SUDHAMA PRASAD v. THE NATIONAL HIGHWAY AUTHORITY OF INDIA & ORS

Calcutta High Court
May 19, 2023
Smart Summary (Beta)

Case Summary: W.P.A. 14267 of 2018 and connected matters

Factual and Procedural Background

Multiple writ petitions (including W.P.A. 14267 of 2018, W.P.A. 14270/14278/14282/14283/14285/14287/14289/14290/14657 of 2018) were heard together because they involved similar issues of law and fact. The petitioners purchased various plots from the erstwhile owner, Smt. Vidya Devi Agarwala, mutated the properties in their names, paid taxes and were in possession. The petitioners learned, in or around June 2018 when faced with threats of demolition or utilisation of the land by Government authorities, that the plots had been the subject of acquisition/requisition processes: an acquisition/requisition notification (no. 472-L.A. dated 5th February 1987) and a notice under section 4(1a) of the West Bengal Land (Requisition and Acquisition) Act, 1948 (published 11th March 1987) existed in respect of the relevant R.S. plots.

The petitioners contended that the requisition/notification was not given effect to and the land was ultimately not acquired; they sought relief invoking, inter alia, section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The State and other respondents disputed the petitioners' claims, asserting that compensation (including rent compensation and LA compensation) had been paid to the erstwhile owner, possession had been handed to the requiring body (PWD) earlier, and that the petitioners were post-vesting purchasers lacking authority to challenge acquisition/requisition.

Procedural history: Hearing concluded on 05.04.2023. Judgment delivered on 19.05.2023 by Suvra Ghosh, J., dismissing the writ petitions.

Legal Issues Presented

  1. Whether post-vesting purchasers (who purchased land after publication of the notice under section 4(1a) of the West Bengal Land (Requisition and Acquisition) Act, 1948) are competent to challenge the acquisition/requisition proceedings?
  2. Whether principles and authorities concerning lapse of acquisition proceedings under the Land Acquisition Act, 1894 (and section 24(2) of the 2013 Act) apply to acquisition/requisition under the West Bengal Land (Requisition and Acquisition) Act, 1948?
  3. Whether the petitioners are entitled to relief (including restoration of title) where compensation had been paid to the erstwhile owner and the State had taken steps towards vesting/possession?

Arguments of the Parties

Petitioners' Arguments

  • The petitioners purchased the plots from Smt. Vidya Devi Agarwala, mutated their names in respect of the same, paid taxes and were in possession of the plots.
  • They discovered a notice under section 4(1a) of the West Bengal Land (Requisition and Acquisition) Act, 1948 but contend that the requisition/notification was not given effect to and the land was ultimately not acquired.
  • They sought relief under section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (arguing lapse/deemed lapse of acquisition) and placed reliance on authorities such as Pimpri Chinchwad New Township Development Authority v. Vishnudev Cooperative Housing Society and Indore Development Authority v. Manoharlal.

