VINOD GUPTA & ANR. v. EMAAR MGF LAND LIMITED & 3 ORS.

National Consumer Disputes Redressal Commission
Jul 4, 2022
Smart Summary (Beta)

Factual and Procedural Background

The present Consumer Complaint under Section 21(a)(i) of the Consumer Protection Act, 1986 was filed by the Complainants, husband and wife, against the Opposite Parties, M/s Emaar MGF Land Limited and M/s Brijbasi Projects Private Limited (referred to as "the Developers"). The Complainants sought refund of the entire amount deposited towards the purchase of a residential unit in the project "The Palm Terraces Select", alleging failure by the Developers to deliver possession as promised.

The Complainants applied on 27.07.2010 for allotment of a residential unit in the project at Sector 66, Gurgaon, with a total sale consideration of ₹1,66,75,890/-. They were allotted Unit No. PTS-05-0801 on the 8th floor of Tower No. 05, measuring 2410 sq. ft., along with two car parking spaces. The Builder Buyer's Agreement was executed on 22.11.2010, stipulating possession within 36 months from the start of construction subject to force majeure conditions.

The Complainants paid approximately 96% of the sale consideration (₹1,61,61,140/-) and obtained a home loan of ₹1,50,00,000/-. Despite this, the Developers failed to complete construction and hand over possession by the promised date of 22.11.2013. The Complainants were not allowed site visits and faced prolonged delay of over seven years, constituting alleged deficiency of service. The complaint sought refund with interest, lump-sum compensation for mental agony and financial loss, and litigation costs.

The Opposite Parties denied the allegations, contending payment defaults by the Complainants, maintainability issues including pecuniary jurisdiction, the applicability of an arbitration clause, and that the Complainants were not consumers under the Act. They asserted possession had been offered and delay was due to force majeure and restructuring of the Developer company.

Legal Issues Presented

  1. Whether the Developer's failure to deliver possession within the stipulated time constitutes deficiency of service under the Consumer Protection Act?
  2. Whether the Complainants qualify as "Consumers" under Section 2(1)(d) of the Consumer Protection Act?
  3. Whether the arbitration clause in the Builder Buyer's Agreement bars the Consumer Forum's jurisdiction?
  4. Whether the Consumer Forum has pecuniary jurisdiction to entertain the complaint given the sale consideration and compensation claimed?
  5. Whether the terms of the Builder Buyer's Agreement, particularly the compensation clause for delay, are fair and enforceable?
  6. Whether the Complainants are entitled to refund of the amount paid along with interest and compensation for delay?

Arguments of the Parties

Complainants' Arguments

  • They paid nearly full sale consideration and complied with all terms but possession was not delivered as promised.
  • Developers failed to allow site visits and did not provide possession even after seven years.
  • The compensation clause providing ₹7.50 per sq. ft. per month for delay is meagre and constitutes unfair trade practice.
  • They are entitled to refund of the entire amount with interest, lump-sum compensation for mental agony, and litigation costs.

