Deepika Chaudhary Chandra And Another Complainant(S) v. Emaar Mgf Land Limited Opp.Party(S).

National Consumer Disputes Redressal Commission
Jun 2, 2022
Smart Summary (Beta)

Summary of Opinion — National Consumer Disputes Redressal Commission

Factual and Procedural Background

The Complaint was filed by Deepika Chaudhary Chandra and Arun Kumar Chandra (Complainants) under Sections 21(a)(i) and 22(1) of the Consumer Protection Act, 1986 against M/s Emaar MGF Land Limited (Opposite Party / OP Developer). The Complainants claim to have booked a residential apartment (Unit No. PTS-10-0502) in the group housing project "Palm Terrace Select" in Sector 66, Gurugram, on 18.07.2010, paying a booking amount of ₹10,00,000/-. An Apartment Buyer's Agreement was exchanged in 2010; the total sale consideration was ₹1,71,56,670/-. Clause 14 of the Agreement provided for delivery of possession within 36 months plus a 3 month grace period. Construction allegedly began on 31.07.2012; possession was therefore due by 31.10.2015.

The Complainants assert they paid approximately 95% of the sale consideration (₹1,68,74,791/-) by May 2018, but possession was delivered only in 2020 and the conveyance deed had not been executed as of 13.07.2021. The Complainants allege deficiency of service, challenge certain Agreement terms as unilateral and unfair, and complain about being charged ₹7 lakh for two car parking spaces. They seek reliefs including possession, interest/compensation for delayed delivery, refund of car parking charges, compensation for mental agony, and litigation costs.

The OP Developer filed a Written Statement contending, inter alia, that: (i) an arbitration clause in the Agreement bars the Commission's jurisdiction; (ii) the Complainants are not "consumers" as they already own a house and booked the unit for investment/speculation; (iii) the Commission lacks pecuniary jurisdiction; (iv) the Agreement's terms (including a capped compensation at ₹7.50 per sq. ft. per month per Clause 16(a)) are binding; and (v) the covered car parking is not part of common area but an exclusive entitlement.

During proceedings the OP offered possession subject to payment of outstanding dues; by Order dated 13.11.2019 the Commission directed the complainants to deposit the admitted and disputed amounts as specified and permitted deposit with the Commission. The Registry was later directed to release the disputed amounts to the OP Developer, subject to the Commission's final determination.

Legal Issues Presented

  1. Whether the disputed sums (including car parking charges, balance of basic sale price and PLC, delay payment charges and advance maintenance) were payable by the Complainants and, as a consequence, whether the disputed amount deposited with the Commission should be released to the OP Developer.
  2. Whether the Complainants were entitled to delayed compensation for late delivery of possession and, if so, the quantum/rate and period of such compensation.

Arguments of the Parties

Complainants' Arguments

  • The Complainants booked the apartment in July 2010 relying on advertisements and assurances that construction and possession would occur within the stipulated time; possession was contractualy due by 31.10.2015 but was delayed until 2020.
  • They paid approx. 95% of the sale consideration (₹1,68,74,791/-) as demanded but the OP failed to deliver possession within the stipulated period.
  • The Apartment Buyer's Agreement contained unilateral and one-sided clauses depriving the Allottees of bargaining power.
  • The OP wrongly charged ₹7 lakh for two basement car parking spaces which the Complainants contend form part of the common area (and therefore ownership should not have been transferred or charged as exclusive entitlement).
  • Reliefs sought included handing over possession in habitable condition, interest at 24% per annum on amounts paid for delayed possession and for installments paid before construction started, refund of car parking charges with 18% interest, ₹20,00,000/- as compensation for mental agony, and ₹2,00,000/- litigation costs.

