BIJAY SAIN v. STATE OF WEST BENGAL AND ORS.
High Court at Calcutta — W.P.A. 15475 of 2021 & connected matters (Suvra Ghosh, J.) — Summary
Factual and Procedural Background
Multiple writ petitions (including W.P.A. 15475/2021, 15646/2021, 15649/2021, 15766/2021, 15794/2021, 15713/2021 and 15717/2021) were heard together because they raised similar issues.
The petitioners claim to be recorded owners of portions of R.S. & L.R. plot no. 82 in mouza Alisha, J.L. No. 77, P.S. Burdwan Sadar (Purba Bardhaman), each asserting title and continuous physical possession since dates in the 1980s–1990s and operating small scale businesses thereon.
Earlier land acquisition proceedings under the Land Acquisition Act, 1894 (LA Case No. 2(IV)/2004-2005) were initiated for plot no. 82: notification under section 4 (7 July 2004), declaration under section 6 (published 18 Feb 2005; substance in Form 5B on 14 Mar 2005) and award declared on 13 Mar 2007 in favour of certain vendors. The petitioners allege they had acquired portions of the plot before initiation of acquisition proceedings but were not served notices under sections 9/12 nor paid compensation and that no physical possession was taken in respect of their portions.
The National Highways Authority of India (NHAI) later issued a notification under section 3A of the National Highways Act, 1956 (publication in vernacular newspaper on 20 Sep 2020 and another under section 3A(1) on 26 June 2020) proposing acquisition for widening NH-19. Notices under section 3C(2) were served and objections by the petitioners were heard and rejected on 21 Dec 2020; subsequently, plot no. 82 was excluded in the declaration under section 3D dated 16 Feb 2021. The petitioners submitted representations (including one on 31 Mar 2021) and filed these writ petitions challenging the state of affairs and seeking mandamus reliefs including consideration of their representation, release of their portions from acquisition or fresh acquisition under the 2013 Act with appropriate compensation.
Hearing concluded on 09.09.2022; judgment delivered on 30.09.2022 by Justice Suvra Ghosh.
Legal Issues Presented
- Whether the earlier land acquisition under the Land Acquisition Act, 1894 (LA Case No. 2(IV)/2004-2005) in respect of the petitioners' portions of plot no. 82 is valid or has lapsed — particularly in light of: (a) alleged non-service of notices under sections 9/12, (b) alleged non-payment/tender of compensation, and (c) section 11A of the 1894 Act and section 24(2) of The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the 2013 Act).
- Whether physical possession of the petitioners' portions was taken by the acquiring authority so as to vest title in the State under section 16 of the 1894 Act.
- Whether the petitioners are entitled to compensation under the 2013 Act because (it is alleged) the 1894 proceedings have lapsed.
- Whether the NHAI's later notifications under the National Highways Act, 1956 supersede the earlier State acquisition notifications, and if the petitioners' plot should have been included in the NHAI declaration under section 3D(1).
- Whether the NHAI's action (including a notice under section 26(2) of the Control of National Highways (Land & Traffic) Act, 2002 and a notice dated 12 Jan 2022) can be acted upon against the petitioners pending consideration of their representation.
Arguments of the Parties
Petitioners' Arguments
- The petitioners asserted they are recorded owners of parts of plot no. 82 by purchase or gift long before acquisition proceedings were initiated and they have been in continuous physical possession and conducting business there.
- They contended the 1894 acquisition suffers gross non-compliance with provisions of sections 5A, 9, 16, 31 and 34 and is hit by section 11A of the 1894 Act; no notice under section 12(2) was served and no tender/payment of compensation was made under section 31.
- They argued that, in any event, section 24(2) of the 2013 Act applies (because an award under section 11 was made five or more years before commencement of the 2013 Act but physical possession was not taken and compensation was not paid), so the 1894 proceedings must be deemed to have lapsed and the State must either initiate fresh acquisition under the 2013 Act or release the land.
- They relied upon documentary evidence of mutation, record of rights, dakhilas, panchayat permissions and other communications to show uninterrupted possession; they disputed the State's certificate of possession as not demonstrating actual delivery of possession.
- They sought consideration of their representation dated 31.03.2021 and either release of their portions or acquisition afresh with compensation at current market rates under the 2013 Act.
State Respondents' Arguments
- The State contended no prayer for cancellation of acquisition had been made before it and that the grievance was addressed by a reasoned order passed by the Special Land Acquisition Officer on 11 Feb 2020.
- The State relied on the statutory record: publication of notifications (section 4, section 6), award declared on 13 Mar 2007 and asserted that possession of the land was handed over to the requiring body (Burdwan Development Authority) on 2 Apr 2007; notices under sections 9(3) and 9(4) were served and adequate opportunity of hearing was granted.
- The State submitted that the LA case (2(IV)/2004-2005) is complete and the writ petitions are not maintainable.
National Highways Authority of India (NHAI) / Burdwan Development Authority
- NHAI argued that the petitioners are not owners because the land had already been acquired and was State (Government) land vested in the Burdwan Development Authority; therefore petitioners were not entitled to compensation.
- NHAI explained that their initial section 3A notification (for six-laning NH-19) was subsequently dropped for this parcel at the stage of issuing the section 3D declaration because it was found to be government land recorded in the names of Burdwan Development Authority; NHAI submitted the petitioners did not challenge the section 3D notification.
