Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Power Grid Corporati... v. Madhya Pradesh Power...

Central Electricity Regulatory Commission
Feb 15, 2021
Smart Summary (Beta)

Factual and Procedural Background

The petition was filed by Power Grid Corporation of India Limited, a deemed transmission licensee, seeking truing up of tariff for the period from the Commercial Operation Date (COD) to 31.3.2019 under the 2014 Tariff Regulations and determination of tariff from 1.4.2019 to 31.3.2024 under the 2019 Tariff Regulations. The tariff pertains to the 400 kV D/C Kakrapar APP-Navsari Transmission Line and the 400 kV D/C Kakrapar APP-Vapi Transmission Line along with associated bays and substations related to Kakrapar Atomic Power Project Units 3 & 4 in the Western Region.

The Investment Approval for the transmission system was accorded in February-March 2014 with an estimated cost of Rs. 37871 lakh. The assets were scheduled for commercial operation on 26.10.2016 but were commissioned on 29.6.2017 after a delay of over eight months, which was condoned. The Commission had earlier approved tariff for the period from COD to 31.3.2019 vide order dated 3.10.2018 in Petition No. 118/TT/2017.

The respondents are distribution licensees and power departments in the Western Region who procure transmission services from the Petitioner. The Petitioner served the petition on respondents and published notice under Section 64 of the Electricity Act, 2003. Madhya Pradesh Power Management Company Limited (MPPMCL) filed a reply raising issues on grossing up of Return on Equity (RoE) and variation in capital cost for the 2014-19 period. The Petitioner filed rejoinder. The matter was heard via video conference on 28.7.2020 and the order was reserved.

Legal Issues Presented

  1. Whether the trued-up tariff for the 2014-19 period and the tariff for the 2019-24 period for the transmission assets should be approved under the respective Tariff Regulations.
  2. Whether the additional capital expenditure (ACE) claimed for both tariff periods is admissible.
  3. Whether the Petitioner can recover shortfall or refund excess Annual Fixed Charges on account of changes in applicable tax rates without separate application.
  4. Whether the Petitioner is entitled to recover filing fees, publication expenses, licensee fees, RLDC fees, and charges separately from beneficiaries.
  5. Whether the Petitioner can claim security expenses and capital spares as per actuals and provisions of the Tariff Regulations.
  6. The appropriate treatment of depreciation, interest on loan, RoE including grossing up for taxes, operation and maintenance expenses, and interest on working capital for the transmission assets.

Arguments of the Parties

Petitioner's Arguments

  • Petitioner sought approval for trued-up tariff for 2014-19 and tariff determination for 2019-24 as per respective Tariff Regulations.
  • Claimed additional capital expenditure within original scope and cut-off dates.
  • Requested permission to recover shortfall/refund excess Annual Fixed Charges due to tax rate changes directly without separate application.
  • Claimed reimbursement of petition filing fees, publication expenses, licensee fees, RLDC fees, and charges separately from beneficiaries.
  • Petitioner asserted that MAT tax rates are applicable and claimed RoE grossed up accordingly.
  • Requested allowance for capital spares at end of tariff block as per actuals.
  • Petitioner sought to file a separate petition for overall security expenses and consequential interest on working capital.
  • Claimed separate O&M expenses for PLCC communication system equipment @2% of project cost.

Respondents' Arguments (MPPMCL)

  • Raised issues regarding grossing up of RoE and variation in capital cost for 2014-19 period.
  • Submitted that capital cost allowed in earlier order should be considered rather than actual capital cost claimed by Petitioner.
  • Contended that Petitioner did not place assessment orders for certain years to support claimed tax rates.
  • Suggested that Initial Spares should be limited as per previously approved norms.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Order dated 3.10.2018 in Petition No. 118/TT/2017 Approval of tariff for transmission assets for 2014-19 period; capital cost and IDC disallowances; norms for Initial Spares and O&M expenses. Used as baseline for truing up capital cost, depreciation, IDC, Initial Spares, O&M expenses, and Annual Fixed Charges for the 2014-19 period.
Order dated 9.5.2020 in Petition No. 19/TT/2020 Restriction on apportionment of capital expenditure towards IT Equipment during truing up; depreciation rates for IT Equipment. Applied to disallow Petitioner's claim for apportionment of capital expenditure to IT Equipment and allowed depreciation @5.28% for IT equipment as part of sub-station for 2014-19 period.
Order dated 2.2.2021 in Petition No. 312/TT/2020 Confirmation of submission of assessment orders and income tax returns for effective tax rate determination. Considered to address MPPMCL's concerns about tax documentation and supported acceptance of effective tax rates based on submitted documents.
Order dated 27.4.2020 in Petition No. 274/TT/2019 Effective tax rate for grossing up RoE based on notified MAT rates under Income Tax Act, 1961. MAT rates notified therein were adopted for grossing up RoE for truing up of 2014-19 tariff period.
Order dated 24.1.2021 in Petition No. 126/TT/2020 Clarification on O&M expenses for PLCC communication system equipment; PLCC considered part of sub-station for O&M norms. Applied to reject Petitioner's claim for separate O&M expenses for PLCC equipment under 2019 Tariff Regulations.

Court's Reasoning and Analysis

The Court systematically analyzed the Petitioner's claims in light of the applicable Tariff Regulations of 2014 and 2019, and prior Commission orders. For the 2014-19 period, the Court applied the principles of prudence check to the capital cost, IDC, Initial Spares, additional capital expenditure, depreciation, interest on loan, RoE, O&M expenses, and interest on working capital. It noted the delay in commissioning was condoned and accepted the capital cost approved earlier, disallowing excess Initial Spares claimed without adequate justification.

Regarding depreciation, the Court followed precedent disallowing apportionment of capital expenditure towards IT Equipment at truing up stage and applied a depreciation rate of 5.28% for IT Equipment included in sub-station assets. The Court accepted the weighted average rate of depreciation and allowed depreciation accordingly.

For RoE, the Court accepted the MAT tax regime applicable to the Petitioner and allowed grossing up of RoE based on notified MAT rates, relying on submitted assessment orders and income tax returns to satisfy concerns about documentation.

O&M expenses were allowed as per normative rates specified in the Tariff Regulations. The Court rejected the Petitioner's claim for separate O&M expenses for PLCC equipment, holding it is part of the sub-station and thus no double allowance is warranted.

For the 2019-24 period, the Court considered the Petitioner’s claimed capital cost as opening capital cost, allowed additional capital expenditure within the original scope and cut-off date, and applied the debt-equity ratio as per the 2019 Regulations. It computed depreciation using weighted average rates, considered interest on loan based on weighted average interest rates, and allowed RoE grossed up with MAT rates applicable for the period.

The Court accepted O&M expenses as per the 2019 Tariff Regulations norms, excluding separate O&M expenses for PLCC. Interest on working capital was approved based on SBI MCLR plus 350 basis points, consistent with the Regulations.

Regarding security expenses, the Court noted that the Petitioner had not claimed them in the instant petition and directed that such expenses be claimed in a consolidated petition already filed (Petition No. 260/MP/2020).

The Court found the Petitioner's prayer to recover filing fees, publication expenses, licensee fees, and RLDC fees from beneficiaries consistent with the 2019 Tariff Regulations and allowed such recovery.

The Court deemed the Petitioner’s claim for GST recovery premature as GST is not currently levied on transmission services but acknowledged the Petitioner may bill GST separately if it is imposed in future.

Holding and Implications

The Court allowed the petition with modifications and clarifications as per the analysis. The trued-up Annual Fixed Charges for the 2014-19 tariff period and the Annual Fixed Charges for the 2019-24 tariff period were approved as detailed in the order.

The Petitioner was permitted to recover filing fees, publication expenses, licensee fees, and RLDC fees separately from beneficiaries. The claim for separate O&M expenses for PLCC equipment was rejected. Security expenses are to be claimed separately in a consolidated petition.

The decision directly affects the tariff determination and recovery mechanism between the Petitioner and beneficiaries but does not establish any new legal precedent beyond application of existing Tariff Regulations and prior orders.

Show all summary ...

1. The instant petition has been filed by Power Grid Corporation of India Limited (hereinafter referred to as “the Petitioner”), a deemed transmission licensee, for truing up of tariff from COD to 31.3.2019 under Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (hereinafter referred to as “the 2014 Tariff Regulations”) and for determination of tariff for the period from 1.4.2019 to 31.3.2024 under Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 (hereinafter referred to as “the 2019 Tariff Regulations”) in respect of 400 kV D/C Kakrapar APP-Navsari Transmission Line along with associated bays at Navsari GIS and 400 kV D/C Kakrapar APP-Vapi Transmission Line along with associated bays at Vapi Sub-station under the transmission system associated with Kakrapar Atomic Power Project 3 & 4 in the Western Region (hereinafter referred to as “the transmission system”).

2. The Petitioner has made the following prayers:

“1) Allow the add cap for 2014-19 and 2019-24 tariff block as claimed as per Para 5 and 7 above.

2) Approve the trued up Transmission Tariff for 2014-19 block and transmission tariff for 2019-24 block for the assets covered under this petition, as per para 6 and 7 above.

3) Allow the petitioner to recover the shortfall or refund the excess Annual Fixed Charges, on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before Hon'ble Commission as provided in Tariff Regulation 2014 and Tariff regulations 2019 as per para 5 and 6 above for respective block.

4) Approve the reimbursement of expenditure by the beneficiaries towards petition filing fee, and expenditure on publishing of notices in newspapers in terms of Regulation 70(1) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019, and other expenditure (if any) in relation to the filing of petition.

5) Allow the petitioner to bill and recover Licensee fee and RLDC fees and charges, separately from the beneficiaries in terms of Regulation 70(3) and (4) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019.

6) Allow the petitioner to bill and adjust impact on Interest on Loan due to change in Interest rate on account of floating rate of interest applicable during 2019-24 period, if any, from the beneficiaries.

7) Allow the petitioner to file a separate petition before Hon'ble Commission for claiming the overall security expenses and consequential IOWC on that security expenses as mentioned at para 6.6 above.

8) Allow the petitioner to claim the capital spares at the end of tariff block as per actual.

9) Allow the Petitioner to bill and recover GST on Transmission Charges separately from the beneficiaries, if GST on transmission is withdrawn from negative list at any time in future. Further, any taxes including GST and duties including cess etc. imposed by any statutory/Govt./municipal authorities shall be allowed to be recovered from the beneficiaries.

and pass such other relief as Hon'ble Commission deems fit and appropriate under the circumstances of the case and in the interest of justice.”