Opposite Party (Developer)'s Arguments

  • The Agreement contains an arbitration clause; therefore, the Consumer Commission has no jurisdiction to entertain the Complaint.
  • The Complainants already own a house in Gurugram and booked the apartment for commercial/investment/speculative purposes; hence they do not fall within the statutory definition of "consumer" under Section 2(1)(d)(ii) of the Act.
  • The Commission lacks pecuniary jurisdiction because the compensation sought cannot exceed ₹1 crore.
  • The terms of the Agreement are binding; in case of delay the remedy is limited to compensation at ₹7.50 per sq. ft. per month under Clause 16(a). The Agreement also provides for charging interest @24% p.a. for delayed payments by the Allottee.
  • Under Clause 1.3 of the Agreement, covered car parking spaces are not part of the common area; the ₹7 lakh charged is for exclusive use of parking spaces and hence is payable.
  • There is no deficiency of service on part of the Developer.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
M/S Emaar MGF Land Limited vs. Aftab Singh - I (2019) CPJ 5 (SC) The arbitration clause in the Agreement does not bar the jurisdiction of the Consumer Fora to entertain the Complaint. The Commission rejected the OP's contention that arbitration precluded its jurisdiction and proceeded to decide the Complaint.
Kavita Ahuja vs. Shipra Estates I (2016) CPJ 31 The onus of proving that a complainant was dealing in real estate (i.e., buying and selling flats as part of business) shifts to the opposite party; mere ownership of a house elsewhere does not automatically make the purchaser a non-consumer. The Commission held the OP failed to discharge the onus; therefore the Complainants qualify as "consumers" under Section 2(1)(d) of the Act.
Ambrish Kumar Shukla & Ors. Vs. Ferrous Infrastructure Pvt. Ltd. (CC No.97 of 2016 decided 07.10.2016) The "value of the services" for pecuniary jurisdiction includes the sale amount agreed to be paid by the flat buyer to the developer; this principle is relevant to determine whether the Commission has pecuniary jurisdiction where the claim exceeds ₹1 crore. The Commission accepted that the agreed sale consideration (₹1,71,56,670/-) brings the case within its pecuniary jurisdiction.
"CC No. 1703 of 2018, Renu Singh vs. Experion Developers Pvt. Ltd." and connected matters (decided 26.10.2021) A larger Bench held the sale consideration agreed between parties is relevant for determination of pecuniary jurisdiction in refund and similar cases. The Court relied on this authority (along with Ambrish) to conclude it had requisite pecuniary jurisdiction given the sale consideration exceeded ₹1 crore.
Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan II (2019) CPJ 34 (SC) Contractual terms that are ex facie one-sided and where purchasers had no real choice to negotiate are not final and binding; such clauses can be held to constitute unfair trade practices under the Consumer Protection Act. The Commission found Clauses 13(a) and 16(a) of the Agreement to be one-sided and unfair, and held the complainants could not be bound by those unfair contractual terms.
Wing Commander Arifur Rahman Khan & Aleya Sultana and Others vs DLF Southern Homes Pvt Ltd and Others [Civil Appeal No. 6239/2019 decided on 24 August 2020] The decision addressed treatment of car parking and related charges in the context of real estate allotments (as applied by the Commission in this opinion). The Commission held that car parking charges and balance of basic sale price and PLC are payable by the Complainants in view of this judgment; advance maintenance would be payable only from actual possession.
Ireo Grace Realtech Pvt. Ltd. vs. Abhishek Khanna & Ors. [Civil Appeal No. 5785/2019 & other connected Appeals] (Judgment dated 11.01.2021) The Developer is obligated to pay delay compensation for the period of delay up to the date possession was offered to the allottees (the opinion quotes the Apex Court's holding on liability for delay compensation). The Commission respectfully followed this principle and held that the Complainants were entitled to delay compensation for the applicable period; on facts it awarded simple interest @8% and costs of ₹25,000/-.

