NIKHIL KUMAR GARG & ANR. v. GARDENVIEW ABODE PRIVATE LIMITED

National Consumer Disputes Redressal Commission
Jan 31, 2023
Smart Summary (Beta)

Summary: National Consumer Disputes Redressal Commission — Consumer Case No. 344 of 2020

Factual and Procedural Background

This matter was a consumer complaint dated 31 January 2023 filed by Nikhil Kumar Garg and Nidhi Tayal (the "Complainants") under Section 21 read with Section 12(1)(a) of the Consumer Protection Act, 1986 against M/s Gardenview Abode Pvt. Ltd. (the "Opposite Party" / developer). The Complainants jointly booked a dwelling unit in the project "Mantri Blossom" at Lalbagh Fort Road, Sudhama Nagar, Bangalore and were allotted unit no. D-1003, 10th Floor, Building D, with a stated super built-up area of 2,700 sq. ft. A Construction Agreement dated 29.06.2016 was executed between the parties.

The Complainants alleged that possession was promised in November 2018 but that the Opposite Party failed to complete construction and deliver possession, resulting in delay. The Complainants claimed to have paid Rs. 2,81,23,870 and to have taken a home loan from ICICI Bank for Rs. 2,40,00,000; they also referred to a Memorandum of Understanding dated 12.06.2016 providing for no EMI till possession. The Complainants sought a 100% refund of amounts paid with penal interest, compensation, and litigation costs.

The Opposite Party filed a written version raising maintainability and other objections, and affidavits in evidence were filed by representatives for both parties. The Commission heard counsel, considered pleadings, affidavits and written arguments, and issued a final order on 31 January 2023.

Legal Issues Presented

  1. Whether the Complainants qualify as "consumers" under Section 2(1)(d) of the Consumer Protection Act, 1986, given the Opposite Party's contention that the unit was purchased for investment/ resale (strategic investor).
  2. Whether the delay in delivery of possession (possession promised November 2018) entitles the Complainants to a refund of amounts paid and/or compensation.
  3. Whether the Buy-Back Agreement or the existence of an arbitration clause precludes the Commission from exercising jurisdiction or requires reference to arbitration.
  4. Whether the contractual clause (Clause 14.5) limiting delayed compensation to Rs. 3 per sq. ft. per month, and other one-sided terms in the construction agreement, are enforceable.
  5. Whether the Opposite Party's plea of force majeure and other reasons (demonetisation, delay in approvals, COVID-19 lockdown, labour/material shortages, RERA extension) justify the delay and absolve the Opposite Party of liability.
  6. Whether the dispute is purely civil/commercial and should be adjudicated by a civil court or other forum (including NCLT or arbitration) rather than the Consumer Commission.

Arguments of the Parties

Complainants' Arguments

  • Possession was contractually to be delivered by 30.11.2018 (Clause 6.1 and Annexure B1), but the Opposite Party failed to deliver despite receipt of substantial payments (claimed total paid: Rs. 2,81,23,870).
  • The Opposite Party failed to provide any valid reason or force majeure condition responsible for the delay in handing over possession.
  • Reliefs sought included 100% refund with penal interest, compensation for mental agony, and litigation costs.

