Government Of Mahara... v. Borse Brothers Engin...

Bombay High Court
Dec 17, 2020
Smart Summary (Beta)

Summary of Opinion — Application for Condonation of Delay under Section 37 of the Arbitration and Conciliation Act, 1996

Factual and Procedural Background

This opinion concerns an application seeking condonation of a stated delay of 103 days in preferring an appeal under Section 37 of the Arbitration and Conciliation Act, 1996. An arbitral award was passed on 05.04.2016 and was challenged under Section 34 of the Act. The Section 34 challenge was dismissed on 23.04.2019. The applicant's counsel is said to have intimated the Executive Engineer only in July 2019, after which a certified copy was applied for on 08.07.2019 and obtained on 24.07.2019. The applicant attributed the cumulative delay to time taken to obtain the certified copy, to obtain legal opinion and to decide to file an appeal under Section 37.

The respondent contested these facts with documentary evidence (a certified copy application and endorsements from the District Court, Dhule, marked Exhibit-R1) indicating that an application for the certified copy was in fact filed on 14.05.2019, with an endorsement that the copy would be delivered to Mr. A.D. Patil of the Irrigation Department and would be ready for delivery on 27.05.2019. The applicant did not controvert these particulars. The judge therefore treated the earlier date as the operative date for receipt of a certified copy and calculated the limitation period accordingly.

The matter also involved consideration of recent Supreme Court authority (N.V. International v. State of Assam, Civil Appeal No. 9244 of 2019, decided 06.12.2019) addressing the maximum outer limit for condonation of delay in appeals under Section 37.

Legal Issues Presented

  1. Whether the delay in filing the appeal under Section 37 of the Arbitration and Conciliation Act, 1996 should be condoned by this Court under Section 5 of the Limitation Act, 1963.
  2. Whether the period of delay asserted by the applicant (stated to be 103 days) or the period calculated from the earlier certified copy application (yielding a delay of more than 120 days) controls the condonation enquiry.
  3. Whether, in view of the Supreme Court judgment in N.V. International v. State of Assam, any delay beyond 120 days in preferring an appeal under Section 37 of the Arbitration Act can be condoned.
  4. What is the effect of Section 43 of the Arbitration and Conciliation Act, 1996 (making provisions of the Limitation Act applicable) on the power to condone delay under Section 5 of the Limitation Act, in light of the above Supreme Court authority.

Arguments of the Parties

Applicant's Arguments (as advanced by Mr. R.N. Dhorde, Senior Advocate)

  • The arbitration award was dated 05.04.2016 and the Section 34 challenge was dismissed on 23.04.2019; the applicant's counsel only intimated the Executive Engineer in July 2019 and then applied for a certified copy on 08.07.2019 (obtained 24.07.2019).
  • The time spent in obtaining the certified copy, obtaining legal opinion from counsel and deciding to challenge the order cumulatively caused the delay; there was no deliberate intention to delay and the applicant would suffer prejudice (interest burden) from not being allowed to appeal.
  • Section 43 of the Arbitration Act makes the Limitation Act applicable, and therefore Section 5 of the Limitation Act empowers the Court to condone delay for sufficient cause; the period of delay should be considered in that framework.
  • The applicant relied on several precedents (Union of India v. Varindera Const. Ltd.; Ganesan v. Commissioner, Tamil Nadu Hindu Religious and Charitable Endowments Board; State of Madhya Pradesh v. Anshuman Shukla; Mukri Gopalan v. Cheppilat Puthanpurayil Aboobacker) to support condonation in appropriate circumstances.

Respondent's Arguments (as advanced by Mr. V.B. Patil, Advocate for respondent No. 1)

