Siddharth Constructions Co. v. India Tourism Development Corporation Ltd. .

Delhi High Court
Sep 14, 2021
Smart Summary (Beta)

Factual and Procedural Background

The petitioner filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 09.05.2020 issued by a Sole Arbitrator, a former judge of this Court. The dispute arose from an agreement dated 02.07.2012 between the petitioner and India Tourism Development Corporation Ltd. (ITDC) concerning construction works for a memorial in Punjab. ITDC invited tenders in February 2011, and the petitioner’s bid was accepted in November 2011. The petitioner was required to complete the works within twelve months from the date of the Letter of Intent or actual site handover, with a completion deadline of 19.12.2012.

The works were completed on 30.01.2018, after a delay of over five years. The petitioner claimed the delay was attributable to ITDC, while ITDC contended that only thirty-nine days of delay were the petitioner’s responsibility. Payments were made in tranches, with delays in clearing the final bill and certain deductions made by ITDC, including compensation for delay. The petitioner initiated arbitration by requesting an arbitrator with mutual consent, which ITDC did not agree to, instead appointing a Sole Arbitrator unilaterally.

The petitioner raised multiple claims including compensation for delay, refund of security deposit, and loss of profits, while ITDC raised counter-claims for expenses incurred due to delay. An interim award was granted in favor of the petitioner for refund of security deposit. The arbitral award partly allowed and partly denied the petitioner’s claims, notably disallowing claims for damages and loss of profit due to delay. The petitioner challenged the award before this Court.

Legal Issues Presented

  1. Whether the arbitral award contains inconsistent and self-contradictory findings amounting to patent illegality under Section 34 of the Arbitration and Conciliation Act, 1996.
  2. Whether the petitioner is entitled to damages for delay in completion of the works, including overhead costs and loss of profits.
  3. Whether the findings of the Arbitral Tribunal regarding responsibility for delay and entitlement to claims are legally sustainable.
  4. The scope and extent of judicial interference permissible under Section 34 of the Arbitration and Conciliation Act, 1996 in reviewing arbitral awards.

Arguments of the Parties

Petitioner's Arguments

  • The arbitral award is inconsistent and contains contradictory findings, particularly regarding delay attribution and claims for damages and loss of profit.
  • A letter from ITDC admitted at least 389 days of delay attributable to ITDC, which the Tribunal relied upon partially but failed to grant damages accordingly.
  • The Tribunal erred in rejecting overhead cost escalation calculated by the Hudson Formula despite the extensive delay in completion.
  • The Tribunal wrongly disallowed loss of profit claims by requiring proof of financial capacity, which was evidenced by tender qualification criteria.
  • The Tribunal’s findings violate public policy and amount to patent illegality as per precedents, including Union of India v Sanghu Chakra Hotels Private Limited.

Respondent's Arguments

The opinion does not contain a detailed account of the respondent’s legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union of India v. Sanghu Chakra Hotels Private Limited (2008 SCC Online Del 912) Mutually inconsistent and self-contradictory findings by arbitrators constitute patent illegality and violate public policy. Petitioner cited this case to argue that contradictory findings in the award should render it liable to be set aside.
Union Of India v. Om Construction Co. (2019 SCC OnLine Del 9037) Requirement that claimants prove actual loss or damage to succeed on claims for damages in arbitration. Cited to support the Tribunal’s approach that damages must be supported by proof and cannot be granted on a normative basis.
GTM Builders and Promoters Pvt. Ltd. v. Sneh Developers Pvt. Ltd. (2018 SCC OnLine Del 9653) Similar principle regarding proof of actual loss in claims for damages or loss of profit. Reinforced the Tribunal’s position on evidentiary requirements for claims.
Kailash Nath Associates v. DDA ((2015) 4 SCC 136) Clarification of the scope of patent illegality as a ground for setting aside arbitral awards. Applied to affirm that not every error of law amounts to patent illegality and that courts should not re-appreciate evidence.
Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation Ltd. (2021 SCC OnLine SC 695) Judicial restraint in interference with arbitral awards; definition and limits of patent illegality; public policy considerations under Section 34. Extensively relied upon to elucidate the limited grounds for interference with arbitral awards and to reject the petitioner’s challenge as beyond permissible scope.
Renusagar Power Co. Ltd. v. General Electric Co. Interpretation of fundamental policy of Indian law and its relevance to public policy in arbitration challenges. Referenced to clarify that contravention of statutes not linked to public policy or interest does not constitute grounds for setting aside awards.

