- Bookmark
- Share
- CaseIQ
Power Grid Corporati... v. Madhya Pradesh Power...
Factual and Procedural Background
The Petitioner, Power Grid Corporation of India Limited, filed a petition seeking truing up of transmission tariff for the 2014-2019 tariff period under the 2014 Tariff Regulations and determination of transmission tariff for the 2019-2024 tariff period under the 2019 Tariff Regulations. The petition pertains to six transmission assets under the Western Region System Strengthening Scheme-XIV in the Western Region.
The transmission project was entrusted to the Petitioner following agreements in regional power system meetings in 2014 and 2015. Investment approval was granted in January 2016 at an estimated cost of Rs. 12067 lakh. The assets were commissioned between August 2017 and December 2018, with some assets having time overruns that were disallowed in a prior order dated 21.1.2020.
The Petitioner seeks approval for trued-up tariff for the 2014-2019 period and tariff for the 2019-2024 period, along with permission to recover various costs such as filing fees, licensee fees, GST (if applicable in future), and interest adjustments due to floating interest rates. The petition was served on the Respondents, who include transmission utilities, distribution licensees, and power departments mainly beneficiaries of the Western Region. MP Power Management Company Limited (MPPMCL) filed a reply raising issues on Income Tax rates and CGST, which were rejected by the Commission based on previous orders.
The matter was heard via video conference on 9.7.2021, and the order was reserved thereafter.
Legal Issues Presented
- Whether the trued-up transmission tariff for the 2014-2019 tariff period for the specified transmission assets should be approved under the 2014 Tariff Regulations.
- Whether the transmission tariff for the 2019-2024 tariff period for the transmission assets should be determined under the 2019 Tariff Regulations.
- Whether the Petitioner can recover shortfalls or refund excess annual fixed charges related to Return on Equity due to changes in applicable Income Tax rates without separate application to the Commission.
- Whether the Petitioner is entitled to reimbursement of petition filing fees, publication expenses, licensee fees, RLDC fees, and GST charges from beneficiaries as per the applicable regulations.
- Whether additional capital expenditures, interest during construction, incidental expenditure during construction, initial spares, and security expenses claims are admissible under the respective Tariff Regulations.
- How the transmission charges should be shared between the Petitioner and MPPTCL, especially concerning transmission charges prior to commissioning of downstream systems and the impact of pending litigation before the Madhya Pradesh High Court.
Arguments of the Parties
Petitioner’s Arguments
- Petitioner sought approval of trued-up tariffs for 2014-2019 and determination of tariff for 2019-2024 for six transmission assets.
- Claimed additional capital expenditure (ACE), interest during construction (IDC), incidental expenditure during construction (IEDC), initial spares, and operation & maintenance expenses within norms prescribed by the Tariff Regulations.
- Requested permission to recover shortfalls or refund excess Annual Fixed Charges on account of Return on Equity due to changes in Income Tax rates directly from beneficiaries.
- Prayed for reimbursement of petition filing fees, publication expenses, licensee fees, RLDC fees, and GST charges from beneficiaries.
- Submitted that downstream systems of MPPTCL for Asset-V and Asset-VI are yet to be commissioned, and tariff should be worked out separately for these assets.
- Claimed that GST on transmission charges, if imposed in future, should be separately billed and recovered from beneficiaries.
- Requested to allow filing a separate petition for security expenses and consequential Interest on Working Capital (IOWC).
- Provided detailed financial and technical data including capital costs, depreciation, loan interest, Return on Equity, and working capital calculations in accordance with applicable regulations.
Respondent (MPPMCL) Arguments
- Raised issues regarding effective Income Tax rates for grossing up Return on Equity during the 2014-2019 tariff period and the effect of CGST.
- Repeated similar contentions raised in other petitions, which have been rejected by the Commission in prior orders.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Order dated 15.11.2018 in Petition No. 37/TT/2018 | Approval of Commercial Operation Date (COD) and transmission tariff for Asset-I for 2014-2019 tariff period | Used as basis for capital cost, depreciation, and tariff approval for Asset-I in truing up process. |
| Order dated 21.1.2020 in Petition No. 311/TT/2018 | Approval of COD and tariff for Assets-II to VI; disallowance of time over-run; transmission charge sharing with MPPTCL | Applied to disallow time over-run costs, approve CODs, and determine transmission charge sharing mechanism with MPPTCL. |
| Order dated 27.4.2020 in Petition No. 274/TT/2019 | Determination of effective MAT rates for grossing up Return on Equity | Commission adopted MAT rates from this order for truing up RoE in present petition. |
| Order dated 3.8.2021 in Petition No. 260/MP/2020 | Approval of security expenses for 2019-2024 tariff period | Security expenses for transmission assets to be shared as per this order; petitioner's prayer for separate petition on security expenses held infructuous. |
| APTEL Judgment dated 2.12.2019 in Appeal Nos. 95 and 140 of 2018 | Computation of Incidental Expenditure During Construction (IEDC) on actual basis after prudence check | Commission followed this principle to allow IEDC on actual basis subject to prudence and disallowed IEDC proportionate to time over-run disallowance. |
Court's Reasoning and Analysis
The Commission undertook a detailed prudence check of the Petitioner’s claims for capital costs, additional capital expenditure (ACE), interest during construction (IDC), incidental expenditure during construction (IEDC), initial spares, and operation and maintenance (O&M) expenses. It considered auditor certificates, prior orders, and applicable tariff regulations for the relevant periods.
The Commission noted that the completion cost was within the approved investment approval cost, hence no cost over-run was found. Time over-runs for certain assets were disallowed as per the prior order dated 21.1.2020.
IDC was allowed on a cash basis considering the Petitioner’s submissions and auditor certificates, adjusting for time over-run disallowances. IEDC was allowed on actual basis following the APTEL judgment, but disallowed proportionately for assets with time over-run not condoned.
Initial spares claims were allowed within the ceiling limits prescribed by the 2014 Tariff Regulations.
Debt-equity ratios were applied as per the respective Tariff Regulations, typically 70:30 normative ratio. Depreciation was computed using weighted average rates and straight-line method, considering the asset life and accumulated depreciation.
Return on Equity (RoE) was trued-up based on the applicable Minimum Alternate Tax (MAT) rates for the 2014-2019 period and estimated MAT rates for the 2019-2024 period, with provisions for true-up based on actual tax paid.
Operation and Maintenance expenses were allowed within normative limits prescribed by the regulations. Interest on Working Capital was computed normatively based on prescribed components and interest rates.
The Commission accepted the Petitioner’s approach to combine certain assets for tariff determination for 2019-2024, while treating Asset-V and Asset-VI separately due to pending commissioning of downstream systems by MPPTCL.
Regarding the sharing of transmission charges, the Commission adhered to its prior order dated 21.1.2020, directing that transmission charges for Assets-II to VI prior to commissioning of downstream systems are to be borne by MPPTCL and thereafter shared under the Point of Connection (PoC) mechanism. However, this sharing arrangement is subject to the outcome of MPPTCL’s pending writ petition before the Madhya Pradesh High Court.
The Petitioner’s claims for filing fees and publication expenses were allowed to be recovered directly from beneficiaries as per Regulation 70 of the 2019 Tariff Regulations. Licence fees and RLDC fees and charges were similarly allowed for recovery.
The Petitioner’s prayer to recover GST on transmission charges was considered premature as GST is currently not levied on transmission services.
The Petitioner’s request to file a separate petition for security expenses and consequential Interest on Working Capital was rendered infructuous as security expenses for the 2019-2024 period were already approved in a separate petition (No. 260/MP/2020).
Holding and Implications
The petition for truing up of transmission tariff for the 2014-2019 tariff period and determination of transmission tariff for the 2019-2024 tariff period is disposed of in terms of the detailed findings and approvals set out in this order.
The Commission approved the trued-up Annual Fixed Charges (AFC) for the 2014-2019 tariff period and the tariff for the 2019-2024 tariff period for the transmission assets, subject to the conditions and adjustments discussed. The recovery of transmission charges from MPPTCL prior to commissioning of downstream systems is allowed as per prior orders but remains subject to the outcome of MPPTCL’s pending writ petition.
The order sets no new precedent beyond the application of existing tariff regulations and prior Commission and APTEL decisions. It primarily resolves the Petitioner’s claims for tariff approval and cost recovery for the specified transmission assets and periods.
1. The Petitioner, Power Grid Corporation of India Limited, has filed the instant petition for truing up of transmission tariff of the 2014-2019 tariff period under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (hereinafter referred to as “the 2014 Tariff Regulations”) and for determination of transmission tariff for the period from 1.4.2019 to 31.3.2024 under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 (hereinafter referred to as “the 2019 Tariff Regulations”) in respect of the following transmission assets under Western Region System Strengthening Scheme-XIV in Western Region (hereinafter referred to as “the transmission project”):
Asset-I: 1×500 MVA, 400/220 kV ICT along with associated transformer bays and 220 kV line bays at Itarsi Sub-station;
Asset-II: 1×500 MVA, 400/220 kV ICT-2 along with associated bays and 2 number 220 kV line bays at 400/220 kV Indore Sub-station;
Asset-III: 2 numbers 220 kV line bays at 400/220 kV Indore Sub-station;
Asset-IV: 1×500 MVA, 400/220 kV ICT-1 along with associated bays at 400/220 kV Indore Sub-station;
Asset-V: 1 number 220 kV line bay at 400/220 kV Indore Sub-station; and
Asset-VI: 1 number 220 kV line bay at 400/220 kV Indore Sub-station.
2. The Petitioner has made the following prayers in this petition:
“1) Allow the Add cap for 2014-2019 and 2019-2024 tariff block as claimed as per Para 5 and 7 above.
2) Approve the trued up Transmission Tariff for 2014-2019 block and transmission tariff for 2019-2024 block for the assets covered under this petition, as per para 6 and 7 above.
3) Allow the petitioner to recover the shortfall or refund the excess Annual Fixed Charges, on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before Hon'ble Commission as provided in Tariff Regulation, 2014 and Tariff regulations 2019 as per para 5 and 6 above for respective block.
4) Approve the reimbursement of expenditure by the beneficiaries towards petition filing fee, and expenditure on publishing of notices in newspapers in terms of Regulation 70 (1) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019, and other expenditure (if any) in relation to the filing of petition.
5) Allow the petitioner to bill and recover Licensee fee and RLDC fees and charges, separately from the beneficiaries in terms of Regulation 70 (3) and (4) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019.
6) Allow the petitioner to bill and adjust impact on Interest on Loan due to change in Interest rate on account of floating rate of interest applicable during 2019-2024 period, if any, from the beneficiaries.
7) Allow the petitioner to file a separate petition before Hon'ble Commission for claiming the overall security expenses and consequential IOWC on that security expenses as mentioned at para 6.6 above.
8) Allow the petitioner to claim the capital spares at the end of tariff block as per actual.
9) Allow the Petitioner to bill and recover GST on Transmission Charges separately from the beneficiaries, if GST on transmission is withdrawn from negative list at any time in future. Further, any taxes including GST and duties including cess etc. imposed by any statutory/Govt./municipal authorities shall be allowed to be recovered from the beneficiaries. and pass such other relief as Hon'ble Commission deems fit and appropriate under the circumstances of the case and in the interest of justice.”
3. Backdrop of the case
a) The Petitioner was entrusted with the implementation of the transmission project and it was discussed and agreed during the 37 Standing Committee Meeting (SCM) on Power System in Western Region held on 5.9.2014. Further, the transformation capacity of 400/220 kV ICT of Itarsi Sub-station has been modified from 315 MVA to 500 MVA in the 38 SCM on Power System Planning in Western Region held on 17.7.2015. The proposal pertaining to the said modification was also discussed and agreed in the 29 Western Regional Power Committee meeting held on 24.7.2015.
b) Investment Approval (I.A.) for the transmission project was accorded by Board of Directors of the Petitioner's company (in its 325 meeting held on 27.1.2016) vide Memorandum Ref. No. C/CP/WRSSXIV dated 11.2.2016 at an estimated cost of Rs. 12067.00 lakh including IDC of Rs. 758.00 lakh (based on August 2015 Price Level) with the broad scope of work as follows:
i. Extension of 400/220 kV Indore (POWERGRID) Sub-station:
—Installation of 2×500 MVA, 400/220 kV, ICTs along with associated transformer bays; and
—220 kV Line bays : 6 numbers.
ii. Extension of 400/220 kV Itarsi (POWERGRID) Sub-station:
—Installation of 1×500 MVA, 400/220 kV, ICT along with associated transformer bays; and
—220 kV Line bays : 2 numbers.
c) The transmission tariff of Asset-I from COD (14.8.2017) to 31.3.2019 was approved by the Commission vide order dated 15.11.2018 in Petition No. 37/TT/2018. There was no time over-run for Asset-I.
d) The Petitioner had filed Petition No. 311/TT/2018 for approval of transmission tariff of 2×500 MVA, 400/220 kV ICTs along with associated bays and 6 numbers 220 kV line bays at 400/220 kV Indore Sub-station from anticipated COD (1.9.2018) to 31.3.2019. However, due to different dates of commercial operation, the Petitioner vide affidavit dated 21.6.2019 had split the forenamed asset into five assets as follows:
Asset as filed in Petition No. 311/TT/2018 Asset split as per affidavit dated 21.6.2019 2×500 MVA, 400/220 kV ICTs along with associated bays and 6 numbers 220 kV line bays at 400/220 kV Indore Sub-station Asset-1: 1×500 MVA, 400/220 kV ICT-2 along with associated bays and 2 numbers 220 kV line bays at 400/220 kV Indore Sub-station Asset-2: 2 numbers 220 kV line bays at 400/220 kV Indore Sub-station Asset-3: 1×500 MVA, 400/220 kV ICT-1 along with associated bays at 400/220 kV Indore Sub-station Asset-4: 1 number 220 kV line bay at 400/220 kV Indore Sub-station Asset-5: 1 number 220 kV line bay at 400/220 kV Indore Sub-station
e) The transmission tariff of Asset-1, Asset-2, Asset-3, Asset-4 and Asset-5 from their respective COD of 2.9.2018, 2.9.2018, 14.10.2018, 14.10.2018 and 5.12.2018 to 31.3.2019 was allowed vide order dated 21.1.2020 in Petition No. 311/TT/2018. The respective COD of Asset-1 to Asset-5 was approved under proviso (ii) of Regulation 4(3) of the 2014 Tariff Regulations due to non-commissioning of the associated downstream transmission system of MPPTCL, which is expected to be completed by 2022-2023.
f) As per I.A. dated 27.1.2016, the scheduled COD of the transmission assets was 27.7.2018 against which Asset-1, Asset-2, Asset-3, Asset-4 and Asset-5 were commissioned with a time over-run of 37 days, 37 days, 79 days, 79 days and 131 days respectively. The entire time over-run in case of of Asset-1, Asset-2, Asset-3, Asset-4 and Asset-5 was dis-allowed vide order dated 21.1.2020 in Petition No. 311/TT/2018.
g) The Petitioner in this petition has used new nomenclature for assets of Petition No. 311/TT/2018 as follows:
Asset nomenclature in Petition No. 311/TT/2018 Asset nomenclature in this petition Asset-1 Asset-II Asset-2 Asset-III Asset-3 Asset-IV Asset-4 Asset-V Asset-5 Asset-VI
h) Further, the trued-up transmission tariff of Asset-I to Asset-VI for the 2014-2019 tariff period has been sought by the Petitioner in this petition. The approval of transmission tariff with respect to Combined Asset (comprising of Asset-I to Asset-VI) for the 2019-2024 tariff period has also been sought by the Petitioner in this petition.
i) As per I.A., the entire scope of work is complete and is covered in this petition.
