Sandeep Kumar Gupta v. Raheja Developers Ltd and Other
Factual and Procedural Background
The complainant, Sandeep Kumar Gupta, applied for an affordable flat under the "Krishna Housing Scheme 2014" advertised by Raheja Developers Ltd. The complainant was allotted Flat No.12005 in Tower No.C-2 with a sale price of Rs. 15,24,022/-, payable in installments, which the complainant duly paid up to Rs. 13,99,161/-. The agreement to sell executed on 09.10.2015 stipulated that possession would be delivered within 48 months from the date of environmental clearance, i.e., by March 2019.
Despite assurances and partial progress, construction was significantly delayed, with only about 10% work completed by September 2019 and no commencement of Tower C-2 construction. The complainant alleged that the opposite parties made false assurances, misrepresented facts, and failed to deliver possession, thereby causing financial loss and mental agony. The complainant sought refund of the deposited amount with interest and compensation for harassment.
The opposite parties initially appeared and filed a written statement but later remained absent during evidence, resulting in an ex-parte proceeding against them. The Commission heard the complainant, reviewed affidavits and documents, and proceeded to decide the matter.
Legal Issues Presented
- Whether the opposite parties were liable for deficiency in service and breach of contractual obligation in failing to deliver possession within the stipulated period.
- Whether the complainant was entitled to refund of the amount paid along with interest due to delay and non-completion of the project.
- Whether the complainant was entitled to compensation for harassment and mental agony caused by the opposite parties' conduct.
Arguments of the Parties
Complainant's Arguments
- The opposite parties advertised and allotted a flat with the assurance of possession within 48 months from environmental clearance.
- The complainant made payments as per schedule without default.
- Construction was delayed beyond the committed period with minimal work done.
- The opposite parties gave false assurances and misrepresented the status of the project.
- The complainant sought refund of Rs. 13,99,161/- with interest at 12% per annum and compensation of Rs. 1,00,000/- for harassment and mental agony.
Opposite Parties' Arguments
- The basic cost of the flat was Rs. 15,24,022/- plus applicable taxes.
- Timely payment of installments was essential; an amount of Rs. 1,98,122/- was still due from the complainant.
- The agreement clause 5.2 allowed for delay subject to force majeure and timely payment.
- The delay was beyond their control and they had kept the complainant updated on progress.
- They aimed to complete the project by October 2021.
- The complainant was aware of delays and did not object for two years.
- They denied all allegations as false and prayed for dismissal of the complaint with costs.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Commission considered the complainant's affidavit and documentary evidence, which remained unrebutted due to the ex-parte status of the opposite parties who failed to present evidence. The Commission noted the contractual terms, including the commitment period for possession, and found that the opposite parties did not complete construction within the stipulated time. The alleged delay was not satisfactorily explained as a force majeure event, and the complainant had complied with payment obligations to a large extent. The Commission accepted the complainant's version as credible and found the opposite parties liable for deficiency in service and breach of contract.
Holding and Implications
The complaint is accepted with costs.
The opposite parties are directed to refund Rs. 13,99,161/- to the complainant along with interest at 9% per annum from the date of each deposit until realization. Additionally, the complainant is awarded Rs. 30,000/- as compensation for harassment and mental agony and Rs. 5,500/- towards litigation expenses. The opposite parties must comply with the order within 30 days of receipt. This decision directly affects the parties by mandating refund and compensation but does not establish a new legal precedent.
. 1
DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION
GURGAON-122001. Consumer Complaint No. 12 of 2020 Date of Institution: 06.01.2020
Date of Decision: 22.02.2022
Sandeep Kumar Gupta son of Sh. Satish Kumar Gupta, resident of House No.731-A/2, Patel Nagar, Gurugram.
……Complainant
Versus
1.Raheja Developers Ltd., Raheja Mall, 3rd Floor, Sector-47, Sohna Road, Gurugram-122001, through its Managing Director.