- Burdwan Development Authority stated it is recorded as owner in the L.R. record of rights and is in possession as requiring body.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| State of Bihar & Others v. Kalyanpur Cement Limited, (2010) 3 SCC 274 | Cited by petitioners (the opinion lists this authority relied upon by petitioners); the specific rule invoked by counsel is not elaborated in the judgment text provided. | The opinion records the citation as relied upon by petitioners but does not describe a direct application of this authority in the court's reasoning. |
| Smt. Bela Das v. Union of India & Ors., W.P. 16237(W) of 2017 (Coordinate Bench order) | Cited by petitioners (High Court order referenced by petitioners); the judgment text does not set out the specific rule relied upon. | The judgment is listed among authorities relied upon by petitioners; the Court noted its existence but did not base a specific legal conclusion solely upon it in the body of reasons. |
| Raghbir Singh Sehrawat v. State of Haryana & Others, (2012) 1 SCC 792 | Establishes that self-serving documents showing delivery of possession cannot be the sole basis for finding that actual possession was taken by the acquiring body. | The Court applied this principle to hold that, where there is no evidence of actual taking of possession and documents are self-serving, possession by the acquiring body cannot be accepted as having been taken. |
| Ferro Alloys Corporation Ltd. v. Union of India, AIR 1999 SC 1236 | Cited by petitioners (listed among authorities relied upon); the judgment text does not detail the specific principle relied upon. | Listed in the petitioners' reliance list; the Court's written reasons do not attribute a particular point of law to this authority in the portions reproduced. |
| K. Lubna & Others v. Beevi & Others, (2020) 2 SCC 524 | Cited by petitioners (listed); the judgment text does not explain the specific principle invoked. | Recorded as cited by petitioners; the Court's reasons do not specify an explicit application drawn from this authority in the provided text. |
| State of West Bengal & Ors. v. M/s Asiatic Investment Limited & Ors., 2009 (2) CLJ (Cal) 637 | Holds that an award made without apportionment (i.e., without apportioning compensation among persons entitled) is invalid. | The Court relied on this Division Bench authority to support the proposition that an award without apportionment is invalid in circumstances where claimants were not served and could not contest apportionment. |
| Prahlad Singh & Others v. Union of India & Others, (2011) 5 SCC 386 | Interprets section 16 of the 1894 Act: vesting under section 16 presupposes actual taking of possession; until possession is taken, the legal presumption of vesting cannot be raised. | The Court invoked this authority to hold that in absence of evidence of actual possession taken by the Collector, vesting under section 16 cannot be presumed. |
| Land Acquisition Officer v. A. Ramachandra Reddy & Others, (2011) 2 SCC 447 | Cited by the Court among authorities addressing acquisition procedures and consequences (also cited with respect to notification supersession in later reasoning). | The Court cited it (alongside Raghunath) for the proposition that a subsequent notification may render an earlier notification redundant/superseded. |
| Raghunath & Others v. State of Maharashtra & Others, AIR 1988 SC 1615 | Earlier authority on the effect of subsequent notifications and related acquisition procedure principles. | The Court relied on this authority to support the view that a later notification can supersede and render an earlier notification redundant. |
| West Bengal Land Acquisition Manual, 1991 (Clause 95(1)) | Provides that awards exceeding Rs. 5 lakhs require previous approval of the Government in the Land & Land Reforms Department. | The Court noted this provision and observed that no such prior approval appears to have been obtained for the award in question. |
| Sharda Devi v. State of Bihar & Another, (2003) 3 SCC 128 | Cited by State counsel (listed among authorities relied upon by State); the opinion does not elaborate the specific principle invoked from this authority in the reproduced text. | Recorded in the State's reliance list; the Court's reasons do not attribute a particular ruling to this authority in the portions provided. |
| Ramniklal N. Bhutta & Another v. State of Maharashtra & Others, (1997) 1 SCC 134 | The Supreme Court emphasised that courts should keep larger public interest in mind when exercising powers to grant stays/injunctions; Article 226 is discretionary and exercised in interest of justice. | The Court cited this principle to frame the exercise of equitable/stay powers in cases of land acquisition and to note public interest considerations. |
| Indore Development Authority v. Manoharlal & Others, (2020) 8 SCC 129 | Interprets "physical possession" under section 24(2) of the 2013 Act and holds that the two conditions in section 24(2) (possession not taken AND compensation not paid) are cumulative and conjunctive — both must be fulfilled for proceedings to lapse. | The Court relied substantially on this authority to determine that proceedings under the 1894 Act lapse only if both possession was not taken and compensation was not paid; applied the detailed discussion of "possession" from Indore to the facts at hand. |
| Orders of this Court referred to by NHAI: W.P. 30214 (W) of 2015 (order dated 23.12.2015) and W.P. No. 18322 (W) of 2017 (order dated 24.11.2017); and W.P. 16237 (W) of 2017 | Coordinate Bench orders on related acquisition/compensation issues; one order was revisited by a later order (noted in the judgment). | The Court reviewed these orders and concluded that their ratios are distinguishable from the present facts and do not assist NHAI in the present proceedings. |
Court's Reasoning and Analysis
The Court considered the rival submissions, the documentary record and the applicable statutory provisions and authorities. The analysis proceeded in a sequence aligning statutory time limits, notice/payment of compensation issues, the concept of physical possession, and the effect of subsequent NHAI notification.
