DELHI DEVELOPMENT AUTHORITY v. RAJ SINGH
Factual and Procedural Background
The Delhi Development Authority (DDA) appealed to the Supreme Court against the judgment dated 27 November 2018 of the Delhi High Court in W.P.(C) No. 10800 of 2016. The High Court had declared that the land acquisition proceedings concerning the respondents’ land had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“2013 Act”) because compensation had not been paid to the landowners.
Before the High Court, the Land Acquisition Collector recorded that possession of the land had been taken on 19 January 2006, yet details regarding payment of compensation were unavailable. The DDA stated it had released Rs 10 crore to the Land & Building Department on 28 August 1990 toward compensation. Relying solely on non-payment to landowners, the High Court allowed the writ petition. The DDA therefore sought relief from the Supreme Court.
Legal Issues Presented
- Whether land acquisition proceedings automatically lapse under Section 24(2) of the 2013 Act when compensation has not been paid to landowners, even though possession of the land was taken by the acquiring authority.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Indore Development Authority v. Manoharlal, (2020) 8 SCC 129 | Interpretation of Section 24 of the 2013 Act: “or” between possession and compensation in Section 24(2) must be read as “nor/and”; deemed lapse occurs only when both (a) possession has not been taken and (b) compensation has not been paid for five years or more before 1-1-2014. | Constituted the binding authority that rendered the High Court’s view unsustainable; Supreme Court applied its ratio to hold that acquisition does not lapse when possession has been taken, irrespective of non-payment of compensation. |
| Pune Municipal Corporation v. Harakchand Misirimal Solanki, (2014) 3 SCC 183 | Earlier interpretation treating non-payment of compensation alone as sufficient for lapse. | Referenced only to note that it was overruled by Indore Development Authority v. Manoharlal; not followed. |
| Sree Balaji Nagar Residential Assn. v. State of T.N., (2015) 3 SCC 353 | Similar earlier view on Section 24(2). | Referenced as overruled; not followed. |
| Indore Development Authority v. Shailendra, (2018) 3 SCC 412 | Contained observations on Section 24 that were subsequently disapproved. | Referenced as not prevailing law after the Constitution Bench decision; not followed. |
Court's Reasoning and Analysis
The Supreme Court, per M.R. Shah J., held that the High Court’s single-factor test—non-payment of compensation—was contrary to the Constitution Bench ruling in Indore Development Authority v. Manoharlal. The Court emphasized the following propositions from that case:
- Section 24(2) causes a deemed lapse only when both possession has not been taken and compensation has not been paid for five years or more prior to 1 January 2014.
- Once possession is taken, the land vests in the State and cannot be divested by Section 24(2).
- Non-payment of compensation alone does not annul the acquisition; at most, it may give rise to a higher-compensation entitlement under the proviso.
Applying these principles, the Court noted that possession of the land had in fact been taken on 19 January 2006. Consequently, the statutory conditions for deemed lapse were not satisfied, irrespective of whether compensation had been directly paid to individual landowners. Therefore, the High Court’s judgment was “unsustainable” and had to be set aside.
Holding and Implications
Appeal Allowed; High Court judgment quashed and original writ petition dismissed.
As a result, the land acquisition proceedings remain valid and effective; the respondents’ claim of lapse under Section 24(2) fails. The decision reiterates and enforces the Constitution Bench ruling in Indore Development Authority v. Manoharlal, but it does not create new precedent beyond affirming that binding interpretation. No costs were awarded.
M.R. Shah, J.:— Feeling aggrieved and dissatisfied with the impugned judgment and order dated 27.11.2018 passed by the High Court of Delhi at New Delhi in Writ Petition (Civil) No. 10800 of 2016 by which the High Court has allowed the said Writ Petition and has declared that the land acquisition proceedings with respect to the land in question under Land Acquisition Act, 1894 is deemed to have lapsed under Subsection (2) of Section 24 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as ‘the Act, 2013’), the Delhi Development Authority has preferred the present appeal.
2. From the impugned judgment and order passed by the High Court it appears that though in the counter affidavit filed before the High Court filed by the Land Acquisition Collector it was stated that the possession was taken on 19.01.2006. However, the details of the payment of compensation are not available with the LAC Branch and therefore it is not possible to state anything about payment of compensation, the High Court has allowed the Writ Petition and has declared that the land acquisition with respect to the land in question is deemed to have lapsed under Sub-section (2) of Section 24 of the Act, 2013 solely on the ground that the amount of compensation was not paid to the land owners.
3. Now it is required to be noted that before the High Court it was stated on behalf of the DDA that it released a sum of Rs. 10 crores to the Land and Building Department way back on 28.08.1990 in respect of the land acquired. Therefore, the High Court has allowed the writ petition and has declared that the acquisition proceedings with respect to the land in question is deemed to have lapsed under sub-section (2) of Section 24 of the Act, 2013 solely on the ground that the compensation was not actually paid to the land owners.
4. The view taken by the High Court is unsustainable in view of the Constitution Bench decision of this Court in the case of Indore Development Authority v. Manoharlal, (2020) 8 SCC 129. In paragraphs 365 and 366, the Constitution Bench of this Court has observed and held as under:—
“365. Resultantly, the decision rendered in Pune Municipal Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3 SCC 183] is hereby overruled and all other decisions in which Pune Municipal Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3 SCC 183] has been followed, are also overruled. The decision in Sree Balaji Nagar Residential Assn. [Sree Balaji Nagar Residential Assn. v. State of T.N., (2015) 3 SCC 353] cannot be said to be laying down good law, is overruled and other decisions following the same are also overruled. In Indore Development Authority v. Shailendra [(2018) 3 SCC 412], the aspect with respect to the proviso to Section 24(2) and whether “or” has to be read as “nor” or as “and” was not placed for consideration. Therefore, that decision too cannot prevail, in the light of the discussion in the present judgment.
366. In view of the aforesaid discussion, we answer the questions as under:
366.1. Under the provisions of Section 24(1)(a) in case the award is not made as on 1-1-2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act.
366.2. In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed.
366.3. The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse.
366.4. The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non-deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Non-deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non-deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act.
366.5. In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non-payment or non-deposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act.
366.6. The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)(b).
366.7. The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2).
366.8. The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1-1-2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years.
366.9. Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not revive stale and time-barred claims and does not reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.”
5. In view of the above, the impugned judgment and order passed by the High Court is unsustainable and deserves to be quashed and set aside and is accordingly quashed and set aside.
6. Present appeal is accordingly allowed.
7. The original writ petition filed by respondent no. 1 herein filed before the High Court being W.P.(C) No. 10800 of 2016 stands dismissed.
8. No costs.