Court's Reasoning and Analysis

The Court analyzed the arbitral award in light of the claims and counter-claims presented by the parties and the evidence on record. It found that the Arbitral Tribunal had substantially accepted the petitioner’s claims for refund of various deductions but rejected claims for additional amounts where evidence was lacking or contradictory. The Tribunal’s rejection of claims related to substitution of materials and crafting of bronze statues was upheld due to absence of supporting documentation or acceptance of reduced payments by the petitioner.

Regarding delay, the Tribunal found that the petitioner was entitled to an extension of time but not to damages for overheads or loss of profits. The Tribunal’s findings that both parties bore some responsibility for delay and that the petitioner failed to prove actual loss or additional costs were accepted by the Court. The petitioner’s argument for normative damages was rejected as there is no legal principle mandating damages on such a basis without proof.

The Court emphasized the principles laid down in Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation Ltd., reiterating the limited grounds for judicial interference under Section 34 and the narrow scope of patent illegality. It held that the petitioner’s challenge did not fall within these grounds, as the Tribunal’s conclusions were possible views based on evidence and contract interpretation.

Holding and Implications

The petition is dismissed.

The Court upheld the arbitral award except to the extent that the petitioner’s claims for damages and loss of profits were disallowed. The decision confirms that courts must exercise restraint in interfering with arbitral awards and that mere errors of law or fact do not constitute patent illegality. The ruling reinforces the principle that claims for damages require proof of actual loss and that normative or speculative damages are not permissible grounds for setting aside awards. No new precedent was established beyond the application of existing principles on the scope of judicial review under Section 34 of the Arbitration and Conciliation Act, 1996.

Show all summary ...

VIBHU BAKHRU, J

1. The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the A&C Act) impugning an arbitral award dated 09.05.2020 (hereinafter the impugned award) delivered by the Arbitral Tribunal constituted by a former judge of this Court as the Sole Arbitrator.

2. The impugned award has been rendered in the context of disputes that have arisen between the parties in relation to an agreement dated 02.07.2012 (hereafter the Agreement). O.M.P. (COMM) 184/2021 Page 2 of 15

3. By the impugned award, the Arbitral Tribunal has partly denied the claims preferred by the petitioner. The Arbitral Tribunal has denied that petitioners claim for damages and loss of profit on account of delay in completion of works. Factual Context

4. India Tourism Development Corporation Ltd. (hereinafter referred to as ITDC) invited tenders on 09.02.2011 for Construction of Memorial of Smt. Vidyavati Ji Mother of Great Martyr Shaheed Bhagat Singh Ji at Village Moranwali, District Hoshiarpur, Punjab (hereinafter referred to as the Memorial).

5. The petitioner tendered its bid to execute the works on 11.04.2011, pursuant to the aforementioned notice inviting tenders. By a letter dated 23.11.2011, ITDC accepted the petitioners bid to execute the works at a price of 3,67,73,933.74/-.

6. Thereafter, ITDC issued a detailed Work Order Work Order no. ITDC Engg/DGM/Moranvali/2012 dated 20.12.2011 in favour of the petitioner. On 02.07.2012, the parties entered into the Agreement. In terms of the Agreement, the petitioner was obliged to complete the works within a prescribed period of 12 (twelve) months to be reckoned from the seventh day of issue of the Letter of Intent or, the date of actual handing over the site, whichever was later. Therefore, the work was to be completed by 19.12.2012. O.M.P. (COMM) 184/2021 Page 3 of 15

7. However, the works could not be completed within the stipulated time. The same were completed on 30.01.2018; that is, after a delay of five years, one month and eleven days. The petitioner claims that the delay in completion of works is for reasons attributable to ITDC.

8. Whilst the petitioner claimed that the delays were justified, ITDC asserted that the petitioner was liable for a delay of thirty-nine days.

9. The RA Bills (Running Account Bills) were cleared by ITDC. However, there was a considerable delay in clearance of the Final Bill. The same was cleared in two tranches. The first tranche of 28 Lacs was paid on 20.11.2018, that is, after a delay of ten months. The second tranche of 10,82,249/- was paid on 02.02.2019, that is, more than one year after completion of the work. In addition to this, ITDC had also deducted certain amounts from the payments due to the petitioner including compensation of 4 lacs on account of delay of thirty-nine days in completion of the works.