4. The Respondents are transmission utilities, distribution licensees and power departments, which are procuring transmission services from the Petitioner, mainly beneficiaries of Western Region.
5. The Petitioner has served the petition on the Respondents and notice regarding filing of this petition has been published in the newspapers in accordance with Section 64 of the Electricity Act, 2003. No comments or objections have been received from the general public in response to the aforesaid notices. Madhya Pradesh Power Management Company Limited (MPPMCL), Respondent No. 1 has filed its reply vide affidavit dated 3.11.2020 and has raised the issues of effective Income Tax rates for grossing up of Return on Equity (RoE) during the 2014-2019 tariff period and effect of CGST. The Petitioner vide affidavit dated 11.11.2020 has filed rejoinder to MPPMCL's reply.
6. It has been placed before us that MPPMCL has been raising the same issues in other petitions as well despite clear findings of the Commission. The contentions of MPPMCL have been rejected by the Commission in other petitions including order dated 21.9.2021 in Petition No. 326/TT/2020. As MPPMCL has not challenged the findings, the same have attained finality. In view of this, the pleas raised by MPPMCL are rejected. Further, MPPMCL's submissions, Petitioner's clarifications thereto and the Commission's findings on the said issues have not been repeated herein for the sake of brevity.
7. This order is issued considering the submissions made by the Petitioner in the petition vide affidavit dated 29.6.2020, MPPMCL's reply filed vide affidavit dated 3.11.2020, the Petitioner's rejoinder filed vide affidavit dated 11.11.2020, the Petitioner's affidavit dated 11.2.2021 and 28.7.2021 filed in reply to technical validation letter dated 28.1.2021 and Record of Proceedings dated 9.7.2021 respectively.
8. The hearing in this matter was held on 9.7.2021 through video conference and the order was reserved. Having heard the representatives of the Petitioner, MPPMCL and after perusal of the materials on record, we proceed to dispose of the petition.
TRUING UP OF ANNUAL FIXED CHARGES FOR THE 2014-2019 TARIFF PERIOD
9. The details of the trued-up transmission charges claimed by the Petitioner in respect of the transmission assets for the 2014-2019 tariff period are as follows:
(Rs. in lakh)
Asset-I Particulars 2017-2018 (Pro-rata for 230 days) 2018-19 Depreciation 83.15 148.81 Interest on Loan 83.78 141.31 Return on Equity 91.31 163.73 Interest on Working Capital 12.22 20.70 O&M Expenses 129.90 213.01 Total 400.36 687.56
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Depreciation 96.78 18.10 48.28 7.00 4.93 Interest on Loan 92.77 15.75 45.89 6.27 4.47 Return on Equity 106.00 18.68 53.39 7.41 5.22 Interest on Working Capital 12.27 3.86 5.76 1.54 1.07 O&M Expenses 123.14 55.61 54.08 22.27 15.42 Total 430.96 112.00 207.40 44.49 31.11
10. The details of the trued-up Interest on Working Capital (IWC) claimed by the Petitioner in respect of the transmission assets for the 2014-2019 tariff period are as follows:
(Rs. in lakh)
Asset-I Particulars 2017-2018 (Pro-rata for 230 days) 2018-19 O&M Expenses 17.18 17.75 Maintenance Spares 30.92 31.95 Receivables 105.90 114.59 Total 154.00 164.29 Rate of Interest (in %) 12.60 12.60 Interest on Working Capital 12.22 20.70
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) O&M Expenses 17.75 8.02 9.73 4.01 4.01 Maintenance Spares 31.95 14.43 17.52 7.22 7.22 Receivables 124.25 32.29 74.66 16.01 16.17 Total Working Capital 173.95 54.74 101.91 27.24 27.40 Rate of Interest (in %) 12.20 12.20 12.20 12.20 12.20 Interest on Working Capital 12.27 3.86 5.76 1.54 1.17
Date of Commercial Operation
11. The Commission vide order 15.11.2018 and 21.1.2020 in Petition No. 37/TT/2018 and Petition No. 311/TT/2018 respectively had approved COD for the transmission assets as follows:
Asset SCOD COD Asset-I 27.7.2018 14.8.2017 Asset-II 2.9.2018* Asset-III 2.9.2018* Asset-IV 14.10.2018* Asset-V 14.10.2018* Asset-VI 5.12.2018*
*COD approved under proviso (ii) to Regulation 4(3)(ii) of 2014 Tariff Regulations.
12. The Commission had approved COD of Asset-II and Asset-III as 2.9.2018, of Asset-IV and Asset-V as 14.10.2018 and of Asset-VI as 5.12.2018 under proviso (ii) of Regulation 4(3) of the 2014 Tariff Regulations due to non-commissioning of the associated downstream transmission system under the scope of MPPTCL. The Petitioner has submitted that the downstream system is expected to be completed by 2022-2023.
Capital Cost
13. The details of the approved cost (FR) along with capital cost as on COD and estimated capital cost as on 31.3.2019, including projected Additional Capital Expenditure (ACE) during the 2014-2019 period, as admitted by the Commission vide order dated 15.11.2018 and 21.1.2020 in Petition No. 37/TT/2018 and Petition No. 311/TT/2018 respectively are as follows:
(Rs. in lakh)
Asset Approved Cost (FR) Capital Cost admitted (as on COD) ACE admitted Estimated Capital Cost admitted (as on 31.3.2019) 2017-18 2018-19 Asset-I 3507.44 2278.30 489.46 396.20 3163.96 Asset-II 3841.48 2928.25 0.00 312.43 3240.70 Asset-III 876.51 505.26 0.00 77.47 582.73 Asset-IV 2964.98 1818.99 0.00 212.07 2030.30 Asset-V 438.25 247.21 0.00 33.84 281.04 Asset-VI 438.25 257.68 0.00 28.13 285.74
14. Based on the Auditor's Certificates dated 13.4.2020, the details of capital cost as on COD and as on 31.3.2019 (including actual ACE during the 2014-2019 period) claimed by the Petitioner are as follows:
(Rs. in lakh)
Asset Approved Cost (FR) Capital Cost (as on COD) Actual ACE Capital Cost (as on 31.3.2019) 2017-18 2018-19 Asset-I 3507.44 2293.16 330.66 277.05 2900.87 Asset-II 3841.48 2990.50 0.00 277.29 3267.79 Asset-III 876.51 516.12 0.00 71.18 587.30 Asset-IV 2964.98 1883.59 0.00 173.76 2057.35 Asset-V 438.25 259.01 0.00 31.28 290.29 Asset-VI 438.25 270.15 0.00 24.26 294.41 Total 12066.91 9398.01
15. We have considered the submissions and claims of the Petitioner regarding capital cost and ACE and have given our findings on the same in the relevant portions of this order.
Cost Over-run
16. Based on the Auditor's Certificates dated 13.4.2020, the capital cost as on COD claimed by the Petitioner for Asset-I, Asset-II, Asset-III, Asset-IV, Asset-V and Asset-VI is Rs. 2293.16 lakh, Rs. 2990.50 lakh, Rs. 516.12 lakh, Rs. 1883.59 lakh, Rs. 259.01 lakh and Rs. 270.15 lakh respectively. Further, the completion cost as on 31.3.2019 (including ACE during the 2014-2019 period) in respect of the transmission assets as per the said Auditor's Certificates is Rs. 9398.01 lakh against the approved FR cost of Rs. 12066.91 lakh.
17. We observe that the completion cost as on 31.3.2019 in respect of all the transmission assets is within the approved cost as per FR. Therefore, there is no cost over-run in this case.
Time Over-run
18. As per I.A. dated 27.1.2016, the scheduled COD of the transmission assets was 27.7.2018 against which Asset-I, Asset-II, Asset-III, Asset-IV, Asset-V and Asset-VI were commissioned with a time over-run of 0 days, 37 days, 37 days, 79 days, 79 days and 131 days respectively. The entire time over-run in the commissioning of Asset-II to Asset-V was dis-allowed vide order dated 21.1.2020 in Petition No. 311/TT/2018.
Interest During Construction (IDC)
19. The Petitioner has submitted the details of IDC discharged up to COD and discharged during 2017-2018 and 2018-2019 in respect of the transmission assets in this petition. IDC on cash basis has also been submitted. Further, the accrued IDC discharged during 2017-2018 and 2018-2019 has not been included in ACE for the respective year in respect of the transmission assets as per the Auditor's Certificates.
20. The Petitioner has submitted that the entire IDC has been discharged during 2017-2018, 2018-2019 and 2019-2020 in respect of the transmission assets. Also, the transmission tariff has been recalculated with the claim of IDC on cash basis and un-discharged IDC on COD has been reduced from the expenditure up to COD and claimed as ACE during the respective year i.e. 2017-2018 for Asset-I and 2018-2019 and 2019-2020 for Asset-II to Asset-VI.
21. The Petitioner vide affidavit dated 11.2.2021 has submitted the cash IDC statements in respect of the transmission assets.
22. We have considered the submissions and claims of the Petitioner and note that the Petitioner has submitted the Auditor's Certificates dated 13.4.2020 in support of its claim of IDC. The Petitioner has also submitted the computation of IDC along with year-wise details of the IDC discharged.
23. In view of the foregoing, IDC allowed has been worked out considering the information submitted by the Petitioner for the transmission assets separately on cash basis. Further, the loan details submitted in Form-9C for the 2014-2019 tariff period and the IDC computation sheet have been considered for the purpose of IDC calculation on cash and accrued basis. Also, the un-discharged IDC as on COD has been considered as ACE during the year in which it has been discharged and, accordingly, based on the information furnished by the Petitioner, IDC considered, is summarized as follows:
(Rs. in lakh)
Asset IDC as per Auditor's Certificates IDC admissible IDC dis-allowed due to computational difference/time overrun not condoned IDC discharged as on COD IDC un-discharged as on COD IDC discharge during 2017-18 2018-19 2019-20 A B C=A-B D Asset-I 41.86 44.93 0.00 27.00 14.86 14.86 - - Asset-II 208.63 195.05 13.58 159.68 35.37 - 29.92 5.45 Asset-III 34.21 31.50 2.70 25.17 6.33 - 5.38 0.95 Asset-IV 91.54 73.40 18.14 67.19 6.21 - 5.14 1.07 Asset-V 17.91 14.99 2.92 12.46 2.53 - 2.15 0.38 Asset-VI 21.48 16.43 5.05 12.64 3.80 - 3.23 0.57
Incidental Expenditure During Construction (IEDC)
24. The Petitioner has submitted that entire IEDC amount mentioned in the Auditor's Certificates is on cash basis and is paid up to COD in respect of the transmission assets.
25. We have considered the submissions and claim of the Petitioner and note that on the issue of “IEDC to be considered in tariff”, the Appellate Tribunal for Electricity (APTEL) vide its judgment dated 2.12.2019 in Appeal Nos. 95 and 140 of 2018 held that IEDC should be computed only on actual basis after due prudence check based on the data submitted in accordance with the Tariff Regulations. Further, vide paragraph 7.12 of the said judgment, APTEL, inter-alia, observed as follow:
“………without prejudice to the contention that hard costs should not be considered, even if hard cost is to be seen then, at least “IEDC” including contingencies should be applied.”
26. In view of the above-mentioned judgment of APTEL, computation of IEDC is to be made on actual basis after due prudence check. As a part of prudence exercise, IEDC allowed as per respective tariff orders for all the transmission assets of the transmission project has been compared with IEDC (including contingencies) for the transmission project as a whole as per the Revised Cost Estimate.
27. We further note that Regulation 11(B)(3) of the 2014 Tariff Regulations provides as follows:
“In case the time over-run beyond SCOD is not admissible after due prudence, the increase of capital cost on account of cost variation corresponding to the period of time over run may be excluded from capitalization irrespective of price variation provisions in the contracts with supplier or contractor of the generating company or the transmission licensee.”
28. Since there was time over-run in the commissioning of Asset-II to Asset-VI which was not condoned by the Commission, IEDC claimed in respect of the transmission assets has been disallowed on pro-rata basis. The details of claimed and allowed IEDC are as follows:
(Rs. in lakh)
Asset IEDC claimed as per Auditor's Certificates IEDC disallowed due to time over-run not condoned IEDC allowed as on COD 1 2 3=(1-2) Asset-I 109.31 0.00 109.31 Asset-II 183.27 7.14 176.13 Asset-III 28.66 1.12 27.54 Asset-IV 115.12 9.17 105.95 Asset-V 14.34 1.14 13.20 Asset-VI 14.88 1.87 13.01 Total 466.58 22.44 13.01
Initial Spares
29. The Petitioner has submitted that Initial Spares with respect to the transmission assets were admitted under sub-station head vide orders dated 15.11.2018 and 21.1.2020 in Petition No. 37/TT/2018 and Petition No. 311/TT/2018 respectively. Also, the Initial Spares have been revised as per the revised Auditor's Certificates as submitted in this petition and the revised amount of Initial Spares have been used for computation of tariff.
30. In view of the above, the Petitioner has requested to allow the following Initial Spares in respect of the transmission assets:
Asset Element Plant & Machinery Cost up to cut-off date (excluding IDC and IEDC) (Rs. in lakh) Initial Spares claimed (Rs.in lakh) Ceiling Limit (in %) Asset-I sub-station 2861.38 171.50 6.00 Asset-II sub-station 2943.75 54.82 6.00 Asset-III sub-station 562.68 18.44 6.00 Asset-IV sub-station 1883.62 36.38 6.00 Asset-V sub-station 281.35 9.22 6.00 Asset-VI sub-station 281.36 9.22 6.00
31. We have considered the submissions and claim of the Petitioner. Initial Spares are allowable subject to the ceiling specified in Regulation 13(d) of the 2014 Tariff Regulations. The Petitioner's claim of Initial Spares with respect to the transmission assets is within the norms specified and are, accordingly, allowed as follows:
Asset Element Capital Cost/P&M cost considered as on cut-off date (Rs.in lakh) Initial Spares claimed (Rs. in lakh) Norms as per the 2014 Tariff Regulations (in %) Initial Spares allowable as per the 2014 Tariff Regulations (Rs. in lakh) Initial Spares allowed (Rs. in lakh) Asset-I sub-station 2861.38 171.50 6.00 171.69 171.50 Asset-II sub-station 2943.75 54.82 6.00 184.40 54.82 Asset-III sub-station 562.68 18.44 6.00 34.74 18.44 Asset-IV sub-station 1883.62 36.38 6.00 117.91 36.38 Asset-V sub-station 281.35 9.22 6.00 17.37 9.22 Asset-VI sub-station 281.36 9.22 6.00 17.37 9.22
Capital Cost allowed as on COD
32. Accordingly, the details of the capital cost approved as on COD after adjustment of IDC, IEDC and Initial Spares are as follows:
(Rs. in lakh)
Asset Capital Cost as on COD as per Auditor's Certificates Less : IDC disallowed as on COD due to IEDC disallowed Capital Cost as on COD (on cash basis) Time over-run not condoned Un-discharged IDC 1 2 3 4 5=(1-2-3-4) Asset-I 2293.16 0.00 14.86 0.00 2278.30 Asset-II 2990.50 13.56 35.37 7.14 2934.41 Asset-III 516.12 2.70 6.33 1.12 505.96 Asset-IV 1883.59 18.14 6.21 9.17 1850.07 Asset-V 259.01 2.92 2.53 1.14 252.42 Asset-VI 270.15 5.05 3.80 1.87 259.44
Additional Capital Expenditure
33. The Petitioner vide Auditor's Certificates dated 13.4.2020 has claimed ACE during the 2014-2019 tariff period in respect of the transmission assets as follows:
(Rs. in lakh)
Asset ACE 2017-18 2018-19 Asset-I 330.66 277.05 Asset-II 0.00 277.29 Asset-III 0.00 71.18 Asset-IV 0.00 173.76 Asset-V 0.00 31.28 Asset-VI 0.00 24.26
34. The Petitioner has submitted that the admissibility of ACE incurred after COD and up to cut-off date is to be dealt in accordance with Regulation 14(1)(i) of the 2014 Tariff Regulations and the admissibility of ACE incurred after cut-off date is to be dealt in accordance with Regulation 14(3)(i) of the 2014 Tariff Regulations. Further, in this case, ACE incurred is within cut-off date and is, accordingly, claimed as per Regulation 14(1)(i) of the 2014 Tariff Regulations.
