- Bookmark
- Share
- CaseIQ
Emaar Mgf Land Ltd. ... v. Kamal Kad And Anothe...
National Consumer Disputes Redressal Commission — First Appeal No. 517 of 2020 (Order dated 18 Feb 2022)
Factual and Procedural Background
This appeal arises under Section 19 of the Consumer Protection Act, 1986, by M/s Emaar MGF Land Ltd. & Another (Appellants/Opposite Parties) against the State Commission, U.T. Chandigarh's Order dated 18.12.2019 in Complaint No. 822 of 2016, which had partly allowed the Complainants' prayer.
Brief factual narrative as stated in the opinion:
- The Respondents/Complainants (Mr. Kamal Kad & Mrs. Aruna Kad) booked a plot in the "Mohali Hills" project, Augusta Park, Sector 109, SAS Nagar, Mohali. The total consideration was Rs. 36,19,104.
- The Respondents paid Rs. 10,35,000 as booking amount on 29.09.2006 and, according to them, cleared the balance between 29.06.2007 and 16.03.2009 (a last amount of Rs. 1,72,500 was waived by the Appellants).
- The Plot Buyer's Agreement was executed on 20.06.2007. Clause 8 provided for possession within 2 years (and not later than 3 years) subject to force majeure; penalty provisions for delay were also included in the Agreement.
- The Respondents claimed that possession was not delivered even after nearly seven years (and in fact more than 14 years from the date of the agreement at the time of this appeal), and therefore issued a legal notice dated 05.11.2015 demanding refund with 18% interest; a reminder followed on 12.01.2016.
- The Respondents filed a Complaint before the State Commission seeking refund of Rs. 34,46,406 (amount paid between Sept 2006 and March 2009) with penalty/interest and compensation. The State Commission partly allowed the Complaint and directed refund of Rs. 34,46,406 with interest @12% p.a. from deposit dates, with a provision for penal interest (3% p.a. additional) if not paid within 30 days, and a direction regarding first charge for any bank loan.
- The Appellants challenged that Order before the NCDRC by raising issues including limitation, alleged willful default by complainants, applicability of a relocation offer (email dated 22.05.2013), and the appropriate rate of interest.
Legal Issues Presented
- Whether the Complaint before the State Commission was barred by limitation (i.e., whether the cause of action was time‑barred).
- Whether the Respondents were willful defaulters in making payments as per agreed timelines.
- Whether an offer of relocation (email dated 22.05.2013) by the Appellants discharged their obligation and bound the Respondents to accept possession.
- Whether the rate of interest/delay compensation awarded by the State Commission (12% p.a.) was appropriate, and if not, what is a fair rate.
Arguments of the Parties
Appellants' (Opposite Parties') Arguments
- The Complaint was barred by limitation and the State Commission lacked territorial and pecuniary jurisdiction.
- The Respondents were willful defaulters for not making payments according to agreed timelines.
- Clause 39 of the Agreement provided for arbitration, and disputes should be referred to an arbitrator.
- The Appellants had offered relocation of the plot (email dated 22.05.2013), which, in their submission, fulfilled their obligations under the Agreement and therefore the Respondents were duty bound to accept possession after making payments.
- The rate of interest of 12% p.a. awarded by the State Commission was said to be in conflict with certain earlier decisions (Appellants argued that a different rate applied in nearby/projectly related cases and that 12% should not be automatically applied).
Respondents' (Complainants') Arguments
- The Respondents paid the balance (between 29.06.2007 and 16.03.2009) but the Appellants neither gave possession nor returned the money despite lapse of more than 14 years from the date of the Agreement.
- The relocation offered later (notably in 2018 as mentioned in the hearing) could not be imposed on the Respondents; they had the discretion to accept or reject an alternative offer after undue delay.