Court's Reasoning and Analysis

The Court proceeded through discrete legal determinations, applying the authorities it cited to the facts before it:

  1. Jurisdiction/Arbitration: Relying on M/S Emaar MGF Land Limited vs. Aftab Singh (2019), the Commission held that the arbitration clause in the Agreement does not oust the jurisdiction of consumer fora. Consequently, the OP's plea that arbitration precluded the Commission from entertaining the Complaint was rejected.
  2. Consumer Status: Applying Kavita Ahuja vs. Shipra Estates, the Commission observed the OP bore the onus of proving that the Complainants were dealing in real estate as a business. The OP failed to produce documentary evidence to discharge that onus; hence the Complainants were held to be "consumers" under the Act.
  3. Pecuniary Jurisdiction: The Court examined Sections 21 and related precedents (Ambrish Kumar Shukla; Renu Singh) and accepted that the agreed sale consideration (₹1,71,56,670/-) must be taken into account to determine pecuniary jurisdiction. Since the sale consideration exceeded ₹1 crore, the Commission concluded it had requisite pecuniary jurisdiction to entertain the Complaint.
  4. Contractual Terms — Fairness and Enforceability: The Commission compared Clauses 13(a) and 16(a) of the Agreement and noted a material imbalance: Clause 16(a) caps developer liability to ₹7.50 per sq. ft. per month for delay, whereas Clause 13(a) permits the developer to charge 24% p.a. interest for delayed payments by the Allottee. Citing Pioneer Urban Land, the Court concluded these terms were ex facie one-sided and unfair; therefore the Complainants could not be strictly bound by these contractual limitations.
  5. Disputed Payments (car parking, balance sale price, PLC, delay payment charges, advance maintenance): Applying the Wing Commander / DLF authority and contractual terms, the Commission concluded that:
    • Car parking charges (and the balance of basic sale price and PLC) are payable by the Complainants in view of the cited Supreme Court judgment.
    • Delay payment charges are payable if the Complainants delayed payment in terms of the Agreement.
    • Advance maintenance charges are payable but only from the date of actual possession.
    Consequently, the Registry was directed to release the disputed amount (deposited with the Commission in compliance with the Order dated 13.11.2019) along with accrued interest, in favor of the OP Developer within two weeks of the operative order.
  6. Delay Compensation: The Court found that possession was contractually due on 31.10.2015 but was handed over only in 2020 (c. five years delay). The conveyance deed had not been executed as of 13.07.2021 despite payment of stamp duty and other charges. Relying on the principle in Ireo Grace Realtech vs. Abhishek Khanna, the Commission held the Developer liable for delay compensation for the period of delay. Having considered the facts and "peculiar facts and circumstances" of the case, the Commission exercised its remedial discretion and awarded compensation in the form of simple interest at 8% per annum on the amounts deposited, computed from 31.10.2015 (the expected date of delivery) until the actual date of handing over possession, together with litigation costs of ₹25,000/-.

The Court's approach shows a methodology of (i) resolving threshold jurisdictional objections through controlling Supreme Court authority; (ii) testing the Agreement's terms for substantive fairness against precedent; and (iii) applying established consumer-law principles to determine the remedy, including an equitable award of interest and costs rather than strict enforcement of the Agreement's capped compensation clause.

Holding and Implications

Holding: The Consumer Complaint stands partly allowed.

Direct orders and consequences for the parties (as spelled out by the Commission):

  • The OP Developer is directed to pay interest on the amount deposited by the Complainants at the rate of 8% per annum with effect from 31.10.2015 (the expected date of delivery) up to the actual date of handing over possession, to be paid within four weeks from the date of the order.
  • The OP Developer is directed to pay litigation costs of ₹25,000/- to the Complainants.
  • The Registry was directed to release the disputed amount deposited with the Commission (in compliance with the earlier 13.11.2019 order) along with accrued interest, if any, in favour of the OP Developer within two weeks from the order date.
  • The pending application(s), if any, stand disposed of.

Broader implications:

  • The decision applies established precedents rather than setting a new precedent. It reinforces that (a) arbitration clauses do not automatically oust consumer fora jurisdiction, (b) the agreed sale consideration is relevant to pecuniary jurisdiction in real estate disputes, and (c) ex facie one-sided contractual clauses may be held to be unfair and unenforceable against buyers in consumer proceedings.
  • No novel legal principle was announced; the Commission's orders implement and apply Supreme Court and internal Commission precedents to the facts of the case.

End of summary.

