Melville Dundas Ltd & Ors v. George Wimpey UK Ltd & Ors (Scotland)
Factual and Procedural Background
Company A (the employer) engaged Company B (the contractor) to design and build a housing development in The City for a contract sum of approximately £7.1 million. The contract incorporated the JCT Standard Form of Building Contract with Contractor’s Design (1998 edition). Under clause 30 the contractor could apply monthly for interim payments, the “final date for payment” being 14 days after each application.
On 2 May 2003 Company B applied for an interim payment of £396,630; the final date for payment was therefore 16 May 2003. Company A did not pay. On 22 May 2003 administrative receivers were appointed to Company B. Clause 27.3.4 entitled the employer to determine the contractor’s employment upon such an appointment, and Company A exercised that right on 30 May 2003. Determination triggered clause 27.6.5.1, which states that the contractor “shall not be entitled to require any further payment” unless specified conditions are satisfied.
Company B sued for the unpaid interim payment. Judge Clarke (Lord Ordinary) dismissed the claim. The Inner House (Extra Division) reversed him ([2006] SLT 95). Company A appealed to the House of Lords.
Legal Issues Presented
- Whether the phrase “any further payment” in clause 27.6.5.1 prevents the contractor from enforcing an interim payment that had already fallen due before determination of the contract.
- Whether clause 27.6.5.1 is rendered ineffective by sections 109–111 of the Housing Grants, Construction and Regeneration Act 1996, in particular the notice requirement in section 111(1).
Arguments of the Parties
Appellant’s Arguments (Company A)
- On its natural meaning clause 27.6.5.1 stops the contractor from “requiring any further payment,” which includes the disputed interim instalment.
- The 1996 Act does not prohibit parties from agreeing circumstances in which a payment that has become due may cease to be payable.
- Section 111(1) cannot apply because it would be impossible to give a withholding notice before the statutory deadline; lex non cogit ad impossibilia.
- Upon insolvency, insolvency set-off entitles the employer to retain the money as security for cross-claims, as recognised in Bouygues v Dahl-Jensen.
Respondent’s Arguments (Company B)
- “Any further payment” in clause 27.6.5.1 should be confined to liabilities arising after determination; a sum already due cannot retrospectively cease to be due.
- Even if the clause covers the interim payment, section 111(1) flatly prohibits withholding payment after the final date unless a timely notice was served. No notice was given, so payment is mandatory.
- The statutory regime is designed to protect cash flow for contractors and should override contractual provisions that defeat that purpose.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd [2000] BLR 522 | Insolvency set-off under rule 4.90 of the Insolvency Rules 1986. | Illustrated that an employer who owes money to an insolvent contractor may set that debt off against its own cross-claim. |
| Modern Engineering (Bristol) Ltd v Gilbert-Ash (Northern) Ltd [1974] AC 689 | Common-law right of set-off against interim certificates. | Cited in governmental consultation to explain why statutory notice provisions were introduced; used contextually by the House. |
| Highland Engineering Ltd v Thomson 1972 SC 87 | Liquidation equated with bankruptcy for purposes of compensation (set-off). | Supported extension of insolvency set-off principles to Scottish liquidation. |
| Stein v Blake [1996] AC 243 | Automatic set-off in bankruptcy. | Referenced to show statutory primacy of insolvency set-off over contractual claims. |
| C & B Scene Concept Design Ltd v Isobars Ltd [2002] BLR 93 | Relationship between payment provisions and adjudication. | Quoted by a dissenting judge to argue that sections 110–111 are ancillary to adjudication. |
Court's Reasoning and Analysis
Judge Hoffmann (for the majority) held that the unqualified words “any further payment” in clause 27.6.5.1 cover the disputed interim sum; reading in a limitation (“not already due”) would contradict both the text and the presence of the proviso. Interim payments are inherently provisional and become part of the employer’s security once the contractor’s employment is determined and insolvency intervenes.
Turning to statutory validity, the majority found that Parts II of the 1996 Act were intended to secure clarity of payment mechanisms, not to dictate substantive risk-allocation after insolvency. Sections 109 and 110 permit parties to define the circumstances in which payments become or cease to be due. Parliament did not intend to invalidate widely used JCT wording without explicit language.
As to section 111(1), the majority reasoned that imposing the notice requirement where the ground for withholding (appointment of receivers) arises after the deadline would make compliance impossible and effectively nullify clause 27.6.5.1. Applying the maxim lex non cogit ad impossibilia, the section was construed not to apply to such a case.
Judges Mance and Neuberger dissented. They considered section 111(1) unambiguous: once the final date passes, payment cannot be withheld absent a compliant notice, regardless of later events.
Holding and Implications
APPEAL ALLOWED. The House of Lords restored the Lord Ordinary’s interlocutor and dismissed the contractor’s action for the interim payment.
Implications: The decision confirms that parties to construction contracts may contractually provide for previously accrued interim payments to cease to be payable upon the contractor’s insolvency or contractual determination, without breaching sections 109–111 of the 1996 Act. It preserves employer security via insolvency set-off and limits the reach of the Act’s notice provisions in circumstances where compliance is impossible. No new statutory rule was created, but existing industry-standard clauses were validated.