Background

3. The brief facts of the case are as under:

a. The Investment Approval (IA) for the transmission system was accorded by the Board of Directors of the Petitioner Company on 26.2.2014 vide Memorandum No. C/CP/Investment/KAPP 3 & 4 dated 4.3.2014 with an estimated cost of Rs. 37871 lakh including Interest During Construction (IDC) of Rs. 2425 lakh based on December, 2013 price level. The scope of work covered under the transmission system associated with the transmission system is as follows:

Transmission line

i. Kakrapar APP-Navsari 400 kV D/C line

ii. Kakrapar APP-Vapi 400 kV D/C line

Sub-stations:

i. Extension of 400/220 kV Navsari GIS Sub-station

ii. Extension of 400/220 kV Vapi Sub-station

b. The transmission assets were scheduled to be put into commercial operation on 26.10.2016. However, they were put into commercial operation on 29.6.2017 after a time over-run of 8 months and 3 days. The time over-run was condoned. The Commission vide order dated 3.10.2018 in Petition No. 118/TT/2017 approved the tariff of the transmission assets for the period from COD to 31.3.2019.

c. As per agreement signed between the Petitioner and NPCIL dated 13.12.2004, Kakrapar Atomic Power Plant (KAPP-3&4; 2X700 MW) was scheduled to be implemented by NPCIL and the components of associated transmission system (ATS) for KAPP-3&4 were to be implemented by the Petitioner. NPCIL vide its letter dated 10.5.2016 intimated the Petitioner that KAPP-3 is scheduled to be put into commercial operation by November, 2017 and KAPP-4 thereafter. As per 41 SCM (Standing Committee Meeting) held on 21.12.2016, it was agreed that charging of Vapi-Kakrapar (KAPP)-Navsari 400 kV D/C line (using Kakrapar generation switchyard) could be taken up by the Petitioner after COD of the lines and switchyard bays at Kakrapar. Accordingly, as a contingency arrangement, the Petitioner charged the Vapi-Kakrapar (KAPP)-Navsari 400 kV D/C line (using Kakrapar generation switchyard).

d. The Petitioner has claimed the trued-up tariff for the transmission asset for the 2014-19 period as under:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 Annual Fixed Charge (AFC)approved vide order dated 3.10.2018 in Petition No. 118/TT/2017 4087.40 5622.86 AFC claimed by the Petitioner in the instant petition 4085.01 5599.01

4. The respondents are distribution licensees and power departments, which are procuring transmission service from the Petitioner, mainly beneficiaries of the Western Region.

5. The Petitioner has served the petition on the Respondents and notice of this petition has been published in newspapers in accordance with Section 64 of the Electricity Act, 2003. No comments/objections have been received from the general public in response to the aforesaid notice published in the newspapers by the Petitioner. Madhya Pradesh Power Management Company Limited (MPPMCL), Respondent No. 1, has filed its reply vide affidavit dated 13.2.2020 and has raised issues of grossing up of RoE and variation in capital cost for the 2014-19 tariff period. The Petitioner, vide affidavit dated 18.5.2020, has filed rejoinder to the reply of MPPMCL. The issues raised by MPPMCL and the clarifications given by the Petitioner are considered in the relevant portions of this order.

6. This order is issued considering the submissions made by the Petitioner in the petition dated 6.11.2019, reply of MPPMCL dated 13.2.2020 and Petitioner's affidavits dated 11.5.2020, 18.5.2020 and 7.8.2020.

7. The hearing in this matter was held on 28.7.2020 through video conference and the order was reserved. Having heard the representatives of the Petitioner and perused the material on record, we proceed to dispose of the petition.

Truing Up of Annual Fixed Charges of the 2014-19 Period

8. The details of the trued-up transmission charges claimed by the Petitioner in respect of the transmission asset is as under:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 Depreciation 1157.62 1623.52 Interest on Loan 1213.95 1582.23 Return on Equity 1291.32 1816.11 Interest on Working Capital 95.39 130.70 O&M Expenses 326.73 446.45 Total 4085.01 5599.01

9. The details of the trued-up Interest on Working Capital (IWC) claimed by the Petitioner in respect of the transmission asset is as follows:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 O&M Expenses 36.01 37.20 Maintenance Spares 64.81 66.97 Receivables 900.38 933.17 Total Working Capital 1001.20 1037.34 Rate of Interest (%) 12.60 12.60 Interest on Working Capital 126.15 130.70 Interest on Working Capital (pro-rata) 95.39 130.70

Capital Cost as on the date of commercial operation

10. The capital cost of the transmission asset has been calculated in accordance with Regulation 9(2) of the 2014 Tariff Regulations.

11. The Commission vide order dated 3.10.2018 in Petition No. 118/TT/2017 had approved the capital cost as under:

(Rs. in lakh)

Capital Cost claimed as on COD (A) IDC disallowed as on COD due to computational difference (B) Undischarged IDC (C) Excess Initial Spares disallowed (D) Capital Cost allowed as on COD (E) = (A-B-C-D) 29811.92 23.66 1738.33 17.81 28032.12

12. MPPMCL submitted that the Commission vide its order dated 3.10.2018 in Petition No. 118/TT/2017 for the tariff period 2014-19 approved the capital cost as on COD as Rs. 28032.12 lakh restricting IDC and excess Initial Spares. However, the Petitioner has considered the actual capital cost as Rs. 29811.92 lakh for arriving at the total cost as on 31.3.2019. In response, the Petitioner in its rejoinder dated 18.5.2020 has submitted a reconciliation table as under:

(Rs. in lakh)

Actual capital cost as on COD as per Auditor certificate (A) Excess Initial Spares disallowed (B) Accrual IDC discharged after COD (C) Admitted cost as per CERC order D= (A)-(B)-(C) Capital Cost as on COD claimed by Petitioner in the instant petition for calculation of tariff E=(A)-(C) 29811.92 17.81 1761.99 28032.12 28049.93

Interest during construction (IDC)

13. The Commission had allowed IDC of Rs. 2472.49 lakh after disallowing Rs. 23.66 lakh and directed the Petitioner to submit the interest rate for SBI loan and discharge of IDC liability at the time of true up of the 2014-19 tariff period in the order dated 3.10.2018 in Petition No. 118/TT/2017. The Petitioner has submitted the required information in the instant petition and claimed IDC of Rs. 2496.15 lakh for the transmission asset and has submitted the Auditor Certificate dated 2.8.2019 in support of the same.

14. On prudence check of the IDC computation, it is observed that there is mismatch in loan amount considered as on COD for IDC computation and submitted in Form 9C. Therefore, the loan amount as on COD submitted in Form-9C has been considered for computation of the IDC. The details of IDC claimed as per Auditor Certificate, IDC allowed, and IDC discharged is as follows:

(Rs. in lakh)

IDC claimed as per Auditor Certificate dated 2.8.2019 IDC disallowed due to computational difference IDC allowed on accrual basis IDC allowed on cash basis as on COD Undischarged IDC liability as on COD Discharge of IDC liability allowed as ACE 2017-18 2018-19 2496.15 23.91 2472.24 734.16 1738.08 33.83 1704.25

Initial Spares

15. Regulation 13(d) of the 2014 Tariff Regulations provides that Initial Spares shall be capitalized as a percentage of plant and machinery cost up to cut-off date, subject to the following ceiling norms:

“(d) Transmission System

Transmission line: 1.00%

Transmission sub-station (Green Field): 4.00%

Transmission sub-station (Brown Field): 6.00%

GIS Sub-station: 5.00%”

16. The Commission vide order dated 3.10.2018 in Petition No. 118/TT/2017 had allowed Initial Spares of Rs. 497.54 lakh and disallowed excess Initial Spares of Rs. 93.40 lakh. The Petitioner in the instant petition has claimed the total Initial Spares of Rs. 590.94 lakh and has submitted Auditor Certificate dated 2.8.2019 in support of the same. The Petitioner vide affidavit dated 11.5.2020 has submitted Form-13 stating that the sub-station is a brown-field sub-station. MPPMCL has submitted that the capital cost allowed in order dated 3.10.2018 in Petition No. 118/TT/2017 may be considered.

17. We have considered the submissions made by MPPMCL and the Petitioner. The Petitioner in Petition No. 118/TT/2017 had claimed Initial Spares for the substations considering them as GIS Sub-stations and accordingly in order dated 3.10.2018 in Petition No. 118/TT/2017, Initial Spares was approved for the sub-stations @5% as per the norms specified for GIS Sub-station in Regulation 13(d) of the 2014 Tariff Regulations. However, in the instant petition, the Petitioner has claimed Initial Spares @6% for the sub-stations considering them as brownfield sub-stations. We note that the transmission asset includes two sub-stations, i.e. Navsari GIS Substation and Vapi AIS Sub-station. The norms specified for GIS Sub-station and Brown-field Sub-station are 5% and 6% respectively in Regulation 13(d) of the 2014 Tariff Regulations. Hence, Initial Spares @6% cannot be allowed for Navsari GIS Substation. The Petitioner has not submitted the reasons for claiming Initial Spares @6% for the sub-stations when one of the sub-stations is a GIS Sub-station. We are of the view that the Initial Spares should be allowed individually on the basis of the nature of the sub-station and the norms specified in Regulation 13(d) of the 2014 Tariff Regulations. The Petitioner has neither submitted any reason for claiming higher rate of Initial Spares, nor made specific prayer to allow it nor has submitted the plant and machinery cost of the GIS Sub-station and the AIS Sub-station separately in this petition. Hence, we are not inclined to allow Initial Spares @6% as claimed by the Petitioner. As such, the Initial Spares allowed in order dated 3.10.2018 in Petition No. 118/TT/2017 is allowed in this order which is as follows:

(Rs. in lakh)

Particulars Plant and Machinery excluding IDC, IEDC, Land cost and cost of Civil works upto the cut-of date Initial Spare claimed as per Auditor Certificate Ceiling Limit (%) Initial Spares computed as per norms Excess Initial Spares disallowed Initial Spares allowed in this order A B C D=(A-B) *C/(100-C) Sub-station (GIS) 4974.92 294.49 5.00 246.34 48.15 246.34 Transmission Line 23641.11 296.45 1.00 235.80 60.65 235.80

18. The excess Initial Spares have been adjusted from respective year's Additional Capital Expenditure (ACE) based on the discharge pattern as under:

(Rs. in lakh)

Period Sub-station Transmission Line Claimed Excess Allowed Claimed Excess Allowed As on COD 278.97 32.63 246.34 205.62 0.00 205.62 2017-18 15.52 15.52 0.00 78.00 47.82 30.18 2018-19 0.00 0.00 0.00 12.83 12.83 0.00 Total 294.49 48.15 246.34 296.45 60.65 235.80

19. The details of the capital cost as on COD approved in the instant petition after adjustment of IDC and excess Initial Spares is as follows:

(Rs. in lakh)