Respondents' (State/NHAI) Arguments

  • The plots were requisitioned/acquired under the West Bengal Land (Requisition and Acquisition) Act, 1948; rent compensation and LA compensation were paid to the land losers (including Vidya Devi).
  • Possession was taken under the relevant provisions (section 3/4 of the 1948 Act) and, according to respondents, possession was handed over to the PWD on 10th July 1968 and construction works have been completed.
  • The petitioners are post-vesting purchasers who purchased after publication of the notice under section 4(1a) and therefore have no right to challenge acquisition/requisition proceedings; any title acquisition by them is ineffective against the State.
  • Section 24 of the 2013 Act (and the jurisprudence on lapse under the 1894 Act) is inapplicable to acquisition under the 1948 Act; the petitioners' delay in approaching the Court was inordinate and unexplained (though petitioners contested the delay argument).
  • The respondents relied upon Indore Development Authority (and other authorities) to support these contentions.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Pimpri Chinchwad New Township Development Authority v/s. Vishnudev Cooperative Housing Society and Others (reported in (2018) 8 Supreme Court Cases 215) Addresses the modalities of taking possession of acquired land by the State and the State's entitlement to release land from acquisition by recourse to section 48 of the Land Acquisition Act, 1894 (withdrawal from acquisition of land of which possession has not been taken). The Court distinguished this authority: Pimpri concerns withdrawal under section 48 of the 1894 Act and cannot be applied to the 1948 Act scenario where, upon publication of notice under section 4(1a) of the 1948 Act, requisitioned land vests absolutely in the Government. Thus Pimpri's ratio was held inapplicable to these cases.
Indore Development Authority v/s. Manoharlal And Others (reported in (2020) 8 SCC 129) Relates to deemed lapse of acquisition proceedings under the Land Acquisition Act, 1894 and to section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (conditions for lapse/deemed lapse). The Court held Indore inapplicable to acquisition under the 1948 Act because the 2013 Act's provisions (including section 24(2) which deals with lapse under the 1894 Act) do not apply to the 1948 Act. Further, the Court noted the conjunctive requirements under section 24(2) (possession not taken and compensation not paid) and found that compensation had been paid to the erstwhile owner, so Indore did not aid the petitioners.
Shiv Kumar and Another v/s. Union of India and Others (reported in (2019) 10 Supreme Court Cases 229) Principle that a person who purchases land subsequent to notification under section 4(1) of the Land Acquisition Act, 1894 is not competent to challenge the validity of acquisition proceedings; post-vesting purchasers acquire no title vis-à-vis the State. The Court applied this principle analogously to the 1948 Act context: petitioners were post-vesting purchasers after publication under section 4(1a) of the 1948 Act and therefore could not challenge the acquisition/requisition proceedings.
V. Chandrasekaran and Another v/s. Administrative Officer and Others (reported in (2012) 12 SCC 133) Supports the principle that post-vesting purchasers cannot challenge acquisition; sale after notification does not confer title capable of challenging State acquisition. The Court relied on this authority (along with Shiv Kumar) to reinforce that the same rule applies under the 1948 Act: purchase after vesting does not confer title and such purchasers cannot invalidate acquisition proceedings.

Court's Reasoning and Analysis

The Court considered the facts, the submissions of parties and the authorities cited. The reasoning proceeded as follows:

  1. Common consideration: All petitions raised similar legal and factual issues and were heard together.
  2. Factual premise: The subject plots were requisitioned under section 3(1) of the West Bengal Land (Requisition and Acquisition) Act, 1948 for construction of road/bridge connected with National Highway 31; notice under section 4(1a) of the 1948 Act was published on 11th March 1987. The petitioners purchased the land after that publication and are therefore admitted post-vesting purchasers.
  3. Legal principle (post-vesting purchaser): The Court relied upon Supreme Court authorities (Shiv Kumar; V. Chandrasekaran) establishing that a purchaser who buys land after publication of the acquisition notification (under the 1894 Act context) cannot challenge acquisition proceedings since the sale deed does not confer title capable of resisting the State; the Court applied the same principle to acquisitions under the 1948 Act.
  4. Effect of payment of compensation: The Court found that rent compensation and LA compensation had been paid to the erstwhile owner (Vidya Devi) pursuant to earlier proceedings (including orders of this Court in writ no. 9860 (W) of 1992). Because compensation was paid and the notice under section 4(1a) was published, the acquisition/requisition process was considered complete and the land vested absolutely in the Government free from encumbrances.
  5. Distinguishing Pimpri: The petitioners' reliance on Pimpri (which concerns withdrawal under section 48 of the 1894 Act where possession has not been taken) was rejected as inapposite because the 1948 Act operates differently — upon publication under section 4(1a) the land vests in the Government — and the release/withdrawal provisions do not have the same operation in the 1948 Act.
  6. On Indore and section 24(2) of the 2013 Act: The Court observed that Indore and the 2013 Act address lapse of acquisition under the 1894 Act. Section 24(2) sets out conjunctive requirements (possession not taken AND compensation not paid) for deemed lapse: both conditions must exist. Since compensation had been paid to the erstwhile owner here, the Court held that the acquisition/requisition could not be deemed to have lapsed, and Indore therefore did not benefit the petitioners.
  7. Admission of possession/record entries: The Court noted that mere mutation/recording of petitioners' names in records of rights, or omission to record the State's title, does not ipso facto create title in favour of the petitioners where vesting and payment of compensation to the erstwhile owner had occurred.
  8. Delay: The respondents drew attention to the inordinate delay in approaching the Court; petitioners countered that they only learned of the requisition when threatened with demolition in June 2018 and filed promptly thereafter. The Court recorded the contention but proceeded to decide on merits and law.

