Shapoorji Pallonji I... v. Power Grid Corporati...
Summary of Judgment — Appellate Tribunal for Electricity (Appeal No. 53 of 2022)
Factual and Procedural Background
The appellant is M/s Shapoorji Pallonji Infrastructure Capital Company Private Limited (SPICCPL). Two 250 MW solar projects (Tuticorin, Tamil Nadu and Anantpur, Andhra Pradesh) were awarded to the appellant. Stage-I connectivity was granted on 24.08.2018 and Stage-II connectivity for 250 MW for each project was granted on 17.01.2019 by Power Grid Corporation of India Ltd. (PGCIL). Pursuant to Transmission Service Agreements dated 12.02.2019, the appellant furnished two Connectivity Bank Guarantees (CBGs) of Rs. 5.0 crore each on 14.02.2019.
NTPC executed Power Sale Agreements with Telangana distribution licensees and subsequent PPAs were entered into by SPVs of the appellant with NTPC on 20.03.2019. These PPAs required approval by the Andhra Pradesh Electricity Regulatory Commission and by the Telangana State Electricity Regulatory Commission within prescribed time-frames; the approvals were not obtained and the PPAs were terminated by mutual consent in August–September 2019. In consequence, the appellant (through its SPVs) requested cancellation of Stage-II connectivity and return of the CBGs. PGCIL revoked Stage-II connectivity by letter dated 04.03.2020 but declined to discharge the CBGs, asserting that the Detailed Procedure then in force provided for discharge of CBGs only after commencement of power evacuation from the plant.
The appellant filed Petition No. 523/MP/2020 before the Central Electricity Regulatory Commission (CERC) on 08.05.2020 seeking, inter alia, relaxation under Regulation 33A and a direction to discharge/return the two CBGs. While the petition was pending, CERC issued a Revised Detailed Procedure on 20.02.2021 modifying treatment of pre-revised CBGs (including treating them as Conn-BG1 of Rs.50 lakh and Conn-BG2 for the balance and specifying forfeiture/refund rules).
CERC, by an order dated 15.02.2022 (impugned in this appeal under Section 111 of the Electricity Act, 2003), partly allowed the appellant's claim and directed forfeiture of Rs. 50.0 lakh from each CBG while refunding the balance. The appellant appealed to the Appellate Tribunal for Electricity and sought vacation of the forfeiture direction.
Legal Issues Presented
- Whether the Central Electricity Regulatory Commission was correct in applying the Revised Detailed Procedure issued on 20.02.2021 to direct the forfeiture of Rs. 50.0 lakh from each Connectivity Bank Guarantee that had been furnished under the Pre-revised Detailed Procedure.
- Whether the Connectivity Bank Guarantees ought to be discharged and returned to the appellant where (a) Stage-II connectivity had been revoked at the appellant's request and (b) no action for encashment of the CBGs had been initiated by PGCIL and PGCIL did not claim any loss.
- Whether a direction for forfeiture of part of the CBGs was permissible in the absence of any demonstrated loss to the transmission utility and consistent with the contract-law principle under Section 73 of the Indian Contract Act.
Arguments of the Parties
Appellant's Arguments
- The appellant sought relaxation under Regulation 33A of the Connectivity Regulations (2009) and asked CERC to direct discharge/return of the two CBGs (Nos. OGT0005190028926 and OGT0005190028921 of Rs.5 crore each).
- The appellant contended that the Detailed Procedure in force when the CBGs were furnished did not provide for forfeiture on revocation in the circumstances of this case and that the CBGs should be returned as PGCIL had not suffered any loss.
Respondent (PGCIL) — Contentions and Concessions
- PGCIL initially declined to discharge the CBGs on the ground that under the Detailed Procedure (pre-revised) CBGs were discharged only after commencement of power evacuation.
