Pentonville Shipping Ltd. v Transfield Shipping Inc (MV Johnny K)

England and Wales High Court (Commercial Court)
Feb 10, 2006
Smart Summary (Beta)

Factual and Procedural Background

An appeal was brought under section 69(3) of the Arbitration Act 1996 against an arbitration award dated 24 March 2005 made by two London maritime arbitrators. The arbitration concerned claims by the owners of a vessel against the charterers for freight, deadfreight, and damages amounting to approximately US$134,682.59. The arbitrators dismissed this claim, and the owners appealed.

The owners, as disponent owners, chartered their Capesize bulk carrier vessel to the charterers for a voyage from Dampier or Port Hedland in Australia to China, with a full cargo of iron ore. The nominated load port was Port Hedland. The charter allowed for a cargo quantity of 170,000 tonnes plus or minus 10% at the owners' option.

The vessel arrived at Port Hedland on 29 September 2003 and tendered Notice of Readiness, requesting 172,700 tonnes of cargo within the contractual tolerance. Loading did not commence until 1 October 2003, after laytime had expired, placing the vessel on demurrage.

A dispute arose during arbitration about the applicable loading rate and laytime, but this was withdrawn by agreement due to the arbitrators' inability to agree on the matter.

The arbitrators found that the delay in berthing was due to normal port congestion at Port Hedland, which had five berths but only two suitable for the vessel. The berths were controlled by the shippers, and the arbitrators found no evidence of vessels berthing ahead of the subject vessel after its arrival. They also found that the shippers made efforts to berth the vessel as soon as possible.

The vessel could have loaded the full contractual cargo and sailed on the high tide in the early hours of 2 October 2003. However, it was ordered to sail with only 156,855 tonnes loaded, a shortfall of 15,845 tonnes, and actually sailed on the high tide in the early hours of 3 October 2003. Further loading could have been completed within hours, and there was sufficient water for the vessel to remain safely at berth fully laden.

The arbitrators found that the vessel had to turn before berthing and that it was not possible for the vessel, once almost fully laden, to leave the berth, anchor, and return to complete loading due to inability to turn in the port.

The vessel was ordered to sail by terminal/port authorities, although the precise identity of the authority issuing the order was not clearly determined by the arbitrators. The owners accepted that the order to leave came from the terminal/port authorities. The arbitrators found the charterers could not be held liable for the order to vacate the berth given by the port authorities.

The arbitrators concluded that the owners' loss was caused by the order of the terminal/port authorities, not by any breach of contract by the charterers, and accordingly dismissed the owners' claim for deadfreight/damages.

Legal Issues Presented

  1. Whether the arbitrators were bound by the precedent set in Aktieselskabet Reidar v. Arcos Ltd to find the charterers liable for deadfreight or damages.
  2. Whether the arbitrators erred in holding that the charterers were not responsible for the order to sail given by the terminal/port authorities, particularly given that the berth was controlled by the shippers.
  3. Whether the order to sail was attributable to the charterers and thus whether the charterers prevented the owners from fulfilling their contractual obligations.

Arguments of the Parties

Appellant's Arguments

  • The arbitrators were bound by the Court of Appeal decision in Aktieselskabet Reidar v. Arcos Ltd to find the charterers liable for deadfreight or damages.
  • The arbitrators failed properly to address the question of causation, as the order to sail was caused by the charterers' failure to load within laytime.
  • The order to sail was a commercially motivated decision by the shippers (charterers), intended to avoid blocking the berth.

Respondent's Arguments

  • If the order to sail was given by the shippers (BHP), the award must be set aside.
  • The arbitrators found the order was given by the port authority, not the shippers.
  • Even if the charterers were responsible for the order, the owners' loss was caused by their own breach in failing to keep the vessel available or by the absence of breach of the safe berth warranty.
  • The demurrage provisions represented the owners' sole remedy for delay in loading.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Aktieselskabet Reidar v. Arcos Ltd [1926] 25 L1.1. Rep. 513 Principles relating to liability for failure to load full cargo and causation in charterparty breaches. The court found the precedent was not determinative in the present case because the vessel could have waited without frustrating the charterparty, and the loss was caused by the order to sail, not by the charterers' breach.
Richco International Ltd v. Alfred C Toepfer International GMBH "The Bonde" [1991] 1 Lloyd's Rep.136 Discussion of the ratio of Reidar v. Arcos and its application. The court considered the analysis academic but noted it supported the view that causation was key and that the owners' loss was not caused by the charterers' breach.
Cosmar Compania Naviera S.A. v. Total Transport Corp. "The Isabelle" [1982] 2 Lloyd's Rep.81; affirmed [1984] 1 Lloyd's Rep.366 Considerations in attributing orders and responsibility between parties in maritime disputes. The court referenced this trilogy of cases to guide the analysis on whether the order to sail was attributable to the charterers.
Mediolanum Shipping Co. v. Japan Lines Ltd "The Mediolanum" [1984] 1 Lloyd's Rep.136 See above. See above.
Newa Line v. Erechthion Shipping Co. S.A. "The Erechthion" [1987] 2 Lloyd's Rep.180 See above. See above.

Court's Reasoning and Analysis

The court analyzed the facts and the arbitrators' findings regarding the delay in loading and the order to sail. It noted that the arbitrators found the vessel could have loaded the full cargo and waited for the next spring tides without frustrating the charterparty. The critical issue was whether the order to sail was attributable to the charterers.

The court observed that the arbitrators did not make a clear, consistent finding on who gave the order to sail—whether it was the port authority or the shippers (charterers). The arbitrators concluded that the charterers could not be held liable for the order given by the port authorities, but the court found this reasoning unclear and possibly incorrect in approach.

The court emphasized the distinction between an order being given by a party and the order being attributable to that party for contractual responsibility. It held that if the order was given by the shippers (charterers), the owners' claim must succeed. Conversely, if the order was truly from the port authority and not attributable to the charterers, the claim fails.

The court found that the arbitrators may not have properly addressed or applied the relevant legal principles regarding attribution of responsibility as set out in the trilogy of maritime cases cited. Consequently, the court exercised its power under section 69(7)(c) of the Arbitration Act 1996 to remit the matter to the arbitrators for reconsideration, particularly the dismissal of the owners' claim for deadfreight/damages and related costs.

Holding and Implications

The court remitted the relevant part of the arbitration award to the arbitrators for reconsideration concerning the dismissal of the owners' claim for deadfreight/damages and consequential costs.

The implication is that the arbitrators must reconsider whether the order to sail was attributable to the charterers and thus whether the owners are entitled to deadfreight or damages. The arbitrators are free to reach the same or a different conclusion upon reconsideration. No new precedent was established by this decision. The direct effect is that the owners' claim was not finally resolved and requires further determination by the arbitrators.