Holding and Implications

Holding: DISMISSED — The writ petitions were dismissed as devoid of merit.

Implications and direct consequences:

  • The petitioners, being post-vesting purchasers who acquired the land after publication of the notice under section 4(1a) of the West Bengal Land (Requisition and Acquisition) Act, 1948, are not entitled to challenge the acquisition/requisition proceedings.
  • The Court concluded that the acquisition/requisition process was complete upon publication of the notice and payment of compensation to the erstwhile owner, and the land vested in the State free from encumbrances; purchase of such vested land does not confer any right, title or interest on the petitioners and they may be deemed trespassers/illegal occupiers in respect of the land.
  • The claim based on section 24(2) of the 2013 Act and the Indore authority was held inapplicable because those provisions and authorities concern the 1894 Act and the 2013 Act's regime; the conjunctive requirements for deemed lapse under section 24(2) were not satisfied here (compensation had been paid).
  • Practical orders: the writ petitions are dismissed; there shall be no order as to costs; allegations in the petitions are deemed not admitted because no affidavit was invited; parties may obtain certified website copies of the judgment on usual formalities.
  • No novel legal principle was declared: the judgment applies established authorities to conclude in these factual circumstances that post-vesting purchasers cannot challenge the acquisition/requisition under the 1948 Act where compensation to the erstwhile owner has been paid and vesting has occurred.

(Suvra Ghosh, J.)

Show all summary ...

IN THE HIGH COURT AT CALCUTTA

CONSTITUTIONAL WRIT JURISDICTION

APELLATE SIDE

The Hon'ble JUSTICE SUVRA GHOSH W.P.A. 14267 of 2018

Smt. Chandrati Devi

v/s.

National Highway Authority of India & Ors. With

W.P.A. 14270 of 2018

Smt. Snehalata Majumdar

v/s.

National Highway Authority of India & Ors. With

W.P.A. 14278 of 2018

Santosh Kumar Prasad

v/s.

National Highway Authority of India & Ors. With

W.P.A. 14282 of 2018

Bimal Kanti Saha

v/s.

National Highway Authority of India & Ors. With

W.P.A. 14283 of 2018

Rabindra Nath Biswas

v/s.

National Highway Authority of India & Ors. With

W.P.A. 14285 of 2018

Sudhama Prasad

v/s.

National Highway Authority of India & Ors.

1

2

With W.P.A. 14287 of 2018 Gita Chhetri (Sharma) v/s.

National Highway Authority of India & Ors. With

W.P.A. 14289 of 2018

Smt. Aishnu Nessa Dewan

v/s.

National Highway Authority of India & Ors. With

W.P.A. 14290 of 2018

Sri Munna Kumar Roy & Anr.

v/s.

National Highway Authority of India & Ors. With

W.P.A. 14657 of 2018

Premlal Gupta

v/s.

National Highway Authority of India & Ors.

For the Petitioners: Mr. Rabi Lal Maitra, Adv. Mr. Rajit Lal Maitra, Adv.,

For the NHAI: Ms. Manika Roy, Adv., For the State in

WPA 14267 of 2018: Md. T.M. Siddiqui, Adv. Mr. N. Chatterjee, Adv.

Ms. A. Pandey, Adv.,

For the State in

WPA 14282 of 2018: Mr. P.P. Roy, Adv. Mr. R.C. Guchhait, Adv.,

For the State in

WPA 14283 of 2018

& WPA 14287 of 2018: Mr. Jahar Lal De, Adv. Mr. Robiul Islam, Adv.

3

For the State in WPA 14285 of 2018: Mr. Jahar Lal De, Adv. Mr. R.C. Guchhait, Adv.

For the State in

WPA 14289 of 2018: Mr. Subhabrata Dutta, Adv. Mr. R.C. Guchhait, Adv.

For the State in

WPA 14290 of 2018: Mr. Jahar Lal De, Adv. Mr. Suddhadeb Adak, Adv.