Developers' Arguments

  • The Complainants defaulted in timely installment payments and were charged delay interest.
  • The complaint is not maintainable due to lack of pecuniary jurisdiction and arbitration clause in the Agreement.
  • The Complainants are not consumers as they own a house and purchased the unit for commercial/speculative purposes.
  • The delay was due to force majeure and restructuring of the Developer company.
  • Time is not the essence of contract and compensation for delay is limited as per the Agreement.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Bharti Knitting vs DHL Courier World Wide Express Courier (1996) 4 SCC 704 Binding nature of contract terms and non-modification by Consumer Fora. Noted by Developer but distinguished in light of unfair terms doctrine and consumer protection.
Deepika Chaudhary Chandra & Ors. vs. Emaar MGF Land Ltd. - Consumer Complaint No. 1337 of 2018 Rejection of arbitration clause as a bar to Consumer Forum jurisdiction; definition of consumer. Applied to reject Developer's objections on arbitration and consumer status.
M/S Emaar MGF Land Limited vs. Aftab Singh - I (2019) CPJ 5 (SC) Arbitration clause does not bar Consumer Forum jurisdiction. Supported the Commission's jurisdiction despite arbitration clause.
Kavita Ahuja vs. Shipra Estates I (2016) CPJ 31 Onus on Developer to prove that Complainant is a speculator dealing in real estate business. Used to hold Complainants qualify as consumers under the Act.
Ambrish Kumar Shukla & Ors. vs. Ferrous Infrastructure Pvt. Ltd. - CC No.97 of 2016 Sale consideration relevant for pecuniary jurisdiction of Consumer Commission. Applied to confirm pecuniary jurisdiction over the complaint.
Renu Singh vs. Experion Developers Private Limited - CC No. 1703 of 2018 Value of services for pecuniary jurisdiction includes sale consideration for refund claims. Supported pecuniary jurisdiction finding in present case.
Pioneer Urban Land & Infrastructure Ltd. vs. Govindan Raghavan II (2019) CPJ 34 (SC) Unfair and one-sided contract terms constitute unfair trade practice; consumer cannot be bound by such terms. Held the delay compensation clause unfair and one-sided, supporting consumer protection.
Sivarama Sarma Jonnalagadda & Anr vs. M/s Maruthi Corporation Limited & Anr - Consumer Complaint No. 379 of 2013 Force majeure cannot be used to indefinitely delay possession; retention of amounts constitutes deficiency and unfair trade practice. Applied to reject Developer's force majeure defense and hold deficiency of service.
Lucknow Development Authority v. M.K Gupta (1994) 1 SCC 243 Construction of house or flat for consideration is "service" under Consumer Protection Act. Confirmed delay in possession amounts to deficiency of service.
Fortune Infrastructure & Anr. v. Trevor D'Lima and Ors. (2018) 5 SCC 442 Buyer cannot be made to wait indefinitely and is entitled to refund with compensation. Supported consumer's right to refund and compensation due to delay.
Kolkata West International City Pvt. Ltd. vs. Devasis Rudra II (2019) CPJ 29 SC Reasonable period for possession; seven years delay is beyond reasonable; refund justified. Applied to hold that the Complainants cannot be made to wait indefinitely and refund is justified.
DLF Homes Panchkula Pvt. Ltd. vs. D.S. Dhanda II (2019) CPJ 117 (SC) Compensation under multiple heads cannot be awarded simultaneously. Applied to restrict compensation to simple interest at 9% p.a. plus costs.

Court's Reasoning and Analysis

The Court examined the Builder Buyer's Agreement and noted the stipulated possession period of 36 months subject to force majeure. The Complainants had paid approximately 96% of the sale consideration and complied with all terms. Despite this, possession was not delivered by the promised date, with the offer of possession made only in 2018, nearly five years late.

The Court rejected the Developer's defense of payment default by the Complainants causing delay, noting that the Developer had the contractual option to cancel or charge interest but did not cancel the booking. The arbitration clause was held not to bar the Consumer Commission's jurisdiction, following Supreme Court precedent.

Regarding the status of the Complainants as consumers, the Court relied on precedent placing the onus on the Developer to prove speculative intent, which was not discharged. The pecuniary jurisdiction was affirmed based on the sale consideration amount.

The Court analyzed the compensation clauses and found them one-sided and unfair, with the Complainants liable to pay 24% interest on delayed payments while receiving only ₹7.50 per sq. ft. per month for delay in possession. This imbalance was held to constitute unfair trade practice per Supreme Court authority.

The Court also found no cogent evidence for force majeure causing delay and held that indefinite waiting by the Complainants is unreasonable. It relied on multiple precedents to affirm that delay in possession amounts to deficiency of service and entitles the Complainants to refund with interest and compensation.

In line with Supreme Court rulings, the Court awarded refund of the principal amount with interest at 9% p.a. and costs of ₹50,000, rejecting claims for lump-sum compensation beyond this. The ruling balanced the rights of the Complainants and the contractual terms, emphasizing fairness and consumer protection.

Holding and Implications

The Consumer Complaint is PARTLY ALLOWED. The Opposite Party Developers are directed to refund the entire principal amount deposited by the Complainants along with interest at 9% per annum from the respective dates of deposit until payment, within six weeks. In case of delay beyond this period, interest shall accrue at 12% per annum. The Complainants are also awarded litigation costs of ₹50,000.