- PGCIL later conceded (by affidavit dated 22.10.2021 before CERC) that: (a) Stage-II connectivity for the projects had been revoked on 04.03.2020 under the Pre-revised Procedure but no action for encashment of the CBGs was initiated due to absence of clear provision; (b) no expenditure was incurred by PGCIL under ISTS for the Anantpur connectivity; and (c) expenditure said to have been incurred for Tuticorin related to common facilities re-utilised/allocated to another entity (NTPC), i.e., PGCIL did not claim financial loss attributable to the appellant's revocation.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Tribunal conducted a step-by-step analysis constrained by the text of the Detailed Procedure (pre-revised) and the Revised Detailed Procedure (issued 20.02.2021):
- Identification of the precise issue: The Tribunal noted that CERC identified "the only issue" as the treatment of the Connectivity Bank Guarantees furnished by the petitioner for the two solar projects.
- Examination of relevant provisions: The Tribunal quoted Clause 10.11 and Clause 11.2 of the Pre-revised Detailed Procedure (which provided that Conn-BG shall be discharged six months after commencement of power evacuation and that failure to complete dedicated transmission lines could lead to encashment and revocation). It also quoted Clause 5.1 (sub-clauses (1)–(4)) of the Revised Detailed Procedure, which (inter alia) treats pre-revised Conn-BGs as Conn-BG1 of Rs.50 lakh and Conn-BG2 for the balance and prescribes forfeiture/refund rules on encashment.
- Assessment of CERC's application of the Revised Procedure: CERC had applied Clause 5.1 of the Revised Detailed Procedure, treating each Rs.5 crore CBG as Conn-BG1 of Rs.50 lakh (forfeitable) and Conn-BG2 of Rs.4.5 crore (refundable), on the basis that the Revised Procedure was procedural and therefore applicable to existing agreements. CERC concluded forfeiture of Rs.50 lakh each because the terminal bays were within the appellant's scope.
- Temporal trigger analysis: The Tribunal emphasized Clause 5.1(1) of the Revised Procedure, which expressly provides that any action already initiated for revocation of Stage-II connectivity or encashment of bank guarantee prior to issuance of the Revised Procedure shall be completed under the Pre-revised Procedure, whereas actions initiated after issuance shall follow the Revised Procedure. The Tribunal therefore located the critical legal trigger not in the characterization of the law as "procedural" but in the timing of initiation of the relevant actions (revocation and/or encashment).
- Application to the facts: The Tribunal found that revocation of Stage-II connectivity had been effected by PGCIL on 04.03.2020 (prior to the Revised Procedure). No encashment action under either procedure had been initiated by PGCIL at any stage. The Tribunal relied on PGCIL's own concessions that it had not incurred loss in relation to Anantpur and that works for Tuticorin were used for another entity. Because no encashment action was initiated after issuance of the Revised Procedure, Clause 5.1 could not be invoked to trigger the Rs.50 lakh forfeiture.
- Contract-law principle: The Tribunal invoked the principle under Section 73 of the Indian Contract Act (compensation is payable only where loss is suffered on account of breach) and observed that PGCIL did not claim any loss requiring compensation. The Tribunal reasoned that forfeiture in the absence of demonstrated loss would be inconsistent with that principle.
- Conclusion from combined analysis: Given that (a) revocation occurred before the Revised Procedure; (b) no encashment action was initiated; and (c) PGCIL did not claim loss, the Tribunal held that CERC erred in applying Clause 5.1(2)–(4) of the Revised Procedure to impose a forfeiture of Rs.50 lakh on each CBG. The Tribunal determined that the just and fair outcome was to order return/discharge of the CBGs.
Holding and Implications
APPEAL ALLOWED; THE IMPUGNED DIRECTION FOR FORFEITURE IS SET ASIDE
Holding (core ruling): The Appellate Tribunal set aside and vacated the portion of the impugned CERC order that directed forfeiture of Rs.50.0 lakh from each of the two Connectivity Bank Guarantees. The Tribunal allowed the appellant's petition before CERC and directed that the two CBGs be returned forthwith. If PGCIL had already encashed any amount pursuant to the impugned order, that amount was to be refunded to the appellant forthwith. The appeal and the pending application were disposed of in these terms.