Capital Cost claimed as on COD on accrual basis (A) Disallowed IDC due to computational difference (B) Un-discharged IDC (C) Excess Initial Spares Disallowed as on COD (D) Capital Cost allowed as on COD on cash basis (E) = (A-B-C-D) 29811.92 23.91 1738.08 32.63 28017.30

Additional Capital Expenditure (ACE)

20. The Commission vide order dated 3.10.2018 in Petition No. 118/TT/2017 had allowed ACE of Rs. 1608.67 lakh and Rs. 2170.12 lakh for 2017-18 and 2018-19, respectively, towards un-discharged liabilities and works deferred for execution. Against this, the Petitioner has claimed ACE of Rs. 1676.28 lakh and Rs. 1826.16 lakh during 2017-18 and 2018-19 respectively, as un-discharged liabilities for works executed within the cut-off date for the transmission asset under Regulation 14(3)(v) of the 2014 Tariff Regulations. The details of ACE claimed by the Petitioner are as under:

(Rs. in lakh)

Particulars Regulation 2017-18 2018-19 Discharge of Liabilities on hard cost Regulation 14(1)(i) 0.00 110.82 ACE towards works deferred for execution (by addition into gross block) Regulation 14(1)(ii) 1690.26 0.00 Discharge of IDC Liability Regulation 14(1)(i) 33.83 1728.16 Total ACE claim 1724.09 1838.98 Less: Excess Initial Spares 47.81 12.83 Total ACE allowed for tariff 1676.28 1826.16

21. ACE claimed by the Petitioner has been allowed under Regulation 14(1)(i) and 14(1)(ii) of the 2014 Tariff Regulations, as it is towards balance and retention payments and balance work deferred for execution. The un-discharged IDC liability as well as un-discharged Initial Spares as on COD has been allowed as ACE during the year of its discharge. The excess Initial Spares have also been adjusted to arrive at ACE for 2017-18 and 2018-19. Further, disallowed IDC liability has been adjusted with ACE of 2018-19. ACE allowed from COD to 31.3.2019 in respect of the transmission asset is as under:

(Rs. in lakh)

Particulars Regulation 2017-18 2018-19 Discharge of Liabilities on hard cost Regulation 14(1)(i) 0.00 110.82 ACE towards works deferred for execution (by addition into gross block) Regulation 14(1)(ii) 1690.26 0.00 Discharge of IDC Liability Regulation 14(1)(i) 33.83 1704.25 Total ACE allowed 1724.09 1815.08 Less: Excess Initial Spares 63.35 12.83 Total ACE allowed for tariff 1660.74 1802.25

22. Accordingly, the capital cost considered for the 2014-19 tariff period is as under:

(Rs. in lakh)

Admitted Capital Cost as on COD ACE Total Capital Cost as on 31.3.2019 2017-18 2018-19 28017.30 1660.74 1802.25 31480.29

Debt-Equity ratio

23. The Petitioner has claimed debt-equity ratio of 70:30 as on the date of commercial operation. Further, the Petitioner has also submitted that equity infused during 2014-19 is not less than 30%. Accordingly, the debt-equity ratio of 70:30 as per Regulation 19 of the 2014 Tariff Regulations has been considered. The details of debt-equity ratio in respect of the transmission asset as on the date of commercial operation and as on 31.3.2019 are as under:

Funding Capital Cost as on COD (Rs. in lakh) (%) ACE (Rs. in lakh) (%) Capital Cost as on 31.3.2019 (Rs. in lakh) (%) Debt 19612.11 70.00 2424.09 70.00 22036.20 70.00 Equity 8405.19 30.00 1038.90 30.00 9444.09 30.00 Total 28017.30 100.00 3462.99 100.00 31480.29 100.00

Depreciation

24. The Petitioner's claim towards depreciation in this petition was found to be higher than the depreciation allowed for the transmission asset in order dated 3.10.2018 in Petition No. 118/TT/2017. The Petitioner has neither given any justification for claiming higher depreciation than that allowed earlier in order dated 3.10.2018 nor made any specific prayer for allowing higher depreciation in this petition. Similar issue had come up in Petition No. 19/TT/2020, wherein the Commission vide order dated 9.5.2020 held as under:

“31. We have considered the submissions of the Petitioner. The instant assets were put into commercial operation during the 2009-14 period and the tariff from the respective CODs to 31.3.2014 was allowed vide orders dated 30.8.2012 and 9.5.2013 in Petition No. 343/2010 and Petition No. 147/TT/2011 respectively. Further, the tariff of the 2009-14 period was trued up and tariff for the 2014-19 period was allowed vide order dated 25.2.2016 in Petition No. 10/TT/2015. The Petitioner did not claim any capital expenditure towards “IT Equipment” in the above said three petitions where tariff for the instant assets for the 2009-14 period was allowed, tariff of the 2009-14 period was trued up and tariff for 2014-19 period was allowed even though there was a clear provision in the 2009 Tariff Regulations and 2014 Tariff Regulations providing depreciation @15% for IT Equipment. Having failed to make a claim as per the 2009 Tariff Regulations(the period during which COD of assets was achieved), the Petitioner has now, at the time of truing up of the tariff allowed for the 2014-19 period has apportioned a part of the capital expenditure to “IT Equipment”. The Petitioner has adopted similar methodology not only in this but in some of the other petitions listed along with the instant petition on 26.2.2020. It is observed that the Petitioner has for the first time apportioned a part of the capital expenditure towards IT Equipment and has claimed depreciation under the head “IT Equipment” @15% at the time of truing up of the tariff of 2014-19 period. Regulation 8(1) of the 2014 Tariff Regulations provides for truing up of the capital expenditure including the additional capital expenditure, incurred up to 31.3.2019, admitted by the Commission after prudence check. We are of the view that scope of truing up exercise is restricted to truing up of the capital expenditure already admitted and apportionment or reapportionment of the capital expenditure cannot be allowed at the time of truing up. Therefore, we are not inclined to consider the Petitioner's prayer for apportionment of capital expenditure towards IT Equipment and allowing depreciation @ 15% from 1.4.2014 onwards. Accordingly, the depreciation @ 5.28% has been considered for IT Equipment as part of the sub-station up to 31.3.2019 while truing up the capital expenditure for the 2014-19 period. During the 2019-24 tariff period, the IT Equipment has been considered separately and depreciation has been allowed @ 15% for the balance depreciable value of IT Equipment in accordance with Regulation 33 read with Sr. No. (p) of the Appendix-I (Depreciation Schedule) of the 2019 Tariff Regulations.”

25. In line with the above said order dated 9.5.2020 in Petition No. 19/TT/2020, the depreciation has been considered @5.28% for IT Equipment as part of the sub-station upto 31.3.2019 while truing up the capital expenditure for the 2014-19 period. During the 2019-24 tariff period, the IT Equipment has been considered separately and depreciation has been allowed @15% for the balance depreciable value of IT Equipment in accordance with Regulation 33 read with Sr. No. (p) of the Appendix-I (Depreciation Schedule) of the 2019 Tariff Regulations. The calculation of weighted average rate of depreciation (WAROD) is placed in Annexure-1. The Gross Block during the tariff period 2014-19 has been depreciated at WAROD (Annexure-I). WAROD has been worked out after taking into account the depreciation rates of assets as prescribed in the 2014 Tariff Regulations and the trued up depreciation allowed during the 2014-19 tariff period is as under:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 Depreciation Opening Gross Block 28017.30 29678.04 ACE 1660.74 1802.25 Closing Gross Block 29678.04 31480.29 Average Gross Block 28847.67 30579.16 Weighted Average Rate of Depreciation (%) 5.28 5.28 Balance useful life of the asset 33 33 Elapsed life at the beginning of the year 0 0 Aggregated Depreciable Value 25962.90 27521.24 Depreciation during the year 1152.57 1615.65 Cumulative Depreciation 1152.57 2768.22 Remaining Aggregate Depreciable Value 24810.33 24753.02

26. The details of the depreciation approved in order dated 3.10.2018 in Petition No. 118/TT/2017, claimed by the Petitioner in the instant petition and trued up in this order is shown as follows:

Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 Approved vide order dated 3.10.2018 in Petition No. 118/TT/2017 1152.16 1623.50 Claimed by the Petitioner in the instant petition 1157.62 1623.52 Allowed after true-up in this order 1152.57 1615.65

Interest on Loan (IoL)

27. The Petitioner has claimed the weighted average rate of IoL, based on its actual loan portfolio and rate of interest. Accordingly, IoL has been calculated based on actual interest rate, in accordance with Regulation 26 of the 2014 Tariff Regulations. Trued up IoL allowed for the transmission asset is as under:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 Interest on Loan Gross Normative Loan 19612.11 20774.62 Cumulative Repayments up to Previous Year 0.00 1152.57 Net Loan-Opening 19612.11 19622.06 Additions 1162.52 1261.58 Repayment during the year 1152.57 1615.65 Net Loan-Closing 19622.06 19267.98 Average Loan 19617.08 19445.02 Weighted Average Rate of Interest on Loan (%) 8.1730 8.1231 Interest on Loan 1212.37 1579.53

28. The details of IoL approved in order dated 3.10.2018 in Petition No. 118/TT/2017, claimed by the Petitioner in the instant petition and trued up in this order is shown in the table below:

(Rs. in lakh)

Particular 2017-18 (Pro-rata for 276 days) 2018-19 Approved vide order dated 3.10.2018 in Petition No. 118/TT/2017 1230.54 1614.11 Claimed by the Petitioner in the instant petition 1213.95 1582.23 Allowed after true-up in this order 1212.37 1579.53

Return on Equity (RoE)

29. The Petitioner has claimed RoE for the transmission asset in terms of Regulations 24 and 25 of the 2014 Tariff Regulations. The Petitioner has submitted that it is liable to pay income tax at MAT rates and has claimed following effective tax rates for the 2014-19 period:

Year Claimed effective tax (in %) Grossed up RoE (Base Rate/1-t) (in %) 2014-15 21.018 19.625 2015-16 21.382 19.716 2016-17 21.338 19.705 2017-18 21.337 19.704 2018-19 21.549 19.758

30. MPPMCL has submitted that the Petitioner has grossed up RoE on the basis of actual taxes paid during 2016-17 and 2017-18 and has not placed on record the assessment orders for 2016-17 and 2017-18. For 2018-19, it has grossed up RoE and has not claimed the effective tax rate based on actual taxes paid for 2018-19. In response, the Petitioner vide affidavit dated 13.7.2020 has submitted that effective rates of tax considered for 2014-15 and 2015-16 are based on Assessment Order issued by Income Tax authorities for the purpose of grossing up of RoE rate. The effective rate of tax considered for 2016-17 and 2017-18 are based on the Income-tax returns filed for the purpose of grossing up of ROE rate of the respective years. Further, for 2018-19, effective tax rate is calculated based on the applicable MAT rate (i.e. MAT 18.50% + Surcharge 12.00% + Cess 4%) for the purpose of grossing up of RoE rate. The Petitioner has also submitted a copy of the Assessment orders for 2014-15 to 2016-17.