Show all summary ...

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

NEW DELHI

CONSUMER CASE NO. 1337 OF 2018

1. DEEPIKA CHAUDHARY CHANDRA & ANR. ...........Complainant(s) Versus

1. M/S. EMAAR MGF LAND LIMITED ...........Opp.Party(s)

BEFORE:

HON'BLE MR. JUSTICE R.K. AGRAWAL,PRESIDENT HON'BLE MR. BINOY KUMAR,MEMBER

For the Complainant : For the Complainants : Mr. Varun Garg, Advocate Mr. Rahul Malhotra, Advocate

For the Opp.Party : For the Opposite Party : Mr. Sunil Mund, Advocate Dated : 02 Jun 2022

ORDER

The present Consumer Complaint has been filed under Section 21(a)(i), 22(1) of the Consumer Protection Act, 1986 (for short "the Act") against Opposite Party M/s. Emaar MGF Land Limited (hereinafter referred to as OP Developer) by Deepika Chaudhary Chandra and her husband Arun Kumar Chandra, Complainants / Allottees of Residential Apartment in a Group Housing Project, namely, "Palm Terrace Select" (for short "the Project"), to be developed and constructed by the OP Developer in Village Badshahpur, Sector 66, Gurugram, Haryana, seeking compensation towards delayed delivery of the possession of the allotted Apartment/Unit besides other reliefs.

1.

According to the Complainant, the brief facts giving rise to filing of the present Complaint are that allured by the advertisement and the assurances given by the representative of the OP Developer that the construction of the Apartment would be completed and possession would be given within stipulated time, the Complainants jointly booked an Apartment in the Group Housing Project, namely, "Palm Terrace Select" (for short "the Project"), to be developed and constructed by the OP Developer in Village Badshahpur, Sector 66, Gurugram, Haryana, on 18.07.2010 by paying a booking amount of ₹10,00,000/-. The Complainants were allotted Unit No. PTS-10- 0502 by the OP Developer vide allotment letter dated 16.08.2010. It is averred that two copies of Apartment Buyer's Agreement (hereinafter referred to as Agreement) were sent by the Developer for signature vide letter dated 17.09.2010 and thereafter one signed set was sent back to them vide letter dated 15.10.2010. However, no date of execution of the Agreement was mentioned on the Agreement. It was also averred that the Agreement contained various unilateral terms and conditions which were wholly one-sided, unfair and without giving any bargaining power to them. As per Agreement the total cost of the Apartment was ₹1,71,56,670/-. As per Clause 14 of the Agreement, the possession of the Apartment was to be

2.

1

delivered within a period of 36 months (plus grace period of 3 months) from the commencement of the construction. It was also averred that despite having received more than 50% of the sale consideration, i.e., of ₹90,47,3674/-, from the date of booking, the OP Developer did not even started the construction. The construction could be started on 31.07.2012, therefore, as per terms of the Agreement the possession of the Apartment was to be delivered by 31.10.2015. The Complainants had deposited more than 95% of the total sale consideration, i.e., ₹1,68,74,791/- as per demands of the OP Developer on different dates upto the date of filing of the Complaint, i.e., May, 2018, despite that OP Developer failed to deliver the possession of the Apartment within stipulated period. It was also averred that the OP Developer has wrongly charged ₹7 lakh towards two car parking as the basement car parking spaces forms part and parcel of the common area, therefore, there is no ownership right which gets transferred to the Allottee. Alleging deficiency in service on the part of the OP Developer, the Complainant has filed the present Consumer Complaint seeking following reliefs:-