35. The Petitioner vide affidavit dated 11.2.2021 has submitted that ACE claimed for 2017-2018 and 2018-2019 is within the cut-off date and is mainly on account of un-discharged liability for the works executed prior to cut-off date and is claimed as per Regulation 14(1)(i) of 2014 Tariff Regulations. Further, ACE is also on account of unexecuted works that are considered as addition in gross block which is on account of the works executed after COD and the same is claimed under Regulation 14(1)(ii) of 2014 Tariff Regulations.
36. The Petitioner vide affidavit dated 11.2.2021 has submitted that there are many works in sub-station such as roads, drains, township, cable trench cover, service room of control room building other than main control room, landscaping works which are normally completed after COD. At the same time, for many works which are completed till COD, payments are made after COD. Final amendments to the work which involve some new items and, therefore, under negotiable rate, are not completed by COD. Hence, it is not possible to freeze the liability of all the works by COD.
37. The Petitioner vide affidavit dated 11.2.2021 has submitted that during true up of tariff which is undertaken after 1 to 5 years, most of the final amendments are issued, payments and material reconciliation get completed, final payments get released and contracts get closed. It is only at that stage that the actual status of payments are reconciled and value of works beyond cut-off date (i.e. value of un-executed works) and the actual liability as on COD are exactly known. Also, the justification for ACE claimed during the 2014-2019 period on account of balance and retention payment and un-executed/balance works (party-wise) has been submitted. Further, ACE claimed during the 2014-2019 has been submitted by the Petitioner in the format wherein head-wise/party-wise, year of actual capitalization, outstanding liability as on COD, discharge and reversal (year-wise), additional liability recognized and outstanding liability as on 31.3.2019 has been mentioned.
38. We have considered the submissions and claims of the Petitioner. ACE claimed by the Petitioner is allowed under Regulation 14(1)(i) for un-discharged liabilities and under Regulation 14(1)(ii) for unexecuted works of the 2014 Tariff Regulations.
Capital Cost for the 2014-2019 tariff period
39. In view of the above, the details of the allowed capital cost as on COD, as on 31.3.2019 and ACE during the 2014-2019 tariff period in respect of the transmission assets are as follows:
Asset Particulars Capital cost as on COD on cash basis ACE allowed Capital Cost as on 31.3.2019 2017-18 2018-19 Asset-I Allowed vide order dated 15.11.2018 in Petition No. 37/TT/2018 2278.30 489.46 396.20 3163.96 Claimed by the Petitioner in the instant petition 2293.16 330.66 277.05 2900.87 Approved in the instant order 2278.30 345.53 277.05 2900.88 Asset-II Allowed earlier in order dated 21.1.2020 in Petition No. 311/TT/2018 2928.25 0.00 312.43 3240.70 Claimed by the Petitioner in the instant petition 2990.50 0.00 277.29 3267.79 Approved in the instant order 2934.41 0.00 307.21 3241.62 Asset-III Allowed earlier in order dated 21.1.2020 in Petition No. 311/TT/2018 505.26 0.00 77.47 582.73 Claimed by the Petitioner in the instant petition 516.12 0.00 71.18 587.30 Approved in the instant order 505.96 0.00 76.56 582.52 Asset-IV Allowed earlier in order dated 21.1.2020 in Petition No. 311/TT/2018 1818.99 0.00 212.07 2030.30 Claimed by the Petitioner in the instant petition 1883.59 0.00 173.76 2057.35 Approved in the instant order 1850.07 0.00 178.90 2028.97 Asset-V Allowed earlier in order dated 21.1.2020 in Petition No. 311/TT/2018 247.21 0.00 33.84 281.04 Claimed by the Petitioner in the instant petition 259.01 0.00 31.28 290.29 Approved in the instant order 252.42 0.00 33.43 285.85 Asset-VI Allowed earlier in order dated 21.1.2020 in Petition No. 311/TT/2018 257.68 0.00 28.13 285.74 Claimed by the Petitioner in the instant petition 270.15 0.00 24.26 294.41 Approved in the instant order 259.44 0.00 27.49* 286.92
*including un-discharged IDC liability as on COD, discharged in 2018-19
Debt-Equity Ratio
40. The Petitioner has claimed debt-equity ratio of 70 : 30 as on COD and for ACE post 31.3.2014. Debt-equity ratio has been considered in accordance with Regulation 19 of the 2014 Tariff Regulations. The details of the debt-equity as on COD and 31.3.2019 in respect of the transmission assets considered for the purpose of truing up of tariff for the 2014-2019 tariff period is as follows:
Funding Capital Cost (as on COD) Rs. in lakh) (in %) Capital Cost (as on 31.3.2019) (Rs. in lakh) (in %) Asset-I Debt 1594.82 70.00 2030.63 70.00 Equity 683.48 30.00 870.25 30.00 Total 2278.30 100.00 2900.88 100.00 Asset-II Debt 2054.09 70.00 2269.14 70.00 Equity 880.32 30.00 972.48 30.00 Total 2934.41 100.00 3241.62 100.00 Asset-III Debt 354.18 70.00 407.77 70.00 Equity 151.78 30.00 174.75 30.00 Total 505.96 100.00 582.52 100.00 Asset-IV Debt 1295.05 70.00 1420.28 70.00 Equity 555.02 30.00 608.69 30.00 Total 1850.07 100.00 2028.97 100.00 Asset-V Debt 176.69 70.00 200.09 70.00 Equity 75.72 30.00 85.75 30.00 Total 252.42 100.00 285.85 100.00 Asset-VI Debt 181.61 70.00 200.85 70.00 Equity 77.83 30.00 86.07 30.00 Total 259.44 100.00 286.92 100.00
Depreciation
41. The depreciation has been allowed as per the methodology provided in Regulation 27 of the 2014 Tariff Regulations after considering capital expenditure as on COD and approved ACE during the 2014-2019 tariff period. The Gross Block during the 2014-2019 tariff period with respect to the transmission assets has been depreciated at Weighted Average Rate of Depreciation (WAROD). WAROD at Annexure-I (Colly.) has been worked out after taking into account the depreciation rates of assets as specified in the 2014 Tariff Regulations and the trued-up depreciation allowed for the transmission assets during the 2014-2019 tariff period is as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Opening Gross Block 2278.30 2623.83 Additional Capitalisation 345.53 277.05 Closing Gross Block 2623.83 2900.88 Average Gross Block 2451.07 2762.36 Weighted average rate of Depreciation (WAROD) (in %) 5.29 5.29 Elapsed useful life of the Asset-at the beginning of the year (Year) 0 0 Balance useful life of the Asset-at the beginning of the year (Year) 25 25 Aggregated Depreciable Value 2205.96 2486.12 Combined Depreciation during the year 81.68 146.06 Remaining Aggregated Depreciable Value 2124.28 2258.39
(Rs.in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Opening Gross Block 2934.41 505.96 1850.07 252.42 259.44 Additional Capitalisation 307.21 76.56 178.90 33.43 27.49 Closing Gross Block 3241.62 582.52 2028.97 285.85 286.92 Average Gross Block 3088.02 544.24 1939.52 269.13 273.18 Weighted average rate of Depreciation (WAROD) (in %) 5.29 5.31 5.28 5.31 5.31 Elapsed useful life of the Asset-at the beginning of the year (Year) 0 0 0 0 0 Balance useful life of the Asset-at the beginning of the year (Year) 25 24 25 24 24 Aggregated Depreciable Value 2779.21 489.82 1745.57 242.22 245.86 Combined Depreciation during the year 94.36 16.72 47.42 6.62 4.65 Remaining Aggregated Depreciable Value 2684.85 473.10 1698.15 235.60 241.21
42. Depreciation with respect to the transmission assets as allowed vide orders dated 15.11.2018 and 21.1.2020 in Petition No. 37/TT/2018 and Petition No. 311/TT/2018 respectively, claimed by the Petitioner in the instant petition and trued-up in the instant order is as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Allowed vide order dated 15.11.2018 in Petition No. 37/TT/2018 83.98 156.19 Claimed by the Petitioner in the instant petition 83.15 148.81 Approved after true-up in this order 81.68 146.06
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Allowed vide order dated 21.1.2020 in Petition No. 311/TT/2018 94.25 16.71 47.05 6.50 4.63 Claimed by the Petitioner in the instant petition 96.78 18.10 48.28 7.00 4.93 Approved after true-up in this order 94.36 16.72 47.42 6.62 4.65
Interest on Loan (IoL)
43. The Petitioner has claimed Weighted Average Rate of Interest (WAROI) on loan based on its actual loan portfolio and rate of interest. Accordingly, IoL has been calculated based on actual interest rates in accordance with Regulation 26 of the 2014 Tariff Regulations. The trued-up IoL allowed in respect of the transmission assets for the 2014-2019 tariff period is as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Gross Normative Loan 1594.82 1836.69 Cumulative Repayments upto Previous Year 0.00 81.68 Net Loan-Opening 1594.82 1755.01 Addition due to Additional Capitalization 241.87 193.94 Repayment during the year 81.68 146.06 Net Loan-Closing 1755.01 1802.90 Average Loan 1674.91 1778.95 Weighted Average Rate of Interest on Loan (in %) 7.941 7.956 Interest on Loan 83.81 141.54
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Gross Normative Loan 2054.09 354.18 1295.05 176.69 181.61 Cumulative Repayments upto Previous Year 0.00 0.00 0.00 0.00 0.00 Net Loan-Opening 2054.09 354.18 1295.05 176.69 181.61 Addition due to Additional Capitalization 215.04 53.59 125.23 23.40 19.24 Repayment during the year 94.36 16.72 47.42 6.62 4.65 Net Loan-Closing 2174.78 391.05 1372.87 193.47 196.20 Average Loan 2114.44 372.62 1333.96 185.08 188.91 Weighted Average Rate of Interest on Loan (in %) 7.580 7.315 7.543 7.308 7.340 Interest on Loan 92.65 15.76 46.59 6.26 4.44
44. IoL in respect of the transmission assets as allowed vide orders dated 15.11.2018 and 21.1.2020 in Petition No. 37/TT/2018 and Petition No. 311/TT/2018 respectively, claimed by the Petitioner in the instant petition and trued-up in the instant order is as follows:
(Rs.in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Allowed vide order dated 15.11.2018 in Petition No. 37/TT/2018 85.17 150.06 Claimed by the Petitioner in the instant petition 83.78 141.31 Approved after true-up in this order 83.81 141.54
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Allowed vide order dated 21.1.2020 in Petition No. 311/TT/2018 91.61 15.73 45.99 6.15 4.43 Claimed by the Petitioner in the instant petition 92.77 15.75 45.89 6.27 4.47 Approved after true-up in this order 92.65 15.76 46.59 6.26 4.44
Return on Equity
45. The Petitioner has claimed RoE in respect of the transmission assets in terms of Regulations 24 and 25 of the 2014 Tariff Regulations. The Petitioner has submitted that it liable to pay income tax at Minimum Alternate Tax (MAT) rates and has claimed the effective tax rates for the 2014-2019 tariff period as follows:
Year Claimed effective tax (in %) Grossed-up RoE (in %) [(Base Rate)/1-t)] 2014-15 21.018 19.625 2015-16 21.382 19.716 2016-17 21.338 19.705 2017-18 21.337 19.704 2018-19 21.549 19.758
46. The Commission in order dated 27.4.2020 in Petition No. 274/TT/2019 had arrived at the effective tax rates based on the notified MAT rates for the Petitioner which are as follows:
Year Notified MAT rates (in %) (inclusive of surcharge & cess) Effective tax (in %) 2014-15 20.961 20.961 2015-16 21.342 21.342 2016-17 21.342 21.342 2017-18 21.342 21.342 2018-19 21.549 21.549
47. MAT rates considered in order dated 27.4.2020 for the purpose of grossing up of rate of RoE for truing up of the tariff of the 2014-2019 tariff period, in terms of the provisions of the 2014 Tariff Regulations, have been considered in the instant case which are as follows:
Year MAT Rate (in %) Grossed-up RoE (in %) [(Base Rate)/(1-t)] 2014-15 20.961 19.610 2015-16 21.342 19.705 2016-17 21.342 19.705 2017-18 21.342 19.705 2018-19 21.549 19.758
48. In view of the above, RoE is trued-up on the basis of the MAT rates applicable in the respective years and is allowed in respect of the transmission assets for the 2014-2019 tariff period as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Opening Equity 683.48 787.14 Addition due to Additional Capitalization 103.66 83.11 Closing Equity 787.14 870.25 Average Equity 735.31 828.70 Return on Equity (Base Rate) (in %) 15.500 15.500 Tax Rate applicable (in %) 21.342 21.549 Rate of Return on Equity (Pre-tax) 19.705 19.758 Return on Equity (Pre-tax) 91.30 163.73
(Rs.in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Opening Equity 880.32 151.78 555.02 75.72 77.83 Addition due to Additional Capitalization 92.16 22.97 53.67 10.03 8.25 Closing Equity 972.48 174.75 608.69 85.75 86.07 Average Equity 926.40 163.27 581.85 80.74 81.95 Return on Equity (Base Rate) (in %) 15.500 15.500 15.500 15.500 15.500 Tax Rate applicable (in %) 21.549 21.549 21.549 21.549 21.549 Rate of Return on Equity (Pre-tax) 19.758 19.758 19.758 19.758 19.758 Return on Equity (Pre-tax) 105.81 18.65 53.23 7.39 5.19
49. RoE in respect of the transmission assets as allowed vide orders dated 15.11.2018 and 21.1.2020 in Petition No. 37/TT/2018 and Petition No. 311/TT/2018 respectively, claimed by the Petitioner in the instant petition and trued-up in the instant order is as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Allowed vide order dated 15.11.2018 in Petition No. 37/TT/2018 93.53 174.48 Claimed by the Petitioner in the instant petition 91.31 163.73 Approved after true-up in this order 91.30 163.73
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Allowed vide order dated 21.1.2020 in Petition No. 311/TT/2018 104.90 18.50 52.42 7.19 5.12 Claimed by the Petitioner in the instant petition 106.00 18.68 53.39 7.41 5.22 Approved after true-up in this order 105.81 18.65 53.23 7.39 5.19
Operation & Maintenance Expenses (O&M Expenses)
50. O&M Expenses in respect of the various elements covered under the transmission assets as claimed by the Petitioner in this petition are within the norms specified in Regulation 29(4)(a) of the 2014 Tariff Regulations and the allowable O&M Expenses are as follows:
(Rs. in lakh)
Asset-I Particulars 2017-2018 (Pro-rata for 230 days) 2018-19 Sub-station Bays Itarsi : 400 kV ICT Bay at Itarsi 1 1 Itarsi : 220 kV ICT Bay at Itarsi 1 1 Itarsi : Itarsi MPPTCL Downstream Bay 1 1 Itarsi : Hoshangabad MPPTCL Downstream Bay 1 1 Norm (Rs. lakh/bay) 400 kV 66.51 68.71 220 kV 46.55 48.10 Total Sub-station O&M 129.91 213.01 Total O&M Expenses 129.91 213.01
(Rs. in lakh)
Asset-II Particulars 2018-2019 (Pro-rata for 211 days) Sub-station Bays Indore : 220 kV Line Bays at Indore 1 Indore : 400 kV Line Bays at Indore 1 Indore : 220 kV ICT-2 Bays at Indore 1 Norm (Rs. lakh/bay) 400 kV 68.71 220 kV 48.10 Total Sub-station O&M 123.14 Total O&M Expenses 123.14