1. Section 11A challenge: The Court examined whether the award (13 Mar 2007) was hit by section 11A of the 1894 Act. It computed the two-year period from the last publication of the substance of the declaration under section 6 (Form 5B published 14 Mar 2005) and found the award of 13 Mar 2007 to be within that two-year statutory period. Consequently, the award was not invalid by virtue of section 11A.
2. Notice, apportionment and compensation: Although the award was within time, the award was declared in favour of the vendors even though petitioners had bought portions earlier. The record did not show that notices under sections 9(3), 9(4) and 12(2) were served on the petitioners, and compensation was not tendered or paid to them. The Court observed that an award made without apportionment and without notice to persons in possession/entitled cannot stand; it referred to the Division Bench decision in State of West Bengal v. M/s Asiatic Investment Ltd. for the proposition that awards without apportionment are invalid.
3. Section 30 remedy not practically available: The State suggested petitioners could use section 30 (reference to Court for apportionment disputes). The Court noted that because petitioners were not made aware of the award and had no notice, they were prevented in practice from invoking section 30 at the relevant time.
4. Clause 95(1) of West Bengal Manual: The Court noted the Manual requires prior Government approval for awards exceeding Rs. 5 lakhs and found no record of such approval for the award in question.
5. Application of section 24(2) of the 2013 Act: The Court set out section 24(2) (the two cumulative conditions: award made five or more years prior to commencement of the 2013 Act AND physical possession has not been taken OR compensation has not been paid — both must be present for proceedings to be deemed lapsed). The Court found that compensation was not paid or tendered to the petitioners; thus one of the conditions in s.24(2) was not fulfilled by the acquiring body.
6. Whether physical possession was taken: The State relied on a certificate of possession dated 2 Apr 2007 indicating handover to the Burdwan Development Authority. The Court examined that document and other material: live land records showing petitioners as raiyats in August 2021, tax receipts accepted in favour of petitioners in 2021, trade registration certificates issued in 2020 and 2021, conversion in classification in 2010, and other documents indicating possession by petitioners. The certificate of possession lacked signatures and presence of independent witnesses; no memorandum of possession drawn up in the presence of witnesses as envisaged by authorities was on record. The Court relied on Indore Development Authority and related authorities to interpret "physical possession": the twin requirements of section 24(2) are conjunctive and possession must be more than symbolic; when actual physical possession has not been taken, vesting under section 16 cannot be presumed.
7. Conclusion on lapse: On the facts, the Court concluded there was no evidence of actual physical possession having been taken by the Collector under section 16 of the 1894 Act; the petitioners were in continuous physical possession until the name of Burdwan Development Authority was recorded during the pendency of the writ petitions (that recording being challenged). Because compensation was not paid and physical possession had not been taken, the Court found the twin conditions for lapse under section 24(2) were satisfied — and thus the earlier 1894 proceedings were deemed to have lapsed (the Court held: "the proceeding is deemed to have lapsed").
8. NHAI's notification and supersession: The Court examined the NHAI's subsequent section 3A/3D actions. It observed that where a fresh notification is issued followed by a final declaration without withdrawing an earlier notification, the subsequent notification is to be understood as having superseded or rendered redundant the earlier one (citing Raghunath and Land Acquisition Officer authorities). The Court found the NHAI's later notification to be in supersession of the State's earlier notification; furthermore, the petitioners' plot had been excluded in the NHAI section 3D declaration without adequate reason and the NHAI's plea to justify that exclusion did not satisfy the Court.
9. Relief as to representation and interim protection: The Court directed that the NHAI's proceeding under section 3A(1) should be taken to its logical conclusion in accordance with law (and noted the earlier 1894 proceeding has lapsed or been abandoned). The petitioners' representation dated 31.03.2021 ought to be considered with reasonable opportunity of hearing to all interested persons. The Court restrained the respondents from giving effect to the NHAI notice dated 12 Jan 2022 insofar as it affected the petitioners and from disturbing the petitioners' peaceful possession until disposal of their representation.
Holding and Implications
Holding: The writ petitions were allowed in the terms of prayers (a) and (c) (the Court granted the relief that the respondent authorities should consider the petitioners' representation dated 31.03.2021 in accordance with law and that the petitioners' portions of plot no. 82 be released from acquisition or, alternatively, be acquired afresh upon compliance with due process and payment of appropriate compensation). The Court expressly restrained respondents from giving effect to the NHAI notice dated 12.01.2022 in respect of the petitioners and from disturbing their possession until disposal of the representation. There was no order as to costs.
Immediate consequences for the parties:
- The respondents are directed to consider the petitioners' representation filed on 31.03.2021, affording reasonable opportunity of hearing to interested persons including the petitioners.
- The respondents are restrained from executing or giving effect to the NHAI notice dated 12.01.2022 against the petitioners and from disturbing the petitioners' peaceful possession of the plot in question until the representation is disposed of.
- No order as to costs was made; urgent certified website copies of the judgment to be supplied on usual formalities.
Broader implications: The Court applied existing principles (notably the interpretation of "physical possession" and the conjunctive requirements of section 24(2) from Indore Development Authority, and principles on possession/vesting from Prahlad Singh and Raghbir Singh Sehrawat) to the factual matrix. The judgment does not announce a new legal principle; it applies established authorities to hold that, on these facts, the 1894 proceedings are deemed to have lapsed and the petitioners' representations must be considered by the acquiring authority with hearing.
