IN RE FELLING OF TREES IN AAREY FOREST (MAHARASHTRA)

Supreme Court Of India
Apr 17, 2023
Smart Summary (Beta)

Factual and Procedural Background

Mumbai Metro Rail Corporation Limited (MMRCL) sought clarification of the Supreme Court’s earlier order dated 29 November 2022, which had modified a status-quo direction and permitted MMRCL to approach the Tree Authority solely for permission to fell 84 trees required for construction of a ramp at the Aarey Colony car shed site (approximately 33 hectares) on Mumbai Metro Line-3.

Following that order:

  • MMRCL initially applied on 19 December 2022 to fell exactly 84 trees.
  • On 2 January 2023, without approaching the Supreme Court, it sought permission to cut 185 trees (124 to be felled and 53 to be transplanted).
  • The Superintendent of Gardens issued a public notice on 12 January 2023 reflecting the higher number.
  • The Tree Authority granted permission on 15 March 2023 for felling 124 trees and transplanting 53, with a compensatory plantation requirement of 1,533 trees.
  • Public-interest litigations were filed in the Bombay High Court, which—recognising that the Supreme Court had limited permission to 84 trees—directed that no trees be felled beyond that number until clarification was obtained.

MMRCL therefore filed the present application for clarification before the Supreme Court.

Legal Issues Presented

  1. Whether the Supreme Court’s order dated 29 November 2022 could be interpreted to allow MMRCL to seek approval for felling/transplanting more than 84 trees without prior leave of the Court.
  2. Whether, in light of subsequent site inspections and changed ground realities, the Court should now permit felling of 124 trees and transplantation of 53 trees as authorised by the Superintendent of Gardens on 15 March 2023.
  3. What remedial or penal measures, if any, should be imposed on MMRCL for acting beyond the scope of the Court’s prior permission.

Arguments of the Parties

MMRCL's Arguments

  • A joint inspection on 19 December 2022—nearly four years after the previous survey—revealed that some trees were missing, dead, fallen, or newly grown, necessitating the updated figure of 185 affected trees.
  • A compilation of relevant documents was placed before the Supreme Court on 5 April 2023 to substantiate the revised numbers.
  • Preventing consideration of the enlarged tree-felling proposal would frustrate the Supreme Court’s earlier order granting liberty to approach the Tree Authority.

Respondents' Arguments

  • A 2020 survey had already formed the basis of MMRCL’s request to fell exactly 84 trees; therefore, the sudden escalation to 177 trees after the 2022 order was not bona fide.
  • The Supreme Court’s 29 November 2022 order was specific and limited; any divergence required an application to the Court before moving the Tree Authority.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court emphasised that its 29 November 2022 order was passed on MMRCL’s express request concerning only 84 trees. Any requirement to cut additional trees should have been brought before the Court first. By directly seeking permission for 185 trees, MMRCL attempted to “overreach the jurisdiction of this Court.”

Nonetheless, the Court balanced this impropriety against the public interest in timely completion of the Metro project. It noted that:

  • Over 2,000 trees had already been felled for the project in earlier stages.
  • Halting work could stall a significant public infrastructure project.

Accordingly, the Court decided to:

  • Modify its earlier order and allow MMRCL to proceed in accordance with the Superintendent of Gardens’ permission dated 15 March 2023 (124 trees to be felled, 53 to be transplanted).
  • Impose a penalty of INR 10 lakhs on MMRCL for its conduct.
  • Direct the Conservator of Forests to verify compliance with all afforestation and transplantation conditions and submit a status report.
  • Request IIT Bombay to independently verify compliance and report within four weeks, with costs borne by MMRCL.

Holding and Implications

The interlocutory application for clarification is disposed of. The Court permits MMRCL to act on the 15 March 2023 permission for felling/transplanting 177 trees, subject to the monetary penalty and strict monitoring directions.

Implications: The Mumbai Metro Line-3 car shed project may proceed without further delay, but MMRCL faces a financial penalty and enhanced oversight. The decision does not create new precedent on environmental law but reinforces the necessity for parties to seek explicit modification of Supreme Court orders before deviating from them.

Show all summary ...