(Rs. in lakh)
Asset-III Particulars 2018-2019 (Pro-rata for 211days) Sub-station Bays Indore : 220 kV Line Bays at Indore 2 Norm (Rs. lakh/bay) 220kV 48.10 Total Sub-station O&M 55.61 Total O&M Expenses 55.61
(Rs. in lakh)
Asset-IV Particulars 2018-2019 (Pro-rata for 169 days) Sub-station Bays Indore : 400 kV ICT-I Bay at Indore 1 Indore : 220 kV ICT-I Bay at Indore 1 Norm (Rs. lakh/bay) 400 kV 68.71 220 kV 48.10 Total Sub-station O&M 54.08 Total O&M Expenses 54.08
(Rs. in lakh)
Asset-V Particulars 2018-2019 (Pro-rata for 169 days) Sub-station Bays Indore : 220 kV Line Bay at Indore 1 Norm (Rs. lakh/bay) 220 kV 48.10 Total Sub-station O&M 22.27 Total O&M Expenses 22.27
(Rs. in lakh)
Asset-VI Particulars 2018-2019 (Pro-rata for 117 days) Sub-station Bays Indore : 220 kV Line Bay at Indore 1 Norm (Rs. lakh/bay) 220 kV 48.10 Total Sub-station O&M 15.42 Total O&M Expenses 15.42
51. O&M Expenses in respect of the transmission assets as allowed vide orders dated 15.11.2018 and 21.1.2020 in Petition No. 37/TT/2018 and Petition No. 311/TT/2018 respectively, claimed by the Petitioner in the instant petition and trued-up in the instant order are as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 169 days) 2018-19 Allowed vide order dated 15.11.2018 in Petition No. 37/TT/2018 129.91 213.01 Claimed by the Petitioner in the instant petition 129.90 213.01 Approved after true-up in this order 129.91 213.01
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117days) Allowed vide order dated 21.1.2020 in Petition No. 311/TT/2018 123.13 55.61 54.08 22.27 15.41 Claimed by the Petitioner in the instant petition 123.14 55.61 54.08 22.27 15.42 Approved after true-up in this order 123.14 55.61 54.08 22.27 15.42
Interest on Working Capital
52. IWC has been worked out as per the methodology provided in Regulation 28 of the 2014 Tariff Regulations. The details of the trued-up IWC approved in respect of the transmission assets for the 2014-2019 tariff period are as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Working Capital for O&M Expenses (1 month of O&M expenses) 17.18 17.75 Working Capital for Maintenance Spares (15% of O&M expenses) 30.92 31.95 Working Capital for Receivables (Equivalent to 2 months of annual fixed cost/annual transmission charges) 105.51 114.16 Total Working Capital 153.61 163.87 Rate of Interest (in %) 12.60 12.60 Interest of Working Capital 12.20 20.65
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Working Capital for O&M Expenses (1 month of O&M expenses) 17.75 8.02 9.73 4.01 4.01 Working Capital for Maintenance Spares (15% of O&M expenses) 31.95 14.43 17.52 7.22 7.22 Working Capital for Receivables (Equivalent to 2 months of annual fixed cost/annual transmission charges) 123.45 31.88 74.54 15.86 16.00 Total Working Capital 173.15 54.32 101.79 27.09 27.22 Rate of Interest (in %) 12.20 12.20 12.20 12.20 12.20 Interest of Working Capital 12.21 3.83 5.75 1.53 1.06
53. IWC in respect of the transmission assets as allowed vide orders dated 15.11.2018 and 21.1.2020 in Petition No. 37/TT/2018 and Petition No. 311/TT/2018 respectively, claimed by the Petitioner in the instant petition and trued-up in the instant order is as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Allowed vide order dated 15.11.2018 in Petition No. 37/TT/2018 12.32 21.28 Claimed by the Petitioner in the instant petition 12.22 20.70 Approved after true-up in this order 12.20 20.65
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Allowed vide order dated 21.1.2020 in Petition No. 311/TT/2018 12.17 3.83 5.71 1.52 1.06 Claimed by the Petitioner in the instant petition 12.27 3.86 5.76 1.54 1.07 Approved after true-up in this order 12.21 3.83 5.75 1.53 1.06
Approved Annual Fixed Charges for the 2014-2019 Tariff Period
54. The trued-up Annual Fixed Charges (AFC) in respect of the transmission assets for the 2014-2019 tariff period are as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Depreciation 81.68 146.06 Interest on Loan 83.81 141.54 Return on Equity 91.30 163.73 Interest on Working Capital 12.20 20.65 O&M Expenses 129.91 213.01 Total 398.90 684.99
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Depreciation 94.36 16.72 47.42 6.62 4.65 Interest on Loan 92.65 15.76 46.59 6.26 4.44 Return on Equity 105.81 18.65 53.23 7.39 5.19 Interest on Working Capital 12.21 3.83 5.75 1.53 1.06 O&M Expenses 123.14 55.61 54.08 22.27 15.42 Total 428.17 110.56 207.07 44.07 30.77
55. Accordingly, the Annual Transmission Charges as allowed vide orders dated 15.11.2018 and 21.1.2020 in Petition No. 37/TT/2018 and Petition No. 311/TT/2018, claimed by the Petitioner in the instant petition and trued-up in the instant order are as follows:
(Rs. in lakh)
Particulars Asset-I 2017-2018 (Pro-rata for 230 days) 2018-19 Allowed vide order dated 15.11.2018 in Petition No. 37/TT/2018 404.92 715.02 Claimed by the Petitioner in the instant petition 400.36 687.56 Approved after true-up in this order 398.90 684.99
(Rs. in lakh)
Particulars Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) Allowed vide order dated 21.1.2020 in Petition No. 311/TT/2018 426.06 110.38 205.26 43.63 30.66 Claimed by the Petitioner in the instant petition 430.96 112.00 207.40 44.49 31.11 Approved after true-up in this order 428.17 110.56 207.07 44.07 30.68
DETERMINATION OF ANNUAL FIXED CHARGES FOR THE 2019-2024 TARIFF PERIOD
56. The Petitioner has combined the transmission assets into one single asset and has claimed combined tariff and has submitted the tariff forms. During the course of hearing held on 9.7.2021, the Petitioner submitted that the downstream systems of MPPTCL with respect to Asset-V and Asset-VI are yet to be commissioned. Accordingly, as per proviso (i) of Regulation 8(1) of the 2019 Tariff Regulations, tariff for Combined Asset (consisting of Asset-I, Asset-II, Asset-III and Asset-IV) and Asset-V, Asset-VI has been worked out separately for the 2019-2024 tariff period in this order.
57. The details of the transmission charges for Combined Asset, Asset-V and Asset-VI for the 2019-2024 tariff period as claimed by the Petitioner vide affidavit dated 28.7.2021 are as follows:
(Rs. in lakh)
Combined Asset Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Depreciation 480.36 487.74 490.38 490.38 490.38 Interest on Loan 432.00 401.32 368.40 332.67 293.24 Return on Equity 499.20 507.30 510.38 510.38 510.38 Interest on Working Capital 57.66 58.84 59.75 60.62 61.29 O&M Expenses 836.04 866.04 896.43 928.62 959.79 Total 2305.26 2321.24 2325.34 2322.67 2315.08
(Rs.in lakh)
Asset-V Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Depreciation 16.34 16.98 17.44 17.44 17.44 Interest on Loan 13.87 13.26 12.48 11.24 9.94 Return on Equity 16.36 17.04 17.53 17.53 17.53 Interest on Working Capital 1.68 1.73 1.77 1.78 1.80 O&M Expenses 22.51 23.30 24.12 24.96 25.84 Total 70.76 72.31 73.34 72.95 72.55
(Rs. in lakh)
Asset-VI Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Depreciation 16.46 17.10 17.57 17.57 17.57 Interest on Loan 14.17 13.55 12.79 11.59 10.26 Return on Equity 16.49 17.16 17.64 17.64 17.64 Interest on Working Capital 1.69 1.74 1.78 1.79 1.81 O&M Expenses 22.51 23.30 24.12 24.96 25.84 Total 71.32 72.85 73.90 73.55 73.12
58. The details of IWC for Combined Asset, Asset-V and Asset-VI for the 2019-2024 tariff period as claimed by the Petitioner vide affidavit dated 28.7.2021 are as follows for the 2019-2024 tariff period:
(Rs. in lakh)
Combined Asset Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 O&M expenses 69.67 72.17 74.70 77.39 79.98 Maintenance Spares 125.41 129.91 134.46 139.29 143.97 Receivables 283.43 286.18 286.69 286.36 284.64 Total Working Capital 478.51 488.26 495.85 503.04 508.59 Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05 Interest on Working Capital 57.66 58.84 59.75 60.62 61.29
(Rs. in lakh)
Asset-V Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 O&M expenses 1.88 1.94 2.01 2.08 2.15 Maintenance Spares 3.38 3.50 3.62 3.74 3.88 Receivables 8.70 8.91 9.04 8.99 8.92 Total Working Capital 13.96 14.35 14.67 14.81 14.95 Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05 Interest on Working Capital 1.68 1.73 1.77 1.78 1.80
(Rs. in lakh)
Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 O&M expenses 1.88 1.94 2.01 2.08 2.15 Maintenance Spares 3.38 3.50 3.62 3.74 3.88 Receivables 8.77 8.98 9.11 9.07 8.99 Total Working Capital 14.03 14.42 14.74 14.89 15.02 Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05 Interest on Working Capital 1.69 1.74 1.78 1.79 1.81
Effective Date of Commercial Operation (E-COD)
59. The Petitioner has claimed E-COD of Combined Asset as 8.5.2018. However, based on the trued-up capital cost and COD of Asset-I, Asset-II, Asset-III and Asset-IV, E-COD of Combined Asset has been worked out as follows:
Asset COD Admitted Capital Cost (as on 31.3.2019) (Rs. in lakh) Weightage of cost (in %) Number of days from last COD Weighted Days Asset-I 14.8.2017 2900.88 33.14 426.00 141.17 Asset-II 2.9.2018 3241.62 37.03 42.00 15.55 Asset-III 2.9.2018 582.52 6.65 42.00 2.79 Asset-IV 14.10.2018 2028.97 23.18 0.00 0.00 Total 8753.99 100.00 159.51 E-COD (Latest COD - Total Weighted Days) 7.5.2018
60. E-COD is used to determine the lapsed life of the project as a whole, which works out as zero (0) year as on 1.4.2019 (i.e. the number of completed years as on 1.4.2019 from E-COD). Further, as tariff for the 2019-2024 period in respect of Asset-V and Asset-VI has been worked out separately, E-COD for the transmission project as a whole will be worked out and considered in the next tariff period while determining tariff for combined assets for the transmission project.
Weighted Average Life (WAL)
61. The life as defined in Regulation 33 of the 2019 Tariff Regulations has been considered for determination of WAL.
62. The Combined Asset may have multiple elements such as land, building, transmission line, sub-station and PLCC and each element may have different span of life. Therefore, the concept of WAL has been used as the useful life of the transmission project as a whole.
63. WAL has been determined based on the admitted capital cost of individual elements as on 31.3.2019 and their respective life as stipulated in the 2019 Tariff Regulations. Accordingly, WAL of Combined Asset has been worked out as 25 years as follows:
Particulars Combined Asset Cost (Rs. in lakh) (1) Life (in Years) (2) Weighted Cost (Rs. in lakh) (3)=(1) x(2) Building 0.00 25 0.00 Transmission Line 0.00 35 0.00 Sub-Station Equipment 8577.00 25 214425.00 PLCC 53.86 15 807.91 IT Equipment and Software 123.13 6.66 820.86 Total 8753.99 216053.77 WAL (in years) (4)=(3)/(1) 25.00 Years
64. WAL as on 1.4.2019 as determined above is applicable prospectively (i.e. for the 2019-2024 tariff period onwards) and no retrospective adjustment of depreciation in previous tariff period is required to be done. As discussed, E-COD of Combined Asset is 7.5.2018 and the lapsed life of the transmission project as a whole works out as zero (0) year as on 1.4.2019 (i.e. the number of completed years as on 1.4.2019 from E-COD). Accordingly, WAL has been used to determine the remaining useful life as on 31.3.2019 to be 25 years.
65. Further, as tariff for the 2019-2024 period in respect of Asset-V and Asset-VI has been worked out separately, WAL for the transmission project as a whole will be worked out and considered in the next tariff period while determining tariff for the combined assets for the whole transmission project.
Capital Cost
66. Regulation 19 of the 2019 Tariff Regulations provides as follows:
“19. Capital Cost: (1) The Capital cost of the generating station or the transmission system, as the case may be, as determined by the Commission after prudence check in accordance with these regulations shall form the basis for determination of tariff for existing and new projects.
(2) The Capital Cost of a new project shall include the following:
(a) The expenditure incurred or projected to be incurred up to the date of commercial operation of the project;
(b) Interest during construction and financing charges, on the loans (i) being equal to 70% of the funds deployed, in the event of the actual equity in excess of 30% of the funds deployed, by treating the excess equity as normative loan, or (ii) being equal to the actual amount of loan in the event of the actual equity less than 30% of the funds deployed;
(c) Any gain or loss on account of foreign exchange risk variation pertaining to the loan amount availed during the construction period;
(d) Interest during construction and incidental expenditure during construction as computed in accordance with these regulations;
(e) Capitalised initial spares subject to the ceiling rates in accordance with these regulations;
(f) Expenditure on account of additional capitalization and de-capitalisation determined in accordance with these regulations;
(g) Adjustment of revenue due to sale of infirm power in excess of fuel cost prior to the date of commercial operation as specified under Regulation 7 of these regulations;
(h) Adjustment of revenue earned by the transmission licensee by using the assets before the date of commercial operation;
(i) Capital expenditure on account of ash disposal and utilization including handling and transportation facility;
(j) Capital expenditure incurred towards railway infrastructure and its augmentation for transportation of coal upto the receiving end of the generating station but does not include the transportation cost and any other appurtenant cost paid to the railway;
(k) Capital expenditure on account of biomass handling equipment and facilities, for co-firing;
(l) Capital expenditure on account of emission control system necessary to meet the revised emission standards and sewage treatment plant;
(m) Expenditure on account of fulfilment of any conditions for obtaining environment clearance for the project;
(n) Expenditure on account of change in law and force majeure events; and
(o) Capital cost incurred or projected to be incurred by a thermal generating station, on account of implementation of the norms under Perform, Achieve and Trade (PAT) scheme of Government of India shall be considered by the Commission subject to sharing of benefits accrued under the PAT scheme with the beneficiaries.