Note: This summary reflects only the matters and statements expressly contained in the provided court opinion. No outside facts or inferences beyond the text of the judgment have been added.
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION
APELLATE SIDE
The Hon"ble JUSTICE SUVRA GHOSH W.P.A. 15475 of 2021
Sudhir Kumar Majumdar & Ors. Vs.
State of West Bengal & Ors. With
W.P.A. 15646 of 2021 Sk. Abdul Gaffar
Vs.
State of West Bengal & Ors. With
W.P.A. 15649 of 2021 Bijay Sain
Vs.
State of West Bengal & Ors. With
W.P.A. 15766 of 2021 Alamgir Mallick
Vs.
State of West Bengal & Ors. With
W.P.A. 15794 of 2021 Rekha Rani Roy & Ors. Vs.
State of West Bengal & Ors.
1
2
With W.P.A. 15713 of 2021 Bishwanath Mondal & Ors. Vs.
State of West Bengal & Ors. With
W.P.A. 15717 of 2021 Marhabuddin Mondal & Anr. Vs.
State of West Bengal & Ors.
For the Petitioner: Mr. Uttiya Roy, Adv., Mr. Arnab Mandal, Adv.
For the Respondent Nos. 5 & 6: Mr. Falguni Majhi, Adv. For the Respondent No. 3: Mr. Subrata Bhattacharya, Adv., Mr. Subhash Ray, Adv.
(In WPA 15766 of 2021)
(In WPA 15794 of 2021)
(In WPA 15713 of 2021)
(In WPA 15717 of 2021)
For the NHAI: Ms. Manika Roy, Adv.
For the State: Mr. A.Roy, Ld. G.P.,
Md. T.M. Siddiqui, Adv.,
Mr. N. Chatterjee, Adv.
Mr. Ansar Mondal, Adv.,
Mr. Ayan Banerjee, Adv.
(In WPA 15646 of 2021)
3
Mr. Chandi Charan De, Adv., (In WPA 15649 of 2021) (In WPA 15717 of 2021) Mr. Haripada Maity, Adv. (In WPA 15649 of 2021) Mr. Anirban Sarkar, Adv. (In WPA 15794 of 2021) Mr. Soumitra Bandyopadhyay, Adv., Mr. Subhasis Bandyopadhyay, Adv. (In WPA 15713 of 2021)
Ms. Chandana Ghosh, Adv. (In WPA 15717 of 2021)
Hearing Concluded on: 09.09.2022 Date: 30.09.2022
SUVRA GHOSH, J. :-
1. Since similar issues are involved in all the writ petitions, they are taken up for consideration and disposal by a common judgment.
2. The prayers of the petitioners are as hereunder:-
"a) a writ in the nature of mandamus directed the respondent authorities to consider the representation dated 31.03.2021, in accordance with law and in the light of the provisions of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013;
c) a writ in the nature of mandamus directing the respondent authorities to release the petitioners" portions of plot no. 82, from the clutches of acquisition and free from any other encumbrances incidental to the aforesaid LA Case No. 2(IV)/2004-2005, or in the alternative, to acquire the same afresh, if so required, but only upon compliance of the due process of
4
law and upon payment of appropriate damage compensation as per the current market rate and in accordance with the present law of the land;"
3. The petitioners in W.P.A. 15475 of 2021 claim to be recorded owners of property in R.S. and L.R. plot no. 82 under L.R. khatian nos. 294, 295, 293 and 296 in mouza- Alisha, J.L. no. 77, P.S. Burdwan Sadar, Dist:- Purba Bardhaman comprising about 0.050 acres since 1988 by virtue of purchase and have been running small scale business therein for earning their livelihood.
4. The petitioner in W.P.A. 15646 of 2021 claims to be recorded owners of property in R.S. and L.R. plot no. 82 under L.R. khatian no. 456 in mouza- Alisha, J.L. no. 77, P.S. Burdwan Sadar, Dist:- Purba Bardhaman comprising about 0.081 acres since 1986 by virtue of purchase and has been carrying on small scale business therein.
5. The petitioner in W.P.A. 15649 of 2021 claims to be recorded owners of property in R.S. and L.R. plot no. 82 under L.R. khatian no. 292 in mouza- Alisha, J.L. no. 77, P.S. Burdwan Sadar, Dist:- Purba Bardhaman comprising about 0.034 acres since 1994 by virtue of purchase and have been running small scale business therein.
6. The petitioner in W.P.A. 15766 of 2021 claims to be recorded owners of property in R.S. and L.R. plot no. 82 under L.R. khatian no. 66 in mouza- Alisha, J.L. no. 77, P.S. Burdwan Sadar, Dist:- Purba Bardhaman comprising about 0.036 acres since 1987 by virtue of purchase and have been running small scale business therein.
5
7. The petitioners in W.P.A. 15794 of 2021 claim to be recorded owners of property in R.S. and L.R. plot no. 82 under L.R. khatian no. 66 in mouza- Alisha, J.L. no. 77, P.S. Burdwan Sadar, Dist:- Purba Bardhaman comprising about 0.10 acres by virtue of purchase in 1985 and a deed of gift executed in 2019 and have been running small scale business therein.
