Corner House Research, R (on the application of) v Secretary of State for Trade & Industry
Factual and Procedural Background
The claimants commenced judicial review proceedings on 29th November 2004 challenging changes made by the Export Credit Guarantee Department ("ECGD") concerning anti-bribery and corruption procedures. Initially, an interim Protective Costs Order ("PCO") was granted by Beatson J to cover preliminary hearings, but Davis J refused to grant a PCO for the substantive hearing scheduled for January 2005. The claimants applied for permission to appeal this refusal. The Court of Appeal granted permission and allowed the appeal, directing that a PCO including a cost-capping element be made. Subsequently, a consent order disposed of the judicial review application before the substantive merits were determined.
Legal Issues Presented
- Whether a Protective Costs Order should be granted in public law judicial review proceedings to enable claimants of limited means to pursue cases of general public importance without undue financial risk.
- The appropriate criteria and principles governing the grant of Protective Costs Orders in public law cases.
- Whether the Export Credit Guarantee Department breached public law standards of fairness and its own consultation policy by failing to consult relevant stakeholders, including the claimants, before implementing changes to anti-corruption procedures.
- The extent to which courts should depart from the traditional "costs follow the event" rule in public interest litigation.
Arguments of the Parties
Appellant's Arguments
- The claimants contended that the ECGD's consultation process was one-sided and failed to involve key stakeholders such as themselves, breaching public law fairness and the department’s own consultation policy.
- They argued that the changes to ECGD's anti-corruption procedures were fundamental and weakened protections against bribery and corruption.
- The claimants asserted they had no private interest in the outcome and that the issues raised were of general public importance, warranting a PCO to enable them to proceed without the risk of prohibitive costs.
- They emphasized that without a PCO, given their limited financial resources, they would be forced to discontinue the proceedings.
- It was argued that the traditional costs rule should not apply rigidly in public law cases involving matters of significant public interest.
Respondent's Arguments
- The ECGD contended that there was no general public law duty to consult beyond what was done and that the revisions to the procedures were neither fundamental nor major.
- They relied on established public law principles and literature to support the absence of a duty to consult in the manner claimed by the appellants.
- The respondent challenged the strength of the claimants' case and the necessity of a PCO, suggesting alternative funding or pro bono representation might be available.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| R v Lord Chancellor ex p CPAG [1999] 1 WLR 347 | Guidelines for granting Protective Costs Orders in public interest litigation. | The court adopted and refined the CPAG criteria, emphasizing exceptional circumstances and public importance for granting PCOs. |
| King v Telegraph Group Ltd [2004] EWCA Civ 613 | Cost-capping orders to balance fairness in cases funded by conditional fee agreements. | The court applied the cost-capping principles to limit the claimants’ financial exposure under the PCO. |
| McDonald v Horn [1995] ICR 685 | Discretionary jurisdiction over costs and exceptions to the "costs follow the event" rule. | Provided foundational principles on costs discretion, especially in complex or public law cases. |
| Wallersteiner v Moir (No 2) [1975] QB 373 | Limits on pre-emptive costs orders and indemnity in minority shareholder actions. | Illustrated the court's reluctance to fetter future costs discretion but recognized indemnity rights in specific contexts. |
| Steele Ford & Newton v CPS [1994] 1 AC 22 | Limits on courts ordering costs to be paid out of central funds absent express statutory authority. | Confirmed courts cannot order public funding for costs by implication, restricting PCO scope to parties involved. |
| R (Refugee Legal Centre) v Home Secretary [2004] EWCA Civ 1296 | Use of PCOs in public interest cases involving systemic unfairness. | Demonstrated practical application of PCOs to protect litigants in cases of significant public importance. |
| British Columbia (Minister of Forests) v Okanagan Indian Band (2003) 114 CCR 2d 108 | Interim costs orders and criteria for costs protection in public law cases. | Referenced for principles on equitable costs orders and balancing access to justice with litigation efficiency. |
| Oshlack v Richmond River Council [1998] HCA 11 | Considerations for departing from the ordinary costs rule in public interest litigation. | Provided comparative perspective emphasizing flexibility in costs discretion for public interest cases. |
| R v Home Secretary ex p Salem [1999] 1 AC 450 | Recognition of public interest in elucidating public law beyond parties' interests. | Supported the principle that public law cases justify different costs considerations due to public importance. |
| R v Somerset County Council ex p Dixon [1998] Env LR 111 | Public law concerns with wrongs and misuses of public power. | Emphasized that public law litigation addresses public wrongs, justifying protective approaches to costs. |
| Steel & Morris v UK (Judgment 15 February 2005) | Recognition of the rights of small campaign groups to operate effectively in a democratic society. | Used to support the claimants’ position as a small NGO needing protection to pursue public interest litigation. |
Court's Reasoning and Analysis
The court began by recognizing the established principle that costs generally follow the event, but acknowledged important distinctions in public law litigation, especially where issues of general public importance are raised by claimants with limited means. It reviewed the traditional approach to costs, statutory provisions, and relevant case law, noting the discretionary nature of costs orders under section 51 of the Supreme Court Act 1981 and CPR rules.
The court endorsed and refined the criteria from R v Lord Chancellor ex p CPAG for granting Protective Costs Orders, emphasizing that such orders should only be made in exceptional circumstances where:
- The issues are of general public importance;
- The public interest requires resolution of those issues;
- The applicant has no private interest in the outcome;
- It is fair and just to make the order considering the parties’ financial resources and likely costs;
- Without the order, the applicant would likely discontinue proceedings and would be reasonable in doing so.
The court lowered the threshold for the merits requirement from "sufficient appreciation" to a "real prospect of success" or "properly arguable" to avoid ancillary litigation. It stressed the importance of enabling litigants to bring public interest challenges without prohibitive financial risk.
Applying these principles, the court found that the case raised issues of general public importance, relating both to the conduct of major British companies in international trade backed by public funds and to the procedural fairness of ECGD's consultation policy. It found that the claimants had no private interest and, given their limited financial resources and the risk of discontinuance without protection, a PCO was justified.
The court identified that ECGD's consultation process had been one-sided, providing privileged access to corporate customers but excluding NGOs with expertise in anti-corruption, thereby breaching public law fairness and ECGD's own consultation policy. It found this procedural unfairness to be a matter of general public importance.
The court also clarified that PCOs should be sought early, preferably on the initiating claim form, supported by evidence including a schedule of future costs. It outlined a procedural framework designed to balance access to justice with cost control and proportionality, including cost caps and consequences for unmeritorious resistance or applications to set aside PCOs.
Holding and Implications
The Court of Appeal ALLOWED the appeal against the refusal of a Protective Costs Order by Davis J.
The court ordered that:
- The Defendant is not permitted to recover its costs of the judicial review proceedings from the Claimant;
- The Claimant's costs are to be capped in accordance with the principles established in King v Telegraph Group Ltd;
- The Claimant is to apply to the senior costs judge to set the level of the costs cap.
The direct effect of this decision was to enable the claimants, a small non-profit organization, to proceed with their judicial review challenge without the prohibitive risk of adverse costs. The ruling affirms the court's discretion to grant PCOs in exceptional public interest cases, providing a framework that balances access to justice with cost control. No new legal precedent beyond the application and refinement of existing principles was established, but the judgment clarifies procedural guidance for future PCO applications.