2.Naveen Raheja, Managing Director, Raheja Developers Ltd., Raheja Mall, 3rd Floor, Sector 47, Sohna Road, Gurugram -122001.
.......Opposite party
Complaint under Section 12 & 14 of Consumer Protection Act,1986
BEFORE: SHRI SANJEEV JINDAL, PRESIDENT.
DR. RISHI DUTT KAUSHIK, MEMBER.
Present: Shri Satish Gupta, Advocate for the complainant. Opposite parties exparte vide order dated 16.12.2021.
ORDER SANJEEV JINDAL, PRESIDENT.
Briefly stated, the complainant has averred that the OP No.1 advertised a scheme for allotment of affordable flats in the name & style of
"Krishna Housing Scheme 2014" in Sector-14, Sohna, Gurugram and invited applications from 19.11.2014 to 30.01.2015. The complainant applied for the allotment of the residential apartment in the aforesaid scheme and was allotted Flat No.12005 at 12th Floor, in Tower No.C-2 having carpet area 414.37 sq.ft. and balcony area 64.58 sq.ft by the opposite party vide Allotment letter dated 09.10.2015, with the assurance that the possession of the same would be given
1
within the stipulated period and construction would be of the best quality. The sale price of the residential apartment was agreed at Rs. 15,24,022/-, which included parking, interest bearing maintenance security, preferential location charges, EDC and IDC etc., if applicable. The payment was to be made by the complainant as per the schedule given by the OPs in installments. It was also agreed that if the payment was delayed by the complainant, then the installments would be paid with penal interest. The complainant made payments to the OPs as per the schedule and never defaulted any installment. In this way, the complainant had already deposited a sum of Rs.13,99,161/- with the OPs as per their demand as shown in Annexure A-3. Vide letter dated 07.05.2015, the complainant was intimated that the site plan of the project had been revised on 12.11.2014 and Environment Clearance Certificate had been received on 09.03.2015 as shown in Annexure A-4. An agreement to sell had been executed between the parties on 09.10.2015 containing all the terms and conditions as well as payment plan. It was assured under Clause No.5.2 of the agreement to sell that the OPs shall complete the construction and offer the possession of the unit of the complainant within 48 months from the date of receiving of environment clearance or sanction of building plans, whichever was later and that was called commitment period. Thus, the OPs were under legal obligation to deliver the possession up to March 2019. (Copy of Agreement to Sell was attached as Annexure A-5). However, on 15.09.2019, when the complainant visited the site no construction work was going on at the site and only 10% work had been carried out by the OPs till then which could be ascertained from the fact that even after a period of more than four years
2
from the date of allotment, no work as assured by the OPs was being carried on. The construction of Tower C-2 had not been commenced by the OPs till today. (Copy of photograph dated 15.09.2019 was attached as Annexure A-6). The OPs in their mail dated 09.08.2018 had assured that the project would be completed by the end of year 2019 but there were no chances of completion of the project in near future, as the construction activities were lying stopped. The OPs had just given the false assurances for completing the project without any intention to complete it. It appeared that the amount collected from the allottees of this project had been transferred to some other project or in personal accounts. At the time of allotment, it was assured by the representatives of the opposite party's company that possession will be delivered within a period of 48 months from the date of allotment, but even after more than almost 4 years no work as assured by the OPs company had been done. Thus, the opposite parties had deceived the complainant under the garb of false assurances and misrepresentations for a huge amount of Rs. 13,99,161/- till date and had been using the hard-earned money of the complainant for their own benefit. Therefore, the complainant had no other option except to seek the refund which had not been paid by the OPs till the present date. As such, the opposite parties were liable to refund the amount in question along with interest @12% per annum and were also liable to pay the damages to the complainants due to deficiency in services on their part. Hence, this complaint. In the end, the complainant prayed that a direction be given to the OPs to refund the deposited amount of Rs.13,99,161/-along with
3
interest @ 12 % p.a. and also a compensation of Rs.1,00,000/- as damages on account of harassment and mental agony.