Opposite Party's Arguments

  • The Complainants are not "consumers" because the unit was purchased for investment purposes and the Complainants allegedly intended to resell (strategic investors).
  • Complainants should have invoked the arbitration clause contained in the Agreement for Construction.
  • The dispute is civil/commercial in nature and requires a full trial before a civil court; maintainability of the complaint is contested.
  • The parties entered into an Agreement for Buy Back (dated 12.07.2016) after the sale and construction agreements.
  • Complainants allegedly concealed material facts including pending litigation before NCLT, Bengaluru, and receipt of Rs. 50,13,534 under a pre-EMI clause.
  • The Opposite Party asserted the basic cost and allotment details (basic cost Rs. 2,70,19,020; allotment on 12.05.2016).
  • The Opposite Party contended the delay arose due to circumstances beyond its control: force majeure reasons such as demonetisation, delay in sanctions/approvals by municipal/government departments, adverse market conditions, COVID-19 lockdown, scarcity of labour and material; RERA had granted time up to 19.09.2021 (or referenced time extensions).
  • The Complainants allegedly participated as investors in an assured-return scheme (purchase of a unit for Rs. 29,64,115 for assured return Rs. 59,28,230 by 12.06.2019), and another refund case (CC/474/2020) was pending before the Commission, supporting the strategic investor contention.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Kolkata West International City Pvt. Ltd. v. Devasis Rudra, C.A. No. 3182 of 2019 (decided 25.03.2019) — II (2019) CPJ 29 SC It is manifestly unreasonable to require a buyer to wait indefinitely for possession; a buyer cannot be expected to wait beyond a reasonable period (illustrative mention of seven years as unreasonable). The Commission applied this principle to conclude that the Complainants could not be made to wait indefinitely after the promised possession date (November 2018) and that prolonged delay justified relief in the form of refund.
Pioneer Urban Land & Infra Ltd. v. Govindan Raghavan, C.A. No. 12238 of 2018 (decided 02.04.2019) Contractual terms in flat-purchase agreements that are one-sided, unfair and adopted by the builder may constitute an unfair trade practice and are not final and binding; purchasers not compelled to accept such terms. The Commission relied on this decision to hold that one-sided terms (including restrictive compensation clauses) in the construction agreement are not enforceable against the Complainants.
Ireo Grace Realtech Pvt. Ltd. v. Abhishek Khanna & Ors., Civil Appeal No. 5785 of 2019 (decided 11.01.2021) Incorporation of one-sided and unreasonable clauses in apartment buyers' agreements constitutes an unfair trade practice under Section 2(1)(r) of the Consumer Protection Act; developers cannot compel buyers to be bound by such terms. The Court reproduced and relied on this passage to support the conclusion that the construction agreement's one-sided terms (e.g., harsh interest for non-payment vs. minimal compensation for delay) are unenforceable and fall within unfair trade practice doctrine.
Pioneer Urban Land & Infrastructure Ltd. v. Geetu Gidwani Verma & Anr., Civil Appeal No. 1677 of 2019 (decided 02.04.2019) Reinforces the principle that ex facie one-sided contractual terms are unfair and may constitute unfair trade practice; flat purchasers may lack meaningful choice to alter such contracts. The Commission cited this decision along with others to discredit the Opposite Party's reliance on contractual limitations of liability and compensation caps in the construction agreement.
Kavita Ahuja v. Shipra Estates, III (2016) CPJ 31 (NCDRC) Onus of establishing that a complainant was dealing in real estate (i.e., in the purchase and sale of properties in the ordinary course of business for profit) shifts to the opposite party; documentary proof is required to show the complainant's business in real estate. The Commission invoked this decision to reject the Opposite Party's contention that the Complainants were strategic investors engaged in property trading, noting the Opposite Party failed to discharge the onus with documentary evidence.

Court's Reasoning and Analysis

The Commission's analysis proceeded by comparing the contractual promise of possession (possession date: 30.11.2018 as per Clause 6.1/read with Annexure B1) with the actual delay (the project remained incomplete at the time of the Opposite Party's affidavit, with RERA time extensions noted). The Commission observed that more than four years had elapsed since the promised date and relied on Supreme Court authority that a purchaser cannot be made to wait indefinitely.

On the question whether the Complainants were "consumers," the Commission examined the Opposite Party's claim that the Complainants were strategic investors who had entered into a Buy-Back Agreement and other assured-return arrangements. The Commission noted the Buy-Back option was to be exercised after 30 months and that the Complainants did not exercise it. The Commission further held that merely booking two residential flats or the Complainant's foreign residence at a time did not ipso facto establish that their intention was never to occupy or that they were in the business of reselling properties. The Commission relied on the precedent (Kavita Ahuja) that the onus to show that a complainant is engaged in the business of trading in real estate rests on the Opposite Party, which they failed to discharge.