10. On 14.03.2019, the petitioner sent a notice and requested for appointment of an arbitrator with mutual consent. It asserted that the appointment procedure mentioned in Clause no. 48 of the Agreement was contrary to Section 12(5) of the A&C Act and, proposed the name of Sh. Amarjit Singh, (Retd.) Chief Engineer, Mohali for being appointed as the Arbitrator with mutual consent.

11. However, ITDC unilaterally appointed Justice (Retired) S.P. Garg, a former judge of this Court as the Sole Arbitrator. O.M.P. (COMM) 184/2021 Page 4 of 15

12. The petitioner filed its Statement of Claims raising several claims. A tabular statement summarizing the claims made, is set out below:- Claim No. 1(a) Compensation for delay which was deducted by ITDC- 4,00,000/- Claim No. 1(b) Refund of security deposit- 5,00,000/- Claim No. 1(c) Compensation for the deduction towards water and electricity charges- 1,48,957/- Claim No. 1(d) Compensation for the deduction from the final bill on account of M/S Aditya Associates- 1,05,891/- Claim No. 1(e) Compensation for the deduction on account of Goods and Service Tax (GST)- 3,74,448/- Claim No. 1(f) On account of granite stone flooring work, paid as Kota Stone Work- 4,80,000/- Claim No. 1(g) On account of non-insurance-96,020/- Claim No.1(h) On account of Non-Insurance Workmen Compensation Policy (WCP)- 15,404/- Claim No. 1(i) On account of crafting of bronze statutes- 10,00,000/- Claim No. 2 On account of losses and damage- 93,27,876/- Claim No. 3 On account of loss of profit- 2,80,35,000/- Claim No.4 On account of 10% of the reduced work- 6,60,801/- Claim No.5 On account of balance security with interest- 5,00,000/-

13. ITDC raised counter-claims. The same are summarized as under:- Counter Claim No. 1 Expenses incurred on security guards- 8,29,595/- O.M.P. (COMM) 184/2021 Page 5 of 15 Counter Claim No. 2 On account of salary amount paid to the engineers posted in Punjab-54,08,954/- Counter Claim No. 3 On account of extra salaries paid by ITDC to their other staff at Head Quarters- 14,85,000/- Counter Claim No. 4 On account of miscellaneous charges incurred during the delayed period-10,53,201/- Counter Claim No.5 On account of business loss- 1,73,93,099/-

14. On 11.11.2019, the Arbitral Tribunal made an interim award in favour of the petitioner for refunding the sum of 5 lacs paid by the petitioner to ITDC as Security Deposit.

15. The Arbitral Tribunal rendered the impugned award on 09.05.2020. The interim award passed on 11.11.2019 for return of 5 lacs towards Security Deposit forms a part of the impugned award.

16. The Arbitral Tribunal also awarded an aggregate sum of 11,40,720 under Claim nos. 1 (a), (c), (d), (e), (g), (h) with interest at the rate of 9% per annum with effect from 09.05.2019 till the date of the award. Further, the petitioner was also awarded future interest at the rate of 9% per annum from the date of the award till the date of payment, in the event, the same was not paid within a period of sixty days.

17. Aggrieved by the impugned award to the extent that it disallowed its claims, the petitioner has filed the present petition. O.M.P. (COMM) 184/2021 Page 6 of 15 Submissions

18. Mr. Kaustubh Anshuraj learned counsel appearing for the petitioner, assailed the impugned award primarily on the grounds that the findings of the Arbitral Tribunal were inconsistent. He submitted that by a letter dated 24.08.2018, which was an admitted document, ITDC had accepted that at least 389 days delay was attributable to ITDC. He pointed out that the Arbitral Tribunal had relied on the said document and allowed the petitioners Claim no. 1(a). But it had disregarded the same and disallowed the petitioners claim for damages and loss of profit on account delay in completion of the contract (Claim nos. 2 and 3).