Hearing Concluded on: 05.04.2023 Date: 19.05.2023

SUVRA GHOSH, J. :-

1. Since all the writ petitions involve similar issues of law and fact, they are taken up for consideration by a common judgment.

2. The petitioners purchased the plots in question from the erstwhile owner Smt. Vidya Devi Agarwala and mutated their names in respect of the same. The petitioners have been residing in the said plots upon payment of tax. Upon threat of utilisation of their land by the Government and demolition of existing structures thereon sometime in June, 2018, the petitioners learnt that an area of land measuring 1.37 acres in R.S. plot no. 530 and .38 acres in R.S. plot no. 531 has been acquired vide notification no. 472-L.A. dated 5thFebruary, 1987. The petitioners obtained a copy of notice under section 4(1a) of the West Bengal Land (Requisition and Acquisition) Act, 1948 demonstrating that the plots in question were acquired in terms of the notice under section 3(1) of the Act. But such notice of requisition was not given effect to and the land in question was released. The record of rights is still in the name of the erstwhile owner and the petitioners are in possession

4

of the property till date. Only rent compensation has been paid by the State respondents and compensation is yet to be disbursed. The petitioners have prayed for an order in terms of section 24(2) of The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.

3. Learned counsel for the petitioners has placed reliance on the authority in Pimpri Chinchwad New Township Development Authority v/s. Vishnudev Cooperative Housing Society and Others reported in (2018) 8 Supreme Court Cases 215 and Indore Development Authority v/s. Manoharlal And Others reported in (2020) 8 SCC 129 in support of his contention.

4. Per contra, learned counsels for the State respondents have submitted that the plots in question were acquired under the Act of 1948 and both rent compensation and award have been paid to the land losers. Possession of the plots has been taken under section 3/4 of the Act of 1948 and construction of road has been completed. The petitioners being post vesting purchasers, have no right to challenge the acquisition proceedings. Also, section 24 of the Act of 2013 pertains to the Land Acquisition Act, 1894 and has no manner of application in the present cases. Acquisition proceedings were concluded and possession handed over to the Public Works Department on 10thJuly, 1968. The inordinate delay in approaching this Court has not been explained by the petitioners. Learned counsel has also relied upon the authority in Indore Development Authority (supra)

5

5. I have considered the submission made on behalf of the parties as well as material on record and the law on the point.

6. It is not in dispute that the plots in question were requisitioned under section 3(1) of the West Bengal Land (Requisition and Acquisition) Act, 1948 for the purpose of construction of road and bridge of National Highway 31 of the river Mahananda at Siliguri and notice under section 4(1a) of the Act of 1948 was published on 11thMarch 1987. The petitioners are admittedly subsequent purchasers who purchased the land after publication of the notification under section 4(1a) of the Act of 1948. According to the petitioners, the land was mutated in their names and they are in possession of the land all throughout. The petitioners say that the notice of requisition was not given effect to and the land was ultimately not acquired, thereby resulting in the proceedings being lapsed.

7. The Hon'ble Supreme Court, in the authorities in Shiv Kumar and Another v/s. Union of India and Others reported in (2019) 10 Supreme Court Cases 229, V. Chandrasekaran and Another v/s. Administrative Officer and Others reported in (2012) 12 SCC 133 and Indore Development Authority (supra) has observed that a person who purchases land subsequent to notification issued under section 4(1) of the Land Acquisition Act, 1894 is not competent to challenge the validity of the acquisition proceedings on any ground whatsoever since the sale deed executed in his favour does not confer upon him any title. Such alienation of the property does not bind the State or the beneficiary under the acquisition since the post vesting purchaser does so at his peril and has no authority to challenge the validity of the acquisition

6

proceedings on any ground whatsoever. He can at best claim compensation on the basis of his vendor's title. The same principle is applicable in case of acquisition under the Act of 1948 and the petitioners, admittedly being post vesting purchasers, cannot challenge the acquisition proceedings on any ground.