Regarding contractual clauses limiting compensation (Clause 14.5: Rs. 3 per sq.ft. per month), the Commission concluded the construction agreement's terms were one-sided and unfair—illustrated by the asymmetry where allottees faced 1.5% per month (18% p.a.) interest on default while compensation for developer default was capped at an inequitable rate. The Commission relied on Supreme Court decisions (Ireo and Pioneer) to hold such one-sided clauses unenforceable as unfair trade practices.

The Opposite Party's force majeure/other operational justifications (demonetisation, delay in approvals, market conditions, COVID-19 lockdown, RERA extensions) were considered but found not convincing. The Commission noted that these grounds have been rejected in other matters and observed that nothing on the part of the Complainants contributed to the Opposite Party's failure to complete the project within a reasonable time.

On balance, applying the cited authorities and the facts (delayed possession, significant sums paid by the Complainants, absence of convincing documentation proving Complainants were traders/investors), the Commission concluded that the Complainants were entitled to refund and other reliefs.

Holding and Implications

Holding:

  • The Opposite Parties are directed to refund Rs. 2,81,23,870 (Rupees Two Crores Eighty One Lakhs Twenty Three Thousand Eight Hundred Seventy Only) to the Complainants, along with interest at 9% per annum from the respective date of each deposit until realisation, within six weeks from the date of this Order.
  • Any return payments previously made by the Opposite Parties to the Complainants shall be set off against the decretal amount, with the same rate of interest (9% p.a.) on each such returned amount from its respective date.
  • The Opposite Party is directed to pay litigation costs of Rs. 50,000 to the Complainants.
  • In the event of non-compliance, amounts payable shall attract interest at 12% p.a. for the period of non-compliance.
  • Pending applications, if any, stand disposed of.

Implications:

The direct and immediate effect of the Order is that the Opposite Party must refund the full amount paid by the Complainants with interest and pay modest litigation costs, subject to set-off for any prior returns. The decision applies established Supreme Court principles regarding (a) the unreasonableness of indefinite delay in delivery of possession and (b) the unenforceability of one-sided contractual clauses in apartment agreements. The opinion does not state that it establishes a new legal precedent; rather it applies existing authority to the facts of this dispute.

This summary is based exclusively on the text of the provided opinion. No information beyond that opinion has been added or inferred.

Show all summary ...

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

NEW DELHI

CONSUMER CASE NO. 344 OF 2020

1. NIKHIL KUMAR GARG & ANR.

SC 279,SHASHTRI NAGAR,GAZIABAD

201002

U.P ...........Complainant(s) Versus

1. GARDENVIEW ABODE PRIVATE LIMITED

EARLIER KNOWN AS DEVADATTA BUILD TECH

PRIVATE LIMITED AND MANTRI GARDEN HOMES

PRIVATE LIMITED HAVING TIE REGD OFFICE

AT:"MANTRI HOUSE" #41, VITTLA MALYA ROAD, BANGALORE-560001, KARNATAKA ...........Opp.Party(s)

BEFORE:

HON'BLE MR. BINOY KUMAR,PRESIDING MEMBER HON'BLE MR. JUSTICE SUDIP AHLUWALIA,MEMBER

For the Complainant : Mr. Aditya Parolia, Advocate Ms. Sumbul Ismail, Advocate

Ms. Ishita Singh, Advocate.

For the Opp.Party : Mr. Shekhar G. Devasa, Advocate Mr. Thashmitha Muthanna, Advocate

Mr. Shashi Bhushan Nagar, Advocate.

Dated : 31 Jan 2023

ORDER

JUSTICE SUDIP AHLUWALIA, MEMBER

This Consumer Complaint has been filed by Complainants namely Nikhil Kumar Garg and Nidhi Tayal (hereinafter together referred as 'Complainants') under Section 21 r/w section 12(1)(a) of the Consumer Protection Act 1986, against M/s Gardenview Abode Pvt. Ltd., seeking refund of the entire amount collected by the Opposite Party from the Complainants towards consideration of the dwelling Unit along with other ancillary reliefs. The brief facts leading upto the Complaint are that the Complainants made a joint booking in a project being developed by the Opposite Party namely 'Mantri Blossom' situated at Lalbagh Fort Road, Sudhama Nagar, Bangalore (hereinafter referred as 'Project'). They were allotted unit bearing no.-D-1003, 10thFloor, Buiding D, admeasuring a super build up area of 2700 sq. ft. The opposite Party executed the Construction Agreement dated 29.06.2016 with the Complainants. The Complainants averred that sale price of the unit was Rs. 2,61,50,000/- excluding tax and other charges. However, the Opposite Party claimed the basic cost of the Unit to be Rs.2,70,19,020 excluding deposit, statutory and other charges.