The decision underscores that arbitration clauses do not bar Consumer Fora jurisdiction, that consumers cannot be bound by unfair and one-sided contract terms, and that indefinite delay in possession constitutes deficiency of service entitling buyers to refund with interest. No new precedent is created but existing consumer protection principles are reaffirmed and applied to the facts.

Show all summary ...

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

NEW DELHI

CONSUMER CASE NO. 3198 OF 2017

1. VINOD GUPTA & ANR. S/O MR MANGE RAM GUPTA R/O H NO. 333, SECTOR 46-A,

CHANDIGARH

2. MRS DEEPIKA GUPTA

W/O MR VINOD GUPTA R/O HOUSE NO. 333, SECTOR 46-A,

CHANDIGARH ...........Complainant(s) Versus

1. EMAAR MGF LAND LIMITED & 3 ORS. THROUGH ITS MANGING DIRECETOR/DIRECTOR

REGD OFFICE AT: 28, ECE HOUSE, KASTURBA

GANDHI MARG,

NEW DELHI-110001

2. M/S BRIJBASI PROJECTS PRIVATE LIMITED THROUGH ITS MANAGING DIRECTOR/DIRECTOR REGD OFFICE AT: 1557, SECTOR-45,

GURGAON

HARYANA

3. SH SHRAVAN GUPTA, MANAGING DIRECTOR

OF EMAAR MGF LAND LTD

28, ECE HOUSE, KASTURBA GANDHI MARG,

NEW DELHI-110001

4. HOUSING DEVELOPMENT FINANCE

CORPORATION LTD

REGD. OFFICE AT: RAMAN HOUSE, 169,

BACKBAY RECLAMATION,

MUMBAI-400020

MAHARASHTRA ...........Opp.Party(s)

BEFORE:

HON'BLE MR. JUSTICE R.K. AGRAWAL,PRESIDENT

HON'BLE DR. S.M. KANTIKAR,MEMBER

HON'BLE MR. BINOY KUMAR,MEMBER

For the Complainant : For the Complainants : Mr. Deepak Aggarwal, Advocate

For the Opp.Party : For the Opposite Parties : Mr. Sunil Mund, Advocate

-1-

Dated : 04 Jul 2022

ORDER

1. The present Consumer Complaint under Section 21(a)(i) of the Consumer Protection Act, 1986 (for short "the Act") has been filed by the Complainants, husband and wife (hereinafter to be referred as the "Complainants") against the Opposite Parties, namely, M/s Emaar MGF Land Limited and M/s. Brijbasi Projects Private Limited (hereinafter to be referred as "the Developers") seeking refund of the entire amount deposited by the Complainants towards the purchase of the Unit in the Project under the name and style of " The Palm Terraces Select" as the Opposite Parties Developer completely failed to deliver the possession as promised.

02. The facts of the case as averred in the Complaint are that the Complainants, husband and wife, vide Application dated 27.07.2010, applied for allotment of a Residential Unit in the Project, namely, "The Palm Terraces Select" (hereinafter to be referred to as "the Project ") proposed to be developed by the Opposite Parties Developer at Sector 66, Gurgaon. The Total sale Consideration of the Unit is 1,66,75,890/-. The Complainants were allotted Unit No. PTS-05-0801 on 8TH Floor in Tower/Block No. 05 admeasuring 2410 Sq. Ft. along with the exclusive right to use two Car Parking Space at the rate of 3,00,000/- each. The Builder Buyer's Agreement (hereinafter to be referred as the Agreement) was executed between the parties on 22.11.2010. As per Clause 14(a) of the Agreement, the physical possession of the allotted Unit was to be handed over to the Complainants within a period of 36 months from the date of start of construction, subject to force majeure conditions. Clause 14(a) of the Agreement reads as under:-

" Subject to terms of this clause and the Allottee(s) having complied with all the terms and conditions of this Agreement and not being in default under any of the provisions of this Agreement and upon complying with all provisions, formalities, documentation etc., as prescribed by the Developer, the Developer shall make all efforts to handover possession of the Unit (which falls within ground plus four floors tower/building) within a period of thirty (30) months from the date of commencement of construction, and for the Unit (which falls within ground plus thirteen floors/building) within a period of thirty six (36) months from the date of commencement of construction, subject to certain limitations as may be provided in this Agreement and timely compliance of the provisions of this Agreement by the Allottee(s). The Allottee(s) agrees and understands that the Developer shall be entitled to a grace of three (3) months, for applying and obtaining the occupation certificate in respect of the Unit and/or the Project"

