Rajiv Narayan v. Union Of India

National Green Tribunal
Feb 23, 2022

1. This application seeks waiver of requirement to pay environmental compensation for failure to set up requisite TSDF in Goa, in terms of orders of this Tribunal dated 26.08.2019 in O.A. 804/2017, Rajiv Narayan v. Union of India

2. By the said order, the Tribunal dealt with the issue of noncompliance of Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016 (HOWM Rules) on matter being remitted to this Tribunal by the Hon'ble Supreme Court in Writ Petition No. 657/1995, The Research Foundation for Science, Technology and Natural Resource Policy v. Union of India, (2005) 10 SCC 510. The Tribunal issued directions for compliance of the Rules by various orders from time to time. The Tribunal noted that as per Rules, TSDF facility with adequate capacity has to be set up and to enforce the direction, the Tribunal required recovery of compensation for failure to comply with the Rules, which results in damage to the environment. The Tribunal considered report of CPCB dated 14.08.2019 which inter-alia suggested action for failure to set up TSDF, as already directed. The relevant part of the report is as follows:—

“….xxx……………………………….xxx………………………………..xxx

15. The report finds following deficiencies in compliance of recommendations of the Committee and orders of this Tribunal by the States, the CPCB and the SPCBs/PCCs:

“4.1. BY STATE/UT DEPARTMENTS

I. Recommendation No. 6.4 : It is necessary that the Hon'ble NGT orders dated 30/07/2018 with regard to setting up of TSDF and taking imitate actions against erring units be strictly complied with by the concerned State/UT Government and SPCBs/PCCs. (State/UT Governments and SPCBs/PCCs : immediate).”

3. In light of above, the Tribunal inter-alia directed as follows:—

“20. ….i.&ii….xxx………………………….xxx…………………………..xxx

iii. As already directed, all the States which have not set up TSDF may do so and the States which fail to set up the same up to 31.03.2020, will be liable to pay environmental compensation of Rs. 10 lakh per month. However, with regard to States which may be categorized as small States, having regard to the quantum and nature of generation of hazardous waste, the liability to pay compensation will start from 01.01.2021. The categorization based on threshold limit of generation of hazardous waste be made by the CPCB within one month from today and placed on its website.”

4. The said directions were reiterated in subsequent orders dated 07.07.2020 and 29.01.2021. Thus, setting up of TSDFs by all the States is mandatory and till it is done, no new industries can be allowed nor those operating and generating hazardous waste can be allowed without regulation in violation of the Rules compliance of which is necessary in the interest of the environment and public health. This aspect does not brook any delay or laxity, as depicted from the present application.

5. None appears for the applicant but we have perused the application which states that the process for setting up TSDF started in 2006 for which EC was granted in 2008. Thereafter, decision was taken that TSDF may be set up by individual companies. Area was allocated, plan for construction was prepared, inventory of waste was also prepared, operator was selected, drawing was approved. Waste was being disposed of through M/s Maharashtra Enviro Power Ltd. or other entities. Covid is another reason for not setting up TSDF. The State has pursued the matter. Consent to operate has been granted by the State PCB. Thus, according to the applicant, no compensation is liable to be paid, as sought to be done by the CPCB vide order dated 26.2.2021 and subsequent orders, in pursuance of order of this Tribunal dated 26.8.2019, supra.

6. We are unable to entertain this application. Once there is acknowledged violation in setting up of TSDF, as required under the Rules and orders of this Tribunal, there is no reason for the waiver of compensation. The application itself states that identical M.A. No. 33/2021 filed by the State of Assam and M.A. No. 34/2021 filed by Chhattisgarh State Industrial Corporation Ltd. have been dismissed.

7. The application is dismissed.