31. We have considered the submissions of the Petitioner and MPPMCL. The Commission vide order dated 2.2.2021 in Petition No. 312/TT/2020 has already dealt with the concerns of MPPMCL. The relevant paragraph of the order are extracted as under:

“39. We have considered the submissions of the Petitioner and MPPMCL. As regards MPPMCL's contention, it is observed that the Petitioner has submitted the assessment orders issued by the Income Tax Department for the years 2014-15, 2015-16 and 2016-17 and the Income Tax returns filed by the Petitioner for years 2017-18 and 2018-19. The Petitioner has submitted the documents pointed out by MPPMCL.”

32. The Commission, vide order dated 27.4.2020 in Petition No. 274/TT/2019, had arrived at the effective tax rate for the Petitioner based on the notified MAT rates and the same is given in the table below. The relevant portion of the order dated 27.4.2020 is as under:

“26. We are conscious that the entities covered under MAT regime are paying Income Tax as per MAT rate notified for respective financial year under IT Act, 1961, which is levied on the book profit of the entity computed as per the Section 115JB of the IT Act, 1961. The Section 115JB(2) defines book profit as net profit in the statement of Profit & Loss prepared in accordance with Schedule-III of the Companies Act, 2013, subject to some additions and deductions as mentioned in the IT Act, 1961. Since the Petitioner has been paying income tax on income computed under Section 115JB of the IT Act, 1961 as per the MAT rates of the respective financial year, the notified MAT rate for respective financial year shall be considered as effective tax rate for the purpose of grossing up of RoE for truing up of the tariff of the 2014-19 tariff period in terms of the provisions of the 2014 Tariff Regulations. Interest imposed on any additional income tax demand as per the Assessment Order of the Income Tax authorities shall be considered on actual payment. However, penalty (for default on the part of the Assessee) if any imposed shall not be taken into account for the purpose of grossing up of rate of return on equity. Any under-recovery or over-recovery of grossed up rate on return on equity after truing up, shall be recovered or refunded to beneficiaries or the long term transmission customers/DICs as the case may be on year to year basis.

27. Accordingly, following effective tax rates based on notified MAT rates are considered for the purpose of grossing up of rate of return on equity:

Year Notified MAT rates (inclusive of surcharge & cess) Effective tax (in %) 2014-15 20.961 20.961 2015-16 21.342 21.342 2016-17 21.342 21.342 2017-18 21.342 21.342 2018-19 21.549 21.549

33. The same MAT rates as considered in the above-mentioned order in Petition No. 274/TT/2019 are considered for the purpose of grossing up of rate of RoE for truing up of the tariff of the 2014-19 period in terms of the provisions of the 2014 Tariff Regulations.

Year Notified MAT rates (inclusive of surcharge & cess) (in %) Base rate of RoE (in %) Grossed up RoE (Base Rate/1-t)(in %) 2014-15 20.961 15.50 19.610 2015-16 21.342 15.50 19.705 2016-17 21.342 15.50 19.705 2017-18 21.342 15.50 19.705 2018-19 21.549 15.50 19.758

34. The Petitioner has claimed RoE for the 2014-19 period after grossing up the RoE of 15.50% with Effective Tax rates (based on MAT rates) each year as per the above said Regulation. RoE is trued up on the basis of the MAT rate applicable for the respective years and is allowed as follows:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 Return on Equity Opening Equity 8405.19 8903.41 Additions 498.22 540.68 Closing Equity 8903.41 9444.09 Average Equity 8654.30 9173.75 Return on Equity (Base Rate) (%) 15.500 15.500 MAT Rate for respective year (%) 21.342 21.549 Rate of Return on Equity (%) 19.705 19.758 Return on Equity 1289.54 1812.50

35. Details of RoE approved in order dated 3.10.2018 in Petition No. 118/TT/2017, claimed by the Petitioner in the instant petition and trued up in this order are as under:

(Rs. in lakh)

Particular 2017-18 (Pro-rata for 276 days) 2018-19 Approved vide order dated 3.10.2018 in Petition No. 118/TT/2017 1282.79 1807.60 Claimed by the Petitioner in the instant petition 1291.32 1816.11 Allowed after true-up in this order 1289.54 1812.50

Operation & Maintenance Expenses (O&M Expenses)

36. Regulation 29(3) of the 2014 Tariff Regulations specifies the norms for O&M Expenses for the transmission system. The O&M Expenses claimed by the Petitioner for the various elements included in the transmission asset are as follows:

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 400 kV: Vapi-Kakrapar bay No. of bays 2 2 Norms (Rs. lakh/Bay) 66.51 68.71 400 kV GIS: Navsari-Kakrapar bay No. of bays 2 2 Norms (Rs. lakh/Bay) 56.84 58.73 Transmission line: Vapi-Kakrapar-Navsari D/C Bundled (4 or more sub-conductors) 151.18 151.18 Norms (Rs. lakh/km) 1.171 1.21 Multi Ckt Bundled with 4 or more sub-conductors 4.07 4.07 Norms (Rs. lakh/km) 2.055 2.123 Total O&M Expenses (Rs. in lakh) 432.10 446.45 Total O&M Expenses (Rs. in lakh) (pro-rata) 326.73 446.45

37. Regulation 29(3) of the 2014 Tariff Regulations specifies the norms for O&M Expenses for the transmission system. Norms specified in respect of the elements covered in the transmission asset are as follows:

Particulars 2017-18 2018-19 Norms for sub-station Bays (Rs. lakh per bay) 400 kV Norms (Rs. lakh/Bay) 66.51 68.71 400 kV GIS Norms (Rs. lakh/Bay) 56.84 58.73 Transmission line D/C Bundled(4 or more sub-conductors) Norms (Rs. lakh/km) 1.171 1.21 Multi Ckt Bundled with 4 or more sub-conductors Norms (Rs. lakh/km) 2.055 2.123

38. We have considered the submission of the Petitioner. The O&M Expenses are allowed for the transmission asset as per the norms specified in the 2014 Tariff Regulations and are as under:

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 400 kV: Vapi-Kakrapar bay No. of bays 2 2 Norms (Rs. lakh/Bay) 66.51 68.71 400 kV GIS: Navsari-Kakrapar bay No. of bays 2 2 Norms (Rs. lakh/Bay) 56.84 58.73 Transmission line: Vapi-Kakrapar-Navsari (km) D/C Bundled(4 or more sub-conductors) 151.18 151.18 Norms (Rs. lakh/km) 1.171 1.21 Multi Ckt Bundled with 4 or more sub-conductors 4.07 4.07 Norms (Rs. lakh/km) 2.055 2.123 Total O&M Expenses (Rs. in lakh) 326.74 446.45

39. The details of the O&M Expenses approved in order dated 3.10.2018 in Petition No. 118/TT/2017, claimed by the Petitioner in the instant petition and trued up in the instant order is shown in the table as under:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 Approved vide order dated 3.10.2018 in Petition No. 118/TT/2017 326.47 446.45 Claimed by the Petitioner in the instant petition 326.73 446.45 Allowed after true-up in this order 326.74 446.45

Interest on Working Capital (IWC)

40. The IWC has been worked out as per the methodology provided in Regulation 28 of the 2014 Tariff Regulations and allowed as under:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 O&M Expenses 36.01 37.20 Maintenance Spares 64.81 66.97 Receivables 898.49 930.76 Total Working Capital 999.31 1034.93 Rate of Interest (%) 12.60 12.60 Interest on Working Capital 95.21 130.40

41. Details of IWC approved vide order dated 3.10.2018 in Petition No. 118/TT/2017, IWC claimed by the Petitioner in the instant petition and as trued up in this order are shown in the table as follows:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 Approved vide order dated 3.10.2018 in Petition No. 118/TT/2017 95.43 131.21 Claimed by the Petitioner in the instant petition 95.39 130.70 Allowed after true-up in this order 95.21 130.40

Approved Annual Fixed Charges for the 2014-19 Tariff Period

42. The trued up annual fixed charges for the instant transmission asset for the 2014-19 period is summarised as under:

(Rs. in lakh)

Particulars/Asset 2017-18 (Pro-rata for 276 days) 2018-19 Depreciation 1152.57 1615.65 Interest on Loan 1212.37 1579.53 Return on Equity 1289.54 1812.50 Interest on Working Capital 95.21 130.40 O&M Expenses 326.74 446.45 Total 4076.42 5584.54

43. The Annual Transmission Charges approved vide order dated 3.10.2018 in Petition No. 118/TT/2017, claimed by the Petitioner in the instant petition and approved after truing up in this order is shown as under:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata for 276 days) 2018-19 Approved vide order dated 3.10.2018 in Petition No. 118/TT/2017 4087.40 5622.86 Claimed by the Petitioner in the instant petition 4085.01 5599.01 Allowed after true-up in this order 4076.42 5584.54

Determination of Annual Fixed Charges for the 2019-24 Tariff Period

44. The Petitioner has claimed following transmission charges for the 2019-24 tariff period:

(Rs. in lakh)

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Depreciation 1673.48 1675.06 1675.06 1675.06 1674.95 Interest on Loan 1505.31 1366.42 1231.69 1097.17 959.53 Return on Equity 1779.54 1781.23 1781.23 1781.23 1781.23 Interest on Working Capital 88.67 87.33 85.81 84.30 82.56 O&M Expenses 323.73 334.85 346.43 358.46 370.78 Total 5370.73 5244.89 5120.22 4996.22 4869.05

45. The details of IWC claimed by the Petitioner in respect of the transmission asset for the 2019-24 tariff period are as under:

(Rs. in lakh)

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 O & M Expenses 26.98 27.90 28.87 29.87 30.90 Maintenance Spares 48.56 50.23 51.96 53.77 55.62 Receivables 660.34 646.63 631.26 615.97 598.65 Total Working Capital 735.88 724.76 712.09 699.61 685.17 Rate of Interest (%) 12.05 12.05 12.05 12.05 12.05 Interest on Working Capital 88.67 87.33 85.81 84.30 82.56

Capital Cost

46. Regulation 19 of the 2019 Tariff Regulations provides as under:

“19. Capital Cost: (1) The Capital cost of the generating station or the transmission system, as the case may be, as determined by the Commission after prudence check in accordance with these regulations shall form the basis for determination of tariff for existing and new projects.