03. According to the Complainants, they have made a payment of 1,61,61,140/- i.e. approx.. 96% of the total sale consideration of 1,66,75,890/- as demanded by the Developer without any default but still the Developer has miserably failed to complete the construction of the Project and to hand over the possession of the allotted Unit, complete in all respect, by 22.11.2013 as promised. It is further averred that the Complainants have obtained the home loan for a total sum of 1,50,00,000/- from the Financial Institution/Bank for making the payment of the costs of allotted Unit and are paying the huge EMI. The Complainants made persuasive efforts to enquire about the exact status of the construction from the Developer but in vein. Even, they were not permitted to visit the site on the pretext of construction work is going on. It is stated that from the last seven years, the Complainants are waiting for offer of possession and as such it is a clear cut

-2-

case of deficiency of service on the part of the Opposite Party Developer. It is also stated that in case of default in making the payment of installment on the part of the Flat Buyers, the Developer is entitled to charge exorbitant interest @24% p.a. in terms of Clause 13(a) of the Agreement, however, for the delay on their part in offering the possession of the allotted Units, they are liable to pay delayed compensation of meagre amount of 7.50 per sq. ft. per month of the Super Area which amounts to an Unfair Trade Practice. Thus, alleging deficiency in service on the part of the Opposite Party Developer, the Complainants have the filed present complaint seeking following reliefs:-

(i) to refund the entire amount of 1,61,61,140/- deposited by the Complainants towards price of residential unit, in question, along with interest @15% p.a. from the respective date of deposits till realization;

(ii) to pay lump-sum compensation in the sum of Rs.5 lakh on account of mental agony, physical harassment, deficiency in providing service, adoption of unfair trade practice, negligence, financial loss, escalation in prices of the real estate;

(iii) to pay cost of litigation to the tune of Rs.2.5 lakh to the Complainant;

04. The Opposite Parties Developer has filed its Written Version denying the contents of the Complaint and contending that the Complainants have been flouting with the terms of the Agreement. They have defaulted in making timely payments of installments despite reminders and delay charges to the tune of 1,35,099/- have been levied upon them. It is further pleaded that; the Complaint is not maintainable before this Commission for want of pecuniary jurisdiction inasmuch as the possession of the allotted Unit had already been offered to the Complainants and the claim, if any, is only for compensation and the same by no stretch of calculation can go beyond 1 crore; since the Complainants owned their house in Chandigarh, the Unit in question has been booked only for commercial purposes or earning profits and as such the Complainants are mere speculators; the Complainants do not fall under the category of "Consumer" as defined under section 2(1)(d) of the Act; the Complaint is barred by limitation as provided u/s 24A of the Act; the terms & conditions of the Agreement are binding upon the parties as held by Hon'ble Supreme Court of India in the matter of Bharti knitting Vs DHL Courier World Wide Express Courier - (1996) 4 SCC 704 ; parties are bound by terms of contract and there is no power or jurisdiction to the Consumer Fora under the Act to direct modification of any Clause of the Agreement; Clause 37 of the Agreement clearly provides that any dispute arising in relation to the terms of the Agreement including interpretation and validity of the terms thereof and the respective rights and obligations of the parties would be settled through Arbitration;

05. On merits of the case, it is rigorously submitted that; there is no cause of action in favour of the Complainants due to delay on their part to make timely payment and as such they are not entitled for the reliefs prayed in the Complaint; Clause 14 (a) of the Agreement clearly provides that the Opposite Party Developer would endeavor to hand over the possession of the allotted Unit within a period of 36 months from the date of commencement of construction subject to force majeure circumstances and on receipt of due installments; time is not the essence of contract; the Hon'ble Supreme Court in the cases of Chand Rani vs. Kamal Rani, 1993 (1) SCC 519 and

Gomathinayagam Pillai vs. Palaniswami Nadar, 1967 (1) SCR 227 , has held that fixation of the period within which the contract has to be performed, does not make the stipulation as to time, the