Dr D.Y. Chandrachud, C.J.:— Mumbai Metro Rail Corporation Limited seeks a clarification of the order of this Court dated 29 November 2022. By the order of this Court, MMRCL was permitted to move the Tree Authority for felling 84 trees. MMRCL submits that 177 trees have to be felled or, as the case may be, transplanted for the Metro Car Shed Land at Aarey Colony admeasuring approximately 33 hectares for Mumbai Metro Line-3. Permission is hence sought to implement the permission which has been granted on 15 March 2023 by the Superintendent of Gardens of the Municipal Corporation of Greater Mumbai for felling 124 trees and transplanting 53 trees.

2. By the order of this Court dated 29 November 2022, an earlier order directing the preservation of the status quo on felling trees was modified, so as to permit MMRCL to move the Tree Authority on its application for felling 84 trees. Following the order of this Court, an application was initially moved on 19 December 2022 for permission to fell 84 trees. On 2 January 2023, MMRCL, however, sought permission to cut 185 trees, without moving this Court.

3. By a communication dated 20 December 2022, the Deputy Superintendent of Gardens intimated the Deputy General Manager (Depot) of MMRCL that the site was jointly inspected by his staff, together with the representatives of MMRCL on 19 December 2022. Following the inspection, the Deputy Superintendent of Gardens sought compliance on the following aspects:

“1. Submit updated proposal for the current status of trees as per a fresh survey.

2. Mention missing/dead/fallen trees and also any new addition to the list of affected trees as a long period has lapsed since the last survey.

3. Number all such trees on the sites with black and white paint;

4. Submit details of land where the trees are to be proposed for transplantation and compensatory plantation.”

4. On 12 January 2023, the Superintendent of Gardens issued a public notice indicating that 185 trees would be affected of which 124 trees would be felled and 53 trees would be transplanted.

5. Since the action proposed was in excess of the 84 trees which were permitted to be felled by the order of this Court, a public interest litigation was moved before the High Court of Judicature at Bombay. The Division Bench, by its order dated 9 March 2023, observed:

“Public Notice has been issued by the Tree Authority. The Petitioner has already raised objection before the Tree Authority. The Petitioner can bring it to the notice of the Tree Authority, the order of the Apex Court. No final order has been passed by the Tree Authority. It is for the Tree Authority to consider whether those trees beyond 84 were shrubs or otherwise.”

6. On 15 March 2023, the Superintendent of Gardens and Tree Officer granted permission for felling 124 trees and transplanting 53 trees, subject to the condition that 1533 trees would be planted on the property. This led to the institution of another public interest litigation before the High Court. The Division Bench, by its order dated 31 March 2023, observed and, in our view, correctly, that this Court had granted permission to move the Tree Authority only to the extent of 84 trees. Hence, the permission which was granted in respect of 177 trees was beyond the permission granted by this Court on 29 November 2022. The High Court held that propriety would require that trees shall not be felled in pursuance of the order dated 15 March 2023 until a clarification was sought from this Court. It is in view of the above factual background, that the application for clarification has been filed by MMRCL.

7. We have heard Mr. Tushar Mehta, Solicitor General appearing on behalf of MMRCL, Mr. Dhruv Mehta, senior counsel appearing on behalf of the Municipal Corporation, and Mr. C U Singh and Mr. Gopal Sankaranarayanan, senior counsel appearing on behalf of the respondents.

8. At the outset, the Court must take notice of the fact that when the order dated 29 November 2022 was passed, it was on the specific request of MMRCL that it should be permitted to pursue its application before the Tree Authority for permission to fell 84 trees for the purpose of the work of the ramp. The Court modified the earlier order of status quo which held the field, to the above extent. If the number of trees that are required to be felled was in excess of the permission which was granted by this Court, to move the Tree Authority to fell 84 trees, propriety required that an application had to be moved before this Court for its permission and for modification of its order dated 29 November 2022. Instead, it appears from the record that though initially the application was made for felling 84 trees, subsequently, a stand was adopted that actual number of trees would be in excess of what was originally envisaged.