Implications:
- Direct effect on the parties: PGCIL must return the two Connectivity Bank Guarantees to the appellant immediately, and must refund any amounts it may have encashed pursuant to the CERC order. The appellant succeeds in having the forfeiture vacated.
- Scope of the decision: The Tribunal's decision rests on the textual operation of Clause 5.1 of the Revised Detailed Procedure (timing of initiation of revocation/encashment) and on the absence of any claim of loss by PGCIL. The Tribunal did not purport to lay down a broader policy rule beyond application of the cited contractual/regulatory provisions to the facts at hand. The opinion states that the direction for forfeiture could not be sustained in these facts; it does not announce a new principle beyond the application of existing contract-law and the procedural wording of Clause 5.1.
This summary is confined to and based exclusively on the content of the judgment provided.
IN THE APPELLATE TRIBUNAL FOR ELECTRICITY
NEW DELHI
(APPELLATE JURISDICTION)
APPEAL NO. 53 OF 2022 &
IA NO. 272 OF 2022
Dated: 12th April 2022
Present: Hon'ble Mr. Justice R.K. Gauba, Officiating Chairperson Hon'ble Mr. Sandesh Kumar Sharma, Technical Member
In the matter of:
M/S SHAPOORJI PALLONJI INFRASTRUCTURE CAPITAL
COMPANY PRIVATE LIMITED
[Through its Authorized Signatory] SP Centre, 4144 Minoo Desai Marg, Colaba, Mumbai - 400 005
Email: pankaj.latey@shapoorji.com ... Appellant(s)
VERSUS
1. POWER GRID CORPORATION OF INDIA LIMITED
(now Central Transmission Utility of India Ltd.)
[Through its Chief Generation Manager] B-9, Qutub Institutional Area, Katwaria Sarai,
New Delhi - 110 016
Email: atul_ag@powergrid.in
2. CENTRAL ELECTRICITY REGULATORY COMMISSION
[Through its Secretary] 3 rd & 4 th Floor, Chanderlok Building, 36, Janpath,
New Delhi- 110 001
Email: secy@cercind.gov.in … Respondents
Counsel for the Appellant (s): Mr. Vishrov Mukherjee Mr. Janmali Manikala
Mr. Damodar Solanki
Counsel for the Respondent (s): Ms. Suparna Srivastava for R-1
1
J U D G M E N T
PER HON'BLE MR. JUSTICE R.K. GAUBA, OFFICIATING CHAIRPERSON
1. This matter was taken up by video conference mode on account of pandemic conditions, it being not advisable to hold physical hearing.
2. The appeal under Section 111 of Electricity Act, 2003 assails the Order dated 15.02.2022 passed by Central Electricity Regulatory Commission (hereinafter referred to as "CERC" or "the Central Commission") in Petition no. 523/MP/2020 whereby the claim of the appellant M/s Shapoorji Pallonji Infrastructure Capital Company Private Limited, inter alia, for discharge or return of Connectivity Bank Guarantees ("CBGs") of Rs.5.0 crore each issued by IndusInd Bank was partly allowed with a direction that an amount of Rs. 50.0 lakh each would stand forfeited, the balance being refunded.
3. The background facts need to be noted in brief.
4. The Central Commission has framed Regulations named Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 (for short, "the Connectivity Regulations"). In terms of Regulation 27 of the Connectivity Regulations, detailed procedure was notified by CERC which came into force from 15.05.2018 it being styled as Detailed Procedure for "Grant of Connectivity to Projects based on Renewable Sources to Inter-State Transmission System" (hereinafter
2
referred to as "the Detailed Procedure"). It may be mentioned here itself that the said Detailed Procedure was modified by issuance of what is known as
"Revised Detailed Procedure" issued on 20.02.2021.
