RAVI DAS v. STATE OF UTTARAKHAND
Manoj Kumar Tiwari, J.:— Heard learned counsel for the parties.
2. Petitioner's family is affected by Tehri Dam Project, and according to petitioner, he is eligible for allotment of a residential plot under the Rehabilitation Policy. Petitioner's father had applied for allotment of residential plot, however, his application was rejected by Grievance Redressal Cell, vide order dated 03.08.2009.
3. Petitioner filed an application dated 03.04.2017 seeking review of the order passed by Grievance Redressal Cell stating that due to illness of his father, review could not be filed earlier. It was contended by petitioner in his review application that application of his father for allotment of residential plot was wrongly rejected, as residential plot was never allotted to him; while, under the Policy, he was entitled for allotment.
4. Petitioner has sought a direction to the Competent Authority to take decision in the review application.
5. It is not in dispute that Grievance Redressal Cell was constituted in terms of an interim order dated 24.04.2007 passed by Hon'ble Supreme Court in an SLP, and upon disposal of SLP, in which the interim order was passed, Grievance Redressal Cell ceased to exist.
6. Learned counsel for petitioner admits that Grievance Redressal Cell does not exist anymore. He, however, contends that Director, Rehabilitation, Tehri Dam Project can review the order passed by Grievance Redressal Cell.
7. Learned counsel for respondent no. 3, on the other hand, contended that in the absence of any express power given to Grievance Redressal Cell to review its order, the Cell cannot review its order.
8. It is further contended that Director cannot review the order of Grievance Redressal Cell.
9. This Court finds substance in the contention raised by learned counsel for respondent no. 3.
10. Review is creature of statute, and in the absence of enabling provision in the statute itself, no authority can review its order.
11. In such view of the matter, the relief, as claimed in the writ petition, cannot be granted.
12. The writ petition is thus dismissed. However, petitioner shall be at liberty to challenge the order passed by Grievance Redressal Cell on 03.08.2009 before appropriate forum. He shall also be at liberty to claim benefit of Section 14 of Limitation Act.