- The acts of the Appellants constituted deficiency in service and entitled the Respondents to refund, interest and compensation.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Meerut Development Authority v. Mukesh Kumar Gupta [IV (2012) CPJ 12] (09.05.2012) | "The failure to deliver possession of the Plot constitutes a recurrent/continuing cause of action." | The Court relied on this to reject the Appellants' limitation objection and to treat the cause of action as continuing. |
| Emaar MGF Land Ltd. & Ors. v. Amit Puri (II 2015 CPJ 568 (NC)) (30.03.2015) | After promised delivery date, the complainant has discretion to accept an offer of possession or seek refund with compensation. | Used to support the proposition that the Respondents could lawfully refuse relocation and seek refund and compensation. |
| Kolkata West International City Pvt. Ltd. v. Devasis Rudra, II (2019) CPJ 29 SC (25.03.2019) | A buyer should not be required to wait indefinitely; where delay is manifestly unreasonable (e.g., seven years), orders for refund were justified. | Cited to demonstrate that prolonged delay justifies refund and that buyers are not bound to wait indefinitely. |
| Ireo Grace Realtech Pvt. Ltd. v. Abhishek Khanna & Anr., Civil Appeal No. 5785 of 2019 (11.01.2021) | Alternate allotment offers cannot be imposed on allottees after inordinate delay; deficiency of service where occupation certificate absent; court suggested refund with interest @9% S.I. per annum (balancing commercial realities after the pandemic). | Relied on to conclude that buyers are not bound to accept alternate offers after undue delay and to justify adopting 9% p.a. as a fair rate of refund interest in current circumstances. |
| M/s BPTP Ltd. & Anr. v. Sanjay Rastogi, Civil Appeal No. 1001-1002 of 2021 (04.12.2021) | Where delay is established, interest awarded in other cases may be scaled down; court reduced an awarded rate to 9% p.a. | Applied to support scaling down the interest rate to 9% p.a. in the present case. |
| M/s Nexgen Infracon Pvt. Ltd. v. Manish Kumar Sinha, Civil Appeal No. 62 of 2021 (11.01.2021) | The rate of interest awarded by a Commission may be scaled down to 9% p.a. in appropriate cases. | Used as additional authority to justify awarding interest at 9% p.a. on refunds. |
| Subodh Pawar v. IREO Grace; IREO v. Surendra Arora (cases referenced) | Instances where counsel for the developer had recorded a statement of refund with interest (noted contextually in IREO-related orders). | Referred in the discussion of market realities and comparative earlier orders; considered in assessing an appropriate interest rate. |
| DLF Homes Panchkula (P) Ltd. v. D.S. Dhanda (2020) 16 SCC 318 (referenced by Appellants) | Illustrative case (in a nearby project) where a particular rate of interest had been applied; relied upon by Appellants to argue applicability of that rate. | The Appellants cited it to contend that 12% should have been applied; the Court considered competing authorities when determining a fair rate. |
| GDA v. Balbir Singh (2004-5 SCC 65 and 2009-175 CC 199) (referenced) | Principle that 12% p.a. cannot be a blanket rate; the rate must be determined from facts of each case after hearing parties. | Cited by the Appellants in arguing against the State Commission's approach; the Court acknowledged that interest must be determined considering facts and precedent. |
Court's Reasoning and Analysis
The Court set out and applied legal principles in a stepwise manner as follows (based on the text):
- The Court heard counsel for both sides and considered the record.
- On limitation: applying the Supreme Court's pronouncement in Meerut Development Authority v. Mukesh Kumar Gupta that non-delivery of possession is a recurring/continuing cause of action, the Court rejected the Appellants' limitation objection. The cause of action was treated as continuing.
- On the relocation offer: the Court rejected the Appellants' contention that an email dated 22.05.2013 offering relocation discharged their obligations. Two reasons were given in the text: (a) the relocation offer was made after more than two years of unexplained delay from the promised date of possession; (b) it is the buyer's discretion whether to accept or reject any relocated plot. The Court relied on its earlier decision in Emaar MGF v. Amit Puri to support the buyer's discretion to refuse an alternate offer and seek refund/compensation.