8. The petitioners in W.P.A. 15713 of 2021 claim to be recorded owners of property in R.S. and L.R. plot no. 82 under L.R. khatian nos. 249, 250, 251 and 252 in mouza- Alisha, J.L. no. 77, P.S. Burdwan Sadar, Dist:- Purba Bardhaman comprising about 0.016 acres since 1985-1987 by virtue of purchase and have been running small scale business therein.
9. The petitioners in W.P.A. 15717 of 2021 claim to be recorded owners of property in R.S. and L.R. plot no. 82 under L.R. khatian nos. 340 and 341 in mouza- Alisha, J.L. no. 77, P.S. Burdwan Sadar, Dist:- Purba Bardhaman comprising about 0.1 acres since 1985-1986 by virtue of purchase and have been running small scale business therein.
10. Land acquisition proceeding was initiated under Act I of 1894 in respect of plot no. 82 for the purpose of development of Commercial Complex. Declaration under section 6 of the Act was published on 18thFebruary, 2005 vide Burdwan No. 18-LA/2/IV/2/2005 dated 15thFebruary, 2005 and award was declared on 13thMarch, 2007 in favour of Laxman Ghosh, Bamapada Ghosh and Bharat Chandra Ghosh despite the petitioners having purchased portions of the plot much prior to initiation of the acquisition proceedings. The petitioners are in continuous uninterrupted
6
physical possession of the plot and no notice was issued to them under the 1894 Act, nor was any award made in their favour. The proposed scheme of the Government was never executed and the LA Case suffers from gross non compliance of the provisions of sections 5A, 9, 16, 31 and 34 of the 1894 Act and also, the alleged award is hit by section 11A of the Act. The petitioners complain that since the entire acquisition proceeding has lapsed and in the meantime The Right to Fair Compensation And Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 has come into effect the petitioners are entitled to compensation under the provisions of the said Act. Neither physical possession of the land was taken by the State respondents, nor compensation paid/deposited in favour of the petitioners for the same.
11. Very recently, the National Highways Authority of India issued notification under section 3A of the National Highways Act, 1956 proposing to acquire portions of the said plot no. 82 for widening of the National Highway-19 and published a notification in the local vernacular newspaper „Bartaman"
on 20thSeptember, 2020. Pursuant to initiation of fresh acquisition proceeding vide LA case no. 18 (NH-19)/2020-2021, notice under section 3C (2) of the National Highways Act, 1956 was served upon the petitioners. Objections tendered by the petitioners against such proposed acquisition were turned down by an order passed on 21stDecember, 2020 upon hearing the petitioners. Subsequently, plot no. 82 was omitted in the declaration under section 3D of the National Highways Act, 1956 dated
7
16thFebruary, 2021. The petitioners were informed that the said plot was acquired vide LA case no. 2(IV)/2004-2005.
12. It is submitted by learned counsel for the petitioners that since the acquisition under the Act of 1894 is hit by section 11A of the Act and also since there is no previous approval of the Government for declaration of the alleged award exceeding Rs. five lakhs as required under the law, no valid award can be said to have been passed and the acquisition proceeding stood lapsed. The proceeding is also hit by section 24 of the Act of 2013 since notice under section 12(2) of the 1894 Act was not served upon majority of the land owners and there was no tender of payment of compensation in terms of section 31 of the Act of the 1894. The authorities neither took possession of the plot in question, nor paid compensation for the same to the petitioners for which the petitioners are entitled to compensation in terms of the 2013 Act.
13. Learned counsel has further submitted that the petitioners were permitted to raise construction in the plot in question by the Pradhan of Baikanthapur- II, Grampanchayat and the plot was converted from sali by a letter issued by the Collector under section 4C of the West Bengal Land Reforms Act, 1955. The communications made to the petitioners by the Panchayat authority demonstrate that the petitioners have been carrying on business in the said plot all throughout. Referring to the certificate of possession submitted by the State respondents, it is submitted on behalf of the petitioners that this document cannot be construed to demonstrate delivery of possession of the property. No notice of hearing on the
8
objections filed under section 5A (1) of the Act of 1894 was served upon the petitioners as also the notice under section 9(3) and 9(4) of the Act. No panchnama was executed for the purpose of taking possession of the plot and the petitioners are still in possession of the same. Notification under section 3D of the National Highways Act, 1956 also does not cover the plot of the petitioners.
14. The document of publication of award produced by the State respondents pertain to draft award signed on 9thMarch, 2007. No notice under section 12(2) of the 1894 Act was issued to the petitioners by the authority.
15. During pendency of the writ petition the State respondents mutated the name of Burdwan Development Authority in the record of rights by exercising their administrative powers and the same has been challenged by the petitioners before the appropriate forum. The National Highways Authority has issued notice under section 26(2) of the Control of National Highways (Land and Traffic) Act, 2002 after filing of the writ petition and the petitioners are under constant threat of dispossession at the instance of the National Highways Authority.