"a) Direct Opposite Party to handover possession of Apartment duly completely in all respect i.e. in habitable condition and in conformity of the specification to the Complainants after taking the complete Completion Certificate and duly registering Apartment in the name of the Complainants as expeditiously as possible;

b) Direct the Opposite Party to pay interest at the rate of 24% per annum on the amounts paid by the Complainants towards delayed possession, calculated from the date when the possession of the residential unit was to be handed over till the date when the actual physical possession handed over to the Complainants;

c) Direct the Opposite Party to pay interest at the rate of 24% per annum on the installments/amounts paid by the Complainants from the date of the allotment of the Unit till the date of start of construction, calculated from the date of their respective deposit up till the 31.07.2012 i.e. the date of start of construction;

d) Direct the Opposite Party to refund Car Parking Charges along with 18% interest therein collected by it from the Complainants;

e) Direct the Opposite Party to pay sum of ₹20,00,000/- (Rupees Twenty Lakhs Only) towards compensation to the Complainants on the account of metal agony, trauma and harassment caused by Opposite Party;

f) Direct Opposite Party to pay sum of ₹2,00,000/- (Rupee Two Lakhs Only) towards litigation cost to the Complainant;

g) Pass/make such other appropriate order and/or directions as this Hon'ble Commission may

2

deem fit and proper in the facts and circumstances of the present case;"

1.

The Complaint was resisted by the Opposite Party Developer by filing its Written Statement in which the Opposite Party Developer averred that there is Arbitration Clause in the Agreement, therefore, the present Complaint is not maintainable before this Commission; the Complainants has owned their house in Gurgaon itself and have booked the Apartment in question for commercial/investment/speculative purpose, therefore, they do not fall within the definition of Consumer in terms of Section 2(1)(d)(ii) of the Act. It was also averred that this Commission has no pecuniary jurisdiction to entertain the Complaint as the compensation sought cannot go beyond ₹1 Crore. Relying upon Judgments passed by the Hon'ble Supreme Court, it was averred that terms & conditions of the Agreement is binding upon the Parties and thus in the case of delay in handing over physical possession of the Apartment, the Complainants are entitled for delayed compensation @ ₹7.50/- per sq. ft. per month in terms of Clause 16(a) of the Agreement. It was further averred that as per Clause 1.3 of the Agreement, the covered car parking space cannot be treated as a part of the Common Area and facilities and the Complainant has been charged ₹7 lakh towards exclusive use of two car parking space by the Complainants. It was averred that there is no deficiency in service on their part and it was prayed that the Consumer Complaint be dismissed.

3.

We have heard Mr. Varun Garg, learned Counsel for the Complainants, Mr. Sunil Mund, learned Counsel for the Opposite Party Developer and perused Complaints, Written Statements and given a thoughtful consideration to the various pleas raised by them.

4.

The Hon'ble Supreme Court in M/S Emaar MGF Land Limited vs. Aftab Singh - I (2019) CPJ 5 (SC), has laid down the law that an Arbitration clause in the Agreement does not bar the jurisdiction of the Consumer Fora to entertain the Complaint. Hence, the objection raised by the Opposite Party Developer that the clause of Arbitration bars this Commission from entertaining the Complaint is unsustainable.

5.

The contention of the Opposite Party Developer that the Complainants have already owns a house in Gurugram and have booked the subject Apartment for commercial/investment/speculative purpose, is completely unsustainable in the light of the judgement of this Commission in Kavita Ahuja vs. Shipra Estates I (2016) CPJ 31, in which the principle laid down is that the onus of establishing that the Complainant was dealing in real estate i.e. in the purchase and sale of plots/ flats in his normal course of business to earn profits, shifts to the Opposite Party, which in the instant case they had failed to discharge by filing any documentary evidence to establish their case. Therefore we are of the considered view that the Complainants do fall under the definition of 'Consumer' as defined under Section 2 (1)(d) of the Act.

6.

So far as the pecuniary jurisdiction is concerned, in terms of Section 21 of the Consumer Protection Act, this Commission possesses the requisite pecuniary jurisdiction where the value of the goods or services as the case may be and the compensation claimed exceeds

7.