- On the substantive question of relief: the Court found there was an unreasonable delay in handing over possession. The Agreement (20.06.2007) required possession within two years and not later than three years; possession ought to have been given by 20.06.2009 or 20.06.2010. Possession had not been given even after 14 years. Drawing on Supreme Court precedents (Kolkata West; IREO Grace) and other authorities, the Court held that buyers in such circumstances are entitled to a refund and reasonable delay compensation.
- On the rate of interest: the Court considered the State Commission's award of 12% p.a. but held that the rate was high in the present context. The Court analyzed recent Supreme Court decisions particularly IREO Grace and subsequent cases where courts have scaled down rates of interest and, taking into account the cited authorities and prevailing commercial realities (including pandemic-related considerations as discussed in those precedents), concluded that 9% per annum simple interest on the deposited amount is a just and fair rate of delay compensation in the present case.
- Disposition: having found the State Commission's order to be lawful in principle but the rate of interest to be excessive, the Court dismissed the appeal as devoid of merit but modified the State Commission's order to award interest at 9% p.a. simple interest on Rs. 34,46,406 (instead of 12%). The Court retained the provision that, failing payment, the amount would carry penal interest — as phrased in the order, a 3% penal interest leading to 12% per annum simple interest in the event of non‑compliance.
Holding and Implications
Core Ruling: The First Appeal is dismissed in substance; the State Commission's order is partly upheld but modified as to the rate of interest. The Appellants/Opposite Parties are directed to pay delay compensation on the deposited amount of Rs. 34,46,406/- at the rate of 9% per annum simple interest instead of the 12% previously awarded by the State Commission. If the Appellants fail to make payment as directed, the amount shall thereafter carry a penal interest of 3% (expressed in the order as resulting in 12% per annum simple interest in the event of default).
Direct consequences and practical effects:
- The Respondents are entitled to refund of the deposited amount with interest at 9% p.a. simple interest (from the respective deposit dates as directed by the State Commission originally).
- Failure to comply with the payment timeline will trigger the penal interest provision specified in the order.
- The Court observed that the case did not raise any substantial question of law; the appeal was dismissed as lacking merit on its primary points (limitation, relocation, and entitlement to refund), with modification only to the rate of interest.
No new legal principle was laid down by this bench; the decision applies existing precedent to the facts and adjusts the rate of interest consistent with recent Supreme Court decisions.
NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
NEW DELHI
FIRST APPEAL NO. 517 OF 2020
(Against the Order dated 18/12/2019 in Complaint No. 822/2016 of the State Commission Chandigarh)
1. EMAAR MGF LAND LTD. & ANR.
(WRONGLY IMPLEADED AS EMAAR MGF LAND
PRIVATE LTD). THROUGH ITS AUTHORISED
SIGNATIORY, OFFICE NO. 40, CENTRAL PLAZA,
SECTOR-105, MOHALI-1600062
2. EMAAR MGF LAND LTD.,
THROUGH ITS AUTHORISED SIGNATORY, 306-307-308, 3RD FLOOR, SQUARE ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017 ...........Appellant(s) Versus
1. KAMAL KAD & ANR. S/O. MR. RAVINDER KUMAR KAD, R/O. FLAT 109, BLOCK-C, NEW GENERATION EXETENSION, DHAKOLI,
ZIRAKPUR, MOHALI,
PUNJAB
2. MRS. ARUNA KAD,
W/O. MR. KAMAL KAD, R/O. FLAT 109, BLOCK-C, NEW
GENERATION EXTENSION, DHAKOLI, ZIRAKPUR,
MOHALI,
PUNJAB ...........Respondent(s)
BEFORE:
HON'BLE DR. S.M. KANTIKAR,PRESIDING MEMBER HON'BLE MR. BINOY KUMAR,MEMBER For the Appellant : Mr. Arjun Jain, Advocate Mr. Vipin Chaudhary, Advocate
For the Respondent : Mr. Rohit Kaushik, Advocate Dated : 18 Feb 2022
ORDER
Binoy Kumar, Member
The present Appeal has been filed under Section 19 of the Consumer Protection Act, 1986 (for short "the Act") by M/s Emaar MGF Land Limited and Another (hereinafter referred to as the 'Appellants/Opposite Parties') assailing the Order dated 18.12.2019 passed by the State Consumer Disputes Redressal Commission, U.T. Chandigarh (hereinafter referred to as the 'State Commission') in Complaint No. 822 of 2016, whereby the Complaint filed by the Complainant was partly allowed.