5. While the Detailed Procedure notified on 15.05.2018 was governing the field, certain events took place which have a bearing on the matter at hand. The petitioner was awarded two 250 MW Solar Projects, one at Tuticorin in the State of Tamil Nadu and the other at Anantpur in the State of Andhra Pradesh, the power generated from such solar power projects intended to be supplied to distribution licensees in the State of Telangana through an intermediary procurer viz. NTPC. In that context, the appellant had approached the first respondent - Power Grid Corporation of India Ltd (for short, "PGCIL") and was granted Stage-I connectivity on 24.08.2018 for
500 MW in relation to Tuticorin Project and 500 MW in relation to Anantpur Project respectively.
6. Subsequently, on 17.01.2019, PGCIL granted to the appellant Stage- II connectivity for 250 MW in relation to Tuticorin Project and for 250 MW for Anantpur Project respectively. In terms of the relevant Regulations and pursuant to the Transmission Service Agreements ("TSAs") dated 12.02.2019 executed by the parties, the appellant furnished, on 14.02.2019, the two Connectivity Bank Guarantees (CBGs) bearing nos.
3
OGT0005190028921 and OGT0005190028926 of Rs.5.0 crore each to the respondent PGCIL, the transmission service provider.
7. On 11.03.2019, pursuant to Letters of Intent (LOIs) dated 17.10.2018 issued by NTPC, Power Sale Agreement ("PSA") was executed between NTPC and the two distribution licensees of the State of Telangana i.e. Northern Power Distribution Company of Telangana Ltd ("TNSPDCL") and Southern Power Distribution Company of Telangana ("TSSPDCL"). Subsequently, on 20.03.2019, two companies (Special Purpose Vehicles or
"SPVs") created by the appellant - M/s Eloise Energy Private Limited ("EEP") and Elaine Renewable Energy Private Limited ("EREPL") - entered into separate Power Purchase Agreements ("PPAs") with NTPC in respect of two projects at Anantpur and Tuticorin.
8. The above said PPAs were presented before Andhra Pradesh Electricity Regulatory Commission ("APERC") for approval which, however, was not accorded by APERC till 20.05.2019. Subsequently, the Telangana State Electricity Regulatory Commission ("TSERC") was approached by the Telangana distribution licensees (TNSPDCL and TSSPDCL) for approval of extension which did not come-forth during the extended period of three months. In the result, the PPAs dated 20.03.2019 were terminated by the parties, with mutual consent, in August-September, 2019, in accordance with the provisions of the said PPAs. It is stated that as a sequel to this
4
development, NTPC returned the Performance Bank Guarantees ("PBGs") of Rs. 125.0 crores (Rs.62.5 crore each) which had been furnished by the appellant under the PPAs.
9. Against the above backdrop, the appellant approached the respondent PGCIL on 15.01.2020, through its SPVs EEPL and EIPL, for cancellation of Stage-II connectivity in respect of Anantpur and Tuticorin projects, termination of PSAs and return of the CBGs. Acceding to the said request, PGCIL revoked the Stage-II connectivity with immediate effect on 04.03.2020 and though returning the consultancy fee and ad hoc operation & maintenance charges in respect of both the projects declined to discharge the CBGs stating that the Detailed Procedure provided for discharge of such CBGs only subsequent to commencement of power evacuation from the power plant.
10. The appellant filed the petition, being no. 523/MP/2020, before CERC on 08.05.2020, on which the impugned order has been passed, setting out its prayers as under:
"a) To exercise power under Regulation 33A of the CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 and relax the procedure set out in Clause 10.11 of the Detailed Procedure for "Grant of Connectivity to Projects Based on Renewable Sources to Inter-State Transmission System";
b) Direct Respondent to discharge/return Connectivity Bank Guarantee No. OGT0005190028926 and Connectivity Bank
5
Guarantee No. OGT0005190028921 of Rs.5 Cr. each issued by IndusInd Bank; and /or
c) Pass such other order / orders, as may be deemed fit and proper in the facts and circumstances of the case."
11. While the abovementioned Petition no. 523/MP/2020 was pending before CERC, Revised Detailed Procedure came to be notified on
20.02.2021.