16. Learned counsel for the petitioners has placed reliance on the following authorities:-
(i) State of Bihar And Others v/s. Kalyanpur Cement Limited reported in (2010) 3 Supreme Court Cases 274,
9
(ii) Smt. Bela Das v/s. Union of India & Ors. reported in W.P. 16237(W) of 2017 passed by a Coordinate Bench of this Court,
(iii) Raghbir Singh Sehrawat v/s. State of Haryana And Others reported in (2012) 1 Supreme Court Cases 792,
(iv) Ferro Alloys Corpn. Ltd. v/s. Union of India reported in AIR 1999 Supreme Court 1236,
(v) K. Lubna And Others v/s. Beevi And Others reported in (2020) 2 Supreme Court Cases 524,
(vi) State of West Bengal & Ors. v/s. M/s. Asiatic Investment Limited & Ors. reported in 2009 (2) CLJ (Cal) 637,
(vii) Prahlad Singh And Others v/s. Union of India And Others reported in (2011) 5 Supreme Court Cases 386,
(viii) Land Acquisition Officer v/s. A. Ramachandra Reddy And Others reported in (2011) 2 Supreme Court Cases 447,
(ix) Raghunath And Others v/s. State of Maharashtra and Others reported in AIR 1988 SC 1615; and West Bengal Land Acquisition Manual, 1991.
17. Learned counsel for the State respondents submits that no prayer for cancellation of acquisition was made before the State respondents and the grievance of the petitioners was appropriately dealt with by a reasoned order passed by the Special Land Acquisition Officer on 11thFebruary,
2020.
10
18. Notification under section 4 of the Land Acquisition Act, 1894 was published on 7thJuly, 2004 and substance of notification under section 4(1) of the Act was issued in Form-3D. Upon disposal of objections under section 5A(1) of the Act declaration under section 6 of the Act was published on 18thFebruary, 2005 and substance of the declaration under section 6 was published in Form-B on 14thMarch, 2005. Award was declared on 13thMarch, 2007 and possession of the acquired land was handed over to the requiring body being the Burdwan Development Authority on 2ndApril, 2007. Notice under 9(3) and 9(4) of the Act was served upon the petitioners and other interested parties and adequate opportunity of hearing was granted to them. The LA case being no. 2(IV)/2004-2005 is complete in every respect and the writ petition is not maintainable.
19. Learned counsel has placed reliance on the following authorities:-
i. Sharda Devi v/s. State of Bihar And Another reported in (2003) 3 Supreme Court Cases 128;
ii. Ramniklal N.Bhutta And Another v/s. State of Maharashtra And Others reported in (1997) 1 Supreme Court Cases 134;
iii. Indore Development Authority v/s. Manoharlal And Others reported in (2020) 8 Supreme Court Cases 129 in support of his contention.
20. It is submitted on behalf of the Burdwan Development Authority that the land has been recorded in the name of the authority in the L.R. record of
11
rights and the said authority being the requiring body is in possession of the land.
21. The National Highways Authority of India has submitted that the writ petitioners are not the owners of the plot in question which has already been acquired, and are therefore not entitled to any compensation. Initially the proposal for acquisition of an area of 0.183 acres in plot no. 82 was submitted by the National Highways Authority of India (in short the NHAI) before the second respondent for six laning project of Panagarh-Palsit section of NH-19. The said proposal was published under section 3A notification of the National Highways Act, 1956 on 26thJune , 2020 but the same was dropped by the competent authority during publication of section 3D notification as it was found that the land was Government land owned by Burdwan Development Authority under the Government of West Bengal and did not belong to the petitioners. The name of Burdwan Development Authority has been recorded in the record of rights and it is State Government land which has been transferred to the Central Government/NHAI. For the said reason the writ petitioner is not entitled to get any compensation in respect of the plot in question which is vested land. The notification under section 3D of the 1956 Act has also not been challenged by the writ petitioners.
22. The National Highways Authority of India has referred to the order of a Coordinate Bench of this Court passed on 23rdDecember, 2015 in W.P. 30214 (W) of 2015 and order passed on 24thNovember, 2017 in W.P. No. 18322 (W) of 2017.
12
23. I have considered the submission made on behalf of the parties, material on record and the law on the subject.
24. The Hon"ble Supreme Court, in the authority in (1997) 1 Supreme Court Cases 134, has emphasized that the Courts should keep the larger public interest in mind while exercising their power of granting stay/injunction and the power under Article 226 being discretionary, will be exercised only in furtherance of interest of justice and not merely on the making out of a legal point. In the matter of land acquisition for public purposes, the interest of justice and public interest coalesce.
25. The petitioners purchased a portion of the plot in question being plot no. 82 and mutated their names in the relevant record of rights. In addition to the certificate of mutation, record of rights, dakhilas, permission of the panchayat to raise construction in the plot and a letter issued by the Additional District Magistrate (G), Burdwan to the District Land & Land Reforms Officer, Burdwan on 23rdNovember, 1995 also confirm the said mutation and approval of the proposed industrial unit in the plot. The said letter also demonstrates that the land did not fall within the proposed acquired land for housing complex as on that date.
26. Record reveals that notification under section 4 of the Land Acquisition Act, 1894 was published on 7thJuly, 2004 and declaration under section 6 of the Act was published in the Calcutta Gazette on 18thFebruary, 2005. Substance of declaration under section 6 of the Act was published in Form
13
5B on 14thMarch, 2005. Award was declared on 13thMarch, 2007 in favour of the vendors of the petitioners.
27. It is envisaged in section 11A of the Act of 1894 that the award should be made within a period of two years from the date of publication of the declaration and the period of two years shall be computed from the last of the publication dates. Since public notice of the substance of declaration under section 6 in Form 5B was made on 14thMarch, 2005, the award declared on 13thMarch, 2007 is within the statutory period of time and is not hit by section 11A of the Act.