19. Mr Anshuraj submitted that the Arbitral Tribunal had returned contradicting findings. Whilst it found that only three days delay was attributable to the petitioner; it subsequently proceeded to also hold that 50-50 delay is attributable to both the parties. Further, the Arbitral Tribunal noted that the petitioner had, by its letter dated 08.11.2013, put ITDC to notice that it would claim compensation for delay in completion of the works. However, in contradiction with this finding, the Arbitral Tribunal held that the petitioner had not put ITDC to notice regarding the quantum of compensation or the period for which such compensation shall be claimed. He referred to the decision of this Court in Union of India v Sanghu Chakra Hotels Private Limited (Delhi): 2008 SCC Online Del 912, in support of his contention that mutually O.M.P. (COMM) 184/2021 Page 7 of 15 inconsistent and self-contradictory findings by the arbitrator is contrary to the public policy of India and suffers from patent illegality.

20. Next, he submitted that the Arbitral Tribunal had erred in rejecting the petitioners claim for overheads cost escalation as computed on the basis of the Hudson Formula. He submitted that the work was to be completed within twelve months but was completed after a delay of five years, one month and eleven days and thus, the petitioner was entitled to overhead charges of 5% of the total contract value (as agreed), multiplied by sixty-one months.

21. He submitted that the Arbitral Tribunal had refused to grant loss of profit by holding that the petitioner did not produce any evidence that it had the financial capacity to earn 2,80,35,000 as profit by undertaking the project beyond the extended period. This was patently erroneous as only Class-I contractors were eligible to bid for the project. The pre-qualification cum tender notice showed the work to be estimated at 3,08,64,031.79/- and, the criteria for being eligible to apply for the tender included the average annual turnover of the firm during the last three years to be at least 30% of the estimated work. The tenderers were also required to submit proof of completing similar work in the last seven years successfully as well as the latest solvency certificate. Reasons and Conclusion

22. The petitioners claim for refund of the deductions made by ITDC on various grounds (Claim No.1) was substantially accepted by O.M.P. (COMM) 184/2021 Page 8 of 15 the Arbitral Tribunal; the Arbitral Tribunal has entered an award of an aggregate amount of 11,40,720/, in favour of the petitioner. The additional amount claimed by the petitioner for using Sadar Ali Stone instead of Kota Stone [Claim No.1(f)] and its claim on account of crafting a bronze statute [Claim No.1(i)] was rejected by the Arbitral Tribunal.

23. The specifications under the Agreement required the petitioner to provide Kota floor stoning in front of the cafeteria. The petitioner had paid for the same. It was petitioners case that it was directed to affix Sadar Ali Granite as flooring instead of Kota Stone. However, the Arbitral Tribunal found that there was no document to establish that the petitioner had been directed to substitute Kota Stone with Sadar Ali Granite as flooring in front of the cafeteria. As opposed to the same, ITDC had placed several communications on record reminding the petitioner to lay only Kota stone flooring. The decision of the Arbitral Tribunal to reject the petitioners claim is thus, based on material and evidence on record and therefore, warrants no interference in these proceedings.

24. The petitioners claim for a sum of 10,00,000/- on account of crafting a bronze statue was rejected by the Arbitral Tribunal. The Arbitral Tribunal found that Item no. 123 of the Bill of Quantities, required the petitioner to fix a bronze statue weighing 2200 Kgs at a cost of 28,00,000/-. It was not disputed that the petitioner had fixed a statute weighing only 1060 Kgs, instead of 2200 Kgs, against the said BoQ item. The Arbitral Tribunal found that by a letter dated 01.07.2014, O.M.P. (COMM) 184/2021 Page 9 of 15 the petitioner had requested that statute of a reduced weight be permitted to be fixed. The same was approved. The pro-rata payment of 13,49,088/- was also released to the petitioner. The Arbitral Tribunal found, after evaluating the material on record, that the petitioner had also accepted the reduced payment. Therefore, the Arbitral Tribunal held that the petitioner was not entitled to the said claim. The said decision cannot be faulted and, in any event, cannot be assailed on the grounds as available under Section 34 of the A&C Act.

25. The petitioners grievance against the impugned award is mainly on account of the decision of the Arbitral Tribunal to deny its claim for damages/loss of overheads (Claim No.2) and loss of profits (Claim no.3) on account of delay in completion of the works. The petitioner had claimed that the delay in completion of the works were attributable to ITDC, which constituted a breach of the Agreement and the petitioner was entitled to damages on account of the same. The Arbitral Tribunal had examined the material on record and found that whilst the petitioner was entitled to extension of time for completion of the contract, it was not entitled to damages on account of overheads/damages (Claim No.2) and loss of profits (Claim No.3) on account of delay in completion of the works.