12. Admittedly, under the Detailed Procedure, as enforced prior to issuance of the Revised Detailed Procedure, there was no express provision made for discharge or return of the CBGs if Stage-II connectivity were revoked, such discharge having been mentioned primarily in relation to the commencement of power evacuation from the power plant. Two specific clauses of the Detailed Procedure (pre-revised) need to be quoted here:
"10.11 Conn-BG shall be discharged six months after commencement of evacuation of power from the renewable project.
…
11.2 The Stage-II Connectivity grantees shall be required to complete the dedicated transmission line(s) and pooling sub- station(s) within 24 months from the date of intimation of bay allocation at existing or new / under-construction ISTS sub- station. If the grantee fails to complete the dedicated transmission line within the stipulated period, the Conn-BG of the grantee shall be encashed and Stage-II connectivity shall be revoked. The payment received in terms of these provisions shall be adjusted in the POC pool.
13. Under the Revised Detailed Procedure, however, Clause 5.1 would provide as under:
6
"5.1 After coming into force of this Procedure, for an entity which has been granted Stage-II Connectivity under the Pre-revised Procedure,
(1) Any action already initiated for revocation of Stage-II Connectivity or encashment of Bank Guarantee prior to the issue of this Procedure shall be completed under the Pre-revised Procedure.
(2) Any action including revocation of Stage-II Connectivity or encashment of Bank Guarantee initiated after the issue of this Procedure shall be in accordance with this Procedure.
(3) Conn-BG submitted under the Pre-revised Procedure shall be treated as ConnBG1 for Rs. 50 lakh and Conn- BG2 for the balance amount.
(4) In the event of encashment of such Conn-BG1 or Conn-BG2 as worked out in terms of sub-clause (3) of Clause 5.1 above, under Clause 10.8 of this Procedure
(i) If the associated bay(s) at the ISTS sub-station is being constructed by Stage-II grantee itself, amount corresponding to Conn-BG1 shall be forfeited and balance amount being treated as Conn-BG2 under this Procedure shall be refunded.
(ii) If the associated bay(s) at the ISTS sub-station is being constructed by ISTS licensee, amount corresponding to Conn-BG1 and amount of ConnBG2 in terms of Clause 10.8(a) of this Procedure shall be forfeited and any excess amount submitted as Conn-BG under the Pre-revised Procedure shall be refunded."
14. The CERC applied the abovementioned Clause 5.1 of the Revised Detailed Procedure observing through the impugned order as under:
"11. We have heard the submissions of the parties and perused the documents available on record. The only issue which arises for our consideration is regarding treatment of Connectivity Bank Guarantee furnished by the Petitioner to the Respondent, for its solar power projects at Anantpur and Tuticorin.
7
12. The Petitioner has stated that it was awarded two 250 MW solar projects, one each at Tuticorin (in the State of Tamil Nadu) and Anantpur (in the State of Andhra Pradesh) and the power from these solar power projects was to be supplied to the Telangana Discoms through an intermediary procurer, NTPC. Subsequently, the Petitioner was granted Stage-II connectivity by the Respondent for 250 MW each with respect to its Tuticorin solar power project and Anantpur solar power project. Consequently, TSAs were entered into with the Respondent and the Petitioner furnished BG of Rs.5 crore under each TSA. The Connectivity was sought for PPAs that was entered into by SPVs of the Petitioner with the Telangana Discoms wherein PPAs required approval of TSERC as a condition precedent within a period of 60 days of effective date of PPAs. However, despite extension of 3 months, the PPAs were not approved by TSERC and accordingly, the parties terminated the PPAs. Consequent to termination of the PPAs, the Petitioner vide its letters dated 15.01.2020 sought to cancel Stage-II connectivity granted to it and requested to return CBGs (of Rs.10 crore). The Respondent vide its letter dated 04.03.2020 revoked the Stage-II Connectivity granted to the Petitioner. However, the Petitioner's request for return of CBGs was declined by the Respondent.
