PEC Ltd v Asia Golden Rice Co Ltd

England and Wales High Court (Commercial Court)
Oct 17, 2012
Smart Summary (Beta)

Factual and Procedural Background

This opinion concerns an application by the Applicant ("PEC") seeking an extension of time to make any application challenging the jurisdiction of a tribunal under section 67 of the Arbitration Act 1996 ("the 1996 Act"). The dispute arises from a contract for the sale of 25,000 metric tonnes of Thai Rice by the Respondent ("AGR") to PEC, which AGR claims was concluded in May 2008 but not performed by PEC.

A GAFTA tribunal issued an award on 2 July 2012 ("the Award") confirming the contract’s conclusion on 15 May 2008, the tribunal’s jurisdiction, and PEC’s obligation to pay AGR US$6,250,000 plus interest, fees, and costs. PEC appealed to the GAFTA Appeal Board on matters other than jurisdiction, as GAFTA rules preclude appeals on jurisdictional issues. The appeal was scheduled for January 2013.

PEC’s primary submission was that no extension of time was required because the time limit under section 70(2) of the 1996 Act would run from the date of the GAFTA Appeal Award. Alternatively, if time runs from the original Award date, PEC sought an extension pursuant to section 80(5) of the 1996 Act and CPR 62.9. AGR contended that the time for a section 67 application had expired and that any extension was at the Court’s discretion.

The parties agreed the Court had jurisdiction to grant an extension and that such an extension should be granted, but the Court considered it necessary to clarify the legal position.

Legal Issues Presented

  1. Whether the time for making an application under section 67 of the Arbitration Act 1996 has expired.
  2. Whether an extension of time should be granted to the Applicant under section 80(5) of the 1996 Act.

Arguments of the Parties

Applicant's Arguments

  • The time limit under section 70(2) of the 1996 Act does not run from the date of the first-tier GAFTA Award but from the date of the GAFTA Appeal Award, as the appeal is an available arbitral process of appeal or review that must be exhausted first.
  • The GAFTA appeal procedure qualifies as an "available arbitral process of appeal or review" under section 70(2), and the use of the word "any" in the statute is deliberate and broad.
  • The Board of Appeal’s award confirms, varies, amends, or sets aside the first-tier Award, thus putting it into its final form, which triggers the running of time.
  • An application to the Court may be unnecessary if the Board of Appeal reverses the first-tier tribunal’s findings.
  • PEC sought an extension of time if the Court found time runs from the first-tier Award.

Respondent's Arguments

  • The time for making an application under section 67 has expired, and any application now requires a Court-granted extension.
  • The first-tier Award, where the tribunal ruled it had jurisdiction, is conclusive and binding as to jurisdiction under GAFTA Rules 8.1(b) and 10.1; no appeal lies on jurisdictional issues.
  • It is incorrect to assert that time does not run because no arbitral appeal on jurisdiction is available; the only way to challenge jurisdiction is by Court application within 28 days of the first-tier Award.
  • It is doubtful that GAFTA appeals fall within "available arbitral process of appeal or review" under section 70(2) of the 1996 Act, as supported by obiter remarks in UR Power v. Kuok.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Kalmneft v Glencore [2002] 1 Lloyd's Rep 128 Factors relevant to an application for extension of time under section 80(5) of the 1996 Act. The Court applied the factors to determine that an extension of time was appropriate given the short delay, uncertainty over time limits, and absence of prejudice.
The Amer Energy [2008] 1 Lloyd's Rep 293 Supporting authority on the factors relevant to extension of time applications. Reinforced the Court’s approach to granting an extension of time.
UR Power v. Kuok [2009] 2 Lloyd's Rep 495 (obiter) Obiter view on whether GAFTA appeals constitute an "available arbitral process of appeal or review" under section 70(2) of the 1996 Act. The Court noted this as an open question but did not decide it, acknowledging the obiter comment but recognizing the practical difficulties in excluding GAFTA appeals.

Court's Reasoning and Analysis

The Court considered the GAFTA 125 Arbitration Rules and the relevant provisions of the Arbitration Act 1996. Under GAFTA Rule 8.1(b), a tribunal’s decision that it has jurisdiction is final and binding with no right of appeal on jurisdictional issues. The Court found that the first-tier Award is conclusive on jurisdiction and that the time limit under section 70(3) of the 1996 Act for challenging jurisdiction runs from the date of that Award, not from any subsequent appeal.

The Applicant’s argument that the time limit should run from the date of the GAFTA Appeal Award was rejected because no available arbitral appeal exists on jurisdictional matters under GAFTA rules. The Court recognized the uncertainty surrounding whether GAFTA appeals constitute an "available arbitral process of appeal or review" but concluded that this question need not be decided for the current case.

Since the time limit for a section 67 challenge had expired, PEC required an extension of time. The Court applied the established factors from Kalmneft v Glencore and The Amer Energy cases, finding that the short delay, the uncertainty over the applicable time limit, and the absence of prejudice to AGR justified granting an extension.

Holding and Implications

The Court granted an extension of time for the Applicant to make any application challenging the tribunal’s jurisdiction under section 67 of the Arbitration Act 1996.

Holding: The application for an extension of time was GRANTED.

The direct effect is that PEC is permitted additional time to challenge the tribunal’s jurisdiction despite the expiry of the statutory time limit. No new legal precedent was established; the decision rests on the application of existing principles regarding time limits and extensions under the Arbitration Act 1996 and GAFTA rules.