(2) The Capital Cost of a new project shall include the following:

(a) The expenditure incurred or projected to be incurred up to the date of commercial operation of the project;

(b) Interest during construction and financing charges, on the loans (i) being equal to 70% of the funds deployed, in the event of the actual equity in excess of 30% of the funds deployed, by treating the excess equity as normative loan, or (ii) being equal to the actual amount of loan in the event of the actual equity less than 30% of the funds deployed;

(c) Any gain or loss on account of foreign exchange risk variation pertaining to the loan amount availed during the construction period;

(d) Interest during construction and incidental expenditure during construction as computed in accordance with these regulations;

(e) Capitalised initial spares subject to the ceiling rates in accordance with these regulations;

(f) Expenditure on account of additional capitalization and de-capitalisation determined in accordance with these regulations;

(g) Adjustment of revenue due to sale of infirm power in excess of fuel cost prior to the date of commercial operation as specified under Regulation 7 of these regulations;

(h) Adjustment of revenue earned by the transmission licensee by using the assets before the date of commercial operation;

(i) Capital expenditure on account of ash disposal and utilization including handling and transportation facility;

(j) Capital expenditure incurred towards railway infrastructure and its augmentation for transportation of coal upto the receiving end of the generating station but does not include the transportation cost and any other appurtenant cost paid to the railway;

(k) Capital expenditure on account of biomass handling equipment and facilities, for co-firing;

(l) Capital expenditure on account of emission control system necessary to meet the revised emission standards and sewage treatment plant;

(m) Expenditure on account of fulfilment of any conditions for obtaining environment clearance for the project;

(n) Expenditure on account of change in law and force majeure events; and

(o) Capital cost incurred or projected to be incurred by a thermal generating station, on account of implementation of the norms under Perform, Achieve and Trade (PAT) scheme of Government of India shall be considered by the Commission subject to sharing of benefits accrued under the PAT scheme with the beneficiaries.

(3) The Capital cost of an existing project shall include the following:

(a) Capital cost admitted by the Commission prior to 1.4.2019 duly trued up by excluding liability, if any, as on 1.4.2019;

(b) Additional capitalization and de-capitalization for the respective year of tariff as determined in accordance with these regulations;

(c) Capital expenditure on account of renovation and modernisation as admitted by this Commission in accordance with these regulations;

(d) Capital expenditure on account of ash disposal and utilization including handling and transportation facility;

(e) Capital expenditure incurred towards railway infrastructure and its augmentation for transportation of coal upto the receiving end of generating station but does not include the transportation cost and any other appurtenant cost paid to the railway; and

(f) Capital cost incurred or projected to be incurred by a thermal generating station, on account of implementation of the norms under Perform, Achieve and Trade (PAT) scheme of Government of India shall be considered by the Commission subject to sharing of benefits accrued under the PAT scheme with the beneficiaries.

(4) The capital cost in case of existing or new hydro generating station shall also include:

(a) cost of approved rehabilitation and resettlement (R&R) plan of the project in conformity with National R&R Policy and R&R package as approved; and

(b) cost of the developer's 10% contribution towards Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) and Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY) project in the affected area.

(5) The following shall be excluded from the capital cost of the existing and new projects:

(a) The assets forming part of the project, but not in use, as declared in the tariff petition;

(b) De-capitalised Assets after the date of commercial operation on account of replacement or removal on account of obsolescence or shifting from one project to another project:

Provided that in case replacement of transmission asset is recommended by Regional Power Committee, such asset shall be de-capitalised only after its redeployment;

Provided further that unless shifting of an asset from one project to another is of permanent nature, there shall be no de-capitalization of the concerned assets.

(c) In case of hydro generating stations, any expenditure incurred or committed to be incurred by a project developer for getting the project site allotted by the State Government by following a transparent process;

(d) Proportionate cost of land of the existing project which is being used for generating power from generating station based on renewable energy; and

(e) Any grant received from the Central or State Government or any statutory body or authority for the execution of the project which does not carry any liability of repayment.”

47. The capital cost of Rs. 31552.37 lakh as on 31.3.2019 has been claimed by the Petitioner against which the Commission allowed Rs. 31480.29 lakh as on 31.3.2019 and the same has been considered as the opening capital cost as on 1.4.2019 for determination of tariff in accordance with Regulation 19 of the 2019 Tariff Regulations.

Additional Capital Expenditure (ACE)

48. Regulation 24 of the 2019 Tariff Regulations provides as under:

“24. Additional Capitalisation within the original scope and upto the cut-off date

(1) The additional capital expenditure in respect of a new project or an existing project incurred or projected to be incurred, on the following counts within the original scope of work, after the date of commercial operation and up to the cut-off date may be admitted by the Commission, subject to prudence check:

(a) Undischarged liabilities recognized to be payable at a future date;

(b) Works deferred for execution;

(c) Procurement of initial capital spares within the original scope of work, in accordance with the provisions of Regulation 23of these regulations;

(d) Liabilities to meet award of arbitration or for compliance of the directions or order of any statutory authority or order or decree of any court of law;

(e) Change in law or compliance of any existing law; and

(f) Force Majeure events:

Provided that in case of any replacement of the assets, the additional capitalization shall be worked out after adjusting the gross fixed assets and cumulative depreciation of the assets replaced on account of de-capitalization.

(2) The generating company or the transmission licensee, as the case may be shall submit the details of works asset wise/work wise included in the original scope of work along with estimates of expenditure, liabilities recognized to be payable at a future date and the works deferred for execution.”

49. The Petitioner has claimed ACE of Rs. 59.98 lakh for the 2019-24 period under Regulations 24(1)(a) and 24(1)(b) of the 2019 Tariff Regulations on account of un-discharged liability towards final payment for works executed and for works deferred for execution within cut-off date.

50. We have considered the submissions of the Petitioner. ACE claimed by the Petitioner has been allowed under Regulation 24(1)(a) and 24(1)(b) of the 2019 Tariff Regulations, as it is towards un-discharged liabilities recognised to be payable at a future date and balance work deferred for execution. The total capital expenditure as on 31.3.2024 is within the apportioned approved cost of Rs. 37871.21 lakh. Accordingly, ACE for 2019-20 and the capital cost as on 31.3.2024 for the transmission asset considered are as under:

(Rs. in lakh)

Capital Cost admitted as on 1.4.2019 ACE for Capital Cost allowed as on 31.3.2024 2019-20 31480.29 59.98 31540.27

Debt-Equity ratio

51. Regulation 18 of the 2019 Tariff Regulations provides as under:

“18. Debt-Equity Ratio: (1) For new projects, the debt-equity ratio of 70:30 as on date of commercial operation shall be considered. If the equity actually deployed is more than 30% of the capital cost, equity in excess of 30% shall be treated as normative loan:

Provided that:

i. where equity actually deployed is less than 30% of the capital cost, actual equity shall be considered for determination of tariff:

ii. the equity invested in foreign currency shall be designated in Indian rupees on the date of each investment:

iii. any grant obtained for the execution of the project shall not be considered as a part of capital structure for the purpose of debt: equity ratio.

Explanation- The premium, if any, raised by the generating company or the transmission licensee, as the case may be, while issuing share capital and investment of internal resources created out of its free reserve, for the funding of the project, shall be reckoned as paid up capital for the purpose of computing return on equity, only if such premium amount and internal resources are actually utilised for meeting the capital expenditure of the generating station or the transmission system.

(2) The generating company or the transmission licensee, as the case may be, shall submit the resolution of the Board of the company or approval of the competent authority in other cases regarding infusion of funds from internal resources in support of the utilization made or proposed to be made to meet the capital expenditure of the generating station or the transmission system including communication system, as the case may be.

(3) In case of the generating station and the transmission system including communication system declared under commercial operation prior to 1.4.2019, debt: equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2019 shall be considered:

Provided that in case of a generating station or a transmission system including communication system which has completed its useful life as on or after 1.4.2019, if the equity actually deployed as on 1.4.2019 is more than 30% of the capital cost, equity in excess of 30%shall not be taken into account for tariff computation;

Provided further that in case of projects owned by Damodar Valley Corporation, the debt: equity ratio shall be governed as per sub-clause (ii) of clause (2) of Regulation 72 of these regulations.

(4) In case of the generating station and the transmission system including communication system declared under commercial operation prior to 1.4.2019, but where debt: equity ratio has not been determined by the Commission for determination of tariff for the period ending 31.3.2019, the Commission shall approve the debt: equity ratio in accordance with clause (1) of this Regulation.

(5) Any expenditure incurred or projected to be incurred on or after 1.4.2019 as may be admitted by the Commission as additional capital expenditure for determination of tariff, and renovation and modernisation expenditure for life extension shall be serviced in the manner specified in clause (1) of this Regulation.”

52. The details of the debt-equity considered for the purpose of computation of tariff for the 2019-24 tariff period is as under:

Particulars Capital Cost as on 1.4.2019 (Rs. in lakh) % ACE 2019-24 (Rs. in lakh) % Capital Cost as on 31.3.2024 (Rs. in lakh) % Debt 22036.20 70.00 41.99 70.00 22078.19 70.00 Equity 9444.09 30.00 17.99 30.00 9462.08 30.00 Total 31480.29 100.00 59.98 100.00 31540.27 100.00

Depreciation

53. Regulation 33 of the 2019 Tariff Regulations provides as under:

“33. Depreciation: (1) Depreciation shall be computed from the date of commercial operation of a generating station or unit thereof or a transmission system or element thereof including communication system. In case of the tariff of all the units of a generating station or all elements of a transmission system including communication system for which a single tariff needs to be determined, the depreciation shall be computed from the effective date of commercial operation of the generating station or the transmission system taking into consideration the depreciation of individual units:

Provided that effective date of commercial operation shall be worked out by considering the actual date of commercial operation and installed capacity of all the units of the generating station or capital cost of all elements of the transmission system, for which single tariff needs to be determined.

(2) The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the Commission. In case of multiple units of a generating station or multiple elements of a transmission system, weighted average life for the generating station of the transmission system shall be applied. Depreciation shall be chargeable from the first year of commercial operation. In case of commercial operation of the asset for part of the year, depreciation shall be charged on pro rata basis.

(3) The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up to maximum of 90% of the capital cost of the asset:

Provided that the salvage value for IT equipment and software shall be considered as NIL and 100% value of the assets shall be considered depreciable;

Provided further that in case of hydro generating stations, the salvage value shall be as provided in the agreement, if any, signed by the developers with the State Government for development of the generating station:

Provided also that the capital cost of the assets of the hydro generating station for the purpose of computation of depreciated value shall correspond to the percentage of sale of electricity under long-term power purchase agreement at regulated tariff:

Provided also that any depreciation disallowed on account of lower availability of the generating station or unit or transmission system as the case may be, shall not be allowed to be recovered at a later stage during the useful life or the extended life.

(4) Land other than the land held under lease and the land for reservoir in case of hydro generating station shall not be a depreciable asset and its cost shall be excluded from the capital cost while computing depreciable value of the asset.