2. Upon notices, initially, the OPs appeared through counsel and filed their written statement but lateron, at the time of adducing their evidence, they opted to remain absent and hence, they were proceeded against ex-parte vide order dated 16.12.2021.
In their written statement, the OPs contended that the basic cost of the flat booked without taxes was Rs. 15,24,022/- and with taxes was Rs. 15,97,283/- and that as per the clause 4.10, the timely payment of the installment was the essence of the contract. As per the ledger Annexure R-6,
an amount of Rs. 198,122/- was still due which was to be paid by the complainant. The Clause 5.2 of the Agreement clearly stated that: - "The Company shall sincerely endeavor to complete the construction and offered the possession of the said unit within 48 months from the date of
the receiving of environmental clearance or sanction of building plans
whichever is later ("Commitment Period") but subject to force majeure
clause of this agreement and timely payment of instalments by the
Allottee(s). However, in case the Company complete the construction
period to the period of 48 months the Allottee shall not raise any objection
in taking the possession after payment of remaining sale price and other
charges stipulated in the agreement to sell. The company obtaining
certificate for occupation and use by the competent authority shall hand
over the said unit to the Allottee for his/her/ their occupation and use,
subject to the Allottee having compiled with all the terms and conditions of
the said policy and agreement to sell and payments made as per the
Payment Plan."
The OPs had always updated the complainant with the progress at the project and further that the OPs had always responded to the queries of the complainant. The OPs were doing their best efforts to complete the construction and offer the possession of the Apartment to the complainant in
4
time. The delay in completing the project was beyond the control of the OPs. The OPs vide their email dated 19.09.2019 had informed the complainant that the project was targeted to be completed by the year October, 2021 tentatively and accordingly the delivery of possession formalities would be initiated as shown in Annexure R-7. The complainant being a permanent resident of Gurgaon, Haryana wanted to invest his money in a property for real estate speculative income and since he was aware of the boom in real estate market, so observing the genuine delay due to force majeure conditions he kept mum for the past 2 years. All other allegations levelled by the complainant were also refuted by the opposite parties as false and frivolous. In the end, the OPs prayed for dismissal of the complaint with costs.
3. To substantiate his case, the complainant has placed on the record of this file his affidavit Ex.PW1/A and some documents which are Ex. P-1 to P-7.
4. We have heard the complainant and have perused the record available on the file carefully. Besides, we have also gone through the written arguments submitted by the complainant.
5. The complainant in his evidence has tendered his affidavit
Ex.PW1/A and certain other documents i.e. Ex. P-1 to P-7. In the aforesaid affidavit, the complainant has reiterated the averments made by him in his pleadings almost on the similar lines and hence the contents of the affidavit are not being reproduced herewith in order to avoid the repetition. The documents i.e. Ex. P-1 to P-7 submitted by the complainant also confirms the aforesaid version of the complainant.
5
Since, the opposite parties in this case have been proceeded against exparte and there is no evidence on their behalf on the record of this file, so the evidence produced on the record of this file by the complainant goes unrebutted and as such this Commission does not find any reason to disbelieve the same. Accordingly, the complaint of the complainant is accepted with costs.
7. Therefore, after considering all the facts and circumstances of the case, we direct the opposite parties to refund the deposited amount to the tune of Rs.13,99,161/- to the complainant along with interest @ 9 % p.a. from the date of each deposit till realization. The complainant is also entitled to compensation for harassment and mental agony to the tune of Rs.30,000/-as well as litigation expenses to the tune of Rs.5500/-. The opposite party shall make the compliance of the order within 30 days from the date of receipt of the copy of this order. The OPs shall make the compliance of the order within 30 days from the date of receipt of the copy of this order. The parties be communicated of the order accordingly and the file be consigned to the records after due compliance.
Announced (Sanjeev Jindal)
22.02.2022 President,
District Consumer Disputes
Redressal Commission, Gurgaon
(Rishi Dutt Kaushik)
Member