1.
Brief facts of the case as narrated in the Complaint are that the Respondents/Complainants (Mr. Kamal Kad & Mrs. Aruna Kad) booked a Plot in the
2.
1
Project 'Mohali Hills' of the Opposite Parties situated in Augusta Park, Sector 109, SAS Nagar, Mohali. The total consideration of the Plot was fixed at Rs.36,19,104/-(Thirty Six Lakh Nineteen Thousand One Hundred and Four Only). The Respondents paid Rs.10,35,000/- (Ten Lakh Thirty Five Thousand Only) as booking amount on 29.09.2006. The Respondents stated that between the 29.06.2007 to 16.03.2009 they had cleared the total consideration amount but last amount of Rs.1,72,500/- was waived off by the Appellants.
The Respondents/Complainants stated that the Plot Buyer's Agreement (Hereinafter referred to as the Agreement) was executed on 20.06.2007. As per clause 8 of the Agreement the possession of the Plot was to be given within 2 years from the date of execution of the Agreement. The Relevant portion of the clause 8 of the Agreement reads as under:
3.
" Subject to Force Majeure conditions and reasons beyond the control of the Company, the Company shall endeavor to deliver possession of the Plot to the Allottee within a period of 2(Two) years from the date execution of this Agreement, but not later than 3(Three) years. In the event that the possession of the Plot is likely to be delayed for reason of any force majeure event or any other reason beyond the control of the Company including government strike or due to civil commotion or by reason of War or enemy action or earthquake or any act of God or if non-delivery is a result of any act, notice, order, rule or notification of the Government…. …then in any of the aforesaid events, the Company shall upon notice claiming force majeure to the Allottee be entitled to such extension of time. the force majeure event persists or the reason beyond the control of the Company exists. In the event the Company fails to deliver the possession of the Plot without existence of any force majeure event or reason beyond the control of the Company within a maximum period of 3(Three) years from the date of execution of this Agreement, the Company shall be liable to pay to the Allottee , a penalty of the sum of Rs. 50/- per sq.yds per month for such period of delay beyond 3(Three) years from the date of this Agreement"
the promoter shall complete the construction of the building within 36 months from the date of signing of this agreement subject to Force Majeure conditions and the timely payment from the Buyer. Force Majeure causes, availability of essential items for construction, delay in grant of permission by any competent authorities and other causes beyond the control of the Promoter…
However in case of delay in completion of the unit attributable to delay of promoter, after 180 days of above said period of 36 months the promoter would pay penalty to the Buyers @5/- per sq ft. Per month for the period of delay…" The Respondents/Complainants stated that as per the terms and conditions of the Agreement the possession of the Plot was to be given within 2 years from the date of the Agreement but inspite of lapse of nearly 7 years the possession has not been given.
4.
2
Aggrieved by the delay the Respondents served a legal notice dated 05.11.2015 through their Advocate demanding their money back with 18% annual interest. They further averred that the Appellants did not reply to the legal notice. The Respondents again sent a reminder notice on 12.01.2016 to refund all the money but the Appellants did not revert to the reminder.
As per the Respondents/Complainants averments, the aforesaid acts, on the part of the Appellants/Opposite Parties, amounted to deficiency in service. When the grievance was not redressed, the Respondents filed a Complaint before the State Commission, U.T., Chandigarh with the following prayer :-
5.
