Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Tafadar Saw Mill, Re... v. Assam Power Distribu...

Gauhati High Court
Mar 31, 2022

Manash Ranjan Pathak, J.:— In view of the order passed today in the connected I.A. (Civil) No. 1038/2022, (i) The Commissioner & Secretary to the Govt. of Assam, Department of Environment & Forest, Dispur, Guwahati, (ii) The Principal Chief Conservator of Forests & Head of Forest Force (HoFF), Assam, Aranya Bhawan, Panjabari, Guwahati-781037, (iii) The Conservator of Forests, Northern Assam Circle, Tezpur and (iv) The Divisional Forest Officer, Nagaon South Division, Hojai as party respondent Nos. 4, 5, 6 & 7 be impleaded as party respondent Nos. 4, 5, 6 & 7 respectively in the present proceeding.

2. Registry shall accordingly correct the cause title.

3. Mr. D Gogoi, learned Standing counsel, Forest Department has entered appearance on behalf of the newly impleaded respondent Nos. 4, 5, 6 & 7.

4. Petitioner shall serve requisite extra copies of this writ petition along with the Annexures appended thereto to Mr. D Gogoi, learned Standing counsel, Forest Department by tomorrow, i.e., 01.04.2022, obtaining necessary acknowledgment from him in that regard.

5. Mr. J Abedin, learned counsel for the petitioner has brought to the notice of the Court that the Conservator of Forest, Northern Assam Circle respondent No. 6 by its communication No. FNAC.39/WBI/Licence/2020/Pt-I/1409-100 dated 18.02.2022 informed all the Divisional Forest Officers including Nagaon South Division, Hojai respondent No. 7 to direct the owners of the Wood Based Industries under their respective control to install APDCL dedicated meter in their units used for sawing purpose with the copy to the local APDCL authorities for its compliance and to submit the receipt (deposit of security money and connection fees etc.) of the same and to complete the entire process by 31.03.2022.

6. On the basis of said communication of the Conservator of Forest, Northern Assam Circle, the Divisional Forest Officer, Nagaon South Division, Hojai by its letter No. FNST/B/WBI/2022/65-55 dated 19.02.2022 directed the petitioner and 12 others Saw Mills of District-Hojai to install dedicated APDCL meter for their unit for sawing purpose and to submit the receipt.

7. It is submitted by the petitioner that since the matter of disconnection of electricity by the respondent APDCL with regard to the petitioner Saw Mill is still pending and as it is yet to deposit the amount in terms of the order of the Court dated 18.09.2019 passed earlier in this proceeding, failure on its part to install dedicated APDCL meter for its Saw Mill within 31.03.2022, though the matter is sub-judice, as noted above; there is all possibility that the Forest Department shall refuse to renew its requisite licence and/or cancel its licence to enabling it to do the business of sawing, selling and manufacturing wood based goods and products, which is petitioner's source of earning and livelihood.

8. As such, the petitioner has made a submission that on its failure to install such dedicated APDCL meter for its sawing unit, the respondent Forest Department shall not take any coercive action against it.

9. However, Mr. Gogoi, learned Standing counsel, Forest Department, on instruction submitted that as the petitioner's unit is without any electrical connection since 2018 and as the petitioner has not applied for any renewal of its licence since then, therefore, the question of renewal of licence of the petitioner by the respondent Forest Department does not arise.

10. List this matter on 05.04.2022.

11. Considering the above, as the present matter may take some time for its disposal, it is made clear that failure on the part of the petitioner to install dedicated APDCL electrical meter for the purpose of sawing in its unit because of pendency of this case, the same shall not be a ground for the respondent Forest Department to take any coercive action against the petitioner in refusing renewal of licence to it for sawing purpose and/or to cancel/reject its licence for sawing and it shall be subject to the outcome of this writ petition.