(3) The Capital cost of an existing project shall include the following:
(a) Capital cost admitted by the Commission prior to 1.4.2019 duly trued up by excluding liability, if any, as on 1.4.2019;
(b) Additional capitalization and de-capitalization for the respective year of tariff as determined in accordance with these regulations;
(c) Capital expenditure on account of renovation and modernisation as admitted by this Commission in accordance with these regulations;
(d) Capital expenditure on account of ash disposal and utilization including handling and transportation facility;
(e) Capital expenditure incurred towards railway infrastructure and its augmentation for transportation of coal upto the receiving end of generating station but does not include the transportation cost and any other appurtenant cost paid to the railway; and
(f) Capital cost incurred or projected to be incurred by a thermal generating station, on account of implementation of the norms under Perform, Achieve and Trade (PAT) scheme of Government of India shall be considered by the Commission subject to sharing of benefits accrued under the PAT scheme with the beneficiaries.
(4) The capital cost in case of existing or new hydro generating station shall also include:
(a) cost of approved rehabilitation and resettlement (R&R) plan of the project in conformity with National R&R Policy and R&R package as approved; and
(b) cost of the developer's 10% contribution towards Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) and Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY) project in the affected area.
(5) The following shall be excluded from the capital cost of the existing and new projects:
(a) The assets forming part of the project, but not in use, as declared in the tariff petition;
(b) De-capitalised Assets after the date of commercial operation on account of replacement or removal on account of obsolescence or shifting from one project to another project:
Provided that in case replacement of transmission asset is recommended by Regional Power Committee, such asset shall be de-capitalised only after its redeployment;
Provided further that unless shifting of an asset from one project to another is of permanent nature, there shall be no de-capitalization of the concerned assets.
(c) In case of hydro generating stations, any expenditure incurred or committed to be incurred by a project developer for getting the project site allotted by the State Government by following a transparent process;
(d) Proportionate cost of land of the existing project which is being used for generating power from generating station based on renewable energy; and
(e) Any grant received from the Central or State Government or any statutory body or authority for the execution of the project which does not carry any liability of repayment.”
67. The capital cost has been dealt in line with Regulation 19(3) of the 2019 Tariff Regulations. The element-wise capital cost (i.e. land, building, transmission line, sub-station and PLCC) as admitted by the Commission as on 31.3.2019 in this order for Asset-I, Asset-II, Asset-III and Asset-IV are clubbed together as follows:
(Rs. in lakh)
Element Asset-I Asset-II Asset-III Asset-IV Capital Cost for Combined Asset (as on 31.3.2019) Sub-station 2851.75 3177.80 537.08 2010.37 8577.00 PLCC 19.33 17.27 17.26 0.00 53.86 IT Equipment and Software 29.79 46.55 28.18 18.60 123.13 Total 2900.88 3241.62 582.52 2028.97 8753.99
68. Similarly, capital cost as on 31.3.2019 for Asset-V and Asset-VI as admitted in this order is as follows:
(Rs. in lakh)
Element Asset-V Asset-VI Sub-station 267.92 269.09 PLCC 8.56 8.47 IT Equipment and Software 9.36 9.36 Total 285.85 286.92
69. The trued-up capital cost of Rs. 8753.99 lakh, Rs. 285.85 lakh and Rs. 286.92 lakh for Combined Asset, Asset-V and Asset-VI respectively has been considered as admitted capital cost as on 1.4.2019 for working out tariff for the 2019-2024 tariff period.
Additional Capital Expenditure
70. Regulation 24 of the 2019 Tariff Regulations provides as follows:
“24. Additional Capitalisation within the original scope and upto the cut-off date
(1) The additional capital expenditure in respect of a new project or an existing project incurred or projected to be incurred, on the following counts within the original scope of work, after the date of commercial operation and up to the cut-off date may be admitted by the Commission, subject to prudence check:
(a) Undischarged liabilities recognized to be payable at a future date;
(b) Works deferred for execution;
(c) Procurement of initial capital spares within the original scope of work, in accordance with the provisions of Regulation 23 of these regulations;
(d) Liabilities to meet award of arbitration or for compliance of the directions or order of any statutory authority or order or decree of any court of law;
(e) Change in law or compliance of any existing law; and
(f) Force Majeure events:
Provided that in case of any replacement of the assets, the additional capitalization shall be worked out after adjusting the gross fixed assets and cumulative depreciation of the assets replaced on account of de-capitalization.
(2) The generating company or the transmission licensee, as the case may be shall submit the details of works asset wise/work wise included in the original scope of work along with estimates of expenditure, liabilities recognized to be payable at a future date and the works deferred for execution.”
71. Based on the Auditor's Certificates dated 13.4.2020, ACE claimed by the Petitioner in respect of the transmission assets in 2019-2020 and 2020-2021 is as follows:
(Rs. in lakh)
Asset ACE (as per Auditor's Certificates) 2019-20 2020-2021 Asset-I 178.47 109.17 Asset-II Asset-III Asset-IV Asset-V 6.12 17.19 Asset-VI 6.12 17.19
72. The Petitioner has submitted that ACE incurred in 2019-2020 and 2020-2021 is within cut-off date and is accordingly claimed as per Regulation 24(1)(a) of the 2019 Tariff Regulations. Further, ACE incurred is on account of any un-discharged liability towards final payment/withheld payment due to contractual exigencies for works executed within the cut-off date.
73. The Petitioner vide affidavit dated 11.2.2021 has submitted that ACE claimed is mainly on account of un-discharged liability for the works executed prior to cut-off date and is claimed as per Regulation 24(1)(a) of the 2019 Tariff Regulations. Also, the justification for ACE claimed during the 2019-2024 period on account of balance and retention payment and works deferred for execution (party-wise) has been submitted by the Petitioner. Further, ACE during the 2019-2024 period is also on account of unexecuted works that are considered as addition in gross block which is on account of the works executed after COD and the same is claimed under Regulation 24(1)(b) of the 2019 Tariff Regulations.
74. We have considered the submissions and claim of the Petitioner. ACE claimed is towards balance and retention payments and un-executed works and the same is allowed under Regulations 24(1)(a) and 24(1)(b) of the 2019 Tariff Regulations, subject to true-up. Therefore, ACE with respect to Combined Asset, Asset-V and Asset-VI is allowed as follows:
(Rs. in lakh)
Asset ACE 2019-20 2020-2021 Combined Asset 178.47 109.17 Asset-V 6.50* 17.19 Asset-VI 6.69* 17.19
* includes discharged liabilities
Capital Cost considered for the 2019-2024 tariff period
75. In view of the above, the capital cost of Combined Asset, Asset-V and Asset-VI considered for the 2019-2024 tariff period, subject to truing-up, is as follows:
(Rs. in lakh)
Asset Capital Cost allowed (as on 1.4.2019) ACE allowed during Capital Cost (as on 31.3.2024) 2019-20 2020-2021 Combined Asset 8753.99 178.47 109.17 9041.63 Asset-V 285.85 6.50 17.19 309.54 Asset-VI 286.92 6.69 17.19 310.80
Debt-Equity Ratio
76. Regulation 18 of the 2019 Tariff Regulations provides as follows:
“18. Debt-Equity Ratio : (1) For new projects, the debt-equity ratio of 70 : 30 as on date of commercial operation shall be considered. If the equity actually deployed is more than 30% of the capital cost, equity in excess of 30% shall be treated as normative loan:
Provided that:
i. where equity actually deployed is less than 30% of the capital cost, actual equity shall be considered for determination of tariff:
ii. the equity invested in foreign currency shall be designated in Indian rupees on the date of each investment:
iii. any grant obtained for the execution of the project shall not be considered as a part of capital structure for the purpose of debt : equity ratio.
Explanation- The premium, if any, raised by the generating company or the transmission licensee, as the case may be, while issuing share capital and investment of internal resources created out of its free reserve, for the funding of the project, shall be reckoned as paid up capital for the purpose of computing return on equity, only if such premium amount and internal resources are actually utilised for meeting the capital expenditure of the generating station or the transmission system.
(2) The generating company or the transmission licensee, as the case may be, shall submit the resolution of the Board of the company or approval of the competent authority in other cases regarding infusion of funds from internal resources in support of the utilization made or proposed to be made to meet the capital expenditure of the generating station or the transmission system including communication system, as the case may be.
(3) In case of the generating station and the transmission system including communication system declared under commercial operation prior to 1.4.2019, debt : equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2019 shall be considered:
Provided that in case of a generating station or a transmission system including communication system which has completed its useful life as on or after 1.4.2019, if the equity actually deployed as on 1.4.2019 is more than 30% of the capital cost, equity in excess of 30% shall not be taken into account for tariff computation;
Provided further that in case of projects owned by Damodar Valley Corporation, the debt : equity ratio shall be governed as per sub-clause (ii) of clause (2) of Regulation 72 of these regulations.
(4) In case of the generating station and the transmission system including communication system declared under commercial operation prior to 1.4.2019, but where debt : equity ratio has not been determined by the Commission for determination of tariff for the period ending 31.3.2019, the Commission shall approve the debt : equity ratio in accordance with clause (1) of this Regulation.
(5) Any expenditure incurred or projected to be incurred on or after 1.4.2019 as may be admitted by the Commission as additional capital expenditure for determination of tariff, and renovation and modernisation expenditure for life extension shall be serviced in the manner specified in clause (1) of this Regulation.
(6) Any expenditure incurred for the emission control system during the tariff period as may be admitted by the Commission as additional capital expenditure for determination of supplementary tariff, shall be serviced in the manner specified in clause (1) of this Regulation.”
77. The debt-equity considered for the purpose of computation of tariff for Combined Asset, Asset-V and Asset-VI for the 2019-2024 tariff period is as follows:
Funding Capital Cost (as on 1.4.2019) (Rs. in lakh) (in %) Capital Cost (as on 31.3.2024) (Rs. in lakh) (in %) Debt 6127.82 70.00 6329.17 70.00 Equity 2626.17 30.00 2712.46 30.00 Asset-V Total 8753.99 100.00 9041.63 100.00 Debt 200.09 70.00 216.68 70.00 Equity 85.75 30.00 92.86 30.00 Total 285.85 100.00 309.54 100.00 Asset-VI Debt 200.85 70.00 217.57 70.00 Equity 86.07 30.00 93.23 30.00 Total 286.92 100.00 310.80 100.00
Depreciation
78. Regulation 33 of the 2019 Tariff Regulations provides as follows:
“33. Depreciation: (1) Depreciation shall be computed from the date of commercial operation of a generating station or unit thereof or a transmission system or element thereof including communication system. In case of the tariff of all the units of a generating station or all elements of a transmission system including communication system for which a single tariff needs to be determined, the depreciation shall be computed from the effective date of commercial operation of the generating station or the transmission system taking into consideration the depreciation of individual units:
Provided that effective date of commercial operation shall be worked out by considering the actual date of commercial operation and installed capacity of all the units of the generating station or capital cost of all elements of the transmission system, for which single tariff needs to be determined.
(2) The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the Commission. In case of multiple units of a generating station or multiple elements of a transmission system, weighted average life for the generating station of the transmission system shall be applied. Depreciation shall be chargeable from the first year of commercial operation. In case of commercial operation of the asset for part of the year, depreciation shall be charged on pro rata basis.
(3) The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up to maximum of 90% of the capital cost of the asset:
Provided that the salvage value for IT equipment and software shall be considered as NIL and 100% value of the assets shall be considered depreciable;
Provided further that in case of hydro generating stations, the salvage value shall be as provided in the agreement, if any, signed by the developers with the State Government for development of the generating station:
Provided also that the capital cost of the assets of the hydro generating station for the purpose of computation of depreciated value shall correspond to the percentage of sale of electricity under long-term power purchase agreement at regulated tariff:
Provided also that any depreciation disallowed on account of lower availability of the generating station or unit or transmission system as the case may be, shall not be allowed to be recovered at a later stage during the useful life or the extended life.
(4) Land other than the land held under lease and the land for reservoir in case of hydro generating station shall not be a depreciable asset and its cost shall be excluded from the capital cost while computing depreciable value of the asset.
(5) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-I to these regulations for the assets of the generating station and transmission system:
Provided that the remaining depreciable value as on 31st March of the year closing after a period of 12 years from the effective date of commercial operation of the station shall be spread over the balance useful life of the assets.
(6) In case of the existing projects, the balance depreciable value as on 1.4.2019 shall be worked out by deducting the cumulative depreciation as admitted by the Commission upto 31.3.2019 from the gross depreciable value of the assets.
(7) The generating company or the transmission licensee, as the case may be, shall submit the details of proposed capital expenditure five years before the completion of useful life of the project along with justification and proposed life extension. The Commission based on prudence check of such submissions shall approve the depreciation on capital expenditure.
(8) In case of de-capitalization of assets in respect of generating station or unit thereof or transmission system or element thereof, the cumulative depreciation shall be adjusted by taking into account the depreciation recovered in tariff by the de-capitalized asset during its useful services.
(9) Where the emission control system is implemented within the original scope of the generating station and the date of commercial operation of the generating station or unit thereof and the date of operation of the emission control system are the same, depreciation of the generating station or unit thereof including the emission control system shall be computed in accordance with Clauses (1) to (8) of this Regulation.
(10) Depreciation of the emission control system of an existing or a new generating station or unit thereof where the date of operation of the emission control system is subsequent to the date of commercial operation of the generating station or unit thereof, shall be computed annually from the date of operation of such emission control system based on straight line method, with salvage value of 10%, over a period of—
a) twenty five years, in case the generating station or unit thereof is in operation for fifteen years or less as on the date of operation of the emission control system; or
b) balance useful life of the generating station or unit thereof plus fifteen years, in case the generating station or unit thereof is in operation for more than fifteen years as on the date of operation of the emission control system; or
c) ten years or a period mutually agreed by the generating company and the beneficiaries, whichever is higher, in case the generating station or unit thereof has completed its useful life.”