"It is therefore respectfully prayed that this Complaint may kindly be allowed with cost and the Opposite Parties be directed to refund the amount deposited of Rs. 34,46,406/-(Thirty Four Lakhs Forty Six Thousand Four Hundred and Six Only) paid between September 2006 and March 2009 plus penalty as per clause 9 of the Buyer Agreement which is approx. 12 Lakh since June 2009 along with the compounded interest @ rate of 24% per annum, compensation of Rs. 11,00,000/- for mental agony and harassment from last 10 years along with litigation expenses and counsel Fees of Rs. 1,10,000/- and any other direction may kindly be passed which this Hon'ble Court deems fit in the interest of justice."
The Appellants/Opposite Parties resisted the Complaint in its written statement by stating that the State Commission is not vested with the territorial and pecuniary jurisdiction. It was further stated that under clause 39 of the Agreement all the disputes shall be referred to an Arbitrator. The Opposite Parties have not assured the Respondents/Appellants that the possession of the Plot will be handed over within 2 years.
6.
The State Commission partly allowed the Complaint by issuing following directions to the Opposite Parties/Appellants:
7.
" This Complaint is partly accepted and the Opposite Parties, jointly and severally, are directed to refund the amount of Rs.34,46,406/- to the Complainants, alongwith interest @12% p.a., from the respective dates of deposit onwards, within a period of 30 days, from the date of receipt of a certified copy of this Order, failing which, thereafter, the said amount of Rs.34,46,406/- shall carry 3% penal interest i.e. 15% p.a.(12%p.a. plus(+) 3% p.a.) from the date of passing of this Order, till realization.
However, it is made clear that if the Complainants have availed loan facility from any Bank/ Financial Institution, for making payment towards part price of the said plot, it will have the first charge of the amount payable, to the extent, the same is due to be paid by the Complainants."
Aggrieved by this Order passed by the State Commission, Appellants/Opposite Parties have filed First Appeal No. 517 of 2020 before this Commission with the following prayer :
8.
3
Set aside the impugned Order dated 18.12.2019 passed by the Hon'ble State Commission in C.C. No. 822 of 2016, in the First Appeal; and
a.
To pass such other and further Orders as may be deemed just and necessary in the facts and circumstances of the present case.
b. The Opposite Parties/Appellants raised following issues in their Appeal which reads as under:
The Complaint filed before the State Commission is grossly barred by time;a. The State Commission overlooked that the Respondents/Complainants are willfull defaulter in making payment as per agreed timelines.
b.
The rate of interest of 12% p.a. is in clear violation of the Judgments of the State Commission in DLF Homes Panchkula (P) Ltd. v. D.S. Dhanda, (2020) 16 SCC 318 which is of a project in the close vicinity of the Project in question and should have been applied, if at all. Moreover, the Judgement of GDA Vs Balbir Singh 2004-5-SCC-65 and 2009-175CC-199 clearly states that 12% p.a. cannot be a blanket rate to be awarded in each case and the same has to be determined from facts of each case after hearing the parties.
c.
The State Commission failed to consider the e-mail dated 22.05.2013, wherein the Appellants relocated the Plot of the Respondents. It overlooked the fact that upon the offer of relocation, the obligations of the Appellants under the Agreement stood fulfilled and the Respondents are duty bound to accept possession after making payments as per the terms of the Agreement.
d.
9.
We have heard the learned Counsel for both the Parties and perused the material available on record.
10.
The learned Counsel of the Respondents/Complainants stated that the Respondents have made the balance payment between 29.06.2007 to 16.03.2009. However, till date, the Appellants have neither given the possession of the Plot nor returned the money despite lapse of more than 14 years from the date of the execution of the Agreement. The learned Counsel further argued that though the relocation was offered in 2018, it cannot be imposed.
11.
The Objection of the Appellants/Opposite Parties that the Complaint filed in the State Commission is barred by limitation is devoid of merit. In this regard, attention is drawn to the Order of the Hon'ble Supreme Court in Meerut Development Authority Vs. Mukesh Kumar Gupta [IV (2012) CPJ 12] decided on 09.05.2012 wherein it was held that :
12.
