Arun Kumar Jha v. State Of Jharkhand And Others

Jharkhand High Court
Jun 23, 2022
Smart Summary (Beta)

Factual and Procedural Background

The petitioner, a former officer of Tata Steel Limited terminated in 2000, has been retaining a quarter previously allotted to him by Tata Steel Limited. The dispute arises from non-payment of electricity bills for this quarter. The petitioner received a letter dated 03.05.2022 from the EIC Billing Department, TSU & IS Ltd., stating an outstanding electricity dues amounting to Rs. 1,21,922.35 and issuing a notice under Section 56(1) of the Electricity Act, 2003 due to non-payment. The petitioner contends that no prior electricity bill was served and believes the dues to be excessive. The petitioner also filed a complaint before the District Forum, East Singhbhum, Jamshedpur challenging the demand.

Legal Issues Presented

  1. Whether the complaint filed by the petitioner before the District Forum under the Consumer Protection Act, 1996 is maintainable given the existence of an Electricity Dispute Redressal Forum constituted by Tata Steel Limited under Section 42(5) of the Electricity Act, 2003.
  2. Whether the petitioner is required to follow the grievance redressal mechanism provided under the Jharkhand State Electricity Regulatory Commission Regulations, including filing a complaint before the Electricity Disputes Redressal Forum constituted by the distribution licensee.
  3. The validity of the outstanding dues claimed by the respondent and the procedure for resolving the dispute.

Arguments of the Parties

Respondent's Arguments

  • The complaint before the District Forum is not maintainable as Tata Steel Limited, the distribution licensee, has constituted an Electricity Dispute Redressal Forum under Section 42(5) of the Electricity Act, 2003.
  • The petitioner should seek redressal through the Jharkhand State Electricity Regulatory Commission (Electricity Supply Code) Regulation, 2015 and the 2020 Regulations on grievance redressal forums and consumer advocacy.

Petitioner's Arguments

  • The petitioner claims no electricity bill was served prior to the impugned notice, thus disputing the correctness and quantum of the outstanding dues.
  • The petitioner undertakes to withdraw the complaint filed before the District Forum within three weeks.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court recognized that the Electricity Dispute Redressal Forum constituted by Tata Steel Limited under the Electricity Act, 2003, is the appropriate forum for resolving disputes related to electricity billing in the concerned area. Consequently, the complaint filed before the District Forum under the Consumer Protection Act, 1996, is not maintainable. The Court accepted the petitioner’s undertaking to withdraw that complaint and directed the petitioner to deposit Rs. 50,000 as an interim measure. The petitioner was further directed to file a complaint before the Electricity Disputes Redressal Forum constituted by Tata Steel Limited, which is required to hear and dispose of the matter on merit within two months. The Court ensured protection of the petitioner’s electricity connection by ordering no disconnection upon deposit of the interim amount until the forum disposes of the complaint. The Court’s directions reflect an application of statutory provisions regulating electricity disputes and emphasize adherence to the prescribed grievance redressal mechanism to maintain orderly resolution of such disputes.

Holding and Implications

The writ petition is disposed of subject to the petitioner withdrawing the complaint before the District Forum, depositing Rs. 50,000 within three weeks, and filing a complaint before the Electricity Disputes Redressal Forum constituted by Tata Steel Limited.

The petitioner’s electrical connection shall not be disconnected upon deposit of the interim amount until the Electricity Disputes Redressal Forum disposes of the complaint within two months. This decision enforces the statutory grievance redressal framework under the Electricity Act, 2003, and the relevant Jharkhand State Electricity Regulatory Commission regulations. No new precedent is established; the ruling primarily directs the parties to follow the existing regulatory and dispute resolution mechanisms.

Show all summary ...

Rajesh Shankar, J.:— The present writ petition has been filed for quashing the letter dated 03.05.2022 (Annexure-1 to the writ petition) issued by the respondent no. 4 - EIC Billing Department (Billing Department), TSU & IS Ltd., Bistupur, Jamshedpur informing the petitioner that an amount of Rs. 1,21,922.35/- is the total outstanding dues for the electrical connection and due to non-payment of the same, a notice under Section 56(1) of the Electricity Act, 2003 is being issued.

2. The petitioner, who happened to be an officer under Tata Steel Limited and was terminated from service in the year 2000, has been retaining the quarter earlier allotted to him by Tata Steel Limited. The present dispute is with respect to non-payment of electricity bills by him for the said quarter. The grievance of the petitioner is that prior to issuance of impugned notice dated 03.05.2022, no electricity bill was served to him and hence, he has the reason to believe that the dues being shown against him is excessive.

3. Mr. M.S. Mittal, learned Senior Counsel for the respondent nos. 4 and 5, at the outset, submits that the petitioner has also filed a complaint before the District Forum, East Singhbhum, Jamshedpur against the demand with respect to the electricity consumption. It is further submitted that Tata Steel Limited, who is the distribution licensee in the concerned area i.e., Jamshedpur has already constituted Electricity Dispute Redressal Forum under Section 42(5) of the Electricity Act, 2003 and, therefore, the complaint filed before the District Forum, East Singhbhum, Jamshedpur under the provisions of the Consumer Protection Act, 1996 is not maintainable. If the petitioner has any grievance against raising of the electricity bills/demand for the electrical connection in question, he should take recourse under the provisions of Jharkhand State Electricity Regulatory Commission (Electricity Supply Code) Regulation, 2015 and Jharkhand State Electricity Regulatory Commission (Guidelines for Establishment of Forum for Redressal of Grievances of the Consumers, Electricity Ombudsman and Consumer Advocacy) Regulations, 2020.

4. At this juncture, Mr. Peeyush Krishna Choudhary, learned counsel for the petitioner, undertakes that the petitioner will withdraw the aforesaid complaint filed before the District Forum, East Singhbhum, Jamshedpur within three weeks from today.

5. Under the aforesaid facts and circumstance, following order is being passed:

(i) In view of the undertaking, the petitioner shall withdraw the complaint from District Forum, East Singhbhum, Jamshedpur within three weeks from today.

(ii) The petitioner shall deposit Rs. 50,000/- out of the impugned demand of Rs. 1,21,922.35/- within the aforesaid period of three weeks.

(iii) The petitioner shall file complaint in the Electricity Disputes Redressal Forum i.e., Tata Steel Limited Forum, constituted by the distribution licensee Tata Steel Limited, situated at Quarter No. L4/73, Kasidih (North), Old Baradwari, Sakchi, Jamshedpur within one week thereafter.

(iv) On filing of the said complaint, the Forum of Tata Steel Limited shall proceed to hear the case on merit and dispose of the same in accordance with law within two months from the date of filing of the said complaint.

(v) On deposit of Rs. 50,000/- against the impugned demand, the electrical connection in question will not be disconnected till disposal of the complaint by the Electricity Disputes Redressal Forum of Tata Steel Limited and the impugned demand in respect to the electrical connection in question will be subject to the outcome of the said complaint.

6. The writ petition is accordingly disposed of with aforesaid observation and direction.

7. I.A. No. 4501 of 2022 also stands disposed of accordingly.