79. Depreciation has been worked out considering the admitted capital expenditure as on 31.3.2019 and accumulated depreciation up to 31.3.2019. The IT equipment has been considered as a part of the Gross Block and depreciated using WAROD. WAROD at Annexure-II (Colly.) has been worked out after considering the depreciation rates of IT and non-IT assets as specified in the 2019 Tariff Regulations. The salvage value of IT equipment has been considered nil, i.e. IT asset has been considered as 100% depreciable. The depreciation allowed for Combined Asset, Asset-V and Asset-VI for the 2019-2024 tariff period is as follows:
(Rs. in lakh)
Combined Asset Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Opening Gross Block 8753.99 8932.46 9041.63 9041.63 9041.63 Addition during the year 2019-2024 due to projected Additional Capitalisation 178.47 109.17 0.00 0.00 0.00 Closing Gross Block 8932.46 9041.63 9041.63 9041.63 9041.63 Average Gross Block 8843.22 8987.04 9041.63 9041.63 9041.63 Weighted average rate of Depreciation (WAROD) (in %) 5.42 5.42 5.41 5.41 5.41 Elapsed useful life at the beginning of the year (Year) 0 1 2 3 4 Balance useful life at the beginning of the year (Year) 25 24 23 22 21 Aggregated Depreciable Value 7971.22 8100.66 8149.79 8149.79 8149.79 Combined Depreciation during the year 479.48 486.86 489.51 489.51 489.51 Aggregate Cumulative Depreciation at the end of the year 865.70 1352.57 1842.07 2331.58 2821.09 Remaining Aggregate Depreciable Value at the end of the year 7105.52 6748.10 6307.72 5818.21 5328.70
(Rs. in lakh)
Asset-V Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Opening Gross Block 285.85 292.35 309.54 309.54 309.54 Addition during the year 2019-2024 due to projected Additional Capitalisation 6.50 17.19 0.00 0.00 0.00 Closing Gross Block 292.35 309.54 309.54 309.54 309.54 Average Gross Block 289.10 300.94 309.54 309.54 309.54 Weighted average rate of Depreciation (WAROD) (in %) 5.63 5.62 5.61 5.61 5.61 Elapsed useful life at the beginning of the year (Year) 0 1 2 3 4 Balance useful life at the beginning of the year (Year) 24 23 22 21 20 Aggregated Depreciable Value 261.12 271.78 279.52 279.52 279.52 Combined Depreciation during the year 16.26 16.90 17.36 17.36 17.36 Aggregate Cumulative Depreciation at the end of the year 22.89 39.79 57.15 74.51 91.87
(Rs. in lakh)
Asset-VI Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Opening Gross Block 286.92 293.61 310.80 310.80 310.80 Addition during the year 2019-2024 due to projected Additional Capitalisation 6.69 17.19 0.00 0.00 0.00 Closing Gross Block 293.61 310.80 310.80 310.80 310.80 Average Gross Block 290.27 302.21 310.80 310.80 310.80 Weighted average rate of Depreciation (WAROD) (in %) 5.62 5.61 5.61 5.61 5.61 Elapsed useful life at the beginning of the year (Year) 0 1 2 3 4 Balance useful life at the beginning of the year (Year) 24 23 22 21 20 Aggregated Depreciable Value 262.18 272.92 280.66 280.66 280.66 Combined Depreciation during the year 16.33 16.97 17.43 17.43 17.43 Aggregate Cumulative Depreciation at the end of the year 20.98 37.94 55.37 72.80 90.23 Remaining Aggregate Depreciable Value at the end of the year 241.20 234.98 225.29 207.86 190.43
Interest on Loan
80. Regulation 32 of the 2019 Tariff Regulations provides as follows:
“32. Interest on loan capital: (1) The loans arrived at in the manner indicated in Regulation 18 of these regulations shall be considered as gross normative loan for calculation of interest on loan.
(2) The normative loan outstanding as on 1.4.2019 shall be worked out by deducting the cumulative repayment as admitted by the Commission up to 31.3.2019 from the gross normative loan.
(3) The repayment for each of the year of the tariff period 2019-2024 shall be deemed to be equal to the depreciation allowed for the corresponding year/period. In case of de-capitalization of assets, the repayment shall be adjusted by taking into account cumulative repayment on a pro rata basis and the adjustment should not exceed cumulative depreciation recovered upto the date of de-capitalisation of such asset.
(4) Notwithstanding any moratorium period availed by the generating company or the transmission licensee, as the case may be, the repayment of loan shall be considered from the first year of commercial operation of the project and shall be equal to the depreciation allowed for the year or part of the year.
(5) The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual loan portfolio after providing appropriate accounting adjustment for interest capitalized:
Provided that if there is no actual loan for a particular year but normative loan is still outstanding, the last available weighted average rate of interest shall be considered;
Provided further that if the generating station or the transmission system, as the case may be, does not have actual loan, then the weighted average rate of interest of the generating company or the transmission licensee as a whole shall be considered.
(5a) The rate of interest on loan for installation of emission control system shall be the weighted average rate of interest of actual loan portfolio of the emission control system or in the absence of actual loan portfolio, the weighted average rate of interest of the generating company as a whole shall be considered.
(6) The interest on loan shall be calculated on the normative average loan of the year by applying the weighted average rate of interest.
(7) The changes to the terms and conditions of the loans shall be reflected from the date of such re-financing.”
81. WAROI on loan has been considered on the basis of the rate prevailing as on 1.4.2019. The Petitioner has prayed that the change in interest rate due to floating rate of interest applicable, if any, during the 2019-2024 tariff period will be adjusted. Accordingly, the floating rate of interest, if any, shall be considered at the time of true up. Therefore, IoL has been allowed in accordance with Regulation 32 of the 2019 Tariff Regulations. IoL allowed for Combined Asset, Asset-V and Asset-VI for the 2019-2024 tariff period is as follows:
(Rs. in lakh)
Combined Asset Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Gross Normative Loan 6127.82 6252.75 6329.17 6329.17 6329.17 Cumulative Repayments upto Previous Year 386.22 865.70 1352.57 1842.07 2331.58 Net Loan-Opening 5741.60 5387.04 4976.60 4487.09 3997.59 Addition due to Additional Capitalization 124.93 76.42 0.00 0.00 0.00 Repayment during the year 479.48 486.86 489.51 489.51 489.51 Net Loan-Closing 5387.04 4976.60 4487.09 3997.59 3508.08 Average Loan 5564.32 5181.82 4731.85 4242.34 3752.83 Weighted Average Rate of Interest on Loan (in %) 7.761 7.743 7.785 7.843 7.817 Interest on Loan 431.84 401.23 368.38 332.71 293.35
(Rs. in lakh)
Asset-V Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Gross Normative Loan 200.09 204.65 216.68 216.68 216.68 Cumulative Repayments upto Previous Year 6.62 22.89 39.79 57.15 74.51 Net Loan-Opening 193.47 181.76 176.89 159.53 142.17 Addition due to Additional Capitalization 4.55 12.03 0.00 0.00 0.00 Repayment during the year 16.26 16.90 17.36 17.36 17.36 Net Loan-Closing 181.76 176.89 159.53 142.17 124.81 Average Loan 187.62 179.33 168.21 150.85 133.49 Weighted Average Rate of Interest on Loan (in %) 7.374 7.374 7.399 7.432 7.429 Interest on Loan 13.84 13.22 12.45 11.21 9.92
(Rs. in lakh)
Asset-VI Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Gross Normative Loan 200.85 205.54 217.57 217.57 217.57 Cumulative Repayments upto Previous Year 4.65 20.98 37.94 55.37 72.80 Net Loan-Opening 196.20 184.56 179.63 162.20 144.77 Addition due to Additional Capitalization 4.69 12.03 0.00 0.00 0.00 Repayment during the year 16.33 16.97 17.43 17.43 17.43 Net Loan-Closing 184.56 179.63 162.20 144.77 127.34 Average Loan 190.38 182.09 170.91 153.48 136.06 Weighted Average Rate of Interest on Loan (in %) 7.392 7.392 7.436 7.505 7.502 Interest on Loan 14.07 13.46 12.71 11.52 10.21
Return on Equity
82. Regulations 30 and 31 of the 2019 Tariff Regulations provide as follows:
“30. Return on Equity : (1) Return on equity shall be computed in rupee terms, on the equity base determined in accordance with Regulation 18 of these regulations.
(2) Return on equity shall be computed at the base rate of 15.50% for thermal generating station, transmission system including communication system and run-of-river hydro generating station, and at the base rate of 16.50% for the storage type hydro generating stations including pumped storage hydro generating stations and run-of-river generating station with pondage:
Provided that return on equity in respect of additional capitalization after cutoff date beyond the original scope, excluding additional capitalization on 7 account of emission control system, shall be computed at the weighted average rate of interest on actual loan portfolio of the generating station or the transmission system or in the absence of actual loan portfolio of the generating station or the transmission system, the weighted average rate of interest of the generating company or the transmission licensee, as the case may be, as a whole shall be considered, subject to ceiling of 14%.
Provided further that:
i. In case of a new project, the rate of return on equity shall be reduced by 1.00% for such period as may be decided by the Commission, if the generating station or transmission system is found to be declared under commercial operation without commissioning of any of the Restricted Governor Mode Operation (RGMO) or Free Governor Mode Operation (FGMO), data telemetry, communication system up to load dispatch centre or protection system based on the report submitted by the respective RLDC;
ii. in case of existing generating station, as and when any of the requirements under (i) above of this Regulation are found lacking based on the report submitted by the concerned RLDC, rate of return on equity shall be reduced by 1.00% for the period for which the deficiency continues;
iii. in case of a thermal generating station, with effect from 1.4.2020:
a) rate of return on equity shall be reduced by 0.25% in case of failure to achieve the ramp rate of 1% per minute;
b) an additional rate of return on equity of 0.25% shall be allowed for every incremental ramp rate of 1% per minute achieved over and above the ramp rate of 1% per minute, subject to ceiling of additional rate of return on equity of 1.00%:
Provided that the detailed guidelines in this regard shall be issued by National Load Dispatch Centre by 30.6.2019.
(3) The return on equity in respect of additional capitalization on account of emission control system shall be computed at the base rate of one year marginal cost of lending rate (MCLR) of the State Bank of India as on 1st April of the year in which the date of operation (ODe) occurs plus 350 basis point, subject to ceiling of 14%;”
“31. Tax on Return on Equity. (1) The base rate of return on equity as allowed by the Commission under Regulation 30 of these regulations shall be grossed up with the effective tax rate of the respective financial year. For this purpose, the effective tax rate shall be considered on the basis of actual tax paid in respect of the financial year in line with the provisions of the relevant Finance Acts by the concerned generating company or the transmission licensee, as the case may be. The actual tax paid on income from other businesses including deferred tax liability (i.e. income from business other than business of generation or transmission, as the case may be) shall be excluded for the calculation of effective tax rate.
(2) Rate of return on equity shall be rounded off to three decimal places and shall be computed as per the formula given below:
Rate of pre-tax return on equity = Base rate/(1-t)
Where “t” is the effective tax rate in accordance with clause (1) of this Regulation and shall be calculated at the beginning of every financial year based on the estimated profit and tax to be paid estimated in line with the provisions of the relevant Finance Act applicable for that financial year to the company on pro-rata basis by excluding the income of non-generation or non-transmission business, as the case may be, and the corresponding tax thereon. In case of generating company or transmission licensee paying Minimum Alternate Tax (MAT), “t” shall be considered as MAT rate including surcharge and cess.
Illustration-
(i) In case of a generating company or a transmission licensee paying Minimum Alternate Tax (MAT) @ 21.55% including surcharge and cess:
Rate of return on equity = 15.50/(1-0.2155) = 19.758%
(ii) In case of a generating company or a transmission licensee paying normal corporate tax including surcharge and cess:
(a) Estimated Gross Income from generation or transmission business for FY 2019-2020 is Rs. 1,000 crore;
(b) Estimated Advance Tax for the year on above is Rs. 240 crore;
(c) Effective Tax Rate for the year 2019-2020 = Rs. 240 Crore/Rs. 1000 Crore = 24%;
(d) Rate of return on equity = 15.50/(1-0.24) = 20.395%.
(3) The generating company or the transmission licensee, as the case may be, shall true up the grossed up rate of return on equity at the end of every financial year based on actual tax paid together with any additional tax demand including interest thereon, duly adjusted for any refund of tax including interest received from the income tax authorities pertaining to the tariff period 2019-2024 on actual gross income of any financial year. However, penalty, if any, arising on account of delay in deposit or short deposit of tax amount shall not be claimed by the generating company or the transmission licensee, as the case may be. Any under-recovery or over-recovery of grossed up rate on return on equity after truing up, shall be recovered or refunded to beneficiaries or the long term customers, as the case may be, on year to year basis.”
83. The Petitioner has submitted that it is liable to pay Income Tax at MAT rate prescribed under the Taxation laws (Amendment) Ordinance 2019. Further, RoE has been calculated @18.782% after grossing up RoE with MAT rate of 17.472% (Base Rate 15% + Surcharge 12% + Cess 4%) based on the formula given in Regulation 31(2) of the 2019 Tariff Regulations for 2019-2024 tariff period. As per Regulation 31(3) of the 2019 Tariff Regulations, the grossed-up rate of RoE at the end of every financial year shall be trued up based on actual tax paid together with any additional tax demand including interest thereon duly adjusted for any refund of tax including interest received from the IT authorities pertaining to 2019-2024 tariff period on actual gross income. However, if any penalty arising on account of delay in deposit or short deposit of tax amount shall not be claimed by the Petitioner. Any under-recovery or over-recovery of grossed up rate on RoE after truing up shall be recovered or refunded to beneficiaries or the long term customers on yearly basis. The Petitioner has further submitted that any adjustment due to additional tax demand including interest duly adjusted for any refund of tax including interest received from IT authorities shall be recoverable/adjustable during 2019-2024 tariff period on yearly basis on receipt of Income Tax assessment order.
