THE EX. ENGINEER, VI... v. NAGORAO GUNDA GAVANE...
Factual and Procedural Background
This opinion concerns multiple Civil Applications filed by the Executive Engineer, Vishnupuri Project Division No.1, Jangamwadi, Nanded, seeking condonation of a delay of 2031 days in instituting appeals arising from impugned awards dated 20.01.2012. The delay in filing these appeals is over six years. The applications state that the delay was due to the time taken to obtain certified copies of the awards, the need for governmental approval and budgetary provisions to pay court fees, and the exhaustion of budgetary allocations for the project. The advocate reportedly paid court fees from an advance fee. The applicants contend that the delay was unintentional and that refusal to condone the delay would cause irreparable loss. The Civil Applications are opposed on the ground that the explanations are insufficient to justify such an inordinate delay.
Legal Issues Presented
- Whether the inordinate delay of over six years in filing the appeals can be condoned on the grounds stated by the applicant, including procedural delays and lack of budgetary provision.
- What constitutes "sufficient cause" for condonation of delay under Section 5 of the Limitation Act, especially in cases involving Government authorities.
- Whether the principles established by the Supreme Court and this Court regarding condonation of delay apply to the facts of these Civil Applications.
Arguments of the Parties
Applicant's Arguments
- The delay in filing appeals was caused by the time taken to obtain certified copies of the awards, which took almost ten months.
- As a Government institution, approval and budgetary sanction were required before filing appeals and paying court fees.
- Requests for funds were made to the Head Office and Government but no response was received, leading to delay.
- The advocate paid court fees from advance fees, indicating efforts to overcome procedural hurdles.
- The project for which land was acquired was old and budgetary allocation was exhausted.
- The delay was unintentional, and refusal to condone delay would cause irreparable loss to the applicants.
Respondents' Arguments
The opinion does not contain a detailed account of the respondents' legal arguments.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Pundlik Jalam Patil (Dead) By Lrs. vs. Executive Engineer, Jalgaon, Medium Project and another, (2008) 17 SCC 448 | Public interest requires avoidance of stale claims and multiplicity of proceedings; delay condonation must not lightly interfere with settled rights, especially when no proper explanation is given. | The Court emphasized that the law of limitation applies equally to Government and citizens; no condonation without proper explanation, especially involving public revenue. |
| Registrar of Companies vs. Rajshree Sugar & Chemicals Ltd. and ors., (2000) 6 SCC 133 | Government must act with reasonable expedition; delay condonation requires more than mere latitude for Government officers. | The Court rejected the excuse of official delay and underscored Government responsibility to avoid negligence. |
| Esha Bhattacharjee vs. Managing Committee of Raghunathpur afar Academy & ors., (2013) 12 SCC 649 | Condonation applications must be drafted with care; courts should not treat delay as trivial nor condone it routinely on subjective grounds. | The Court stressed the need for objective assessment and curbing nonchalant attitudes towards delay. |
| Postmaster General and Ors. vs. Living Media India Limited and anr., (2012) 3 SCC 563 | Government departments cannot claim delay due to bureaucratic procedures; law of limitation binds all equally; condonation is exception, not rule. | The Court refused to condone delay of 427 days by Government department due to lack of acceptable explanation. |
| Basawaraj and anr. vs. Special Land Acquisition Officer, (2013) 14 SCC 81 | Sufficient cause means adequate reason preventing timely approach; negligence or inactivity is no ground for condonation; courts must adhere to statutory provisions. | The Court clarified that condonation without justification violates statutory law and cannot be granted by imposing conditions. |
| State of Maharashtra and ors. vs. Vithu Kalya Govari and ors., (2008) 6 Mh.L.J. 239 | State is not excused from negligence or inaction causing delay; "official hassle" or multi-level approvals do not justify condonation. | The Court held that prejudice to claimants from delay must be considered; onus lies on State to show sufficient cause for delay. |
Court's Reasoning and Analysis
The Court examined the explanations offered for the inordinate delay of over six years in instituting the appeals. It noted the absence of any satisfactory explanation for the ten-month delay in obtaining certified copies of the awards. The claim that budgetary constraints and procedural approvals caused the delay was found insufficient, as Government entities are expected to act with reasonable diligence and cannot rely on bureaucratic hurdles as justification.
The Court relied on established Supreme Court precedents emphasizing that the law of limitation applies equally to Government and citizens, and condonation of delay is an exception requiring a bona fide and sufficient cause. It rejected the applicants' reliance on a prior case where delay was condoned on concession, clarifying such orders do not constitute binding precedent.
The Court highlighted that condoning stale claims and allowing multiplicity of proceedings is contrary to public interest, particularly when settled rights are involved. It further stressed that Government departments have a special obligation to act diligently and cannot expect courts to routinely condone delay due to procedural delays or lack of budgetary sanction.
Applying these principles, the Court concluded that the applicants failed to demonstrate sufficient cause to justify condonation of the extraordinary delay.
