedures, and the mitigation of loss in repudiation cases. It also highlights the risks and costs of protracted litigation in construction disputes.