2.

1

3. The Complainants have further stated that the Opposite Party promised to deliver the unit in November, 2018.

The Opposite Party, however, failed to complete the construction and deliver possession even after delay of more than one year.

5. The Complainants further submitted that they have taken a home loan from ICICI Bank for Rs.2,40,00,000/- and subsequently entered into a Memorandum of Understanding dated 12.06.2016 stating that there will be no EMI till the possession of the said flat

4.

The Complainants claim to have paid Rs.2,81,23,870 till date. And further submit that the project is still on going and the possession will not be granted in near future. Hence, aggrieved by the delay, the Complainants have filed the present complaint before this Commission with the following prayers -

6.

a. Direct the Opposite Party for an immediate 100% refund of the total amount paid by the complainants for the unit is INR 2,81,23,870 (Rupees Two Crore eighty One Lacs Twenty Three Thousand Eight Hundred and Seventy Only) along with a penal interest of 18% per annum from the date of receipt of each payment; b. Direct the Opposite Party to pay compensation of Rs. 10,00,000/- (Rupees ten Lakhs only) to the complainants for mental agony, harassment, discomfort and undue hardships caused to complainants as a result of the above acts and omissions on the part of the Opposite Party;

c. Direct the Opposite Party to litigation costs to the tune of Rs. 2.00 Lakhs.

7. The Opposite Party has filed its written version and raised the following objections- The Complainants are not 'consumers' as the unit was purchased for investment purposes, for making profit ,and they do not want to take possession of the flat; a.

The Complainants should have invoked the arbitration clause as provided in Agreement of Construction;

b.

The dispute raised by the Complainants is purely civil in nature and a commercial dispute, and the facts in issue require a full-fledged trial before a competent Civil Court for a proper adjudication;

c.

The parties had entered into Agreement for Buy Back Scheme dated 12.07.2016, which was after the Agreement for sale dated 29.06.2016, and the Agreement for Construction dated 29.06.2016;

d.

The Complainants have not disclosed about the litigation between the parties pending before the NCLT, Bengaluru;

e.

The Complainants have suppressed material facts including receipt of amount Rs.50,13,534/- from Opposite Party under the pre EMI clause;

f.

The basic cost of the unit was Rs.2,70,19,020 and Opposite Party had allotted the said flat on 12.05.2016;

g.

The Opposite Party failed to complete the project due to circumstances beyond its control. The Real Estate Regulatory Authority vide its order dated 17.10.2017 for h.

2

approval of the project had granted time upto 19.09.2021. Due to lockdown during Covid-19, works again stopped from February, 2020. The Opposite Party has stated that it is making sincere efforts to complete the project as per the extension of time as granted by the concerned Authorities. The Opposite Party has further stated that the construction of project is substantially complete and it will be delivered as agreed by it before the

RERA.

8. Hence, the Opposite Party contends that the complaint is not maintainable and the same is to be directed to appropriate Forum for a proper adjudication of the dispute.

9. Rejoinder has been filed behalf of the Complainants. The Complainants have further stated that the Opposite Party has failed to provide any reason or force majeure conditions responsible for the delay in handing over of possession.

10. In addition to the objections as stated above, Ld. Counsel for Opposite Party has also argued that Complainants had approached Opposite Party to invest in the project and purchased a unit for an amount Rs.29,64,115/- for a period of 36 months for assured fixed returnable amount of Rs.59,28,230/- at the end of 36 months from date of entire investment i.e. by 12.06.2019. It was further argued that the complainant's another case bearing No. CC/474/2020 for refund is also pending before this Hon'ble Commission. Hence, the Complainants are strategic investors.