Holding and Implications
The Court DISMISSED the Civil Applications seeking condonation of delay.
As a direct consequence, the appeals and applications for stay connected to these proceedings were also disposed of. The decision enforces the principle that Government bodies must adhere to limitation periods and cannot expect leniency without adequate justification. No new precedent was established; the ruling reaffirmed existing legal standards on delay condonation and the responsibilities of Government authorities.
{1}
ca4218.odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD
(1) CIVIL APPLICATION NO.42 OF 2018 IN
FIRST APPEAL ST.NO.36287 OF 2017
The Executive Engineer, Vishnupuri Project Division No.1, Jangamwadi, Nanded Applicant Versus
Kashinath s/o Maroti & others Respondents
WITH
(2) CIVIL APPLICATION NO.43 OF 2018 IN
FIRST APPEAL ST.NO.36294 OF 2017
The Executive Engineer, Vishnupuri Project Division No.1, Jangamwadi, Nanded Applicant Versus
Ahmedsab Abdulsab & others Respondents
WITH
(3) CIVIL APPLICATION NO.44 OF 2018 IN
FIRST APPEAL ST.NO.36296 OF 2017
The Executive Engineer, Vishnupuri Project Division No.1, Jangamwadi, Nanded Applicant Versus
Laxman Gangaji (deceased) through legal heirs & another Respondents
WITH
(4) CIVIL APPLICATION NO.45 OF 2018 IN
FIRST APPEAL ST.NO.36292 OF 2017
The Executive Engineer, Vishnupuri Project Division No.1,
{2}
Jangamwadi, Nanded Applicant Versus
Narayan Madhavrao Wadgaoker & others Respondents
WITH
(5) CIVIL APPLICATION NO.46 OF 2018 IN
FIRST APPEAL ST.NO.36300 OF 2017
The Executive Engineer, Vishnupuri Project Division No.1, Jangamwadi, Nanded Applicant Versus
Ganpat Laxman Vesmode & others Respondents
WITH
(6) CIVIL APPLICATION NO.47 OF 2018 IN
FIRST APPEAL ST.NO.36298 OF 2017
The Executive Engineer, Vishnupuri Project Division No.1, Jangamwadi, Nanded Applicant Versus
Nagorao Gunda Gavane (died), through Lrs & others Respondents Mr.H.M.Shaikh, advocate for applicants.
CORAM : M.S.SONAK, J.
DATE : 11th January, 2018.
P.C. :
1 In all these Civil Applications, a prayer is made to condone delay of 2031 days caused in institution of the appeals.
{3}
2 The reasons stated in the Civil Applications are virtually identical. It is stated that the impugned awards were made on 20.01.2012. The certified copies were applied for almost after ten months i.e. on 12.10.2010 and the same were delivered on 29.10.2012. There is absolutely no explanation as to why it took 10 months to obtain certified copies of the award. Be that as it may. It is further stated in the Civil Applications that since the applicant is a Government Institution, it had to take approval and make budgetary provision to file appeals. It is stated that a request was made for some amount to pay the court fee to file these appeals, to the Head Office as well as the Government. However, there was no response either from the Head Office or from the Government. In the application, it is stated that it is the advocate has paid the court fees from out of advance advocate's fees. There is a further statement that the project, for which the land was required, was old and the budgetary allocation has been exhausted. For all these reasons, it is stated that the delay was unintentional and if delay is not condoned, the applicants will suffer great irreparable loss, which cannot be compensated by any other means. Learned Counsel for the applicants submit that if the delay is not condoned, it will cause problem for future.
3 Aforesaid is the only explanation for condonation of inordinate delay of 2031 days i.e. over six years in the institution of these appeals.
4 Such explanation can hardly constitute any sufficient cause for condonation of delay. There are absolutely no details in the application. In any case, on the ground that the acquiring
{4}
body or the Government had no budgetary provision even to pay the court fees for institution of these appeals, prima facie, is not a ground sufficient to explain inordinate delay of over six years in institution of these appeals.
5 Learned Counsel for the applicant relies upon the decision of this Court in batch of Civil Applications bearing No.10247 of 2016, which came to be disposed of on 11.07.2017. In the said order, at paragraph no.2, it is recorded that the learned Counsel appearing on behalf of original claimants has given no objection to condone the delay. It is, in these circumstances, delay came to be condoned. Such an order, which is made on concession, cannot constitute a precedent.
6 In Pundlik Jalam Patil (Dead) By Lrs. vs. Executive Engineer, Jalgaon, Medium Project and another, (2008) 17 SCC 448, the Hon'ble Supreme Court has held that pursing stale claims and multiplicity of proceedings in no manner subserves public interest. These public interest parameters ought to be kept in mind by the courts while exercising the discretion dealing with the application filed under section 5 of the Limitation Act. Dragging the land-losers to courts of law years after the termination of legal proceedings would not serve any public interest. Settled rights cannot be lightly interfered with by condoning inordinate delay without there being any proper explanation of such delay on the ground of involvement of public revenue. This serves no public interest. Though, the State or its instrumentalities seeking condonation of delay may be entitled to certain amount of latitude but the law of limitation is same for
{5}
citizens and for Governmental authorities. It would be a different matter where the Government makes out a case where public interest was shown to have suffered owing to acts of fraud or collusion on the part of its officers or agents and where the officers were clearly at cross purposes with it. In a given case, if any, such facts are pleaded and proved they cannot be excluded from consideration. In cases with which we are concerned, no such facts have been either pleaded or proved.