(5) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-I to these regulations for the assets of the generating station and transmission system:

Provided that the remaining depreciable value as on 31st March of the year closing after a period of 12 years from the effective date of commercial operation of the station shall be spread over the balance useful life of the assets.

(6) In case of the existing projects, the balance depreciable value as on 1.4.2019 shall be worked out by deducting the cumulative depreciation as admitted by the Commission upto 31.3.2019 from the gross depreciable value of the assets.

(7) The generating company or the transmission licensee, as the case may be, shall submit the details of proposed capital expenditure five years before the completion of useful life of the project along with justification and proposed life extension. The Commission based on prudence check of such submissions shall approve the depreciation on capital expenditure.

(8) In case of de-capitalization of assets in respect of generating station or unit thereof or transmission system or element thereof, the cumulative depreciation shall be adjusted by taking into account the depreciation recovered in tariff by the de-capitalized asset during its useful services.”

54. The IT equipment has been considered as a part of the Gross Block and depreciated using weighted average rate of depreciation (WAROD) (as placed in Annexure-II). WAROD has been worked out after taking into account the depreciation rates of IT and non-IT assets as prescribed in the 2019 Tariff Regulations The salvage value of IT equipment has been considered nil, i.e. IT asset has been considered as 100 per cent depreciable. The calculation of WAROD for the 2019-24 period is placed in Annexure-II. The depreciation has been worked out considering the admitted capital expenditure as on 31.3.2019 and accumulated depreciation up to 31.3.2019. The depreciation allowed for the transmission asset is as under:

(Rs. in lakh)

Particular 2019-20 2020-21 2021-22 2022-23 2023-24 Opening Gross Block 31480.29 31540.27 31540.27 31540.27 31540.27 Addition during the year 2019-24 due to projected ACE 59.98 0.00 0.00 0.00 0.00 Closing Gross Block 31540.27 31540.27 31540.27 31540.27 31540.27 Average Gross Block 31510.28 31540.27 31540.27 31540.27 31540.27 Weighted average rate of Depreciation (WAROD) (%) 5.30 5.30 5.30 5.30 5.30 Balance useful life at the beginning of the year 32 31 30 29 28 Elapsed Life 1 2 3 4 5 Aggregated Depreciable Value 28364.21 28391.20 28391.20 28391.20 28391.20 Depreciation during the year 1669.67 1671.25 1671.25 1671.25 1671.25 Aggregate Cumulative Depreciation 4437.89 6109.14 7780.39 9451.64 11122.89 Remaining Aggregated Depreciable Value 23926.32 22282.06 20610.81 18939.56 17268.31

Interest on Loan (IoL)

55. Regulation 32 of the 2019 Tariff Regulations provides as under:

“32. Interest on loan capital: (1) The loans arrived at in the manner indicated in Regulation 18 of these regulations shall be considered as gross normative loan for calculation of interest on loan.

(2) The normative loan outstanding as on 1.4.2019 shall be worked out by deducting the cumulative repayment as admitted by the Commission up to 31.3.2019 from the gross normative loan.

(3) The repayment for each of the year of the tariff period 2019-24 shall be deemed to be equal to the depreciation allowed for the corresponding year/period. In case of de-capitalization of assets, the repayment shall be adjusted by taking into account cumulative repayment on a pro rata basis and the adjustment should not exceed cumulative depreciation recovered upto the date of de-capitalisation of such asset.

(4) Notwithstanding any moratorium period availed by the generating company or the transmission licensee, as the case may be, the repayment of loan shall be considered from the first year of commercial operation of the project and shall be equal to the depreciation allowed for the year or part of the year.

(5) The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual loan portfolio after providing appropriate accounting adjustment for interest capitalized:

Provided that if there is no actual loan for a particular year but normative loan is still outstanding, the last available weighted average rate of interest shall be considered;

Provided further that if the generating station or the transmission system, as the case may be, does not have actual loan, then the weighted average rate of interest of the generating company or the transmission licensee as a whole shall be considered.

(6) The interest on loan shall be calculated on the normative average loan of the year by applying the weighted average rate of interest.

(7) The changes to the terms and conditions of the loans shall be reflected from the date of such re-financing.”

56. The weighted average rate of IoL has been considered on the basis of rate prevailing as on 1.4.2019. The Petitioner has prayed that the change in interest rate due to floating rate of interest applicable, if any, during the 2019-24 tariff period may be adjusted. Accordingly, the floating rate of interest, if any, shall be considered at the time of true up. Therefore, IoL has been allowed in accordance with Regulation 32 of the 2019 Tariff Regulations. IoL allowed for the transmission asset is as under:

(Rs. in lakh)

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Gross Normative Loan 22036.21 22078.19 22078.19 22078.19 22078.19 Cumulative Repayments upto Previous Year 2768.22 4437.89 6109.14 7780.39 9451.64 Net Loan-Opening 19267.98 17640.30 15969.05 14297.80 12626.55 Additions 41.99 0.00 0.00 0.00 0.00 Repayment during the year 1669.67 1671.25 1671.25 1671.25 1671.25 Net Loan-Closing 17640.30 15969.05 14297.80 12626.55 10955.30 Average Loan 18454.14 16804.68 15133.42 13462.17 11790.92 Weighted Average Rate of Interest on Loan (%) 8.1413 8.1158 8.1238 8.1354 8.1238 Interest on Loan 1502.40 1363.83 1229.41 1095.21 957.87

Return on Equity (RoE)

57. Regulation 30 and Regulation 31 of the 2019 Tariff Regulations provides as under:

“30. Return on Equity: (1) Return on equity shall be computed in rupee terms, on the equity base determined in accordance with Regulation 18 of these regulations.

(2) Return on equity shall be computed at the base rate of 15.50% for thermal generating station, transmission system including communication system and run-of-river hydro generating station, and at the base rate of 16.50% for the storage type hydro generating stations including pumped storage hydro generating stations and run-of-river generating station with pondage:

Provided that return on equity in respect of additional capitalization after cut-off date beyond the original scope shall be computed at the weighted average rate of interest on actual loan portfolio of the generating station or the transmission system

Provided further that:

i. In case of a new project, the rate of return on equity shall be reduced by 1.00% for such period as may be decided by the Commission, if the generating station or transmission system is found to be declared under commercial operation without commissioning of any of the Restricted Governor Mode Operation (RGMO) or Free Governor Mode Operation (FGMO), data telemetry, communication system up to load dispatch centre or protection system based on the report submitted by the respective RLDC;

ii. in case of existing generating station, as and when any of the requirements under (i) above of this Regulation are found lacking based on the report submitted by the concerned RLDC, rate of return on equity shall be reduced by 1.00% for the period for which the deficiency continues;

iii. in case of a thermal generating station, with effect from 1.4.2020:

a) rate of return on equity shall be reduced by 0.25% in case of failure to achieve the ramp rate of 1% per minute;

b) an additional rate of return on equity of 0.25% shall be allowed for every incremental ramp rate of 1% per minute achieved over and above the ramp rate of 1% per minute, subject to ceiling of additional rate of return on equity of 1.00%:

Provided that the detailed guidelines in this regard shall be issued by National Load Dispatch Centre by 30.6.2019.”

“31. Tax on Return on Equity. (1) The base rate of return on equity as allowed by the Commission under Regulation 30 of these regulations shall be grossed up with the effective tax rate of the respective financial year. For this purpose, the effective tax rate shall be considered on the basis of actual tax paid in respect of the financial year in line with the provisions of the relevant Finance Acts by the concerned generating company or the transmission licensee, as the case may be. The actual tax paid on income from other businesses including deferred tax liability (i.e. income from business other than business of generation or transmission, as the case may be) shall be excluded for the calculation of effective tax rate.

(2) Rate of return on equity shall be rounded off to three decimal places and shall be computed as per the formula given below:

Rate of pre-tax return on equity = Base rate/(1-t)

Where “t” is the effective tax rate in accordance with clause (1) of this Regulation and shall be calculated at the beginning of every financial year based on the estimated profit and tax to be paid estimated in line with the provisions of the relevant Finance Act applicable for that financial year to the company on pro-rata basis by excluding the income of non-generation or non-transmission business, as the case may be, and the corresponding tax thereon. In case of generating company or transmission licensee paying Minimum Alternate Tax (MAT), “t” shall be considered as MAT rate including surcharge and cess.

Illustration-

(i) In case of a generating company or a transmission licensee paying Minimum Alternate Tax (MAT) @ 21.55% including surcharge and cess:

Rate of return on equity = 15.50/(1-0.2155) = 19.758%

(ii) In case of a generating company or a transmission licensee paying normal corporate tax including surcharge and cess:

(a) Estimated Gross Income from generation or transmission business for FY 2019-20 is Rs. 1,000 crore;

(b) Estimated Advance Tax for the year on above is Rs. 240 crore;

(c) Effective Tax Rate for the year 2019-20 = Rs. 240 Crore/Rs. 1000 Crore = 24%;

(d) Rate of return on equity = 15.50/(1-0.24) = 20.395%.

(3) The generating company or the transmission licensee, as the case may be, shall true up the grossed up rate of return on equity at the end of every financial year based on actual tax paid together with any additional tax demand including interest thereon, duly adjusted for any refund of tax including interest received from the income tax authorities pertaining to the tariff period 2019-24 on actual gross income of any financial year. However, penalty, if any, arising on account of delay in deposit or short deposit of tax amount shall not be claimed by the generating company or the transmission licensee, as the case may be. Any under-recovery or over-recovery of grossed up rate on return on equity after truing up, shall be recovered or refunded to beneficiaries or the long term customers, as the case may be, on year to year basis.”