"the failure to deliver possession of the Plot constitutes a recurrent/continuing cause of action."
The ground of the Appellants/Opposite Parties in their Appeal that they offered relocation of Plot vide e-mail dated 22.05.2013 and therefore the Respondents/Complainants are bound to accept the possession is rejected. Firstly, the relocation of the Plot was offered after more than 2 years of unexplained delay from the proposed date of possession. Secondly, it is the Respondents/Buyer discretion whether to accept/reject the relocated
13.
4
Plot. In this regard attention is drawn to the Order of this Commission in the case of
Emaar MGF Land Ltd. & Ors. Vs. Amit Puri- {(II 2015 CPJ 568 (NC)}, decided on 30.03.2015, Wherein this Commission has held as under:
"After the promised date of delivery, it is the discretion of the Complainant whether to accept the offer of possession, if any, or to seek refund of the amounts paid by him with some reasonable compensation and it is well within his right to seek for refund of the principal amount with interest and compensation."
We find that there is no doubt to the fact that there has been an unreasonable delay in handing over the possession of the Plot to the Respondents/Complainants as per 'the Agreement'. The Respondents cannot wait for an indefinite time as they have invested heavy amount with the intention to get the possession of the Plot on time. There are a number of Case Laws wherein the Hon'ble Supreme Court has decided favourably on the right of the buyers for getting refund of their money in case of undue and unreasonable delay by the Developer in giving possession in terms of the Agreement.
14.
Reliance is placed on the Judgment of the Hon'ble Supreme Court in Kolkata West International City Pvt. Ltd. Vs. Devasis Rudra, II (2019) CPJ 29 SC, decided on 25.03.2019 in which the Hon'ble Apex Court has observed as hereunder :
15.
".....It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period. A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund. In the circumstances, we are of the view that the orders passed by SCDRC and by the NCDRC for refund of moneys were justified."
The Hon'ble Supreme Court in the recent case of Ireo Grace Realtech Pvt. Ltd. Vs. Abhishek Khanna & Anr. in Civil Appeal No. 5785 of 2019 decided on 11.1.2021, has held as under:-
16.
"The Developer made an alternate offer of allotment of apartments in Phase 1 of the Project. The allottees are however not bound to accept because of the inordinate delay in completing the construction of the Towers where units were allotted to them. The Occupation Certificate is not available even as on date, which clearly amounts to deficiency of service. The allottees cannot be made to wait indefinitely for possession of the apartments allotted to them nor can they be bound to take the apartments in Phase 1 of the Project. The allottees have submitted that they have taken loans, and are paying high rates of interest to the tune of 7.9% etc. to the Banks.
5
Consequently, we hold that the allottees in Chart B are entitled to refund of the entire amount deposited by them".
We notice that there has been an unreasonable delay in development of the Plot. The Plot was booked by the Respondents/Complainants in the year 2006. Thereafter, an Agreement was signed on 20.06.2007. As per clause 8 of the Agreement, the possession of the Plot was to be given within 2 years and not later than 3 years from the date of signing of the Agreement. Thus, the possession of the Plot was to be given by 20.06.2009 or 20.06.2010 as per the Agreement. The Appellants/Builder has not given possession of the Plot to the Respondents even after lapse of 14 years from the date of execution of the Agreement and 11 years from the promised date of possession. Therefore, the Respondents are entitled for a fair and reasonable delay compensation apart from getting refund of the amount deposited.
17.
We notice that the delay compensation awarded by the State Commission is high, therefore, on the issue of what would constitute a reasonable rate of interest in the present time, attention is drawn to the Order of Hon'ble Supreme Court in the case of Ireo Grace Realtech Pvt. Ltd. Vs. Abhishek Khanna & Anr. in Civil Appeal No. 5785 of 2019, decided on 11.01.2021 while dealing with the question of awarding compensation for delay in handing over the possession has held as under:-
18.