84. We have considered the submissions of the Petitioner. MAT rate applicable in 2019-2020 has been considered for the purpose of RoE, which shall be trued-up with actual tax rate in accordance with Regulation 31(3) of the 2019 Tariff Regulations. RoE allowed for Combined Asset, Asset-V and Asset-VI for the 2019-2024 tariff period is as follows:
(Rs. in lakh)
Combined Asset Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Opening Equity 2626.17 2679.71 2712.46 2712.46 2712.46 Addition due to Additional Capitalization 53.54 32.75 0.00 0.00 0.00 Closing Equity 2679.71 2712.46 2712.46 2712.46 2712.46 Average Equity 2652.94 2696.09 2712.46 2712.46 2712.46 Return on Equity (Base Rate) (in %) 15.500 15.500 15.500 15.500 15.500 Tax Rate applicable (in %) 17.470 17.470 17.470 17.470 17.470 Rate of Return on Equity (Pre-tax) 18.780 18.780 18.780 18.780 18.780 Return on Equity (Pre-tax) 498.28 506.38 509.45 509.45 509.45
(Rs. in lakh)
Asset-V Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Opening Equity 85.75 87.70 92.86 92.86 92.86 Addition due to Additional Capitalization 1.95 5.16 0.00 0.00 0.00 Closing Equity 87.70 92.86 92.86 92.86 92.86 Average Equity 86.73 90.28 92.86 92.86 92.86 Return on Equity (Base Rate) (in %) 15.500 15.500 15.500 15.500 15.500 Tax Rate applicable (in %) 17.470 17.470 17.470 17.470 17.470 Rate of Return on Equity (Pre-tax) 18.780 18.780 18.780 18.780 18.780 Return on Equity (Pre-tax) 16.29 16.96 17.44 17.44 17.44 Asset-VI Opening Equity 86.07 88.07 93.23 93.23 93.23 Addition due to Additional Capitalization 2.00 5.16 0.00 0.00 0.00 Closing Equity 88.07 93.23 93.23 93.23 93.23 Average Equity 87.07 90.65 93.23 93.23 93.23 Return on Equity (Base Rate) (in %) 15.500 15.500 15.500 15.500 15.500 Tax Rate applicable (in %) 17.470 17.470 17.470 17.470 17.470 Rate of Return on Equity (Pre-tax) 18.780 18.780 18.780 18.780 18.780 Return on Equity (Pre-tax) 16.35 17.03 17.51 17.51 17.51
Operation & Maintenance Expenses
85. Regulation 35(3)(a) of the 2019 Tariff Regulations provides as follows:
35. Operation and Maintenance Expenses (3) Transmission system: (a) The following normative operation and maintenance expenses shall be admissible for the transmission system:
Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Norms for sub-station Bays (Rs. Lakh per bay) 765 kV 45.01 46.60 48.23 49.93 51.68 400 kV 32.15 33.28 34.45 35.66 36.91 220 kV 22.51 23.30 24.12 24.96 25.84 132 kV and below 16.08 16.64 17.23 17.83 18.46 Norms for Transformers (Rs. Lakh per MVA) 765 kV 0.491 0.508 0.526 0.545 0.564 400 kV 0.358 0.371 0.384 0.398 0.411 220 kV 0.245 0.254 0.263 0.272 0.282 132 kV and below 0.245 0.254 0.263 0.272 0.282 Norms for AC and HVDC lines (Rs. Lakh per km) Single Circuit (Bundled Conductor with six or more sub-conductors) 0.881 0.912 0.944 0.977 1.011 Single Circuit (Bundled conductor with four sub-conductors) 0.755 0.781 0.809 0.837 0.867 Single Circuit (Twin & Triple Conductor) 0.503 0.521 0.539 0.558 0.578 Single Circuit (Single Conductor) 0.252 0.260 0.270 0.279 0.289 Double Circuit (Bundled conductor with four or more sub-conductors) 1.322 1.368 1.416 1.466 1.517 Double Circuit (Twin & Triple Conductor) 0.881 0.912 0.944 0.977 1.011 Double Circuit (Single Conductor) 0.377 0.391 0.404 0.419 0.433 Multi Circuit (Bundled Conductor with four or more sub-conductor) 2.319 2.401 2.485 2.572 2.662 Multi Circuit (Twin & Triple Conductor) 1.544 1.598 1.654 1.713 1.773 Norms for HVDC stations HVDC Back-to-Back stations (Rs. Lakh per 500 MW) (Except Gazuwaka BTB) 834 864 894 925 958 Gazuwaka HVDC Back-to-Back station (Rs. Lakh per 500 MW) 1,666 1,725 1,785 1,848 1,913 500 kV Rihand-Dadri HVDC bipole scheme (Rs. Lakh) (1500 MW) 2,252 2,331 2,413 2,498 2,586 ±500 kV Talcher - Kolar HVDC bipole scheme (Rs. Lakh) (2000 MW) 2,468 2,555 2,645 2,738 2,834 ±500 kV Bhiwadi-Balia HVDC bipole scheme (Rs. Lakh) (2500 MW) 1,696 1,756 1,817 1,881 1,947 ±800 kV, Bishwanath-Agra HVDC bipole scheme (Rs. Lakh)(3000 MW) 2,563 2,653 2,746 2,842 2,942
Provided that the O&M expenses for the GIS bays shall be allowed as worked out by multiplying 0.70 of the O&M expenses of the normative O&M expenses for bays;
Provided further that:
(i) the operation and maintenance expenses for new HVDC bi-pole schemes commissioned after 1.4.2019 for a particular year shall be allowed pro-rata on the basis of normative rate of operation and maintenance expenses of similar HVDC bi-pole scheme for the corresponding year of the tariff period;
(ii) the O&M expenses norms for HVDC bi-pole line shall be considered as Double Circuit quad AC line;
(iii) the O&M expenses of ±500 kV Mundra-Mohindergarh HVDC bipole scheme (2500 MW) shall be allowed as worked out by multiplying 0.80 of the normative O&M expenses for ±500 kV Talchar-Kolar HVDC bi-pole scheme (2000 MW);
(iv) the O&M expenses of ±800 kV Champa-Kurukshetra HVDC bi-pole scheme (3000 MW) shall be on the basis of the normative O&M expenses for ±800 kV, Bishwanath-Agra HVDC bi-pole scheme;
(v) the O&M expenses of ±800 kV, Alipurduar-Agra HVDC bi-pole scheme (3000 MW) shall be allowed as worked out by multiplying 0.80 of the normative O&M expenses for ±800 kV, Bishwanath-Agra HVDC bi-pole scheme; and
(vi) the O&M expenses of Static Synchronous Compensator and Static Var Compensator shall be worked at 1.5% of original project cost as on commercial operation which shall be escalated at the rate of 3.51% to work out the O&M expenses during the tariff period. The O&M expenses of Static Synchronous Compensator and Static Var Compensator, if required, may be reviewed after three years.
(b) The total allowable operation and maintenance expenses for the transmission system shall be calculated by multiplying the number of sub-station bays, transformer capacity of the transformer (in MVA) and km of line length with the applicable norms for the operation and maintenance expenses per bay, per MVA and per km respectively.
(c) The Security Expenses and Capital Spares for transmission system shall be allowed separately after prudence check:
Provided that the transmission licensee shall submit the assessment of the security requirement and estimated security expenses, the details of year-wise actual capital spares consumed at the time of truing up with appropriate justification.”
86. The O&M Expenses in respect of the various elements covered under Combined Asset, Asset-V and Asset-VI as claimed by the Petitioner for the 2019-2024 tariff period are within the norms specified in the 2019 Tariff Regulations and, accordingly, the O&M Expenses allowed for the 2019-2024 tariff period are as follows:
(Rs. in lakh)
Combined Asset Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Sub-station Bays Itarsi : 400 kV ICT Bay at Itarsi 1 1 1 1 1 Itarsi : 220 kV ICT Bay at Itarsi 1 1 1 1 1 Itarsi : Itarsi MPPTCL Downstream Bay 1 1 1 1 1 Itarsi : Hoshangabad MPPTCL Downstream Bay 1 1 1 1 1 Indore : 220 kV Line Bay at Indore 2 2 2 2 2 Indore : 400 kV ICT Bay at Indore 1 1 1 1 1 Indore : 220 kV ICT-2 Bay at Indore 1 1 1 1 1 Indore : 220 kV Line Bay at Indore 2 2 2 2 2 Indore : 400 kV ICT-I Bay at Indore 1 1 1 1 1 Indore : 220 kV ICT-I Bay at Indore 1 1 1 1 1 Norm (Rs. lakh/bay) 400 kV 32.15 33.28 34.45 35.66 36.91 220 kV 22.51 23.30 24.12 24.96 25.84 Total Sub-station Expenses 299.04 309.54 320.43 331.62 343.29 Transformers Itarsi : ICT (MVA) 500 500 500 500 500 Indore : ICT 1 and 2 (MVA) 1000 1000 1000 1000 1000 Norm (Rs. lakh/transformer) 400 kV sub-station ICT 0.358 0.371 0.384 0.398 0.411 Total Transformer O&M 537.00 556.50 576.00 597.00 616.50 Total O&M Expenses 836.04 866.04 896.43 928.62 959.79
(Rs. in lakh)
Asset-V Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Sub-station Bays Indore : 220 kV Line Bay at Indore 1 1 1 1 1 Norm (Rs. lakh/bay) 220 kV 22.51 23.30 24.12 24.96 25.84 Total Sub-station O&M 22.51 23.30 24.12 24.96 25.84 Total O&M Expenses 22.51 23.30 24.12 24.96 25.84
(Rs. in lakh)
Asset-VI Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Sub-station Bays Indore : 220 kV Line Bay at Indore 1 1 1 1 1 Norm (Rs. lakh/bay) 220 kV 22.51 23.30 24.12 24.96 25.84 Total Sub-station O&M 22.51 23.30 24.12 24.96 25.84 Total O&M Expenses 22.51 23.30 24.12 24.96 25.84
Interest on Working Capital
87. Regulations 34(1)(c), 34(3), 34(4) and 3(7) of the 2019 Tariff Regulations provide as follows:
“34. Interest on Working Capital: (1) The working capital shall cover:
(c) For Hydro Generating Station (including Pumped Storage Hydro Generating Station) and Transmission System:
(i) Receivables equivalent to 45 days of annual fixed cost;
(ii) Maintenance spares @ 15% of operation and maintenance expenses including security expenses; and
(iii) Operation and maintenance expenses, including security expenses for one month.”
“(3) Rate of interest on working capital shall be on normative basis and shall be considered as the bank rate as on 1.4.2019 or as on 1st April of the year during the tariff period 2019-2024 in which the generating station or a unit thereof or the transmission system including communication system or element thereof, as the case may be, is declared under commercial operation, whichever is later:
Provided that in case of truing-up, the rate of interest on working capital shall be considered at bank rate as on 1st April of each of the financial year during the tariff period 2019-2024.”
“(4) Interest on working capital shall be payable on normative basis notwithstanding that the generating company or the transmission licensee has not taken loan for working capital from any outside agency.”
“3. Definitions …
(7) ‘Bank Rate’ means the one year marginal cost of lending rate (MCLR) of the State Bank of India issued from time to time plus 350 basis points;”
88. The Petitioner has submitted that it has computed IWC for the 2019-2024 period considering the SBI Base Rate plus 350 basis points as on 1.4.2019. The Petitioner has considered the rate of IWC as 12.05%. IWC is worked out in accordance with Regulation 34 of the 2019 Tariff Regulations. The Petitioner has considered the rate of IWC as 12.05%. The Rate of Interest considered is 12.05% (SBI 1 year MCLR applicable as on 1.4.2019 of 8.55% plus 350 basis points) for 2019-2020, for 2020-2021 has been considered as 11.25% (SBI 1 year MCLR applicable as on 1.4.2020 of 7.75% plus 350 basis points) whereas 2021-2022 onwards has been considered as 10.50% (SBI 1 year MCLR applicable as on 1.4.2020 of 7.00% plus 350 basis points). The components of the working capital and interest allowed thereon for Combined Asset, Asset-V and Asset-VI for the 2019-2024 tariff period is as follows:
Combined Asset Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 O&M Expenses (O&M expenses for 1 month) 69.67 72.17 74.70 77.39 79.98 Maintenance Spares (15% of O&M Expenses) 125.41 129.91 134.46 139.29 143.97 Receivables (Equivalent to 45 days of annual fixed cost/annual transmission charges) 283.19 285.45 285.50 285.16 283.45 Total Working Capital 478.26 487.53 494.67 501.84 507.40 Rate of Interest (in %) 12.05 11.25 10.50 10.50 10.50 Interest of Working Capital 57.63 54.85 51.94 52.69 53.28
(Rs. in lakh)
Asset-V Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 O&M Expenses (O&M Expenses for 1 month) 1.88 1.94 2.01 2.08 2.15 Maintenance Spares (15% of O&M Expenses) 3.38 3.50 3.62 3.74 3.88 Receivables (Equivalent to 45 days of annual fixed cost/annual transmission charges) 8.68 8.88 8.99 8.94 8.87 Total Working Capital 13.93 14.31 14.62 14.77 14.90 Rate of Interest (in %) 12.05 11.25 10.50 10.50 10.50 Interest of Working Capital 1.68 1.61 1.53 1.55 1.56
(Rs. in lakh)
Asset-VI Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 O&M Expenses (O&M expenses for 1 month) 1.88 1.94 2.01 2.08 2.15 Maintenance Spares (15% of O&M expenses) 3.38 3.50 3.62 3.74 3.88 Receivables (Equivalent to 45 days of annual fixed cost/annual transmission charges) 8.72 8.92 9.04 9.00 8.92 Total Working Capital 13.98 14.36 14.67 14.82 14.95 Rate of Interest (in %) 12.05 11.25 10.50 10.50 10.50 Interest of Working Capital 1.68 1.62 1.54 1.56 1.57
Annual Fixed Charges of the 2019-2024 Tariff Period
89. The transmission charges allowed for Combined Asset, Asset-V and Asset-VI for the 2019-2024 tariff period are as follows:
(Rs. in lakh)
Combined Asset Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Depreciation 479.48 486.86 489.51 489.51 489.51 Interest on Loan 431.84 401.23 368.38 332.71 293.35 Return on Equity 498.28 506.38 509.45 509.45 509.45 Interest on Working Capital 57.63 54.85 51.94 52.69 53.28 O&M Expenses 836.04 866.04 896.43 928.62 959.79 Total 2303.27 2315.36 2315.71 2312.98 2305.38
(Rs. in lakh)
Asset-V Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Depreciation 16.26 16.90 17.36 17.36 17.36 Interest on Loan 13.84 13.22 12.45 11.21 9.92 Return on Equity 16.29 16.96 17.44 17.44 17.44 Interest on Working Capital 1.68 1.61 1.53 1.55 1.56 O&M Expenses 22.51 23.30 24.12 24.96 25.84 Total 70.58 71.99 72.90 72.52 72.12
(Rs. in lakh)
Asset-VI Particulars 2019-20 2020-2021 2021-22 2022-23 2023-24 Depreciation 16.33 16.97 17.43 17.43 17.43 Interest on Loan 14.07 13.46 12.71 11.52 10.21 Return on Equity 16.35 17.03 17.51 17.51 17.51 Interest on Working Capital 1.68 1.62 1.54 1.56 1.57 O&M Expenses 22.51 23.30 24.12 24.96 25.84 Total 70.95 72.37 73.31 72.97 72.56
Filing Fee and Publication Expenses
90. The Petitioner has sought reimbursement of fee paid by it for filing the petition and publication expenses. The Petitioner shall be entitled for reimbursement of the filing fees and publication expenses in connection with the present petition, directly from the beneficiaries on pro-rata basis in accordance with Regulation 70(1) of the 2019 Tariff Regulations.
Licence Fee & RLDC Fees and Charges
91. The Petitioner shall be entitled for reimbursement of licence fee in accordance with Regulation 70(4) of the 2019 Tariff Regulations for the 2019-2024 tariff period. The Petitioner shall also be entitled for recovery of RLDC fee and charges in accordance with Regulation 70(3) of the 2019 Tariff Regulations for the 2019-2024 tariff period.
Goods and Services Tax
92. The Petitioner has submitted that, if GST is levied at any rate and at any point of time in future on charges of transmission of electricity, the same shall be borne and additionally paid by the Respondent(s) to the Petitioner and the same shall be charged and billed separately by the Petitioner. Further, additional taxes, if any, are to be paid by the Petitioner on account of demand from Government/Statutory authorities, the same may be allowed to be recovered from the beneficiaries. The Petitioner has prayed to bill and recover GST on transmission charges separately from the beneficiaries, if at any time GST on transmission is withdrawn from negative list at any time in future.
93. We have considered the submissions of the Petitioner. Since GST is not levied on transmission services at present, we are of the view that Petitioner's prayer is premature.
Security Expenses
94. The Petitioner has submitted that security expenses for the transmission assets are not claimed in the instant petition and it would file a separate petition for claiming the overall security expenses and the consequential IWC.
95. We have considered the above submissions of Petitioner. The Petitioner has claimed consolidated security expenses for all the transmission assets owned by it on projected basis for the 2019-2024 tariff period on the basis of actual security expenses incurred in 2018-2019 in Petition No. 260/MP/2020. The Commission vide order dated 3.8.2021 in Petition No. 260/MP/2020 approved security expenses from 1.4.2019 to 31.3.2024. Therefore, security expenses will be shared in terms of the order dated 3.8.2021 in Petition No. 260/MP/2020. Accordingly, the Petitioner's prayer in the instant petition for allowing it to file a separate petition for claiming the overall security expenses and consequential IWC has become infructuous.