8. The land under acquisition was admittedly owned by one Vidya Devi. Pursuant to an order of this Court in a writ petition being no. 9860 (W) of 1992 passed on 22ndJanuary, 1993 and modified on 8thJuly, 1994, rent compensation was paid to the affected persons including Vidya Devi along with interest thereon and the erstwhile owner also received LA compensation on 27thJune, 1994. The said owner chose to part with the land subsequent to receipt of compensation in lieu of acquisition of the same. The process of acquisition was complete upon publication of notice under section 4(1a) of the Act and payment of compensation to the erstwhile owner and the land vested absolutely in the Government free from all encumbrances. The petitioners have primarily laid emphasis on the fact that possession of the land was not taken by the Government and the land has been mutated in their favour. The petitioners have relied upon the authority in Pimpri Chinchwad New Township Development Authority (supra) to demonstrate the modalities of taking possession of vested land by the State. The authority deals with taking of possession of acquired land by the State and entitlement of the State to release the land from acquisition proceedings by taking recourse to the provision of section 48 of the Land Acquisition Act, 1894. The said provision deals with withdrawal from acquisition of any land

7

of which possession has not been taken. The said provision can be distinguished from the provision laid down under the Act of 1948 wherein upon publication of notice under section 4(1a) of the Act, the requisitioned land vests absolutely in the Government free from all encumbrances. The question of release from requisition under section 6 of the Act arises when any land requisitioned under section 3 is not acquired. Therefore the ratio decidendi of the authority relied upon by the petitioners is not applicable in the facts and circumstances of the present cases. Moreover, according to the respondents, possession of the land was handed over to the requiring body being the PWD on 10thJuly, 1968. Even at the cost of reiteration, it is recorded that since compensation has been received by the erstwhile owner of the land and the land has been vested in the State, the petitioners being post vesting purchasers are not entitled to challenge the acquisition proceedings on any ground whatsoever. Purchase of vested land does not confer any right, title or interest upon the petitioners and the petitioners may be deemed to be trespassers/illegal occupiers in respect of the same.

9. The petitioners have taken refuge in the authority in Indore Development Authority (supra) in claiming title in respect of the plots in question. The said authority deals with deemed lapse of acquisition proceedings under the Land Acquisition Act, 1894 and section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The Act of 2013 deals with lapse of acquisition proceedings under the Act of 1894 and has no manner of application in acquisition proceedings under the Act of 1948. Even under section 24(2) of

8

the Act of 2013, the acquisition proceedings shall be deemed to have lapsed if physical possession of the land has not been taken or compensation not paid in the event award under section 11 of the Act of 1894 has been made 5 years or more prior to the commencement of this Act. The twin requirements in this provision are possession of the acquired land being taken and compensation being paid. If possession is taken but compensation not paid there would be no lapse. Similarly, if compensation is paid and possession not taken, there would be no lapse. The requirements are cumulative and conjunctive in nature.

10. In the case in hand, since compensation was paid to the erstwhile owner Vidya Devi, the acquisition proceedings shall not lapse even in the event of not taking possession of the acquired land. Therefore the authority in Indore Development Authority (supra) does not come to the aid of the petitioners herein.

11. Acquisition proceedings was complete upon publication of notice under section 4(1a) of the Act of 1948 in the official gazette and compensation for the same has been disbursed in favour of the erstwhile owner. Therefore the question of release of the land from requisition does not arise. Mere recording of the petitioners' names in the record of rights or omission to record the plots in question in favour of the State does not ipso facto confer any right, title or interest upon the petitioners in respect thereof.

12. Last but not the least, learned counsels for the respondents have drawn the attention of the Court to the inordinate and unexplained delay made by the

9

petitioners in approaching the Court. According to the petitioners, they learnt about the requisition and acquisition upon obtaining a copy of notice under section 4(1a) of the Act of 1948 sometime in June, 2018 when the Government authorities threatened to demolish the existing structures on their land for utilisation of the land. The writ petitions being filed soon thereafter, there was no delay on the part of the petitioners in approaching the Court.

13. In the light of the discussion made hereinabove, this Court is of the view that the writ petitions are devoid of any merit and are liable to be dismissed.

14. Accordingly, the writ petitions are dismissed.

15. There shall however be no order as to costs.

16. Since no affidavit is invited, the allegations contained in the writ petitions are deemed not to be admitted.

17. Urgent certified website copies of this judgment, if applied for, be supplied to the parties expeditiously on compliance with the usual formalities.

(Suvra Ghosh, J)