…
14. A plain reading of clause 5.1(3) of the Revised Detailed Procedure indicates that a Connectivity Bank Guarantee submitted under the Detailed Procedure (prerevised) shall be treated as Conn-BG1 for Rs.50 lakh and Conn-BG2 for the balance amount. Further, in terms of clause 5.1(4)(i) of the Revised Detailed Procedure, in the event of encashment of BG, if the associated bay(s) at the ISTS sub-station is being constructed by Stage-II grantee itself, amount corresponding to Conn-BG1 shall be forfeited and balance amount (being treated as Conn-BG2) shall be refunded. We are of the view that the Revised Detailed Procedure is a procedural law and is to be applied even on existing agreements.
15. We observe that in the present case, the Respondent had revoked the Stage II Connectivity granted to the Petitioner vide its letter dated 04.03.2020. However, the Respondent had not initiated any action for encashment of Bank Guarantee under the Detailed Procedure (pre- revised). Therefore, any action pertaining to encashment of
8
Connectivity BG has to be dealt under the Revised Detailed Procedure in terms of clause 5.1(2) of the Revised Detailed Procedure.
16. Since the terminal bays for the Anantpur solar power project and Tuticorin solar power project was under the scope of the Petitioner, in terms of clause 5.1(3) read with clause 5.1(4)(i) of the Revised Detailed Procedure, the amount of Rs.50 lakh (corresponding to Conn-BG1) shall be forfeited and balance amount of Rs.4.5 crore (corresponding to Conn-BG2) shall be refunded to the Petitioner for each solar power project."
15. It may be mentioned at this stage that PGCIL has fairly conceded, even by additional affidavit submitted on 22.10.2021 before CERC, inter alia, that:
(a) Stage-II Connectivity granted to SPICCPL for Anantpur and Tuticorin Projects have been revoked on 04.03.2020 under the Pre-revised Procedure / Detailed Procedure, however no action was initiated towards encashment of Conn-BGs submitted by SPICCPL in absence of any clear provision.
(b) No expenditure has been incurred under ISTS for Connectivity granted to SPICCPL at N P Kunta (bay no. 224) for its Anantpur Project.
(c) Regarding expenditure incurred under ISTS for Connectivity granted to SPICCPL at Tuticorin-II GIS (bay no.
211) for its Tuticorin Project, these works were identified as common facilities works at Tuticorin-II GIS S/s for facilitating connectivity to RE developers. Upon revocation of Stage-II connectivity, the bay no. 211 was allocated to NTPC."
16. From the above facts, affirmed on behalf of PGCIL itself, it is clear that PGCIL does not claim any loss suffered on account of grant of Stage-II connectivity or its revocation, upon request of the appellant, in relation to the two projects. There is no expenditure incurred by PGCIL in relation to
9
Anantpur project, the expenditure incurred for the purposes of Tuticorin project having been properly utilized for another entity.
17. As has been noted earlier, the appellant had approached the CERC with a prayer for relaxation of the conditions respecting CBGs for exercise of power available to it (CERC) under Regulation 33A of Connectivity Regulations. In our considered view, in the matter at hand, there was no need for such power of relaxation to be invoked in as much as under the Detailed Procedure brought in force from 2018 the only occasion for CBGs to be invoked was in the event of inordinate delay due to non-performance during the period prior to commencement of the power evacuation, the CBGs having served the purpose and liable to be discharged upon such commencement of power evacuation after the elapse of the period specified for the same.
18. On careful scrutiny of the facts at hand, we are of the view that CERC has fallen into error by applying the Revised Detailed Procedure which was issued on 20.02.2021, merely on the reasoning that it is a procedural law and is to be applied even on existing agreement. The question as to whether Revised Detailed Procedure is procedural was not germane or of any consequence for the simple reason Clause 5.1, as extracted earlier, itself makes it clear that it would apply if the revocation of Stage-II connectivity
10
was ordered or action initiated for encashment of bank guarantee "after the issue of this Procedure".