"(i) We are of the view that allottees at Serial Nos.1 and 2 in Chart A are obligated to take possession of the apartments, since the construction was completed, and possession offered on 28.6.2019, after the issuance of Occupation Certificate on 31.5.2019.The Developer is however obligated to pay delay compensation for the period of delay which has occurred from 27.11.2018 till the date of offer of possession was made to the allottees."
In its Order, it further held that -
"We have considered the rival submissions made by both the parties. The Delay Compensation specified in the Apartment Buyer's Agreement of Rs. 7.5 per sq. ft. which translates to 0.9% to 1% p.a. on the amount deposited by the Apartment Buyer cannot be accepted as being adequate compensation for the delay in the construction of the project. At the same time, we cannot accept the claim of the Apartment Buyers for payment of compound interest @ 20% p.a., which has no nexus with the commercial realities of the prevailing market. We have also taken into consideration that in Subodh Pawar v. IREO Grace, this Court recorded the statement of the Counsel for the Developer that the amount would be refunded with Interest @ 10% p.a. A similar order was passed in the case of IREO v. Surendra Arora. However, the Order in these cases were passed prior to the out-break of the pandemic. We are cognizant of the prevailing market conditions as a result of Covid-19 Pandemic, which have greatly impacted the construction industry. 53 In these circumstances, it is necessary to balance the competing interest of both parties. We think it would be in the interests of justice and fair play that the amount deposited by the Apartment Buyers is refunded with Interest @ 9% S.I. per annum from 27.11.2018 till the date of payment of the entire amount."
The Hon'ble Supreme Court has taken similar view in M/s BPTP Limited and Another V. Sanjay Rastogi in Civil Appeal No. 1001-1002 of 2021 decided on 04.12.2021, Wherein it was
6
held as under:
" …..The appellant failed to deliver possession within the contractual period. There is no error in the finding on the basis of which a refund of consideration has been directed. However, in the alternative, it has been submitted Mr Siddharth Bhatnagar, learned senior counsel that the rate of interest may be suitably scaled down having regard to the earlier decisions of this Court including the decision in IREO Grace Realtech (P) Ltd. v. Abhishek Khanna, (2021) 3 SCC
241. Having regard to the rate of interest of which has been fixed in other cases such as the present, we reduce the interest from 10% to 9% per annum. The Appellant is, however directed to ensure that full payment in compliance with the Order of the NCDRC with interest at the rate of 9% per annum is paid over to the respondent on or before 15 July 2021. The Hon'ble Supreme Court has taken similar view in M/s Nexgen Infracon Pvt. Ltd. Vs Manish Kumar Sinha in Civil Appeal No. 62 of 2021 decided on 11.01.2021, wherein it was held as under:
"…. This take us to the next question whether the rate of interest awarded by the Commission be maintained or whether such rate is required to be scaled down. In keeping with the directions issued by this Court in the case of Prateek Infra projects, we scale down the interest from 12% & 14% as ordered by the Commission to 9% per annum. We also modify the direction restraining the appellant from deduction the tax at source. It is, therefore, directed that the amounts deposited by the respondents in respect of the apartment in question shall be refunded to them along with interest@9% per annum from the dates of respective deposits. The other direction issued by the Commission as regards of cost of litigation is maintained.
19. There are a numbers of Orders and Judgments of this Commission and Hon'ble Supreme Court where an interest rate of 9% has been awarded as delay compensation on amount deposited by buyer/purchasers. Thus, the interest rate of 9% is just and fair.
20. In view of the discussion above, we are of the considered view that the Order of the State Commission does not suffer from any illegality. We find that there is no merit in the Appeal as no question of law is involved. We, therefore, dismiss the Appeal by partly upholding the Order of the State Commission by modifying it to the extent that the Appellants/Opposite Parties pay delay compensation on the deposited amount @9% per annum simple interest instead of 12% failing which, the said amount of Rs.34,46,406/- shall carry 3% penal interest i.e. 12% per annum simple interest.
......................
DR. S.M. KANTIKAR
PRESIDING MEMBER
......................
BINOY KUMAR
MEMBER
7
Alert