28. Strangely, the award was declared in favour of the vendors of the petitioners though the petitioners acquired title and possession in respect of the property much prior to issuance of the notification under section 4 of the Act or declaration of award. There is no document on record which suggests that notice under section 9(3) and 9(4) of the 1894 Act was served on the petitioners who were owners and occupiers of the plot at the relevant time. Even after declaration of award notice under section 12(2) of the Act was not served on the petitioners as appears from the record. As a consequence no compensation was also paid to the petitioners.
29. Learned counsel for the State respondents has submitted that it is open to the petitioners to take recourse of section 30 of the Act of 1894 which says that in case of any dispute as to the apportionment of the amount of compensation or as to the persons to whom it is payable, the Collector may refer the same to the decision of the Court.
14
30. In the present case, since the petitioners were not served notice of the award and had no knowledge about the same until their possession was hindered at the behest of the authorities, they were not in a position to take recourse to section 30 of the Act of 1894. Such an award made without apportionment has been held to be invalid by an Hon"ble Division Bench of this Court in the authority in State of West Bengal and Others v/s. M/s. Asiatic Investment Limited and Others reported in 2009 (2) CLJ (Cal) 636.
31. Clause 95(1) of the West Bengal Land Acquisition Manual, 1991 envisages that all awards exceeding Rs. five lakhs in each land acquisition case requires previous approval of the Government in the Land and Land Reforms Department. No such approval appears to have been taken by the acquiring body prior to declaration of award.
32. Referring to section 24(2) of The Right to Fair Compensation And Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, learned counsel for the petitioners has submitted that since no compensation was paid to the petitioners and physical possession of land has not been taken by the authority, the proceeding shall be deemed to have lapsed and the State respondent should either initiate fresh acquisition proceeding under the Act of 2013 and pay compensation to them accordingly or release the land in favour of the petitioners.
33. The law laid down in section 24(2) of the 2013 Act is set out:-
15
24(2) "Notwithstanding anything contained in sub-section (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said section 11 has been made five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act:"
34. That compensation was not paid to the petitioners and no notice under section 9(3) and 9(4) and /or section 12(2) of the 1894 Act was served on the petitioners have been discussed earlier. Section 31 (1) of the 1894 Act mandates tender of payment of compensation to the persons entitled thereto or depositing the same in accordance with law. True, taking possession is not dependent upon payment of compensation and once possession is taken under sections 16 or 17 of the 1894 Act, the land vests absolutely with the State and there is no divesting upon non payment of compensation. In such circumstances, compensation shall carry interest @ 9% or 15% in terms of section 34 of the 1894 Act. The documents relied upon by the State respondents in this regard do not demonstrate payment or tender of compensation to the awardees. Therefore one of the conditions laid down in section 24(2) of the 2013 Act has not been fulfilled by the acquiring body.
35. With regard to whether physical possession of the land was taken by the State respondents in terms of section 24(2) of the 2013 Act, the only
16
document relied upon by the State respondents is the certificate of possession executed on behalf of the State respondents in favour of the Burdwan Development Authority, being the requiring body, on 2ndApril, 2007. During pendency of the writ petition the name of the requiring body has been recorded in the LR record of rights on an application filed by the Burdwan Development Authority on 2ndSeptember, 2021 the said order being challenged by the petitioners. Though the State respondents claim to have handed over physical possession of the plot in question in favour of the Burdwan Development Authority, the live data downloaded by the petitioners indicates that their names are recorded as raiyats as in the month of August, 2021. Tax paid by the petitioners was accepted by the authority even in 2021 and classification of the property was converted from sali in 2010. Trade registration certificate was issued in favour of the petitioners by the panchayat in respect of the plot in question even in 2020 and 2021.
36. The Hon"ble Supreme Court, in the authority in Indore Development Authority (supra) has dealt with the term "physical possession" in detail. In the said judgment it is made clear that two conditions specified in section 24(2) for lapsed of proceedings are (i) possession of the acquired land has not been taken and (ii) compensation has not been paid. If possession is taken but compensation not paid there would be no lapse. Similarly, if compensation is paid and possession not taken, there would also be no lapse. The twin requirements are cumulative and conjunctive in nature. Proceedings initiated under the 1894 Act shall lapse only when possession
17
of the acquired land has not been taken and compensation has also not been paid. In dealing with the mode of taking possession under the 1894 Act, the Hon"ble Supreme Court has held that drawing of panchnama which may be a mode of taking possession is not enough when actual physical possession remains with the land owner. Once possession is taken under section 16 and 17 of the 1894 Act, the land is vested with the State and drawing of panchnama for taking possession is sufficient. Upon the land being vested with the State and drawing up a memorandum of taking possession by the State, physical possession is deemed to be taken by the State. The Hon"ble Supreme Court has continued to say that possession comprises control over the property and the will to exercise such control. What is important is the visible intention of possession. Once such possession is taken, it vests with the State free from all encumbrances. The judgment records that in case of acquisition of large tract of land it may not be possible for the acquiring authority to take physical possession of each and every parcel of the land and it will be sufficient if symbolic possession is taken by preparing appropriate document in the presence of independent witnesses and getting their signatures on such document. Also, the provision of the 2013 Act cannot be extended to denude title which has already vested in the beneficiaries of the acquisition.