19. The language employed in Clause 5.1(1) of Revised Detailed Procedure leaves no room for doubt that if action for revocation of Stage-II connectivity had been initiated prior to issuance of the Revised Detailed Procedure, the manner in which CBGs are to be dealt with is governed by
"Pre-revised Procedure". Similarly, if action had been initiated for encashment of bank guarantee prior to issuance of the Revised Detailed Procedure, such action will also have to be completed under the "Pre-revised Procedure". It all hinges on initiation of action to give trigger for two events;
(i) revocation of Stage-II connectivity, and (ii) encashment of CBGs. If the action for initiation of either is after the issuance of the Revised Procedure, it would be under the said Revised Procedure; else, the pre-revised procedure would continue to apply. In the present case, revocation was already complete. No action for encashment was initiated, before or after, by the contracting party (PGCIL). We may elaborate.
20. The request for revocation of Stage-II connectivity had concededly been made on 15.01.2021, more than a year prior to the issuance of the Revised Detailed Procedure. The said request had been acceded to by the respondent PGCIL on 04.03.2021, again more than eleven months prior to issuance of the Revised Detailed Procedure.
11
21. The purpose of requirement of CBGs is to insulate or indemnify the transmission utility against any loss it might incur on account of defaults on the part of the entity entering into TSA in timely compliances till the commencement of evacuation of power. As noted earlier, no loss has been suffered by the respondent PGCIL on account of either grant of Stage-II connectivity or its revocation.
22. More important than the above, however, is the fact that PGCIL has not initiated at any stage, not even till date, any action for encashment of CBGs. If there was any need for compensation for the loss suffered, PGCIL would have initiated action for encashment of the CBGs while granting revocation as requested, on 04.03.2020. From this conduct, from the correspondence exchanged (compelling the appellant to approach the CERC), and from the submissions made, it is clear that PGCIL was clueless as what was to be done with the CBGs that had been furnished as a pre- condition for grant of the Stage-II connectivity, after the same had been revoked and the TSAs cancelled upon request albeit with mutual consent. Since PGCIL had not suffered any financial loss in the process and since it was not finding a cause to initiate action to encash CBGs under the extant Detailed Procedure, the only just and fair dispensation to be accorded on the petition of the appellant by CERC was to allow the CBGs to be discharged and returned.
12
23. The provision contained in Clause 5.1(2), (3) & (4) of the Revised Detailed Procedure could not have been invoked by CERC to impose virtually a penalty of Rs.50.0 lakh each against the two CBGs on the appellant on the assumption that action for encashment of CBGs had been initiated after the issuance of the Revised Detailed Procedure for the simple reason there is no claim of such action having been initiated at any stage by
PGCIL.
24. The decision of CERC also falls foul of Section 73 of the Indian Contract Act wherein compensation is payable to the party to the contract in the event it has suffered loss due to inability of the party to discharge contract. In the facts at hand, it bears repetition to say, there is no claim made by PGCIL of having suffered any loss as requires to be compensated. Concededly, there has been no occasion for PGCIL to invoke Clause 11.2 of the Pre-revised Detailed Procedure to claim a right to encashment of CBGs.
25. For the foregoing reasons, the impugned order directing forfeiture of Rs. 50.0 lakh each from the two CBGs cannot be upheld. The said direction is hereby set aside and vacated. The petition of the appellant before the CERC for substantive relief is allowed. The two Connectivity Bank Guarantees, mentioned earlier, shall be returned forthwith. If PGCIL has encashed the bank guarantees to the extent of forfeiture permitted by CERC
13
through the impugned order, the said amount shall be refunded forthwith to the appellant.
26. The appeal and the pending application are disposed of in above terms.
PRONOUNCED IN THE VIRTUAL COURT THROUGH VIDEO
CONFERENCING ON THIS 12TH DAY OF APRIL, 2022.
(Sandesh Kumar Sharma) (Justice R.K. Gauba)
Technical Member Officiating Chairperson vt