58. The Petitioner has submitted that MAT rate is applicable to the Petitioner's company. Accordingly, the MAT rate applicable for 2019-20 has been considered for the purpose of RoE, which shall be trued up with actual tax rate in accordance with Regulation 31(3) of the 2019 Tariff Regulations. RoE allowed for the transmission asset is as under:

(Rs. in lakh)

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Opening Equity 9444.09 9462.08 9462.08 9462.08 9462.08 Additions 17.99 0.00 0.00 0.00 0.00 Closing Equity 9462.08 9462.08 9462.08 9462.08 9462.08 Average Equity 9453.08 9462.08 9462.08 9462.08 9462.08 Return on Equity (Base Rate) (%) 15.50 15.50 15.50 15.50 15.50 MAT Rate for respective year (%) 17.472 17.472 17.472 17.472 17.472 Rate of Return on Equity (%) 18.782 18.782 18.782 18.782 18.782 Return on Equity 1775.43 1777.12 1777.12 1777.12 1777.12

Operation & Maintenance Expenses (O&M Expenses)

59. The O&M expenses claimed by the Petitioner for the transmission asset for the 2019-24 period are as under:

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 400 kV: Vapi-Kakrapar bay No. of bays 2 2 2 2 2 Norms (Rs. lakh/Bay) 32.15 33.28 34.45 35.66 36.91 400 kV GIS: Navsari-Kakrapar bay No. of bays 2 2 2 2 2 N orms (Rs. lakh/Bay) 22.505 23.296 24.115 24.962 25.837 Transmission line: Vapi-Kakrapar-Navsari (151.18 km) D/C Bundled (4 or more sub-conductors) 151.18 151.18 151.18 151.18 151.18 Norms (Rs. lakh/km) 1.322 1.368 1.416 1.466 1.517 Multi Ckt Bundled with 4 or more sub-conductors 4.07 4.07 4.07 4.07 4.07 Norms (Rs. lakh/km) 2.319 2.401 2.485 2.572 2.662 PLCC Cost 255.94 255.94 255.94 255.94 255.94 Norms (Rs. lakh) 2.0% of the original project cost related to such communication system Total O&M expense (Rs. in lakh) 323.73 334.85 346.43 358.46 370.78

60. Regulations 35(3) and (4) of the 2019 Tariff Regulations provides as follows:

“35. Operation and Maintenance Expenses:

(3) Transmission system: (a) The following normative operation and maintenance expenses shall be admissible for the transmission system:

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Norms for sub-station Bays (Rs. Lakh per bay) 765 kV 45.01 46.60 48.23 49.93 51.68 400 kV 32.15 33.28 34.45 35.66 36.91 220 kV 22.51 23.30 24.12 24.96 25.84 132 kV and below 16.08 16.64 17.23 17.83 18.46 Norms for Transformers (Rs. Lakh per MVA) 765 kV 0.491 0.508 0.526 0.545 0.564 400 kV 0.358 0.371 0.384 0.398 0.411 220 kV 0.245 0.254 0.263 0.272 0.282 132 kV and below 0.245 0.254 0.263 0.272 0.282 Norms for AC and HVDC lines (Rs. Lakh per km) Single Circuit (Bundled Conductor with six or more sub-conductors) 0.881 0.912 0.944 0.977 1.011 Single Circuit (Bundled conductor with four sub-conductors) 0.755 0.781 0.809 0.837 0.867 Single Circuit (Twin & Triple Conductor) 0.503 0.521 0.539 0.558 0.578 Single Circuit (Single Conductor) 0.252 0.260 0.270 0.279 0.289 Double Circuit (Bundled conductor with four or more sub- 1.322 1.368 1.416 1.466 1.517 Double Circuit (Twin & Triple Conductor) 0.881 0.912 0.944 0.977 1.011 Double Circuit (Single Conductor) 0.377 0.391 0.404 0.419 0.433 Multi Circuit (Bundled Conductor with four or more sub-conductor) 2.319 2.401 2.485 2.572 2.662 Multi Circuit (Twin & Triple Conductor) 1.544 1.598 1.654 1.713 1.773 Norms for HVDC stations HVDC Back-to-Back stations (Rs. Lakh per 500 MW) (Except Gazuwaka BTB) 834 864 894 925 958 Gazuwaka HVDC Back-to-Back station (Rs. Lakh per 500 MW) 1,666 1,725 1,785 1,848 1,913 500 kV Rihand-Dadri HVDC bipole scheme (Rs. Lakh) (1500 MW) 2,252 2,331 2,413 2,498 2,586 ±500 kV Talcher-Kolar HVDC bipole scheme (Rs. Lakh) (2000 MW) 2,468 2,555 2,645 2,738 2,834 ±500 kV Bhiwadi-Balia HVDC bipole scheme (Rs. Lakh) (2500 MW) 1,696 1,756 1,817 1,881 1,947 ±800 kV, Bishwanath-Agra HVDC bipole scheme (Rs. Lakh) (3000 MW) 2,563 2,653 2,746 2,842 2,942

Provided that the O&M expenses for the GIS bays shall be allowed as worked out by multiplying 0.70 of the O&M expenses of the normative O&M expenses for bays;

Provided further that:

i. the operation and maintenance expenses for new HVDC bi-pole schemes commissioned after 1.4.2019 for a particular year shall be allowed pro-rata on the basis of normative rate of operation and maintenance expenses of similar HVDC bi-pole scheme for the corresponding year of the tariff period;

ii. the O&M expenses norms for HVDC bi-pole line shall be considered as Double Circuit quad AC line;

iii. the O&M expenses of ±500 kV Mundra-Mohindergarh HVDC bipole scheme (2000 MW) shall be allowed as worked out by multiplying 0.80 of the normative O&M expenses for ±500 kV Talchar-Kolar HVDC bi-pole scheme (2000 MW);

iv. the O&M expenses of ±800 kV Champa-Kurukshetra HVDC bi-pole scheme (3000 MW) shall be on the basis of the normative O&M expenses for ±800 kV, Bishwanath-Agra HVDC bi-pole scheme;

v. the O&M expenses of ±800 kV, Alipurduar-Agra HVDC bi-pole scheme (3000 MW) shall be allowed as worked out by multiplying 0.80 of the normative O&M expenses for ±800 kV, Bishwanath-Agra HVDC bi-pole scheme; and

vi. the O&M expenses of Static Synchronous Compensator and Static Var Compensator shall be worked at 1.5% of original project cost as on commercial operation which shall be escalated at the rate of 3.51% to work out the O&M expenses during the tariff period. The O&M expenses of Static Synchronous Compensator and Static Var Compensator, if required, may be reviewed after three years.

(b) The total allowable operation and maintenance expenses for the transmission system shall be calculated by multiplying the number of substation bays, transformer capacity of the transformer (in MVA) and km of line length with the applicable norms for the operation and maintenance expenses per bay, per MVA and per km respectively.

(c) The Security Expenses and Capital Spares for transmission system shall be allowed separately after prudence check:

Provided that the transmission licensee shall submit the assessment of the security requirement and estimated security expenses, the details of year-wise actual capital spares consumed at the time of truing up with appropriate justification.

(4) Communication system: The operation and maintenance expenses for the communication system shall be worked out at 2.0% of the original project cost related to such communication system. The transmission licensee shall submit the actual operation and maintenance expenses for truing up.”

61. The Petitioner has claimed O&M Expenses separately for the PLCC under Regulation 35(4) of the 2019 Tariff Regulations @2% of its original project cost in the instant petition. The Petitioner has made similar claim in other petitions as well. Though PLCC is a communication system, it has been considered as part of the substation in the 2014 Tariff Regulation and the 2019 Tariff Regulations and the norms for sub-station have been specified accordingly. Accordingly, the Commission vide order dated 24.1.2021 in Petition No. 126/TT/2020 has already concluded that no separate O&M Expenses can be allowed for PLCC under Regulation 35(4) of the 2019 Tariff Regulations even though PLCC is a communication system. Therefore, the Petitioner's claim for separate O&M Expenses for PLCC @2% is not allowed. The relevant portions of the order dated 24.1.2021 in Petition No. 126/TT/2020 are extracted hereunder:

“103. Thus, although PLCC equipment is a communication system, it has been considered as a part of sub-station, as it is used both for protection and communication. Therefore, we are of the considered view that rightly, it was not considered for separate O&M Expenses while framing norms of O&M for 2019-24 tariff period. While specifying norms for bays and transformers, O&M Expenses for PLCC have been included within norms for O&M Expenses for sub-station. Norms of O&M Expenses @2% of the capital cost in terms of Regulation 35(4) of the 2019 Tariff Regulations have been specified for communication system such as PMU, RMU, OPGW etc. and not for PLCC equipment.”

“105. In our view, granting of O&M Expenses for PLCC equipment @2% of its capital cost under Regulation 35(4) of the 2014 Tariff Regulations under the communication system head would tantamount to granting O&M Expenses twice for PLCC equipment as PLCC equipment has already been considered as part of the sub-station. Therefore, the Petitioner's prayer for grant of O&M Expenses for the PLCC equipment @2% of its capital cost under Regulation 35(4) of the 2014 Tariff Regulations is rejected.

106. The principle adopted in this petition that PLCC is part of sub-station and accordingly no separate O&M Expenses is admissible for PLCC equipment in the 2019-24 tariff period under Regulation 35(4) of the 2019 Tariff Regulations shall be applicable in case of all petitions where similar claim is made by the Petitioner. As already mentioned, the Commission, however, on the basis of the claim made by the Petitioner has inadvertently allowed O&M Expenses for PLCC equipment @2% of its original project cost, which is applicable for other “communication system”, for 2019-24 period in 31 petitions given in Annexure-3 of this order. Therefore, the decision in this order shall also be applicable to all the petitions given in Annexure-3. Therefore, PGCIL is directed to bring this decision to the notice of all the stakeholders in the 31 petitions given in Annexure-3 and also make revised claim of O&M Expenses for PLCC as part of the sub-station at the time of truing up of the tariff allowed for 2019-24 period in respective petitions.”

62. Therefore, the Petitioner's claim for separate O&M Expenses for PLCC @2% is not allowed.

63. The O&M Expenses allowed as per the norms specified in the 2019 Tariff Regulations for the transmission assets is as under:

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 400 kV: Vapi-Kakrapar bay No. of bays 2 2 2 2 2 Norms (Rs. lakh/Bay) 32.15 33.28 34.45 35.66 36.91 400 kV GIS: Navsari-Kakrapar bay No. of bays 2 2 2 2 2 Norms (Rs. lakh/Bay) 22.505 23.296 24.115 24.962 25.837 Transmission line: Vapi-Kakrapar-Navsari (km) D/C Bundled (4 or more sub-conductors) 151.18 151.18 151.18 151.18 151.18 Norms (Rs. lakh/km) 1.322 1.368 1.416 1.466 1.517 Multi Ckt Bundled with 4 or more sub-conductors 4.07 4.07 4.07 4.07 4.07 Norms (Rs. lakh/km) 2.319 2.401 2.485 2.572 2.662 Total O&M Expenses (Rs. in lakh) 318.61 329.74 341.31 353.34 365.67

Interest on Working Capital (IWC)

64. Regulation 34(1)(c), Regulation 34(3), Regulation 34(4) and Regulation 3(7) of the 2019 Tariff Regulations specify as under:

“34. Interest on Working Capital: (1) The working capital shall cover:

(a) For Coal-based/lignite-fired thermal generating stations:

(i) Cost of coal or lignite and limestone towards stock, if applicable, for 10 days for pit-head generating stations and 20 days for non-pit-head generating stations for generation corresponding to the normative annual plant availability factor or the maximum coal/lignite stock storage capacity whichever is lower;

(ii) Advance payment for 30 days towards cost of coal or lignite and limestone for generation corresponding to the normative annual plant availability factor;

(iii) Cost of secondary fuel oil for two months for generation corresponding to the normative annual plant availability factor, and in case of use of more than one secondary fuel oil, cost of fuel oil stock for the main secondary fuel oil;

(iv) Maintenance spares @ 20% of operation and maintenance expenses including water charges and security expenses;

(v) Receivables equivalent to 45 days of capacity charge and energy charge for sale of electricity calculated on the normative annual plant availability factor; and

(vi) Operation and maintenance expenses, including water charges and security expenses, for one month.