-3-

essence of the contract and when a contract relates to a sale of immovable property, it will normally be presumed that time is not the essence of the contract; the Project got delayed due to reasons which were beyond their control; the Developer has undergone re-structuring and in order to ensure focused leadership and development of the on-going Projects by way of process of demerger of the Opposite Party pursuant to a Scheme of Arrangement under Section 391-394 of the Companies Act, 1956; the Project in question has been completed and after obtaining the Occupancy Certificate, the offer of possession has been made to the Complainants vide letter dated 14.03.2018; as per Clause 16(a) of the Agreement, if the Developer is not able to hand over the possession to the allottees(s), they shall be entitled to the payment of compensation for delay @ 7.50 per sq. ft. per month of the Super Area till the date of notice of possession;

06. We have heard the learned Counsel for the Parties and perused the material available on record and evidence adduced by the parties.

07. The preliminary issues raised by the Developer and the defence taken by them justifying delay in completion of the Project in question have already been dealt with by this Commission in the case of Deepika Chaudhary Chandra & Ors. Vs. Emaar MGF Land Ltd. - Consumer Complaint No. 1337 of 2018 decided on 02.06.2022 which relates to the same Project, namely,

"Palm Terrace Select" and the same Opposite Parties. While rejecting all the afore-mentioned contentions of the Opposite Parties, this Commission has held as under:-

" The Complaint was resisted by the Opposite Party Developer by filing its Written Statement in which the Opposite Party Developer averred that there is Arbitration Clause in the Agreement, therefore, the present Complaint is not maintainable before this Commission; the Complainants has owned their house in Gurgaon itself and have booked the Apartment in question for commercial/investment/speculative purpose, therefore, they do not fall within the definition of Consumer in terms of Section 2(1)(d)(ii) of the Act. It was also averred that this Commission has no pecuniary jurisdiction to entertain the Complaint as the compensation sought cannot go beyond 1 Crore. Relying upon Judgments passed by the Hon'ble Supreme Court, it was averred that terms & conditions of the Agreement is binding upon the Parties and thus in the case of delay in handing over physical possession of the Apartment, the Complainants are entitled for delayed compensation @ 7.50/- per sq. ft. per month in terms of Clause 16(a) of the Agreement….

We have heard Mr. Varun Garg, learned Counsel for the Complainants, Mr. Sunil Mund, learned Counsel for the Opposite Party Developer and perused Complaints, Written Statements and given a thoughtful consideration to the various pleas raised by them.

The Hon'ble Supreme Court in M/S Emaar MGF Land Limited vs. Aftab Singh - I (2019) CPJ 5 (SC), has laid down the law that an Arbitration clause in the Agreement does not bar the jurisdiction of the Consumer Fora to entertain the Complaint. Hence, the objection raised by the Opposite Party Developer that the clause of Arbitration bars this Commission from entertaining the Complaint is unsustainable.

-4-

The contention of the Opposite Party Developer that the Complainants have already owns a house in Gurugram and have booked the subject Apartment for commercial/investment/ speculative purpose, is completely unsustainable in the light of the judgement of this Commission in Kavita Ahuja vs. Shipra Estates I (2016) CPJ 31, in which the principle laid down is that the onus of establishing that the Complainant was dealing in real estate i.e. in the purchase and sale of plots/ flats in his normal course of business to earn profits, shifts to the Opposite Party, which in the instant case they had failed to discharge by filing any documentary evidence to establish their case. Therefore, we are of the considered view that the Complainants do fall under the definition of 'Consumer' as defined under Section 2 (1)(d) of the Act .

So far as the pecuniary jurisdiction is concerned, in terms of Section 21 of the Consumer Protection Act, this Commission possesses the requisite pecuniary jurisdiction where the value of the goods or services as the case may be and the compensation claimed exceeds 1 Crore.As held by a three Members Bench of this Commission in CC No.97 of 2016 Ambrish Kumar Shukla & Ors. Vs. Ferrous Infrastructure Pvt. Ltd., decided on 07.10.2016, the value of the services in such a case would mean the sale amount agreed to be paid by the Flat Buyer to the Developer, which has been held to lay down the law correctly on the issue relating to pecuniary jurisdiction and the sale consideration which was agreed between the Parties for buying the goods or hiring or availing the services is relevant for determination of pecuniary jurisdiction in cases of refund also by a larger Bench of 5 Members of this Commission in "CC No. 1703 of 2018, Renu Singh vs. Experion Developers Private Limited" and other connected matters decided on 26.10.2021.In the present case, even the agreed sale consideration is 1,71,56,670/-.Therefore, it would be difficult to say that this Commission does not possess the requisite pecuniary jurisdiction.