11. Affidavit in Evidence has been filed by Mr. Nikhil Kumar Garg on behalf of the complainants. Affidavit in Evidence has been filed by Mr. Girish Gupta H.S. on behalf of the Opposite Party.

12. Heard the Ld. Counsel for the parties. Perused the material available on record and the written arguments filed by both the parties.

13. Ld. Counsel for the Complainants has argued that as per Clause 6.1 read with Annexure B1 enclosed with the Agreement, the possession was to be offered by November, 2018. However the Opposite Party has failed to deliver the possession despite payment of substantial sum of Rs. 2,81,23,870/-.

14. It has not been denied on behalf of the Opposite Party that as per the Agreement/understanding between the Parties, possession of the dwelling Unit was to be delivered to the Complainants by 30.11.2018. In his Affidavit in Evidence, the Authorised Representative of the Opposite Party; Mr. Girish Gupta, HS, has stated that there has been no deliberate delay in completion of the Project by the Opposite Party. In Para 11 of the Affidavit, he has also stated that the delay occurred on account of Force Majeure reasons like demonetisation and delay in sanctions/approvals by the concerned Local Municipal and Government Departments, the circumstances of which are/were beyond the control of the Opposite Party. He has also stated that "market conditions also contributed to the delay which is beyond the control of the Opposite Party". In addition, the delay has been ascribed to lockdown situation due to outbreak of COVID, scarcity of labour and supply of materials to speed-up the construction and completion of the Project. Further, from the Affidavit in Evidence of the said OPW-Mr. Girish Gupta, which is seen to have been attested on 19.2.2022, it transpires that the Project was still not complete, although it had been mentioned in Para 11

3

therein that the Real Estate Regulatory Authority had granted time till 29.9.2021 for completing the same. So, it is more than four years now after expiry of the due date in November, 2018 as promised to the Complainants.

15. In such circumstances, the present case would appear to be squarely covered by the decisions of the Hon'ble Supreme Court in C.A No.3182 of 2019 dated 25.03.2019 "(Kolkata West International City Pvt. Ltd. Versus Devasis Rudra)", and in C.A. No. 12238 of 2018 dated 02.04.2019 "(Pioneer Urban Land & Infra Ltd. versus Govindan Raghavan)", in which it has been observed that a Purchaser/allottee cannot be made to wait for an indefinite time.

16. The Hon'ble Supreme Court in "Kolkata West International City Pvt. Ltd. Vs. Devasis Rudra", II (2019) CPJ 29 SC, decided on 25.03.2019 had observed as hereunder -

"…..It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March, 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period. A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund. In the circumstances, we are of the view that the orders passed by SCDRC and by the NCDRC for refund of moneys were justified…….".

17. Regarding the contention that the Complainants are not 'consumers' since they had entered into a Buy-back Agreement with the Opposite Parties, it may be mentioned that the same Agreement was entered into on 12.7.2016 in which an option was given to the Complainant to return the property in question to the Developer in case they intended to sell the same after a period of 30 months i.e. after the month of January, 2019, in which event they would have been entitled to an amount of Rs. 59,28,230/-, but the sale price would go to the Developer. It is also noteworthy that such option to sell was to have been exercised by the Complainants in 30 months' time. They never exercised such option which itself would indicate that he did not have any intention to sell the said flat.

18. Further, the fact that the Complainants had booked two residential flats would not ipso facto mean that their intention was necessarily to make any strategic profit making investment with a view to sell any unit, from the very time they opted for purchase. There is nothing on record, much less in documents, filed on behalf of the Opposite Parties to show that the Complainants are engaged in the business of buying and selling properties with a view to earn profits therefrom. The fact that at the relevant time the one of the Complainants was based in Singapore, or is subsequently now residing in Ghaziabad cannot ipso facto give rise to any presumption that his intention was never to personally shift into the Apartment in question at Bangalore, at any subsequent stage.