Capital Spares
96. The Petitioner has sought reimbursement of capital spares at the end of tariff period. The Petitioner's claim, if any, shall be dealt with in accordance with the provisions of the 2019 Tariff Regulations.
Sharing of Transmission Charges
97. The Petitioner vide affidavit dated 28.7.2021 has submitted that the Commission vide order dated 21.1.2020 in Petition No. 311/TT/2020 had decided that in respect of Asset-II, Asset-III and Asset-IV, the transmission charges from COD up to the actual charging of downstream system (i.e. 10.12.2018, 12.12.2018 and 10.12.2018 for Asset-II, III and IV respectively) shall be borne by MPPTCL and, thereafter, it will be shared under PoC mechanism. Also, the Commission had decided that transmission charges for Asset-V and Asset-VI shall be borne by MPPTCL up to COD of downstream transmission system under the scope of MPPTCL and thereafter shared under PoC mechanism. Further, the Petitioner has been raising bilateral bills on MPPTCL in respect of Asset-V and Asset-VI. MPPTCL has filed a Writ Petition before the Hon'ble High Court of Madhya Pradesh against the Commission's order dated 21.1.2020 in Petition No. 311/TT/2018. For Asset-V and Asset-VI, MPPTCL has not made any payment of transmission charges to the Petitioner so far.
98. In view of the above, the Petitioner has prayed to allow recovery of transmission charges from COD up to the actual charging of the downstream system from MPPTCL and thereafter, to be shared under PoC mechanism as allowed by the Commission vide order dated 21.01.2020 in Petition no. 311/TT/2018.
99. We have considered the submissions of the Petitioner and note that the Commission vide order dated 21.1.2020 in Petition No. 311/TT/2020 had approved COD of Asset-1, Asset-2, Asset-3, Asset-4 and Asset-5 (which have been nomenclature of Asset-II, Asset-III, Asset-IV, Asset-V and Asset-VI respectively in this petition). The relevant extracts of the said order are as follows:
“75. The transmission charges in case of Asset-1 from 2.9.2018 (COD) to 9.12.2018 (one day before actual charging of downstream system) will be borne by the MPPTCL and thereafter from 10.12.2018 (Date of Power flow) onwards it will be shared under POC mechanism.
76. The transmission charges in case of Asset-2 from 2.9.2018 (COD) upto 11.12.2018 (one day before actual charging of downstream system) will be borne by the MPPTCL and thereafter from 12.12.2018 (Date of Power flow) onwards it will be shared under POC mechanism.
77. The transmission charges in case of Asset-3 from 14.10.2018 (COD) upto 9.12.2018 (one day before actual charging of downstream system) will be borne by the MPPTCL and thereafter from 10.12.2018 (Date of Power flow) onwards it will be shared under POC mechanism.
78. The transmission charges in case of Asset-4 from 14.10.2018 (COD) upto commissioning of downstream transmission system under the scope of MPPTCL shall be borne by MPPTCL and thereafter it will be shared under POC mechanism.
79. The transmission charges in case of Asset-5 from 5.12.2018 (COD) upto commissioning of downstream network under the scope of MPPTCL will be borne by the MPPTCL and thereafter it will be shared under POC mechanism.”
100. In line of the afore-stated decision, we are of the considered view that the transmission charges with respect to Asset-II to Asset-VI shall be shared as follows:
a) In case of Asset-II, from 2.9.2018 (COD) up to 9.12.2018 (one day before actual charging of downstream system) to be borne by MPPTCL and thereafter from 10.12.2018 (date of power flow) onwards, to be shared under POC mechanism.
b) In case of Asset-III, from 2.9.2018 (COD) up to 11.12.2018 (one day before actual charging of downstream system) to be borne by MPPTCL and thereafter from 12.12.2018 (date of power flow) onwards, to be shared under POC mechanism.
c) In case of Asset-IV, from 14.10.2018 (COD) up to 9.12.2018 (one day before actual charging of downstream system) to be borne by MPPTCL and thereafter from 10.12.2018 (date of power flow) onwards, to be shared under POC mechanism.
d) In case of Asset-V, from 14.10.2018 (COD) up to commissioning of downstream system under the scope of MPPTCL to be borne by MPPTCL and thereafter will be shared under POC mechanism.
e) In case of Asset-VI, from 5.12.2018 (COD) up to commissioning of downstream system under the scope of MPPTCL to be borne by MPPTCL and thereafter will be shared under POC mechanism.
101. With effect from 1.7.2011, sharing of transmission charges for inter-State transmission systems was governed by the provisions of the 2010 Sharing Regulations and with effect from 1.11.2020 (after repeal of the 2010 Sharing Regulations), sharing of transmission charges is governed by the 2020 Sharing Regulations. Accordingly, the liabilities of DICs for arrears of transmission charges determined through this order shall be computed DIC-wise in accordance with the provisions of respective Tariff Regulations and Sharing Regulations and shall be recovered from the concerned DICs through Bills under Regulation 15(2)(b) of the 2020 Sharing Regulations. Billing, collection and disbursement of the transmission charges for subsequent period shall be recovered in terms of provisions of the 2020 Sharing Regulations as provided in Regulation 57 of the 2019 Tariff Regulations.
102. We also note that MPPTCL has filed a Writ Petition before the Hon'ble High Court of Madhya Pradesh against the Commission's order dated 21.1.2020 in Petition No. 311/TT/2018. Accordingly, the sharing of transmission charges as mentioned above shall be subject to the outcome of the Writ Petition pending before Hon'ble High Court of Madhya Pradesh.
103. To summarise:
a) The trued-up AFC approved for the transmission assets for the 2014-2019 tariff period are as follows:
(Rs. in lakh)
Asset-I 2018-2019 (Pro-rata for 230 days) 2018-19 398.90 684.99
Asset-II Asset-III Asset-IV Asset-V Asset-VI 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 211 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 169 days) 2018-2019 (Pro-rata for 117 days) 428.17 110.56 207.07 44.07 30.77
b) AFC allowed for Combined Asset, Asset-V and Asset-VI for the 2019-2024 tariff period in this order are as follows:
(Rs. in lakh)
Asset 2019-20 2020-2021 2021-22 2022-23 2023-24 Combined Asset 2303.27 2315.36 2315.71 2312.98 2305.38 Asset-V 70.58 71.99 72.90 72.52 72.12 Asset-VI 70.95 72.37 73.31 72.97 72.56
104. Annexure-I (Colly.) and Annexure-II (Colly.) given hereinafter shall form part of the order.
105. This order disposes of Petition No. 671/TT/2020 in terms of the above discussions and findings.
Asset-I Annexure-I (Colly.) 2014-19 Admitted Capital Cost as on COD (Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2019 (Rs. in lakh) Rate of Depreciation (in %) Annual Depreciation as per the 2014 Tariff Regulations Capital Expenditure as on COD 2017-18 2018-19 2014-2015 (Rs. in lakh) 2015-2016 (Rs. in lakh) 2016-2017 (Rs. in lakh) 2017-2018 (Rs. in lakh) 2018-2019 (Rs. in lakh) Sub Station 2237.90 339.62 274.23 2851.75 5.28 - - - 127.13 143.33 PLCC 19.20 0.13 0.00 19.33 6.33 - - - 1.22 1.22 IT Equipment and software 21.19 5.78 2.82 29.79 5.28 - - - 1.27 1.50 TOTAL 2278.30 345.53 277.05 2900.88 - - - 129.62 146.06 Average Gross Block (Rs. in lakh) - - - 2451.07 2762.36 Weighted Average Rate of Depreciation (in %) - - - 5.29 5.29
Asset-II 2014-19 Admitted Capital Cost as on COD (Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2019 Rs. in lakh) Rate of Depreciation (in %) Annual Depreciation as per the 2014 Tariff Regulations Capital Expenditure as on COD 2018-19 2014-2015 (Rs. in lakh) 2015-2016 (Rs. in lakh) 2016-2017 (Rs. in lakh) 2017-2018 (Rs. in lakh) 2018-2019 (Rs. in lakh) Sub-station 2884.03 293.76 3177.80 5.28 - - - - 160.03 PLCC 17.09 0.17 17.27 6.33 - - - - 1.09 IT Equipment and software 33.28 13.27 46.55 5.28 - - - - 2.11 TOTAL 2934.41 307.21 3241.62 - - - - 163.23 Average Gross Block (Rs. in lakh) - - - - 3088.02 Weighted Average Rate of Depreciation (in %) - - - - 5.29
Asset-III 2014-19 Admitted Capital Cost as on COD (Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2019 (Rs. in lakh) Rate of Depreciation (in %) Annual Depreciation as per the 2014 Tariff Regulations Capital Expenditure as on COD 2018-19 2014-2015 (Rs.in lakh) 2015-2016 (Rs. in lakh) 2016-2017 (Rs. in lakh) 2017-2018 (Rs. in lakh) 2018-2019 (Rs. in lakh) Sub-station 468.68 68.40 537.08 5.28 - - - - 26.55 PLCC 17.08 0.18 17.26 6.33 - - - - 1.09 IT Equipment and software 20.20 7.97 28.18 5.28 - - - - 1.28 TOTAL 505.96 76.56 582.52 - - - - 28.92 Average Gross Block (Rs. in lakh) - - - - 544.24 Weighted Average Rate of Depreciation (in %) - - - - 5.31
Asset-IV 2014-19 Admitted Capital Cost as on COD (Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2019 (Rs. in lakh) Rate of Depreciation (in %) Annual Depreciation as per the 2014 Tariff Regulations Capital Expenditure as on COD 2018-19 2014-2015 (Rs. in lakh) 2015-2016 (Rs. in lakh) 2016-2017 (Rs. in lakh) 2017-2018 (Rs. in lakh) 2018-2019 (Rs. in lakh) Sub-station 1836.68 173.69 2010.37 5.28 - - - - 101.55 IT Equipment and software 13.40 5.21 18.60 5.28 - - - - 0.84 TOTAL 1850.07 178.90 2028.97 - - - - 102.39 Average Gross Block (Rs. in lakh) - - - - 1939.52 Weighted Average Rate of Depreciation (in %) - - - - 5.28
Asset-V 2014-19 Admitted Capital Cost as on COD (Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2019 (Rs. in lakh) Rate of Depreciation (in %) Annual Depreciation as per the 2014 Tariff Regulations Capital Expenditure as on COD 2018-19 2014-2015 (Rs. in lakh) 2015-2016 (Rs. in lakh) 2016-2017 (Rs. in lakh) 2017-2018 (Rs. in lakh) 2018-2019 (Rs. in lakh) Sub Station 237.21 30.71 267.92 5.28 - - - - 13.32 PLCC 8.49 0.07 8.56 6.33 - - - - 0.54 IT Equipment and software 6.71 2.65 9.36 5.28 - - - - 0.43 TOTAL 252.42 33.43 285.85 - - - - 14.29 Average Gross Block (Rs. in lakh) - - - - 269.13 Weighted Average Rate of Depreciation (in %) - - - - 5.31
Asset-V 2014-19 Admitted Capital Cost as on COD (Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2019 (Rs. in lakh) Rate of Depreciation (in %) Annual Depreciation as per the 2014 Tariff Regulations Capital Expenditure as on COD 2018-19 2014-2015 (Rs. in lakh) 2015-2016 (Rs. in lakh) 2016-2017 (Rs. in lakh) 2017-2018 (Rs. in lakh) 2018-2019 (Rs. in lakh) Sub-station 244.38 24.71 269.09 5.28 - - - - 13.56 PLCC 8.36 0.11 8.47 6.33 - - - - 0.53 IT Equipment and software 6.69 2.67 9.36 5.28 - - - - 0.42 TOTAL 259.44 27.49 286.92 - - - - 14.51 Average Gross Block (Rs. in lakh) - - - - 273.18 Weighted Average Rate of Depreciation (in %) - - - - 5.31
Combined Asset Annexure-II (Colly.) 2019-24 Admitted Capital Cost as on 31.3.2019 (Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2024 (Rs. in lakh) Rate of Depreciatio n (in %) Annual Depreciation as per the 2019 Tariff Regulations Capital Expenditure as on COD 2019-20 2020-2021 2019-2020 (Rs. in lakh) 2020-2021 (Rs. in lakh) 2021-2022 (Rs. in lakh) 2022-2023 (Rs. in lakh) 2023-2024 (Rs. in lakh) Building 0.00 0.00 28.07 28.07 3.34 0.00 0.47 0.94 0.94 0.94 Sub Station 8577.00 174.61 74.46 8826.07 5.28 457.48 464.05 466.02 466.02 466.02 PLCC 53.86 3.75 6.64 64.25 6.33 3.53 3.86 4.07 4.07 4.07 IT Equipment and software 123.13 0.11 0.00 123.24 15.00 18.48 18.49 18.49 18.49 18.49 TOTAL 8753.99 178.47 109.17 9041.63 479.48 486.86 489.51 489.51 489.51 Average Gross Block (Rs. in lakh) 8843.22 8987.04 9041.63 9041.63 9041.63 Weighted Average Rate of Depreciation (in %) 5.42 5.42 5.41 5.41 5.41
Asset-V
2019-24 Admitted Capital Cost as on 31.3.2019 Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2024 (Rs. in lakh) Rate of Depreciation (in %) Annual Depreciation as per the 2019 Tariff Regulations Capital Expenditure as on COD 2019-20 2020-2021 2019-2020 (Rs. in lakh) 2020-2021 (Rs. in lakh) 2021-2022 (Rs. in lakh) 2022-2023 (Rs. in lakh) 2023-2024 (Rs. in lakh) Sub Station 267.92 6.48 15.53 289.93 5.28 14.32 14.90 15.31 15.31 15.31 PLCC 8.56 0.01 1.66 10.23 6.33 0.54 0.60 0.65 0.65 0.65 IT Equipment and software 9.36 0.01 0.00 9.37 15.00 1.41 1.41 1.41 1.41 1.41 TOTAL 285.85 6.50 17.19 309.54 16.26 16.90 17.36 17.36 17.36 Average Gross Block (Rs. in lakh) 289.10 300.94 309.54 309.54 309.54 Weighted Average Rate of Depreciation (in %) 5.63 5.62 5.61 5.61 5.61
Asset-VI
2019-24 Admitted Capital Cost as on 31.3.2019 (Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2024 (Rs. in lakh) Rate of Depreciation (%) Annual Depreciation as per the 2019 Tariff Regulations Capital Expenditure as on COD 2019-20 2020-2021 2019-2020 (Rs. in lakh) 2020-2021 (Rs. in lakh) 2021-2022 (Rs. in lakh) 2022-2023 (Rs. in lakh) 2023-2024 (Rs. in lakh) Sub-station 269.09 6.66 15.53 291.27 5.28 14.38 14.97 15.38 15.38 15.38 PLCC 8.47 0.02 1.66 10.15 6.33 0.54 0.59 0.64 0.64 0.64 IT Equipment and software 9.36 0.01 0.00 9.38 15.00 1.41 1.41 1.41 1.41 1.41 TOTAL 286.92 6.69 17.19 310.80 16.33 16.97 17.43 17.43 17.43 Average Gross Block (Rs. in lakh) 290.27 302.21 310.80 310.80 310.80 Weighted Average Rate of Depreciation (%) 5.62 5.61 5.61 5.61 5.61
Alert