37. In the case in hand, there is not an iota of evidence to show that possession of the land was taken by the Collector under section 16 of the 1894 Act. No memorandum of possession as indicated by the Hon"ble Supreme Court was drawn up in presence of witnesses and the certificate
18
of possession is bereft of either signatures or presence of witnesses. The documents on record unambiguously demonstrate that the petitioners are in physical possession of the plot in question all throughout until the name of Burdwan Development Authority has been recorded during pendency of the writ petition, the same being under challenge.
38. As laid down in section 16 of the Act of 1894, vesting of the acquired land takes place as soon as possession is taken by the Collector after passing an award under section 11. Section 16 presupposes actual taking of possession and till that is done, legal presumption of vesting enshrined in section 16 cannot be raised in favour of the acquiring authority. [Prahlad Singh and Others (supra)]. In the authority in Raghvir Singh Sehrawat (supra), the Hon"ble Supreme Court has held that there being no evidence to show that actual possession of the land had been taken after giving notice to the appellant or that he was present at the site when possession was delivered to the requiring body, the documents showing delivery of possession which are self-serving documents cannot be made the basis for recording a finding that possession of the acquired land was taken. The ratio decidendi of both the cases is similar to the case in hand wherein there is no document to show taking of physical possession by the acquiring body. The legality and the validity of the documents of possession relied upon by the petitioners are also not under challenge. Had possession been taken under section 16 of the Act of 1894, the proceeding could not be said to have lapsed for non payment of compensation. Once the land vests, it cannot be divested even if there is some irregularity in the
19
acquisition proceedings. Lapsing is provided only when possession has not been taken, nor compensation paid [Indore Development Authority (supra)]. Herein, since possession of the plot in question has not been taken by the acquiring body, the question of vesting of the plot does not arise and absolute title and possession cannot be said to be conferred upon the State. The twin requirements of section 24 (2) of the Act of 2013 not being satisfied, the proceeding is deemed to have lapsed.
39. It is submitted on behalf of the National Highways Authority of India that since the plot in question is vested land the petitioners are not entitled to any compensation. The contention of the National Highways Authority has not been accepted by this Court as discussed earlier. Record reveals notification under section 3A (1) of the National Highways Act, 1956 was published on 26thJune, 2020 for acquisition of the plot in question. Objections submitted by the petitioners were considered and rejected in proceedings under section 3C (2) of the Act of 1956 as the land was required for greater interest of the public and reasonable compensation in terms of the Act would be given to the land loser. Surprisingly, the plot of the petitioners was excluded in the declaration issued by the authority under section 3D (1) of the Act without assigning any reason for the same. The plea taken by the authority before this Court to justify the said act does not hold water. The National Highways Authority has gone a step further to issue notice under section 26(2) of the Control of National Highways (Land and Traffic) Act, 2002 to the petitioners directing them to remove unauthorised occupation in the plot in question. The petitioners
20
have filed objection to the said notice before the concerned authority which is pending.
40. It is trite law that when fresh notification is issued in respect of a plot followed by final declaration without withdrawing the earlier notification, the authority can be construed to have abandoned the earlier notification by issuing subsequent notifications. The earlier notification becomes redundant upon issuance of the subsequent notification, the subsequent notification having deemed to have superseded the earlier one. [Raghunath and Others (supra) and Land Acquisition Officer-cum-RDO (supra)].
41. In view of the above, it can be concluded that the subsequent notification issued by the National Highways Authority of India is in supersession of the earlier notification issued by the State authorities and in view of rejection of the objections filed by the petitioners to the said notification, the petitioners" plot ought to have been included in the declaration under section 3D (1) of the 1956 Act.
42. The order passed in W.P. 30214 (W) of 2015 on 23rdDecember, 2015 relied upon by the National Highways Authority was revisited by an order passed on 12thFebruary, 2018 in W.P. 16237 (W) of 2017, both by Coordinate Benches of this Court and the Learned Judge, in the later order, observed that the petitioner"s possession in the land in question could not be interfered with since an arbitral award was passed without hearing the petitioner even before the reference was made by the petitioner. The other judgment passed in W.P. No. 18322 (W) of 2017 deals with determination
21
of compensation payable to the petitioners and the manner in which the arbitration process was carried out. Section 3D and 3E of the Act of 1956 were also dealt with in the said order. The ratio of these orders can be distinguished from the facts and circumstances of the present case and the said orders do not come to the aid of the National Highways Authority herein.
43. Since proceeding under section 3A (1) of the Act of 1956 has been initiated by the National Highways Authority in respect of the plot in question amongst other plots, the said proceeding should be taken to its logical conclusion by the authority in accordance with law, moreso, as the earlier proceeding under the Act of 1894 has lapsed or in the alternative, has been abandoned. Also, the application of the petitioners submitted before the Land Acquisition Collector, Purba Burdwan on 31stMarch, 2021 ought to be considered in the light of the observation made in this judgment upon affording reasonable opportunity of hearing to all the interested persons including the petitioners.
44. In view of the above, the writ petitions are allowed in terms of prayers (a) and (c) thereto.
45. The respondents are restrained from giving effect to the notice issued by the National Highways Authority of India on 12thJanuary, 2022 in so far as the petitioners are concerned and from disturbing the peaceful possession of the petitioners in respect of the plot in question till disposal of the representation submitted by them.
22
46. There shall however be no order as to costs.
47. Urgent certified website copies of this judgment, if applied for, be supplied to the parties expeditiously on compliance with the usual formalities.
(Suvra Ghosh, J)