Ghanshyam Thakur v. State Of Himachal Pradesh And Others
Sandeep Sharma, J. (Oral):— Petitioner was engaged on daily wage basis as beldar in the year 1998, in the Irrigation and Public Health Department, Division at Karsog, District Mandi, Himachal Pradesh. In the year 2007, services of the petitioner were regularized by the respondent-department in terms of the policy of regularization framed by the Government of Himachal Pradesh. Since, despite there being repeated requests/representations, respondents failed to consider the prayer made on behalf of the petitioner for grant of work charge status in terms of the law laid down by this Court in Rakesh Kumar case, petitioner was compelled to approach erstwhile H.P. State Administrate Tribunal by way of Original Application No. 4019 of 2015, which now stands transferred to this Court and reregistered as CWPOA No. 5660 of 2019, praying therein following reliefs:—
i) That the respondent department may kindly be directed to grant work charge status/Regularization (in terms of the Rakesh Kumar case) w.e.f.1.1.2006 with all consequential benefits and arrear may kindly be ordered to be released in favour of the applicant in time bound manner;
ii) That the respondents department may kindly be directed to re-fix the pay of applicant w.e.f.1.1.2006 and arrear be released in favour of applicant in time bound manner;
2. Respondents in their reply have stated that the petitioner is not entitled for grant of work charge status after completion of 8 years in the light of the judgment rendered by this Court in CWP No. 2735 of 2010, titled as Rakesh Kumar v. State of Himachal Pradesh, decided on 28.07.2010 because in the aforesaid judgment, it has been categorically held that question of conferment of work charge status does not arise in case the establishment ceases to be a work charged establishment.
3. Mr. Sanjeev Sood, learned Additional Advocate General while inviting attention of this Court to the reply filed by the respondents, contends that since work charge establishment ceased to exist on 19.6.2001 for class-III and on 12.12.2005 for class-IV in IPH Department, prayer having been made on behalf of the petitioner cannot be accepted and as such, same be rejected outrightly. Besides above, learned Additional Advocate General contends that the applicant/petitioner was regularized with effect from 10.10.2007 prospectively, whereas he has filed OA No. 9 of 2015 after a lapse of 9 years and as such, his claim being totally time barred deserves to be rejected out rightly.
4. Having heard learned counsel representing the parties and perused the material available on record, this Court finds that though the petitioner stands regularized with effect from10.10.2007 prospectively, but since he had completed 8 years continuous service as on 31.12.2005, he is entitled for grant of work charge status with effect from 1.1.2006. Division Bench of this Court vide judgment dated 10.5.2018 passed in CWP No. 3111 of 2016 titled State of H.P v. Sh. Ashwani Kumar, has categorically held that work charge establishment is not a pre-requisite for conferment of work charge status nor conversion of work charge employees into regular employees would make the existence of such establishment non-existent. Besides above, in the aforesaid judgment Division Bench of this Court has specifically observed that while deciding the issue, it is to be borne in mind that the petitioner are only class-IV worker (Beldars) and the schemes announced by the Government clearly provides that the department concerned should consider the workmen concerned for bringing them on the work charged category and as such, there is an obligation cast upon the department to consider the case of daily waged workman for conferment of daily work charge status on the completion of required number of years in terms of the policy. It is not in dispute that aforesaid judgment rendered by this Court in Ashwani Kumar's case (supra) has attained finality. Moreover, issue/question involved in the case at hand otherwise stands settled in number of cases i.e. CWP No. 4489 of 2009, titled Ravi Kumar v. State of H.P., which was further upheld by Hon'ble Apex Court in Special Leave to Appeal (C) No. 33570/2010 titled State Of H.P v. Pritam Singh and connected matters.
5. Apart from above, judgment rendered in CWP No. 3301/2016, titled Narotam Singh v. HPSEB Ltd. is also based upon the decision rendered by the Hon'ble Apex Court in Bhagwati Prasad v. Delhi State Mineral Development Corporation . (1990) 1 SCC 361, as well as judgment rendered by this Court in CWP No. 9970 of 2012 titled Laxmi Devi v. State of H.P. decided on 26.11.2012.
6. Another objection raised by learned Additional Advocate General with regard to delay and laches deserves outright rejection in the light of the judgment rendered by Division Bench of this Court in CWP No. 2735 of 2010, titled as Rakesh Kumar v. State of H.P. decided on 28 July, 2010, wherein it has been held as under:—
“6. The simple question is whether the delay defeats justice? In analyzing the above issue, it has to be borne in mind that the petitioners are only class-IV workers (Beldars). The schemes announced by the Government clearly provided that the department concerned should consider the workmen concerned for bringing them on the work-charged category. So, there is an obligation cast on the department to consider the cases of the daily waged workmen for conferment of the work-charged status, being on a work-charged establishment, on completion of the required number of years in terms of the policy. At the best, the petitioners can only be denied the interest on the eligible benefits and not the benefits as such, which accrued on them as per the policy and under which policy, the department was found to confer the status, subject to the workmen satisfying the required conditions.”
7. It is quite apparent from the aforesaid exposition of law laid down by the Division Bench of this Court, which has attained finality that once schemes announced by the Government provides for conferment of work charge status of an employee/workman after his/her having completed requisite period, it is the duty of the department to consider the cases of such workmen for conferment of work charge status on completion of required number of years in terms of the policy. Claim of the petitioner for work charge status cannot be defeated on the ground of delay and laches, at best he can be only denied the interest on the eligible benefits and not the benefits as such, which may have accrued to him on account of grant of conferment of work charge status.
8. Consequently, in view of the above, present petition is allowed and respondents are directed to grant work charge status to the petitioner from the date he had completed 8 years of regular service in the department i.e. 1.1.2006 alongwith all consequential benefits. However, it is clarified that petitioner would not be entitled to any interest on the consequential benefits, which he may receive on account of grant of work charge status after completion of eight years.
9. In the aforesaid terms, present petition stands disposed of, so also pending applications, if any.