The plea of the learned Counsel for the Developer regarding binding nature of the Agreement/Contract whereby the Parties are bound by the terms and conditions of the Agreement, to compensate the Complainant for delay in terms of Clause 16(a) of the Agreement, we have gone through the Clause 13(a) and 16(a) of the Agreement, which read as under:-

"13(a) In case of delay in making payment by the Allotment (s) to the Developer as per the Schedule of Payment as stated in Annexure-2, the Developer shall have right to terminate the Agreement and forfeit the Earnest Money as detailed hereinabove. The Developers shall also be entitled to charge interest @24% p.a. till the date of payment. 16(a) Subject to Clause 31, in case within a period as set out in clause 14(a), the Developers is not able to hand over the possession to the Allottee(s), the Allottee(s) shall be entitled to the payment of compensation for delay at the rate of 7.50/- (Rupees seven and fifty paise only) per sq. ft. per month of the Super Area till the date of notice of possession under the provision of clause 15(a) provided the

-5-

Allottee(s) has complied with all the terms and conditions of this Agreement. The Allottee(s) shall have no other claim against the Developer in respect of the said Unit and Parking Space under this Agreement during the said period of twelve (12) months" A bare perusal of above Clauses makes it clear that as per Clause 16(a) of the Agreement, in case of delay the Opposite Party Developer is liable to pay 7.50/- per sq. ft. of the super built up area of the Apartment per month for the period of delay in offering of possession, whereas in terms of Clause 13(a) in case of late payment, the Complainants/Buyers are liable to pay interest @24% p.a.This shows that the terms of the Agreement are wholly one-sided and unfair. Therefore, the Complainants cannot be made bound to the terms of the Agreement, which are one-sided and unfair in the light of the recent Judgment of the Hon'ble Apex Court in Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan, II (2019) CPJ 34 (SC), wherein the Apex Court has observed as follows:

"6.7. A terms of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The contractual terms of the Agreement dated 08.05.2012 are ex-facie one sided, unfair and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2(r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder."

7. In view of the above discussion, we have no hesitation in holding that the terms of the Apartment Buyer's Agreement dated 08.05.2012 were wholly one-sided and unfair to the Respondent-Flat Purchaser. The Appellant-Builder cannot seek to bind the Respondent with such one-sided contractual terms."

08. We also do not find any substance in the contention of the Developer that due to default on the part of the Complainants in timely making payment of the installments, there was delay in completion of the Project. If there was default on the part of the Complainants in making the payments on due time, the Developer in terms of the Agreement was at liberty to either cancel their booking and refund the amount or to charge the interest on delayed payment. Having not exercising the option to cancel the booking and to charge the interest on the delayed payment, the Developer cannot take shelter under this pretext for delay in the Project.

09. The undisputed facts of the case are that the Complainants have applied for purchase of Unit in the aforesaid Project of the Opposite Party Developer on 22.11.2010. The Complainants were allotted Unit No. PTS-05-0801 on 8thFloor in Tower/Block No.5. The Builder Buyer's Agreement was executed between the parties on 221.11.2010. As per Clause 14(a) of the Agreement dated 22.11.2010, the Developer was under an obligation to hand over the physical possession of the allotted unit, complete in all respect, within a period of 36 months from the date of start of construction subject to force majeure conditions. There is no denial to the fact that the Complainants have paid a sum of 1,61,61,140/- i.e. approx.. 96% of the total sale consideration of

