Factual and Procedural Background
This case concerns a claim by the Plaintiff that a prior adjudication should be set aside on the grounds that the adjudicator lacked jurisdiction. The Plaintiff was the unsuccessful party and the paying party in the adjudication, which was conducted under the Housing Grants, Construction and Regeneration Act 1996 and the Scheme for Construction Contracts (England and Wales) Regulations 1998. The Defendant, as the successful payee party, seeks to uphold the adjudication and enforce the award as a judgment debt.
The Plaintiff, a contractor who subcontracted work at a location referred to as Rugby to the Defendant, faced ten interim payment applications by the Defendant during the contract. The tenth application was referred twice to adjudication by the Defendant. The Plaintiff challenged the adjudicator's jurisdiction on several grounds. The first adjudication resulted in no payment to the Defendant, while the second adjudication awarded sums in the Defendant's favour.
The Defendant sought to enforce the second adjudication award via winding up proceedings in Scotland, during which the status of the award was a key issue. The Plaintiff initially awaited the Defendant's proceedings before raising jurisdictional challenges in court. Following delays, the Plaintiff initiated this action seeking declarations concerning the adjudication awards. The Defendant counterclaimed for judgment to enforce the awards. The court set a timetable and ordered a payment into court of the disputed sum. The Plaintiff's amended particulars of claim alleging lack of jurisdiction based on a compromise were rejected, and the matter proceeded to trial on the original jurisdiction issue.
Legal Issues Presented
- Whether the adjudicator had jurisdiction to decide the second adjudication, given that the dispute was alleged to be the same or substantially the same as a previous adjudication under paragraph 9(2) of the Scheme for Construction Contracts (England and Wales) Regulations 1998;
- Whether the second adjudication award should be set aside on the basis of lack of jurisdiction;
- Whether the Defendant is entitled to judgment enforcing the second adjudication award as a judgment debt.
Arguments of the Parties
Plaintiff's Arguments
- The adjudicator had no jurisdiction to decide the second adjudication because the dispute was substantially the same as the first adjudication, triggering paragraph 9(2) which requires resignation of the adjudicator in such cases.
- Adjudication decisions have only temporary finality and do not give rise to issue estoppel or res judicata.
- The second adjudication merely re-shaped the original claim with minor changes, but did not raise new claims; therefore, the adjudicator erred in not resigning.
- A party should not be permitted to pursue a second adjudication on a slightly altered claim after failing in the first.
Defendant's Arguments
- The disputes in the two adjudications were different, not the same or substantially the same, because they related to different claims or valuations arising from the contract.
- The adjudicator was entitled to conclude that the second adjudication dealt with a distinct dispute, focusing on a flexible claim for valuations rather than the specific claim in the first adjudication.
- Case law supports the position that multiple adjudications can be valid where the disputes differ, even if related to the same contract.
- The adjudicator’s decision was correct and binding, and the Defendant is entitled to judgment enforcing the award.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| VHE Construction v RBSTB Trust Co Ltd (2000) BLR 187 | Confirmed that two adjudications concerning the same contract can be distinct if the disputes differ, and both adjudicators can have jurisdiction and issue binding decisions. | The court relied on this case to support the Defendant’s argument that the second adjudication was a separate dispute and validly decided. |
| Sherwood and Cason Limited v McKenzie Engineering Limited (2000) Construction Industry Law Letter | Held that courts should inquire whether two adjudications relate to the same or substantially the same dispute, giving weight to the adjudicator’s decision on jurisdiction and only intervening if there are substantial grounds to find error. | The court noted this case in relation to the jurisdictional inquiry and the principle of deference to the adjudicator’s view on whether disputes overlap. |
| Fast Track Contractors Ltd v Morrison Construction Ltd (2000) BLR 168 | Explained that a "dispute" is a single issue or set of issues referred at a point in time, and characterisation of the dispute is fact-sensitive; adjudication references must be carefully construed in context. | The court applied this reasoning to determine that the two adjudications involved different disputes due to differences in the referral notices and claims. |
Court's Reasoning and Analysis
The court analysed the parties’ submissions and the adjudications in detail. The central issue was whether the second adjudication concerned the same or substantially the same dispute as the first, triggering the adjudicator’s mandatory resignation under paragraph 9(2) of the Scheme.
The court accepted the Defendant’s argument that although both adjudications arose from the same contract and related to similar subject matter, the disputes themselves were different. The referral notices and claims differed in scope and detail, with the first adjudication addressing a specific claim which was rejected, and the second adjudication concerning a broader, more flexible claim for valuation of work done.
The court considered case law, particularly the VHE Construction case, which supports the validity of multiple adjudications on different disputes arising from the same contract. It also noted that the adjudicator had carefully considered the jurisdictional challenge and distinguished the issues between the two adjudications.
The court concluded that the adjudicator was correct in not resigning and in deciding the second adjudication. The Plaintiff’s challenge on jurisdiction was therefore unsuccessful.
Holding and Implications
The court DISMISSED the Plaintiff’s claim to set aside the second adjudication award for lack of jurisdiction.
The Defendant is entitled to judgment enforcing the sums awarded in the second adjudication as a judgment debt. Costs are to be paid by the Plaintiff, including those arising from procedural delays and late service. The court noted no new precedent was established beyond confirming existing principles regarding the nature of disputes in adjudication and the limited scope for jurisdictional challenges.
Alert