THE STATE OF HIMACHAL PRADESH v. RAJIV

Supreme Court Of India
Feb 24, 2023
Smart Summary (Beta)

Supreme Court of India — Civil Appeal (2023)

Factual and Procedural Background

The State of Himachal Pradesh utilised portions of the respondents’ land in 1996 for construction of the Banuti – Pahal road in District Shimla. A notification under Section 4 of the Land Acquisition Act, 1894 was issued on 17 May 1996 but subsequently allowed to lapse; no compensation was ever paid. In 2016, two decades later, the landowners filed CWP No. 771 of 2016 before the High Court seeking directions for acquisition, compensation, or return of possession. The State contended that the land had been voluntarily given without claim for compensation.

The learned Single Judge allowed the writ petition and directed the State to initiate acquisition proceedings. The State filed a Letters Patent Appeal (LPA) with a delay of 354 days. The Division Bench refused to condone the delay, effectively dismissing the LPA. The State appealed to the Supreme Court, which, instead of remanding, decided to examine the merits of the Single Judge’s order.

Legal Issues Presented

  1. Whether the landowners’ writ petition filed after 21 years was barred by delay and laches, thereby precluding relief.
  2. Whether, in the absence of written consent, the State could retain private land used for a public road without paying compensation under the Land Acquisition Act, 1894.
  3. If compensation was payable, what valuation date, statutory benefits, and interest, if any, should apply.

Arguments of the Parties

Appellant (State of Himachal Pradesh)

  • The writ petition was filed after an unexplained delay of 21 years; the Single Judge erred in granting relief despite laches.
  • The road was constructed with the landowners’ consent and on their request, coupled with an understanding that no compensation would be claimed; although no written document existed, this barred subsequent claims.

Respondents (Original Writ Petitioners)

  • No evidence existed of any written consent to relinquish compensation rights.
  • The 1996 Section 4 notification lapsed without acquisition; the State neither initiated fresh proceedings nor paid compensation.
  • The State cannot evade its constitutional obligation to pay compensation merely by citing delay; reliance placed on Sukh Dutt Ratra v. State of Himachal Pradesh, (2022) 7 SCC 505.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sukh Dutt Ratra v. State of Himachal Pradesh, (2022) 7 SCC 505 The State cannot retain private property without paying compensation; absence of written consent entitles landowners to compensation notwithstanding delay. Relied upon to affirm that delay/laches do not extinguish the owners’ right to compensation where the State has expropriated land without statutory acquisition.

Court's Reasoning and Analysis

The Supreme Court noted that the State’s sole defence was delay and alleged oral consent. It found no written evidence indicating voluntary relinquishment of compensation. The Court reasoned that:

  • The initial Section 4 notification of 17 May 1996 evidenced the State’s intent to acquire; allowing it to lapse did not legitimise continued occupation without compensation.
  • Applying the principle in Sukh Dutt Ratra, constitutional protection of property under Article 300-A requires payment of just compensation irrespective of delay.
  • To balance equities and account for the petitioners’ 20-year delay in approaching the court, the Court exercised powers under Articles 136 and 142 to:
    • Treat 17 May 1996 as the “deemed date of acquisition”.
    • Direct compensation based on market value as on that date, with all statutory benefits under the 1894 Act, except interest for the period between 17 May 1996 and the date of filing of the writ petition.

Holding and Implications

APPEAL ALLOWED / DISPOSED OF.

The Court directed the State to calculate compensation on the basis of the 17 May 1996 market value, grant all statutory benefits (excluding interest for the 20-year period of laches), and complete the entire process—including evidentiary hearing and payment—within six months. The decision reinforces that the State cannot avoid compensating landowners for unauthorised occupation merely by pleading delay, while also recognising equitable limitations on interest where claimants sleep over their rights. No new precedent was expressly set, but the ruling follows and applies Sukh Dutt Ratra to similar factual circumstances.

Show all summary ...

M.R. Shah, J.:— Feeling aggrieved and dissatisfied with the impugned judgment and order dated 01.10.2020 passed by the High Court of Himachal Pradesh in CMP (M) No. 1375 of 2019 in LPA No. 50 of 2020 by which the Division Bench of the High Court has refused to condone the delay in preferring the LPA against the judgment and order passed by the learned Single Judge passed in CWP No. 771 of 2016, the State of Himachal Pradesh has preferred the present appeal.

2. Though the present appeal is against the impugned order passed by the Division Bench of the High Court refusing to condone the delay in preferring the LPA, instead of remanding the matter to the Division Bench to decide the appeal on merits and to consider the legality and validity of the judgment and order passed by the Hon'ble Judge, we have heard the learned counsel appearing on behalf of the respective parties on merits against the judgment and order passed by the learned Single Judge.

3. That the respondents herein - original writ petitioners filed the writ petition before the learned Single Judge of the High Court being CWP No. 771 of 2016 and prayed for the following reliefs:

“(i) That the respondents may be directed to produce entire record in connection with construction work of road from village Banuti to village Loharb in Tehsil and District Shimla along with entire record of the remaining portion from Loharb to Mauja Pahal Tehsil Sunni showing the process and proceeding which were started for acquisition of land and for payment of amount of compensation.

(ii) That the respondent may be directed not to deprive the petitioners of their property without adopting due process of law and that they should act in accordance with law and make payment of amount of compensation as per provision law.

(iii) That in case the respondents are, not ready and willing to start and complete acquisition proceeding and make payment of amount of compensation in that event they may be directed to hand over the physical possession of the land in question to the petitioner and also they may be held liable to pay use and occupation charges from the period from 1996 to date.