(b) For Open-cycle Gas Turbine/Combined Cycle thermal generating stations:

(i) Fuel cost for 30 days corresponding to the normative annual plant availability factor, duly taking into account mode of operation of the generating station on gas fuel and liquid fuel;

(ii) Liquid fuel stock for 15 days corresponding to the normative annual plant availability factor, and in case of use of more than one liquid fuel, cost of main liquid fuel duly taking into account mode of operation of the generating stations of gas fuel and liquid fuel;

(iii) Maintenance spares @ 30% of operation and maintenance expenses including water charges and security expenses;

(iv) Receivables equivalent to 45 days of capacity charge and energy charge for sale of electricity calculated on normative plant availability factor, duly taking into account mode of operation of the generating station on gas fuel and liquid fuel; and

(v) Operation and maintenance expenses, including water charges and security expenses, for one month.

(c) For Hydro Generating Station (including Pumped Storage Hydro Generating Station) and Transmission System:

(i) Receivables equivalent to 45 days of annual fixed cost;

(ii) Maintenance spares @ 15% of operation and maintenance expenses including security expenses; and

(iii) Operation and maintenance expenses, including security expenses for one month.

(2) The cost of fuel in cases covered under sub-clauses (a) and (b) of clause (1) of this Regulation shall be based on the landed fuel cost (taking into account normative transit and handling losses in terms of Regulation 39 of these regulations) by the generating station and gross calorific value of the fuel as per actual weighted average for the third quarter of preceding financial year in case of each financial year for which tariff is to be determined:

Provided that in case of new generating station, the cost of fuel for the first financial year shall be considered based on landed fuel cost (taking into account normative transit and handling losses in terms of Regulation 39 of these regulations) and gross calorific value of the fuel as per actual weighted average for three months, as used for infirm power, preceding date of commercial operation for which tariff is to be determined.

(3) Rate of interest on working capital shall be on normative basis and shall be considered as the bank rate as on 1.4.2019 or as on 1st April of the year during the tariff period 2019-24 in which the generating station or a unit thereof or the transmission system including communication system or element thereof, as the case may be, is declared under commercial operation, whichever is later:

Provided that in case of truing-up, the rate of interest on working capital shall be considered at bank rate as on 1st April of each of the financial year during the tariff period 2019-24.

(4) Interest on working capital shall be payable on normative basis notwithstanding that the generating company or the transmission licensee has not taken loan for working capital from any outside agency.”

“3. Definitions. - In these regulations, unless the context otherwise requires:-

‘Bank Rate’ means the one year marginal cost of lending rate (MCLR) of the State Bank of India issued from time to time plus 350 basis points;”

65. The Petitioner has submitted that it has computed IWC for the 2019-24 period considering the SBI Base Rate plus 350 basis points as on 1.4.2019. The Petitioner has considered the rate of IWC as 12.05%.

66. IWC is worked out in accordance with Regulation 34 of the 2019 Tariff Regulations. The ROI considered is 12.05% (SBI 1-year MCLR applicable as on 1.4.2019 of 8.55% plus 350 basis points) for 2019-20, whereas, ROI for 2020-21 onwards has been considered as 11.25% (SBI 1-year MCLR applicable as on 1.4.2020 of 7.75% plus 350 basis points). The components of the working capital and interest allowed thereon are as under:

(Rs. in lakh)

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 O&M Expenses 26.55 27.48 28.44 29.45 30.47 Maintenance Spares 47.79 49.46 51.20 53.00 54.85 Receivables 658.33 643.94 628.62 613.38 596.14 Total Working Capital 732.67 720.88 708.26 695.83 681.46 Rate of Interest (%) 12.05 11.25 11.25 11.25 11.25 Interest on Working Capital 88.29 81.10 79.68 78.28 76.66

Annual Fixed Charges of the 2019-24 Tariff Period

67. The transmission charges allowed for the transmission asset for the 2019-24 tariff period are as under:

(Rs. in lakh)

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Depreciation 1669.67 1671.25 1671.25 1671.25 1671.25 Interest on Loan 1502.40 1363.83 1229.41 1095.21 957.87 Return on Equity 1775.43 1777.12 1777.12 1777.12 1777.12 Interest on Working Capital 88.29 81.10 79.68 78.28 76.66 O & M Expenses 318.61 329.74 341.31 353.34 365.67 Total 5354.39 5223.04 5098.77 4975.20 4848.57

Filing Fee and the Publication Expenses

68. The Petitioner has sought reimbursement of fee paid by it for filing the petition and publication expenses. The Petitioner shall be entitled for reimbursement of the filing fees and publication expenses in connection with the present petition, directly from the beneficiaries on pro-rata basis in accordance with Regulation 70(1) of the 2019 Tariff Regulations.

Licence Fee & RLDC Fees and Charges

69. The Petitioner shall be entitled for reimbursement of licence fee in accordance with Regulation 70(4) of the 2019 Tariff Regulations for the 2019-24 tariff period. The Petitioner shall also be entitled for recovery of RLDC fee and charges in accordance with Regulations 70(3) of the 2019 Tariff Regulations for the 2019-24 tariff period.

Security Expenses

70. The Petitioner has submitted that security expenses for the transmission asset are not claimed in the instant petition and it would file a separate petition for claiming the overall security expenses and the consequential IWC. The Petitioner has requested to consider the actual security expenses incurred during 2018-19 for claiming estimated security expenses for 2019-20 which shall be subject to true up at the end of the year based on the actuals. The Petitioner has submitted that similar petition for security expenses for 2020-21, 2021-22, 2022-23 and 2023-24 shall be filed on a yearly basis on the basis of the actual expenses of previous year subject to true up at the end of the year on actual expenses. The Petitioner has submitted that the difference, if any, between the estimated security expenses and actual security expenses as per the audited accounts may be allowed to be recovered from the beneficiaries on a yearly basis.

71. We have considered the submissions of the Petitioner and BRPL. We are of the view that the Petitioner should claim security expenses for all the transmission assets in one petition. It is observed that the Petitioner has already filed the Petition No. 260/MP/2020 claiming consolidated security expenses on projected basis for the 2019-24 tariff period on the basis of actual security expenses incurred in 2018-19. Therefore, security expenses will be dealt with in Petition No. 260/MP/2020 in accordance with the applicable provisions of the 2019 Tariff Regulations.

Goods and Services Tax

72. The Petitioner has submitted that, if GST is levied at any rate and at any point of time in future on Charges of Transmission of Electricity, the same shall be borne and additionally paid by the respondent(s) to the Petitioner and the same shall be charged & billed separately by the Petitioner. Further additional taxes, if any, are to be paid by the Petitioner on account of demand from Government/Statutory authorities, the same may be allowed to be recovered from the beneficiaries.

73. We have considered the submission of the Petitioner. Since GST is not levied on transmission service at present, we are of the view that Petitioner's prayer is premature.

Capital Spares

74. The Petitioner has sought reimbursement of capital spares at the end of tariff block. The Petitioner's claim, if any, shall be dealt with in accordance with the provisions of the 2019 Tariff Regulations.

Sharing of Transmission Charges

75. The billing, collection and disbursement of the transmission charges approved shall be governed by the provisions of Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, or the Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2020, as applicable, as provided in Regulation 43 of 2014 Tariff Regulations for the 2014-19 tariff period and Regulation 57 of the 2019 Tariff Regulations for the 2019-24 tariff period.

76. To summarise, the trued-up Annual Fixed Charges allowed for the transmission asset for the years 2017-19 in the 2014-19 tariff period are as under:

(Rs. in lakh)

Particulars 2017-18 (Pro-rata 276 days) 2018-19 Annual Fixed Charges 4076.42 5584.54

77. The Annual Fixed Charges allowed for the transmission asset for the 2019-24 tariff period are as under:

(Rs. in lakh)

Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Annual Fixed Charges 5354.39 5223.04 5098.77 4975.20 4848.57

78. This order disposes of Petition No. 15/TT/2020.

Annexure-I

2014-19 Admitted Capital Cost as on 29.6.2017 (COD) (Rs. in lakh) ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2019 (Rs. in lakh) Rate of Depreciation as per Regulations Annual Depreciation as per Regulations (Rs. in lakh) Particulars 2017-18 2018-19 2017-18 2018-19 Building Civil Works & Colony 61.99 15.62 3.77 81.37 3.34% 2.33 2.65 Transmission Line 23185.58 1155.31 1460.00 25800.89 5.28% 1254.70 1323.74 Sub Station 4502.92 467.50 322.27 5292.69 5.28% 250.10 270.95 PLCC 220.13 22.25 13.37 255.76 6.33% 14.64 15.77 IT Equipment (Incl. Softw are) 46.68 0.06 2.84 49.57 5.28% 2.47 2.54 Total 28017.30 1660.74 1802.25 31480.29 1524.23 1615.65 Average Gross Block 28847.67 30579.16 Weighted Average Rate of Depreciation 5.28% 5.28%

Annexure-II

2019-24 Admitted Capital Cost as on 1.4.2019 (Rs. in lakh) Projected ACE (Rs. in lakh) Admitted Capital Cost as on 31.3.2024 (Rs. in lakh) Rate of Depreciation as per Regulations Annual Depreciations as per Regulations (Rs. in lakh) Particulars 2019-20 2019-20 2020-21 2021-22 2022-23 2023-24 Building Civil Works & Colony 81.38 0.00 81.38 3.34% 2.72 2.72 2.72 2.72 2.72 Transmission Line 25800.90 54.36 25855.26 5.28% 1363.72 1365.16 1365.16 1365.16 1365.16 Sub Station 5292.69 5.62 5298.31 5.28% 279.60 279.75 279.75 279.75 279.75 PLCC 255.75 0.00 255.75 6.33% 16.19 16.19 16.19 16.19 16.19 IT Equipment (Incl. Software) 49.57 0.00 49.57 15.00% 7.44 7.44 7.44 7.44 7.44 Total 31480.29 59.98 31540.27 1669.67 1671.25 1671.25 1671.25 1671.25 Average Gross Block 31510.28 31540.27 31540.27 31540.27 31540.27 Weighted Average Rate of Depreciation 5.30% 5.30% 5.30% 5.30% 5.30%