3

₹1 Crore. As held by a three Members Bench of this Commission in CC No.97 of 2016 Ambrish Kumar Shukla & Ors. Vs. Ferrous Infrastructure Pvt. Ltd., decided on 07.10.2016, the value of the services in such a case would mean the sale amount agreed to be paid by the Flat Buyer to the Developer, which has been held to lay down the law correctly on the issue relating to pecuniary jurisdiction and the sale consideration which was agreed between the Parties for buying the goods or hiring or availing the services is relevant for determination of pecuniary jurisdiction in cases of refund also by a larger Bench of 5 Members of this Commission in "CC No. 1703 of 2018, Renu Singh vs. Experion Developers Private Limited" and other connected matters decided on 26.10.2021. In the present case, even the agreed sale consideration is ₹1,71,56,670/-. Therefore, it would be difficult to say that this Commission does not possess the requisite pecuniary jurisdiction.

The plea of the learned Counsel for the Developer regarding binding nature of the Agreement/Contract whereby the Parties are bound by the terms and conditions of the Agreement, to compensate the Complainant for delay in terms of Clause 16(a) of the Agreement, we have gone through the Clause 13(a) and 16(a) of the Agreement, which read as under:-

•

"13(a) In case of delay in making payment by the Allotment (s) to the Developer as per the Schedule of Payment as stated in Annexure-2, the Developer shall have right to terminate the Agreement and forfeit the Earnest Money as detailed hereinabove. The Developers shall also be entitled to charge interest @24% p.a. till the date of payment..

16(a) Subject to Clause 31, in case within a period as set out in clause 14(a), the Developers is not able to hand over the possession to the Allottee(s), the Allottee(s) shall be entitled to the payment of compensation for delay at the rate of ₹7.50/- (Rupees seven and fifty paise only) per sq. ft. per month of the Super Area till the date of notice of possession under the provision of clause 15(a) provided the Allottee(s) has complied with all the terms and conditions of this Agreement. The Allottee(s) shall have no other claim against the Developer in respect of the said Unit and Parking Space under this Agreement during the said period of twelve (12) months"

•

8.

A bare perusal of above Clauses makes it clear that as per Clause 16(a) of the Agreement, in case of delay the Opposite Party Developer is liable to pay ₹7.50/- per sq. ft. of the super built up area of the Apartment per month for the period of delay in offering of possession, whereas in terms of Clause 13(a) in case of late payment, the Complainants/Buyers are liable to pay interest @24% p.a. This shows that the terms of the Agreement are wholly one-sided and unfair. Therefore, the Complainants cannot be made bound to the terms of the Agreement, which are one-sided and unfair in the light of the recent Judgment of the Hon'ble Apex Court in Pioneer Urban Land & Infrastructure Ltd.

9.

4

Vs. Govindan Raghavan, II (2019) CPJ 34 (SC), wherein the Apex Court has observed as follows:

"6.7. A terms of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The contractual terms of the Agreement dated 08.05.2012 are ex-facie one sided, unfair and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2(r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder.

7. In view of the above discussion, we have no hesitation in holding that the terms of the Apartment Buyer's Agreement dated 08.05.2012 were wholly one-sided and unfair to the Respondent-Flat Purchaser. The Appellant-Builder cannot seek to bind the Respondent with such one-sided contractual terms."

During the course of Proceedings, the OP Developer vide letter dated 28.08.2019 had offered the possession of the Apartment to the Complainants subject to payment of the outstanding dues, followed by reminder letter dated 03.10.2019 vide which the Complainants were called upon to clear the outstanding dues of ₹22,89,282/-. Vide Order dated 13.11.2019 on the Application moved by the Complainants seeking permission to deposit the amount with this Commission, following directions were passed:-

10.

"The OP is directed to deliver possession of the allotted flat to the complainant complete in all respects within four weeks from today subject to the complainant paying the entire admitted amount including the VAT and Stamp Duty and depositing the disputed amount, if any, with this Commission during pendency of the complaint without prejudice to the rights and contentions of the parties in this complaint. The complainant shall comply with this order within four weeks from today.

The amount, if any, deposited with this Commission shall be kept in an automatically renewable FDR of a nationalized bank and the final order with respect to that amount and interest which accrues on it, shall be passed at the time of final disposal of the complaint. The IA stands disposed of."

In compliance of the Order dated 13.11.2019, the Complainants have deposited following amount :-

11.