26. The Arbitral Tribunal had accepted the petitioners claim for refund of deduction of 4,00,000/- on account of delay in completion of the contract [Claim No.1(a)] as the Arbitral Tribunal found that the completion of the contract was delayed for various reasons for which the claimant [the petitioner] was not at fault alone. The Tribunal also O.M.P. (COMM) 184/2021 Page 10 of 15 found that ITDC had not given any prior notice to the petitioner for deducting the sum of 4,00,000/- on account of delay of thirty-nine days in completion of the contract.

27. In addition, the Arbitral Tribunal found that there was no material on record to establish that ITDC had suffered any loss on account of alleged delay of thirty-nine days in completion of the contract in question. In view of its aforesaid findings, the Arbitral Tribunal found that the deduction of 4,00,000/- made by ITDC from the amounts payable to the petitioner, on account of non-allowable delay of thirty- nine days was unjustified.

28. It was contended on behalf of the petitioner that in view of the findings of the Arbitral Tribunal in respect of Claim no.1(a), the petitioner was also entitled for claim of damages/compensation for overheads during the extended period of the contract as well as loss of profits for the said period. It was also contended that the findings of the Arbitral Tribunal that both the parties were in part responsible for the delay and there was slow progress of the work, is inconsistent with the Arbitral Tribunals findings in respect of Claim No.1(a).

29. The aforesaid contention is unmerited. The finding that the petitioner was entitled to extension of time for completion of delay on account of reasons not attributable to it does not mean that the Arbitral Tribunal had found ITDC to be responsible for delay in completion of the works and in breach of the Agreement. The Arbitral Tribunal had examined the hindrance register and had found that the hindrances that O.M.P. (COMM) 184/2021 Page 11 of 15 resulted in delay justified grant of extension of time for completion of the contract. But that did not mean that ITDC was solely responsible for such delays. ITDC had never accepted or admitted that the entire delay was attributable to it.

30. It is also petitioners claim that the delay caused due to various reasons which included delay on account of elections, obstruction by villagers, water logging etc. could not be by any stretch be attributed to ITDC.

31. The Arbitral Tribunal found that the petitioner had not produced evidence of suffering or incurring any loss on account of cost of tools, plants etc. It had also produced no material to establish that it had paid any additional cost for electricity or water.

32. It is the petitioners contention that its claim for damages and overhead charges (Claim no. 2) was liable to be allowed on normative basis as 5% of the contract value was attributable to overhead charges under the Agreement. The petitioner contends that the impugned award is vitiated by patent illegality as the Arbitral Tribunal has not accepted the same. This contention is, plainly, unmerited. The Arbitral Tribunals decision to not accept the petitioners claim as the petitioner had failed to produce proof of actual damages, cannot be faulted. There is no principle of law that mandates that damages must be allowed on normative basis in all cases. The question as to whether the petitioner has sufficiently established that it had incurred any loss or damage is a question of fact and the Arbitral Tribunals decision in this regard is O.M.P. (COMM) 184/2021 Page 12 of 15 final. The petitioners claim for loss of profit was also disallowed on similar grounds. The Arbitral Tribunal had referred to the decisions of this Court in Union Of India v. Om Construction Co.: 2019 SCC OnLine Del 9037 and GTM Builders and Promoters Pvt. Ltd. v. Sneh Developers Pvt. Ltd.: 2018 SCC OnLine Del 9653 and, the decision of the Supreme Court in Kailash Nath Associates v. DDA: (2015) 4 SCC 136 and had held that the petitioner was required to prove actual proof of loss of damages. The said view cannot by any stretch be stated to be patently erroneous or one that vitiates the impugned award on the ground of patent illegality.