19. As such, the contention of the Opposite Party that the Complainants are not a

"Consumers" within the meaning of Section 2 (1) (d) of the Consumer Protection Act, 1986, in

4

as much as they had booked the property in question for commercial purposes i.e. only for resale, is untenable especially in view of an earlier decision of this Commission in "Kavita Ahuja Vs. Shipra Estates" III (2016) CPJ 31, in which it has been laid down that the onus of establishing that the Complainant was dealing in real estate i.e. in the purchase and sale of plots in his normal course of business to earn profits, shifts upon the Opposite Party, which in the instant case the Opposite Parties have failed to discharge by any documentary evidence in this regard. Therefore, we are of the considered view that the Complainant is a 'Consumer' as defined under Section 2(1)(d) of the Act.

20. The Opposite Parties have also claimed that the Complainants are not entitled to any delayed compensation at the rate claimed by them, but any compensation on that account, if at all awardable, cannot exceed Rs. 3/-per sq.ft. per month as per Clause 14.5 of the Agreement for Construction. A bare perusal of the aforesaid Agreement goes to show that its terms and conditions are wholly one-sided and unfair, considering that in the event of any default in payment of instalments, the Complainants/allottees were liable to pay interest @ 1.5.% per months, which therefore would be 18% p.a. from the due date of payment of instalment. Such inequitable condition in the Agreement is certainly not an enforceable against the Complainants in view of two decisions of the Apex Court in "Ireo Grace Realtech Pvt. Ltd. Vs. Abhishek Khanna & Ors., Civil Appeal No. 5785 of 2019, decided on 11.1.2021" and

"Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan, Civil Appeal No. 12238 of 2018" With "Pioneer Urban Land & Infrastructure Ltd. Vs. Geetu Gidwani Verma & Anr., Civil Appeal No. 1677 of 2019, decided on 2.4.2019"; the relevant portion of the both the judgments are re-produced as below-

"Ireo Grace Realtech Pvt. Ltd. Vs. Abhishek Khanna & Ors.

"19.7 We are of the view that the incorporation of such one-sided and unreasonable clauses in the Apartment Buyer's Agreement constitutes an unfair trade practice under Section 2(1)(r) of the Consumer Protection Act. Even under the 1986 Act, the powers of the consumer fora were in no manner constrained to declare a contractual term as unfair or one-sided as an incident of the power to discontinue unfair or restrictive trade practices. An "unfair contract" has been defined under the 2019 Act, and powers have been conferred on the State Consumer Fora and the National Commission to declare contractual terms which are unfair, as null and void. This is a statutory recognition of a power which was implicit under the 1986 Act.

In view of the above, we hold that the Developer cannot compel the apartment buyers to be bound by the one-sided contractual terms contained in the Apartment Buyer's Agreement."

"Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan

"6.7. A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The

5

contractual terms of the Agreement dated 08.05.2012 are ex-facie one-sided, unfair, and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2 (r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder."

21. The grounds for delay as made out on behalf of the Opposite Parties to make out a case of 'Force Majeure' conditions are also not convincing and the same grounds have been rejected by not only this Commission but even by the Hon'ble Supreme Court of India in innumerable other matters. In any event, nothing on part of the Complainants at any stage contributed to the failure of the Opposite Parties to complete the Project within a reasonable time.

Consequently, the Opposite Parties are directed to refund to the Complainant Rs. 2,81,23,870/- (Rupees Two Crores Eighty One Lakhs Twenty Three Thousand Eight Hundred Seventy Only) alongwith interest @ 9% p.a. from the respective date of each deposit till realisation, within six weeks from the date of passing of this Order.

22.

Any return payments made by the Opposite Parties to the Complainants shall be set-off against the Complainant's decretal amount alongwith, the same rate of interest i.e. 9% p.a. on each such returned amount, if any, from each respective date.

23.

The Opposite Party is also directed to pay to the Complainants Rs. 50,000/- as litigation costs.

24.

25. In the event of non-compliance of this Order, the amounts to be paid shall attract an interest rate of 12% p.a. for the same period.

Pending applications, if any, also stand disposed off.26.

......................

BINOY KUMAR

PRESIDING MEMBER