Chonga Venkata Ramadevi v. Government of Andhra Pradesh,

Andhra Pradesh High Court
Jul 7, 2023

HON'BLE SRI JUSTICE R. RAGHUNANDAN RAO WRIT PETITION No.20085 of 2013

ORDER:

Heard Sri Sanku, learned counsel for the petitioner and Sri N.Sri Hari, learned counsel for the respondent-Gram Panchayat.

2. The petitioner had constructed a building in

349.3 sq.yards of land in R.S.No.17/2, 17/3 and 15/1 at Bommuru Village and Gram Panchayat, Rajahmundry Rural Mandal. The petitioner states that this building consists of a ground floor, 1stfloor, 2ndfloor and an additional floor in which a Training College known as "Sri KYN Hindu Teachers Training College" is running. The petitioner had received a notice from the 2ndrespondent on 19.06.2013 informing the petitioner that she had raised constructions beyond the permission granted to the petitioner and that the said unauthorised constructions would be removed if no reply is received within 7 days from the date of receipt of the said notice.

3. The petitioner being aggrieved by the said notice has approached this Court with the grievance that the said

1

notice has been issued on account of collapse of a building somewhere else and the said notice is a knee jerk reaction to the other collapse. She further contends that the notice is actually an order of demolition, without an opportunity being given to the petitioner, and the same is violative of principles of natural justice apart from the provisions of Andhra Pradesh Panchayat Raj Act.

4. Respondent Nos.2, 4, 5 and 6 have filed separate counter affidavits. In these counter affidavits, the stand of the respondents is that the petitioner had obtained permission for construction of ground+2 floors while she has constructed a 3rdfloor and the same is irregular and needs to be removed. The respondents submit that the petitioner instead of approaching them with the physical documents to show how the building is in accordance with the building permission has approached this Court and as such, the writ petition is not maintainable.

5. A perusal of the impugned notice dated 19.06.2023 would show that the said notice does not contain the actual irregularities or the details of the constructions that are now sought to be removed. In the absence of such

2

details, the petitioner would not be in a position to answer the said notice. Consequently, it must be held that the show cause notice is not strictly in accordance with the requirements of law.

6. In the circumstances, the show cause notice dated 19.06.2023 and also the subsequent proceedings of 02.07.2013 are set aside, leaving it open to the respondents to take appropriate action against the petitioner after giving adequate opportunity of hearing and notice to the petitioner.

7. Accordingly, this Writ Petition is allowed. There shall be no order as to costs.

As a sequel, pending miscellaneous petitions, if any, shall stand closed.

____________________________

R. RAGHUNANDAN RAO, J.

07.07.2023