7 In Registrar of Companies vs. Rajshree Sugar & Chemicals Ltd. and ors., reported in (2000) 6 SCC 133], the Hon'ble Supreme Court held that though some latitude has to be shown to the Government in deciding the question of delay, that does not give a license to the officers of the Government to shirk their responsibility to act with reasonable expedition.
8 In Esha Bhattacharjee vs. Managing Committee of Raghunathpur afar Academy & ors., (2013) 12 SCC 649], the Hon'ble Supreme Court has held that an application for condonation of delay should be drafted with careful concern and not in a haphazard manner harbouring the notion that the courts are required to condone delay on the bedrock of the principle that adjudication of a lis on merits is seminal to justice dispensation system. Further, the Hon'ble Supreme Court has held that an application for condonation of delay should not be dealt with in a routine manner on the basis of individual philosophy which is basically subjective. The increasing tendency to perceive delay as a non-serious matter and, hence, lackadaisical propensity can be exhibited in a nonchalant manner requires to be curbed, of course,
{6}
within legal parameters.
9 In Postmaster General and Ors. vs. Living Media India Limited and anr., (2012) 3 SCC 563], the Hon'ble Supreme Court declined to condone the delay of 427 days in filing the special leave petition by observing that department cannot take advantage of various earlier decisions where a very liberal approach was adopted when it came to condone delay on the part of Government agencies. The Hon'ble Supreme Court observed that the claim on account of impersonal machinery and inherited bureaucratic methodology of making several notes cannot be accepted in view of the modern technologies being used and available. The law of limitation undoubtedly binds everybody including the Government. It is the right time to inform all the government bodies, their agencies and instrumentalities that unless they have reasonable and acceptable explanation for the delay and there was bona fide effort, there is no need to accept the usual explanation that the file was kept pending for several months/years due to considerable degree of procedural red-tape in the process. The government departments are under a special obligation to ensure that they perform their duties with diligence and commitment. Condonation of delay is an exception and should not be used as an anticipated benefit for government department. The law shelters everyone under the same light and should not be swirled for the benefit of a few. Considering the fact that there was no proper explanation offered by the Department for the delay except mentioning of various dates, the Hon'ble Supreme Court held that, the Department has miserably failed to give any acceptable and cogent reasons sufficient to condone such a huge
{7}
delay.
10 In Basawaraj and anr. vs. Special Land Acquisition Officer, (2013) 14 SCC 81] the Hon'ble Supreme Court went on to observe that the law on the issue can be summarised to the effect that where a case has been presented in the court beyond limitation, the applicant has to explain the court as to what was the "sufficient cause" which means an adequate and enough reason which prevented him to approach the court within limitation. In case a party is found to be negligent, or for want of bona fide on his part in the facts and circumstances of the case, or found to have not acted diligently or remained inactive, there cannot be a justified ground to condone the delay. No court could be justified in condoning such an inordinate delay by imposing any condition whatsoever. The application is to be decided only within the parameters laid down by this Court in regard to the condonation of delay. In case there was no sufficient cause to prevent a litigant to approach the court on time condoning the delay without any justification, putting any condition whatsoever, amounts to passing an order in violation of the statutory provisions and it tantamounts to showing utter disregard to the legislature.
11 The Division Bench of this Court in State of Maharashtra and ors. vs. Vithu Kalya Govari and ors., [2008
(6) Mh.L.J.239] has observed that the State is not expected to be negligent or to take no action for years and let the matters become time barred on account of its negligence and inaction. The usual reason of "official hassle" or "approval at different levels" is hardly
{8}
sufficient to justify condonation of delay of about two years. In law, advantage has accrued to the non-applicants claimants and the same cannot be withdrawn in a mechanical manner and that too without any sufficient cause being shown by the applicants. Despite, awards/judgments of the Courts, which have attained finality, the claimants are not permitted to receive compensation in respect of their lands, which came to be compulsorily acquired, is itself, sufficient prejudice to them. Therefore, before any delay can be condoned and the claimants subjected to further prolonged litigation, the onus to show sufficient cause lies upon the applicant-State.
12 Applying aforesaid principles to the facts of this case, there is no case made out to condone inordinate delay of 2031 days i.e. over six years in institution of these appeals.
13 Civil Applications are, therefore, dismissed. As a consequence, the appeals and applications for stay do not survive and also stand disposed of.
M.S.SONAK
JUDGE
adb/ca4218