(iv) Any other suitable relief as consider just and proper under the facts and circumstances of the petition may kindly be granted to petitioners.”

4. It was the case on behalf of the original writ petitioners that the land in question was utilized by the State for the construction of Banuti to Pahal Road as far as back in the year 1996, however, till date, no compensation in view of the same has been paid to them. The petition was opposed by the State by filing a reply contending inter alia that at the time when the road was constructed through the land of the writ petitioners, it was on their request and on the condition that they will not claim any compensation. It was submitted that however at that time no written document was executed in this respect. It was submitted in the reply that due to this reason the construction work of the road was completed without acquisition proceedings by the State Government. It was also submitted that the road was constructed on the demand of public of the area including the writ petitioners. It was submitted that had there been any truth in the plea of the writ petitioners, the writ petitioners would have raised the objection during the long period of 20 years.

5. Having heard learned counsel appearing on behalf of the original writ petitioners as well as the State and taking into consideration the fact that some portion of the land of the writ petitioners has been utilized for the purpose of construction of the road and no compensation has been paid and the land has been used without acquiring the land under the provisions of the Land Acquisition Act, 1894 (hereinafter referred to as ‘the Act, 1894’), the learned Single Judge allowed the writ petition and directed the appellants to initiate the process for acquisition of the land of the writ petitioners in accordance with law.

6. Feeling aggrieved and dissatisfied with the judgment and order passed by the learned Single Judge, the State preferred the Letters Patent Appeal before the Division Bench of the High Court allowing the delay of 354 days in preferring the LPA. By the impugned order the Division Bench of the High Court has refused to condone the delay and consequently has dismissed the LPA on the ground of limitation. Hence, the present appeal.

7. Shri Abhimanyu Jhamba, learned counsel appearing on behalf of the State has vehemently submitted that in the facts and circumstances of the case, the learned Single Judge has materially erred in directing to initiate the process for acquisition of the land of the original writ petitioners in a writ petition which was filed after a period of 21 years from the date of the use of the land in question which was used for the construction of road.

8. It is submitted that before the learned Single Judge it was the specific case on behalf of the State that the land was used with the consent of the original writ petitioners and the same was done on the request of the writ petitioners and with condition that they will not claim compensation for the same.

9. Thus, the impugned judgment and order passed by the learned Single Judge has been assailed mainly on the ground of delay and laches.

10. Present appeal is vehemently opposed by Ms. Radhika Gautam, learned counsel appearing on behalf of the original writ petitioners.

11. It is submitted that nothing is on record that at the relevant time the original writ petitioners consented for the use of their land for construction of road without claiming compensation for the same.

12. It is vehemently submitted that as such initially a notification under Section 4 of the Act, 1894 was issued for acquisition of the land at Village Tikkari on 17.05.1996, however the notification so issued under Section 4 of the Act, 1894 was permitted to lapse.

13. It is submitted that thereafter neither the fresh acquisition proceedings were initiated nor even the compensation with respect to the land used for construction of road has been paid.

14. It is submitted that the State on the ground of delay and laches cannot evade its legal responsibility towards those from whom private property has been expropriated. Reliance is placed upon the recent decision of this Court in the case of Sukh Dutt Ratra v. State of Himachal Pradesh, (2022) 7 SCC 505.

15. Relying upon the aforesaid decision, it is further submitted that as observed and held by this Court in the said decision in absence of written consent to voluntarily give up their land, the land owners are entitled to the compensation in terms of law.

16. Having heard learned counsel appearing for the respective parties and in the facts and circumstances of the case and when the writ petition and the claim of the original writ petitioners to claim the compensation for the land used for construction of the road has been opposed by the State solely on the ground of delay and laches, we are of the opinion that on the certain conditions which shall be considered herein below the original writ petitioners - owners of the land used by the State for construction of the road shall be entitled to the compensation for their lands which have been used by the State without acquisition under the Act, 1894.

17. At this stage, it is required to be noted that in the present case as such initially the Notification under Section 4 was issued for acquisition of the land at Village Tikkari on 17.05.1996. However thereafter the notification so issued under Section 4 of the Act, 1894 was permitted to lapse. Therefore, 17.05.1996 can be directed to be treated as a deemed acquisition on that day and the original landowners may be awarded the compensation considering the market price as on 17.05.1996, however with all other statutory benefits excluding the interest from 17.05.1996 till the writ petition was filed before the High Court. If the aforesaid order is passed in exercise of this Court's extra ordinary jurisdiction under Articles 136 & 142 of the Constitution, the same can be said to be just and proper and doing the complete justice between the parties.

18. In view of the above and for the reasons stated above, present appeal stands disposed of by directing that 17.05.1996 be treated as the deemed date of acquisition under Section 4 of the Act, 1894 and the original owners/writ petitioners shall be entitled to the compensation considering the market price of the land in question used by the State for construction of the road as on 17.05.1996. However, considering the fact that there was a huge delay of 20 years in filing the writ petition before the High Court, we direct that though the original writ petitioners shall be entitled to all the statutory benefits which may be available under the Act, 1894 from 17.05.1996, however they shall not be entitled to any interest under the Act, 1894 from 17.05.1996 to the date of filing of the writ petition.

19. Now the State/appropriate authority to calculate the amount of compensation as above after giving an opportunity to the original writ petitioners to lead the evidence on the market price as on 17.05.1996 and thereafter to make the payment of compensation as above within a period of 2 months from the date of actual calculation of the amount of compensation. However, the entire exercise shall be completed within a period of six months from today.

20. Present appeal stands allowed/disposed of in terms of the above.

21. However, in the facts and circumstances of the case there shall be no order as to costs.