  • Recent Supreme Court authority (N.V. International v. State of Assam, decided 06.12.2019) has emphatically held that any delay beyond 120 days in preferring an appeal under Section 37 of the Arbitration Act cannot be condoned; therefore the issue is no longer res integra.
  • Documentary evidence (Exhibit-R1) shows an application for certified copy was filed on 14.05.2019 and indicated delivery to Mr. A.D. Patil on 27.05.2019, which implies the applicant may have obtained the certified copy earlier than asserted; the applicant did not file a rejoinder or otherwise controvert this evidence.
  • The applicant has not come to court with clean hands and has relied on a convenient plea regarding late intimation by counsel without filing an affidavit from the counsel to substantiate that claim; therefore the request for condonation should be rejected.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union Of India v. Varindera Const. Ltd.; SLP(C) No. 23155/2013 decided on 17.09.2018 Earlier decision relied upon by the applicant; referenced in later Supreme Court authority. The Court noted that this decision was referred to by the Supreme Court in N.V. International and therefore need not be separately parsed; it does not assist the applicant in view of N.V. International.
Ganesan represented by Power Agent G. Rukmani Ganesan v. Commissioner, Tamil Nadu Hindu Religious and Charitable Endowments Board; (2019) 7 SCC 108 Holds that when a special/local law specifically provides for applicability of the Limitation Act, Section 5 of the Limitation Act would apply to appeals before statutory/quasi-judicial authorities or tribunals. The Court acknowledged that Section 43 of the Arbitration Act makes the Limitation Act applicable (so Section 5 could apply), but held that N.V. International's outer limit on condonation (beyond 120 days) prevents the applicant from deriving any benefit from Ganesan.
State of Madhya Pradesh v. Anshuman Shukla; (2014) 10 SCC 814 Held that Section 5 of the Limitation Act is applicable to revisions under Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983. The Court observed this precedent but found it not directly bearing on the facts of the present matter.
Mukri Gopalan v. Cheppilat Puthanpurayil Aboobacker; (1995) 5 SCC 5 Held that Section 5 of the Limitation Act would be applicable for preferring appeals under the Kerala Buildings (Lease and Rent Control) Act, 1965. The Court treated this as a precedent illustrating application of Section 5 in statutory contexts but did not find it decisive in overcoming the Supreme Court's ruling in N.V. International regarding the outer limit for condonation under Section 37.
N.V. International v. The State of Assam; Civil Appeal No. 9244 of 2019, arising out of SLP (C) No. 23808/2019, decided on 06.12.2019 The Supreme Court added a 30-day grace period under Section 5 of the Limitation Act to the 90 days provided by statute for filing appeals under Section 37 of the Arbitration Act, producing an effective outer limit of 120 days; delays beyond 120 days are not liable to be condoned. The Court treated this authority as decisive. Relying on paragraph 5 of that judgment, the Court held that delay beyond 120 days in preferring an appeal under Section 37 cannot be condoned and thus refused to exercise discretion to condone the delay in the present case.

Court's Reasoning and Analysis

The Court proceeded in two strands: (i) a factual enquiry into when the certified copy was sought and likely obtained, and (ii) a legal enquiry into whether any delay beyond the statutory period could be condoned in light of controlling Supreme Court authority.

On the factual strand, the Court examined the documentary evidence (Exhibit-R1) — an application filed by the applicant's counsel for a certified copy dated 14.05.2019 with an endorsement that the copy was to be handed to Mr. A.D. Patil of the Irrigation Department and that delivery was slated for 27.05.2019. The applicant did not controvert these facts or provide an alternative explanation. Based on this absence of dispute and the documentary proof, the Court proceeded on the assumption that a certified copy was obtained pursuant to the 14.05.2019 application and that the limitation period should be calculated from that earlier date.

On the legal strand, the Court considered the applicant's submission that Section 43 of the Arbitration Act makes the Limitation Act applicable and that Section 5 therefore permits condonation for sufficient cause. The Court acknowledged that Section 5 could, in principle, apply (and that other precedents have applied Section 5 in similar statutory contexts), but observed that the Supreme Court in N.V. International expressly addressed the exercise of Section 5 in the context of appeals under Section 37 and established an outer limit: the statutory 90 days plus a 30-day grace under Section 5 gives an effective maximum of 120 days, beyond which condonation is not permissible.

The Court noted that it must proceed on the assumption that the Supreme Court was aware of Section 43 of the Arbitration Act when it made its pronouncement in N.V. International, and therefore declined to accept the applicant's contention that Section 43 renders the period of delay "inconsequential." Because, calculated from the date the Court deemed operative (the 14.05.2019 application and likely delivery on 27.05.2019), the delay exceeded 120 days, the Court concluded that there was neither a sufficient cause nor the power to condone the delay.

Holding and Implications

APPLICATION REJECTED

Holding: The application for condonation of delay is rejected. The Court found that, on the evidence before it, the limitation period must be calculated from the earlier certified copy application (14.05.2019/27.05.2019), resulting in a delay exceeding 120 days, and that the Supreme Court's ruling in N.V. International precludes condonation of any delay beyond 120 days in appeals under Section 37 of the Arbitration Act.