With the Opposite Party Developer (Admitted Amount)

Lien Marked Fixed Deposit for HVAT Liability ₹1,50,891/- Registration Charges & Pasting Charges E-Challan ₹ 50,003/- E-Stamp Paper ₹9,50,820/-

Cheque for water connection charges

₹5,006/-

5

Total ₹11,56,720/- With this Commission (Disputed Amount) Basic, Covered Car Park, PLC ₹9,45,158/- Delayed Payment Charges ₹ 1,17,328/- Advanced Monthly Maintenance Charges ₹1,19,440/- Total ₹11,81,926/-

Precisely, in the present case, the controversy revolves around two issues firstly, payment of disputed amount and secondly, delayed compensation.

12.

So far as the payment of disputed amount is concerned, Car Parking charges are to be paid by the Complainants in view of the Judgment passed by the Hon'ble Supreme Court in "Wing Commander Arifur Rahman Khan and Aleya Sultana and Others vs DLF Southern Homes Pvt Ltd and Others [Civil Appeal No 6239/2019 decided on 24 August 2020]". Balance of Basic Sale Price and PLC are also payable by the Complainants as per terms of the Agreement. The Complainants are duty bound to make the payments as per demand of the OP Developer and in case of delay in making the payment, the Complainants are liable to pay Delay Payment Charges as per terms of the Agreement. As far as Advance Maintenance Charges are concerned, it will also be paid by the Complainants to the OP Developer but the Advance Maintenance Charges will be applicable only with effect from the date of actual possession of the Apartment to the Complainants.

13.

Consequently, the Registry is directed to release the disputed amount deposited by the Complainants in compliance of the Order dated 13.11.2019, alongwith accrued interest, if any, in favour of the OP Developer within two weeks from today.

14.

Now coming to the issue of delayed compensation, it is not in dispute that the Complainants booked the Apartment with the OP Developer on 18.07.2010. As per Clause 14 of the Agreement the OP Developer was obligated to deliver the possession of the Apartment by 31.10.2015 but despite having received a huge sum of ₹1,68,74,791/- , i.e., almost 95% of the total sale consideration, the OP Developer failed to deliver the possession of the Apartment within stipulated period and the possession was actually handed over only in the year 2020, i.e., with a delay of approximately five years and the Conveyance Deed has also not been executed till 13.07.2021 despite having received the stamp duty and other charges from the Complainants far back in the year 2020, which in our considered view is a clear case of deficiency in service on the part of the OP Developer.

15.

We find it a fit case to place reliance on the Judgment dated 11.01.2021 passed by the Hon'ble Supreme Court in "Ireo Grace Realtech Pvt. Ltd. vs. Abhishek Khanna & Ors." [Civil Appeal No. 5785 / 2019 & other connected Appeals], in which the Hon'ble Apex Court has observed as hereunder :

16.

6

The Developer is however obligated to pay Delay Compensation for the period of delay which has occurred from 27.11.2018 till the date of offer of possession was made to the allottees…."

1.

Respectfully following the principle laid down by the Hon'ble Supreme Court in "Ireo Grace Realtech Pvt. Ltd. vs. Abhishek Khanna & Ors." (supra), we are of the considered view that the Complainants are entitled for Compensation for delay in delivery of the possession of the Apartment. Keeping in view the peculiar facts and circumstances of the case, we are of the view that the compensation in the form of simple interest @ 8% p.a. alongwith cost of ₹25,000/- would meet the ends of justice.

17.

Consequently, the Opposite Party Developer is directed to pay interest on the amount deposited @8% w.e.f. 31.10.2015, i.e., the expected date of delivery of the possession, till the actual date of handing over of the possession of the Apartment to the Complainants, within four weeks from today. The OP Developer shall also pay cost of ₹25,000/- to the Complainants.

18.

The Consumer Complaint stands partly allowed in above terms. The pending application, if any, also stands disposed off.

19.

......................J

R.K. AGRAWAL

PRESIDENT

......................

BINOY KUMAR

MEMBER

7