Aspect Contracts (Asbestos) Ltd v Higgins Construction Plc

United Kingdom Supreme Court
Jun 17, 2015
Smart Summary (Beta)

Factual and Procedural Background

Company A was engaged by Company B to carry out an asbestos survey of certain residential blocks in The City in 2004. Company B later alleged that asbestos-containing materials, not identified in Company A’s report, were discovered during redevelopment works in 2005. After negotiations and mediation failed, Company B commenced adjudication in 2009 under the Housing Grants, Construction and Regeneration Act 1996 and the Scheme for Construction Contracts.

Judge Jackson, acting as adjudicator, awarded Company B £490,627 plus interest, and Company A paid £658,017 in total on 6 August 2009. Company B took no further action and the contractual and tort limitation periods for its underlying claim expired by early 2011.

On 3 February 2012, Company A issued the present proceedings seeking repayment of the sum paid, advancing an implied-term claim (and, later, an alternative restitutionary claim). Company B counter-claimed for the balance of its original claim (£331,855) but faced a limitation defence. Judge Akenhead rejected Company A’s claim; the Court of Appeal (Judges Longmore, Rimer and Tomlinson) reversed that decision. Company B appealed to the Supreme Court.

Legal Issues Presented

  1. Whether the Scheme for Construction Contracts implies a term entitling a paying party to recover any overpayment made pursuant to an adjudicator’s decision once the dispute is finally determined.
  2. The applicable limitation period for such a repayment claim and for any counter-claim by the payee.
  3. Whether, absent an implied term, a restitutionary right to repayment arises at common law.

Arguments of the Parties

Company A’s Arguments

  • An implied term arises from the Act and Scheme that, upon final determination, any overpayment made under an adjudicator’s decision must be repaid.
  • Alternatively, repayment is recoverable in restitution once the basis of the payment falls away.
  • The cause of action accrues on payment (6 August 2009), giving six years to sue; the claim is therefore timely.
  • Company B’s counter-claim for the unpaid balance is statute-barred under the Limitation Act 1980.

Company B’s Arguments

  • No implied term exists; the paying party’s sole remedy is to seek declaratory relief within the original limitation period for the underlying breach.
  • Any claim for repayment is therefore time-barred because Company A failed to sue within six years of the alleged breach in 2004/2005.
  • Even if a repayment claim is possible, Company B should receive a corresponding fresh six-year period to pursue the balance of its own claim.
  • The court lacks jurisdiction to grant consequential repayment orders absent an independent cause of action.

Table of Precedents Cited

PrecedentRule or Principle Cited ForApplication by the Court
Guaranty Trust Co v Hannay [1915] 2 KB 536 Scope of declaratory relief and its consequential powers. Court held the decision does not support granting repayment orders without an independent juridical basis.
P&O Nedlloyd BV v Arab Metals Co (The “UB Tiger”) [2005] EWHC 1276 Declaratory actions may be claims “founded on simple contract”. Distinguished; a negative declaration of non-liability does not trigger Limitation Act sections 2 or 5.
Premium Nafta Products Ltd v Fili Shipping Co [2007] UKHL 40 Broad construction of disputes subject to arbitration/adjudication. Accepted that coterminous tort claims can fall within statutory adjudication.
Fillite (Runcorn) Ltd v Aqua-lift (1989) 45 BLR 27 Earlier, narrower approach to arbitration clauses. Cited to contrast with Premium Nafta; broader approach preferred.
Woolf v Collis Removal Service [1948] 1 KB 11 Interpretation of dispute clauses. Referenced in discussion of adjudicable tort claims.
Astro Vencedor v Mabanaft [1971] 2 QB 588 Arbitration scope principles. Part of authorities on wide interpretation of “arising under”.
Empresa Exportadora de Azucar v Industria Azucarera Nacional [1983] 2 Lloyd’s Rep 171 Further authority on arbitral jurisdiction. Cited in same context as Astro Vencedor.
Chimimport plc v G D'Alexio Sas [1994] 2 Lloyd’s Rep 366 Construction of arbitration agreements. Used to illustrate evolution towards broader approach.
Henderson v Merrett Syndicates Ltd [1995] 2 AC 145 Separate limitation periods for contract and tort. Supported distinction between contractual and tortious limitation.
Sempra Metals Ltd v Inland Revenue [2007] UKHL 34 Restitutionary interest for time value of money. Basis for allowing interest on any overpayment repaid.
Kleinwort Benson Ltd v Sandwell BC [1994] 4 All ER 890 Limitation period for restitution “founded on simple contract”. Relied on to apply six-year period to restitution claims.
Kleinwort Benson Ltd v Lincoln CC [1999] 2 AC 349 Effect of mistake on limitation in restitution. Cited to confirm Sandwell analysis.
Walker Construction v Quayside Homes [2014] EWCA Civ 93 Obiter support for first-instance view rejecting implied term. Overruled; Supreme Court states those observations were wrong.

Court's Reasoning and Analysis

The Supreme Court held that adjudication is expressly intended as a provisional, “pay now, argue later” mechanism. Paragraph 23(2) of the Scheme obliges parties to comply with the adjudicator’s decision until final determination, but does not itself create finality.

Because the Scheme is implied into every relevant construction contract, the Court inferred a further necessary term: once the underlying dispute is finally determined, any payment proven to exceed the payer’s true liability must be repaid. This implication preserves the provisional character of adjudication and avoids an “irrational gap” whereby an over-payment could never be recovered.

The Court rejected Company B’s contention that repayment could be obtained only via negative declaratory relief. Such an approach was labelled “artificial” because it ignores the pivotal fact of payment in 2009. Moreover, seeking a declaration is not a claim “founded on contract or tort” for limitation purposes; therefore sections 2 and 5 of the Limitation Act do not time-bar Company A’s restitution or implied-term claim.

Analysing limitation, the Court held that the cause of action for repayment accrues on the date of payment. Consequently, Company A had six years from 6 August 2009 to sue, making the 2012 claim timely. By contrast, Company B’s claim for the balance of its original loss accrued in 2004/2005 and is now statute-barred.

The Court also clarified that, on a final determination of the dispute, the tribunal must examine the entire underlying merits afresh; the adjudicator’s reasoning carries no evidential weight. Interest on any overpayment is recoverable, reflecting restitutionary principles outlined in Sempra Metals.

Finally, the Court dismissed the suggestion that a fresh limitation period should revive Company B’s counter-claim merely because Company A commenced repayment proceedings. Receipt of money does not generate a new cause of action for additional sums.

Holding and Implications

Appeal DISMISSED. The Supreme Court affirmed the Court of Appeal’s decision that:

  • The Scheme implies a contractual right, alternatively a restitutionary right, for a paying party to recover any overpayment made under an adjudicator’s decision once the dispute is finally determined.
  • The limitation period for such a claim is six years from the date of payment.
  • Company B’s counter-claim for the balance of its original claim is time-barred.

Implications: The judgment secures symmetry between the provisional nature of adjudication and parties’ substantive rights, confirming that payers retain a clear route to restitution without being blocked by limitation periods tied to the original breach. It overrules contrary obiter remarks in Walker Construction v Quayside Homes and provides authoritative guidance on limitation and restitution in the adjudication context, without setting entirely new precedent but clarifying the interaction between the Act, the Scheme and the Limitation Act 1980.