Implications: As a direct consequence of this decision, the applicant will not be permitted to file the delayed appeal under Section 37. The Court treated the Supreme Court's pronouncement in N.V. International as the controlling legal position and did not lay down any new precedent. The decision's practical effect is limited to denying the discretionary relief sought by the applicant in this matter; the opinion does not purport to modify or depart from the law as laid down by the Supreme Court.

Prepared strictly on the basis of material contained in the provided opinion. No information beyond the text of the opinion has been added or inferred.

Show all summary ...

Mangesh S. Patil, J.:— This is an application seeking condonation of delay, stated to be of 103 days, in preferring an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (“Act”, for short).

2. Mr. R.N. Dhorde, learned Senior Advocate for the applicant submits that the arbitration award was passed on 05.04.2016. It was challenged under Section 34 of the Act. The decision was rendered on 23.04.2019 whereby the challenge was dismissed. However, it is only in the month of July 2019, the concerned Advocate representing the applicant had intimated the Executive Engineer about the decision. It is thereafter that a certified copy was applied for on 08.07.2019. It was obtained on 24.07.2019. Some time thereafter was lost in having legal opinion from the concerned Advocate and in taking a decision for challenging the impugned order under Section 37 of the Act. All these, cumulatively led in causing the delay. There was no intention to cause delay. The applicant was not to gain anything by causing delay, rather a heavy burden of interest would be carried by the applicant. He would, therefore, submit that there was sufficient and genuine cause for which the delay be condoned.

3. The learned Senior Advocate would further submit that unlike Section 34, no separate limitation is provided for preferring an appeal under Section 37 of the Act. By virtue of Section 43 of that Act, the provisions of the Limitation Act, 1963 would be applicable and consequently, this Court has the power under Section 5 of that Act to condone the delay for sufficient cause. Since it is a matter involving the Government office, it is not unusual that some time is lost in taking necessary steps before filing a proceeding in the Court by law. He would, therefore, submit that the cause being put forth by the applicant is sufficient and the delay deserves to be condoned. The learned Senior Advocate would rely on the decisions in the following cases:—

(i) Union Of India Petitioner(S) v. Varindera Const. Ltd. (S).; SLP(C) No. 23155/2013 decided on 17.09.2018

(ii) Ganesan represented by its Power Agent G. Rukmani Ganesan v. Commissioner, Tamil Nadu Hindu Religious and Charitable Endowments Board; (2019) 7 SCC 108

(iii) State of Madhya Pradesh v. Anshuman Shukla; (2014) 10 SCC 814

(iv) Mukri Gopalan v. Cheppilat Puthanpurayil Aboobacker .; (1995) 5 SCC 5

4. Per contra, Mr. V.B. Patil, learned Advocate for respondent No. 1 strenuously submits that the issue is no more res integra. The Supreme Court has now consistently laid down and in the latest judgment in the case of N.V International v. the State of Assam; Civil Appeal No. 9244 of 2019, arising out of SLP (C) No. 23808/2019, decided on 06.12.2019, has emphatically laid down that any delay beyond 120 days in preferring appeal under Section 37 of the Act cannot be condoned.

5. Mr. Patil, learned Advocate would further submit that even on facts, the applicant has not come to the Court with clean hands. He would point out from the certified copy obtained from the District Court, Dhule (Exhibit-R1), that the application for obtaining the certified copy was, in fact, filed on 14.05.2019 and not in the month of July 2019. He further points out that even in this very application filed by the Advocate representing the applicant, he had specifically indicated that the certified copy was to be handed over to Mr. A.D. Patil from the Irrigation Department, Dhule. He would further point out that from the endorsement on this application put by the concerned staff of the District Court, Dhule, a specific date was given for delivery of the copy as 27.05.2019. It will have to be assumed that it is pursuant to such endorsement, Mr. A.D. Patil of the Irrigation Department in all probability must have received the certified copy on 27.05.2019. Learned Advocate Mr. Patil would, therefore, submit that there is no whisper in the form of rejoinder to this specific evidence put forth by the respondent. He would, therefore, submit that it is only to suit the purpose, Mr. A.D. Patil was again asked to submit an application for obtaining certified copy, which he accordingly filed on 18.07.2019 and it is on the basis of the certified copy obtained pursuant thereto that now the limitation is being sought to be extended. He would, therefore, submit that since the cause being put forth by the applicant is not sufficient and when even it has not come with clean hands the discretion cannot be exercised in its favour.