-6-

1,66,75,890/- to the Developer, however, they have completely failed to complete the Project and hand over the possession of the allotted Unit to the Complainants till 22.11.2013 as promised. As admitted in the Written Version, the offer of possession was made to the Complainants only on 14.03.2018 i.e after expiry of period of about 5 years from the committed date of delivery. According to the Developer, the delay in offering the possession has occurred due to the reasons which were force-majeure and beyond their control. However, no cogent material has been adduced by the Developer to establish that the completion of construction and offer of possession has been delayed on account of reasons beyond their control. In this regard, a reference is made to the Order passed by this Commission in Sivarama Sarma Jonnalagadda & Anr vs. M/s Maruthi Corporation Limited & Anr - Consumer Complaint No. 379 of 2013 decided on 21.09.2021

wherein it was held as under:-

" We are of the view that the Complainant cannot be made to wait indefinitely for the delivery of possession and the act of the Opposite Party in relying on force majeure clause while retaining the amounts deposited by the Complainant , is not on only an act of deficiency of service but also amounts to unfair trade practice."

10. In the case of Emmar MGF Land Ltd. & Ors. vs. Amit Puri - [II (2015) CPJ 568 (NC)],

this Commission has held that after the promised date of delivery, it is the discretion of the Complainant whether to accept the offer of possession, if any, or to seek refund of the amounts paid by him with some reasonable compensation and it is well within his right to seek for refund of the principal amount with interest and compensation.

11. In another Landmark judgement of the Hon'ble Supreme Court, titled Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghvan, ll (2019) CPJ 34 (SC), decided on 02.04.2019 it was held as under:

" In the present case, admittedly the Appellant-Builder obtained the Occupancy Certificate almost 2 years after the date stipulated in the Apartment Buyer's Agreement. As a consequence, there was a failure to hand over possession of the flat to the Respondent-Flat Purchaser within a reasonable period. The Occupancy Certificate was obtained after a delay of more than 2 years on 28.08.2018 during the pendency of the proceedings before the National Commission.

In Lucknow Development Authority v. M.K Gupta .. Gupta: (1994) 1 SCC 243, this Court held that when a person hires the services of a builder, or a contractor, for the construction of a house or a flat, and the same is for a consideration, it is a

"service" as defined by Section 2 (o) of the Consumer Protection Act, 1986. The inordinate delay in handing over possession of the flat clearly amounts to deficiency of service.

In Fortune Infrastructure and Anr. v. Trevor D'Lima and Ors., : (2018) 5 SCC 442 this Court held that a person cannot be made to wait indefinitely for possession of the flat allotted to him, and is entitled to seek refund of the amount paid by him, along with compensation.

-7-

The Respondent-Flat Purchaser has made out a clear case of deficiency of service on the part of the Appellant-Builder. The Respondent-Flat Purchaser was justified in terminating the Apartment Buyer's Agreement by filing the Consumer Complaint, and cannot be compelled to accept the possession whenever it is offered by the Builder. The Respondent-Purchaser was legally entitled to seek refund of the money deposited by him along with appropriate compensation."

12. Further, in the case of Kolkata West International City Pvt. Ltd. Vs. Devasis Rudra - II (2019) CPJ 29 SC, the Hon'ble Apex Court has observed as under :-

".....It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period. A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund.

In the circumstances, we are of the view that the orders passed by the SCDRC and by the NCDRC for refund of moneys were justified."

13. In the instant case also, the Complainants cannot be made to wait indefinitely for possession of their allotted Unit and the Complainants are entitled for refund of the principal amount with reasonable interest. Accordingly, keeping in view the ratio laid down by the Hon'ble Supreme Court in DLF Homes Panchkula Pvt. Ltd Vs. D.S. Dhanda - II (2019) CPJ 117 (SC) , that compensation under multiple heads cannot be awarded, we are of the considered view that simple interest in the form of compensation @ 9% p.a. would meet the ends of justice together with costs of 50,000/-.

14. In view of the aforesaid discussion, we partly allow the Complaint with a direction to the Opposite Party Developer to refund the entire principle amount along with interest @9% p.a. from the respective date of deposit till payment, within a period of six weeks from the date of passing of this Order failing which the amount shall carry interest @12% p.a. for the said period. The Complainants are also entitled for costs of 50,000/-.

15. The Consumer Complaint is allowed in above terms. The pending applications, if any, also stand disposed of.

......................J

R.K. AGRAWAL

PRESIDENT

......................

DR. S.M. KANTIKAR

MEMBER

-8-

......................

BINOY KUMAR

MEMBER

-9-