9. As a matter of fact, it would be necessary to refer to the affidavit which was filed by the Chief Project Manager of MMRCL before the High Court of Judicature at Bombay in which the following averments were incorporated:

“24) In the aforesaid and such other relevant background of facts, in the humble submission of this Respondent, the number of trees that are required to be felled is an aspect which is incidental to the proposal which is pending for consideration before the first Respondent in respect of which the Hon'ble Supreme Court has granted liberty to the present Respondent to pursue, which is being done by the present Respondent. I therefore say that not permitting the answering Respondents to prosecute the present application in issue covering more number of trees over and above the number of trees incidentally mentioned in the aforesaid order of the Hon'ble Supreme court, in fact would amount to frustrating the said order and/or preventing its implementation in its true letter and spirit.

*********

26) I hasten to state that if the contention of the Petitioner is accepted that will in fact amount to causing impediment in the effective implementation of the order of the Hon'ble Supreme Court. At this juncture, it also will be apposite to consider the well settled principle of law that the Judgment of the Hon'ble Supreme Court and/or of this Hon'ble Court cannot be read as a statute. I say that the Petitioner wants this Hon'ble Court to read the order of the Hon'ble Supreme Court as a statute, which is impermissible.”

10. The above averments in the affidavit which was filed by MMRCL indicate that it was well aware of the fact that the order of this Court continued to operate. MMRCL sought to justify its application for felling of trees in excess of what was permitted by the specific directions of this Court. Such an exercise was clearly not contemplated in the order of this Court. We are constrained to observe that MMRCL has made an attempt to overreach the jurisdiction of this Court.

11. The issue which, however, needs to be considered in the application for clarification is whether permission should be granted in terms of the order which has been passed by the Superintendent of Gardens.

12. In the IA for clarification, it has been submitted that subsequent to the order of 29 November 2022, a joint inspection took place on 19 December 2022 between the officers of the Municipal Corporation and MMRCL since a period of approximately three years and ten months covering four monsoon seasons had elapsed from the date of the previous inspection which took place on 20 March 2019. It has been stated that in the course of the joint inspection, it was found that some trees were “missing/dead/fallen” and additional plants and trees had grown since the date of the previous inspection. Hence, it has been sought to be urged that the updated number of affected trees were estimated at 185, pursuant to which a public notice notice was issued by the Tree Authority on 12 January 2023.

13. The Solicitor General, while adverting to the contents of the IA, also submitted that a compilation of relevant documents was placed on the record of this Court on 5 April 2023.

14. On the other hand, it has been submitted by Mr. C U Singh and Mr. Gopal Sankaranarayanan that a survey was conducted in 2020 and, as a matter of fact, it was based on the survey that MMRCL had sought permission to prune a certain number of trees and to fell 84 trees. Senior counsel submitted that this Court permitted MMRCL to move the Tree Authority specifically with reference to the proposal for 84 trees. In other words, it has been urged before this Court that the fresh proposal which was made before the Tree Authority after the order of this Court dated 29 November 2022 was clearly not bona fide having due regard to the events which had transpired, resulting in the order of this Court.

15. It was improper on the part of MMRCL to move the Tree Authority for the felling of any trees in excess of 84 trees. If circumstances had transpired which led to a variation in the number of trees to be cut, the only correct course of action would have been to move this Court. We are, hence, of the view that it would be necessary for the Court to penalize MMRCL for its conduct. Having said that, the issue is as to whether the permission which has been granted on 15 March 2023 should be stayed by the Court, at the present stage. Any such direction will have the consequences of bringing the public project to a standstill. Such a course of action would not be desirable. As the Court noted in its previous order, substantial steps have already been taken by felling over 2000 trees for the purpose of the project. In this backdrop, we modify the previous order by permitting MMRCL to act in compliance with the order dated 15 March 2023. However, this shall be subject to the following directions:

(i) MMRCL shall, within a period of two weeks, deposit an amount of Rupees Ten Lakhs with the Conservator of Forests;

(ii) The Conservator of Forests shall ensure that all directions which have been contained in the previous orders of the Tree Authority for afforestation have been duly complied with;

(iii) The Conservator of Forests shall submit a report before this Court indicating the status of compliance in regard to the directions which have been issued up-to-date for afforestation and for transplantation of trees; and

(iv) In order to enable this Court to have objective assistance in regard to the compliance of the directions for afforestation, we request the Director of IIT Bombay to depute a team for the purpose of verifying compliance. A report shall accordingly be submitted before this Court within a period of four weeks. The costs, charges and expenses payable shall be borne by MMRCL.

16. The IA is accordingly disposed of.