6. The learned Advocate Mr. Patil would further submit that though it is now being projected by the applicant that its Advocate did not intimate the decision promptly, it is a convenient plea. No affidavit of the learned Advocate has been filed to substantiate it. Therefore, it is liable to be discarded.

7. I have carefully gone through the papers. There can be no doubt in view of the documentary evidence in the form of copy of the application tendered by the Advocate representing the applicant for obtaining a certified copy (Exhibit-R1) that in fact, after pronouncement of the judgment and order in the proceeding under Section 34 of the Act, the concerned Advocate had applied for certified copy on 14.05.2019. The endorsement further reads that it was to be handed over to Mr. A.D. Patil of the Irrigation Department, Dhule, who is a staff from the office of the applicant. The further endorsements also clearly show that the certified copy was ready and was to be delivered on 27.05.2019. Inspite of such a stand and document, the applicant has not controverted this or has not come up with any other stand touching this aspect. It is therefore apparent that the applicant is not coming to the Court with clean hands even while seeking the discretionary relief of condonation of delay.

8. It is precisely for this reason, one will have to proceed by assuming that it is pursuant to the first application dated 14.05.2019 that the applicant must have obtained a certified copy and the limitation will have to be calculated accordingly. Going by such calculation, certainly there is a delay of more than 120 days and not 103 days as is being claimed by the applicant.

9. In view of the observations and conclusion of the Supreme Court in the case of N.V. International (supra) and particularly the observations in paragraph No. 5, the question of condonation of delay of more than 120 days does not survive. The observations read thus:—

“We may only add that what we have done in the aforesaid judgment is to add to the period of 90 days, which is provided by statute for filing of appeals under Section 37 of the Arbitration Act, a grace period of 30 days under Section 5 of the Limitation Act by following Lachmeshwar Prasad Shukul (supra), as also having regard to the object of speedy resolution of all arbitral disputes which was uppermost in the minds of the framers of the 1996 Act, and which has been strengthened from time to time by amendments made thereto. The present delay being beyond 120 days is not liable, therefore, to be condoned.”

10. Therefore, apart from the facts and circumstances discussed hereinabove, even in view of this emphatic observations of the Supreme Court, the delay being beyond 120 days cannot be condoned.

11. Mr. Dhorde, learned Senior Advocate would strenuously submit that since Section 43 of the Arbitration and Conciliation Act, 1996 specifically lays down that the provisions of Limitation Act would be applicable and Section 5 of that Act gives power to condone the delay on sufficient cause being shown, the period of delay is inconsequential. He would submit that there is no reference to this provision of Section 43 in the judgment of the Supreme Court in the case of N.V. International (supra).

12. With respect, one will have to proceed with the assumption that the Supreme Court was alive to the existence of such a provision in the Statute and still, has proceeded to make these observations.

13. So far as the decisions cited by the learned Senior Advocate on behalf of the applicant, in the case of Union Of India Petitioner(S) v. Varindera Const. Ltd. (S)., (supra), it has been referred to by the Supreme Court in the case of N.V. International (supra) and one need not decipher it and suffice to say that referring to this decision, it has now been laid down by the Supreme Court in the case of N.V. International (supra) as mentioned hereinabove in paragraph No. 5 quoted from that judgment (supra).

14. In the case of Ganesan (supra), it has been laid down that if any special or local law specifically provides for applicability of provisions of Limitation Act in deciding the appeal by statutory authority, quasi-judicial authority or Tribunal, the provisions of Section 5 of the Limitation Act would apply. Since the Act contains a specific provision under Section 43, obviously even Section 5 of the Limitation Act would be applicable in the matter in hand. However, the point is, when the Supreme Court in the case of N.V. International (Supra), has emphatically laid down the outer limit beyond which the delay cannot be condoned in respect of appeals under Section 37 of the Act, the applicant is not entitled to derive any benefit from the decision in the case of Ganesan (supra).

15. In the case of State of Madhya Pradesh (supra), the Supreme Court held that Section 5 of the Limitation Act is applicable to the Revisions preferred under Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983. Obviously the decision would not have any bearing on the fact situation of the matter in hand.

16. In the case of Mukri Gopalan (supra), it was held that Section 5 of the Limitation Act would be applicable for preferring the appeals under the Kerala Buildings (Lease and Rent Control) Act, 1965.

17. In view of such state-of-affairs, there is no sufficient cause and even power to condone the delay which is of more than 120 days. The application is rejected.