33. The following observations made by the Supreme Court in its recent decision in Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation Ltd.: 2021 SCC OnLine SC 695 are relevant and set out below:

24. This Court has in several other judgments interpreted Section 34 of the 1996 Act to stress on the restraint to be shown by courts while examining the validity of the arbitral awards. The limited grounds available to courts for annulment of arbitral awards are well known to legally trained minds. However, the difficulty arises in applying the well-established principles for interference to the facts of each case that come up before the courts. There is a disturbing tendency of courts setting aside arbitral awards, after dissecting and reassessing factual aspects of the cases to come to a conclusion that the award needs intervention and thereafter, dubbing the award to be vitiated by either perversity or patent illegality, apart from the other grounds available for annulment of the award. This approach would lead to corrosion of the object of the 1996 Act and the endeavours made to preserve this object, O.M.P. (COMM) 184/2021 Page 13 of 15 which is minimal judicial interference with arbitral awards. That apart, several judicial pronouncements of this Court would become a dead letter if arbitral awards are set aside by categorising them as perverse or patently illegal without appreciating the contours of the said expressions.

25. Patent illegality should be illegality which goes to the root of the matter. In other words, every error of law committed by the Arbitral Tribunal would not fall within the expression patent illegality. Likewise, erroneous application of law cannot be categorised as patent illegality. In addition, contravention of law not linked to public policy or public interest is beyond the scope of the expression patent illegality. What is prohibited is for courts to re-appreciate evidence to conclude that the award suffers from patent illegality appearing on the face of the award, as courts do not sit in appeal against the arbitral award. The permissible grounds for interference with a domestic award under Section 34(2-A) on the ground of patent illegality is when the arbitrator takes a view which is not even a possible one, or interprets a clause in the contract in such a manner which no fair- minded or reasonable person would, or if the arbitrator commits an error of jurisdiction by wandering outside the contract and dealing with matters not allotted to them. An arbitral award stating no reasons for its findings would make itself susceptible to challenge on this account. The conclusions of the arbitrator which are based on no evidence or have been arrived at by ignoring vital evidence are perverse and can be set aside on the ground of patent illegality. Also, consideration of documents which are not supplied to the other party is a facet of perversity falling within the expression patent illegality.

26. Section 34 (2) (b) refers to the other grounds on which a court can set aside an arbitral award. If a dispute which is not capable of settlement by arbitration is the subject- matter of the award or if the award is in conflict with O.M.P. (COMM) 184/2021 Page 14 of 15 public policy of India, the award is liable to be set aside. Explanation (1), amended by the 2015 Amendment Act, clarified the expression public policy of India and its connotations for the purposes of reviewing arbitral awards. It has been made clear that an award would be in conflict with public policy of India only when it is induced or affected by fraud or corruption or is in violation of Section 75 or Section 81 of the 1996 Act, if it is in contravention with the fundamental policy of Indian law or if it is in conflict with the most basic notions of morality or justice. In Ssangyong (supra), this Court held that the meaning of the expression fundamental policy of Indian law would be in accordance with the understanding of this Court in Renusagar Power Co. Ltd.

v. General Electric Co. In Renusagar (supra), this Court observed that violation of the Foreign Exchange Regulation Act, 1973, a statute enacted for the national economic interest, and disregarding the superior courts in India would be antithetical to the fundamental policy of Indian law. Contravention of a statute not linked to public policy or public interest cannot be a ground to set at naught an arbitral award as being discordant with the fundamental policy of Indian law and neither can it be brought within the confines of patent illegality as discussed above. In other words, contravention of a statute only if it is linked to public policy or public interest is cause for setting aside the award as being at odds with the fundamental policy of Indian law. If an arbitral award shocks the conscience of the court, it can be set aside as being in conflict with the most basic notions of justice. The ground of morality in this context has been interpreted by this Court to encompass awards involving elements of sexual morality, such as prostitution, or awards seeking to validate agreements which are not illegal but would not be enforced given the prevailing mores of the day.

27. In light of the principles elucidated herein for interference with an arbitral award by a court in exercise O.M.P. (COMM) 184/2021 Page 15 of 15 of its jurisdiction under Section 34 of the 1996 Act, we proceed to consider the questions that arise in these Appeals as to whether the Division Bench of the High Court was right in setting aside the award of the Arbitral Tribunal dated 11.05.2017.

34. The challenge laid by the petitioner to the impugned award is, thus, outside the scope of the grounds on which challenge to an arbitral award is permissible under Section 34(2) or 34(2A) of the A&C Act.

35. The petition is unmerited and is, accordingly, dismissed. VIBHU BAKHRU, J SEPTEMBER 14, 2021