- Bookmark
- Share
- CaseIQ
R. Narayanan v. Government of Tamil ...
Factual and Procedural Background
Nagercoil Municipal Corporation constructed shops at Vadaseri Christopher Bus Stand and offered licenses by public tender/auction on 16.10.2019. The Petitioner was the successful bidder for Shop No.12-A (Phase I) and was granted a three-year license commencing 1.11.2019. The Petitioner paid substantial sums upfront, including one year’s license fee in advance, refundable deposit and security deposit.
Following the Covid-19 outbreak, central and state directives (including the NDMA order dated 24.3.2020 and Tamil Nadu G.O.(Ms) No.152 dated 23.3.2020) resulted in closure of the Bus Stand and the shops. A total lockdown prevailed from 24.3.2020 to 6.9.2020, after which restrictions were partially relaxed. The Petitioner alleged financial loss, decided not to seek renewal, and sought relief from payment of license fee for the total lockdown period and reduction/proportionate revision thereafter by submitting a representation.
The Petitioner filed a writ petition under Article 226 seeking writ of mandamus to forbear the Respondents from demanding license fee for 24.3.2020 to 6.9.2020 and to revise license fee proportionately thereafter. The respondents (Government and Local Body) asserted that contractual obligation to pay the monthly license fee was absolute and not excused by supervening events, but pointed to G.O.(D) No.298 (dated 2.9.2020) which had waived lease/rental for 1.4.2020 to 31.5.2020. The petition proceeded to adjudication and the court considered contractual doctrines and constitutional principles in determining relief.
Legal Issues Presented
- Whether the Petitioner is relieved from the obligation to pay license fee for the period of total lockdown (24.3.2020 to 6.9.2020) in view of the Covid-19 restrictions and government orders.
- Whether the Doctrine of Frustration (Section 56, Indian Contract Act, 1872) or the principle of force majeure can be invoked to excuse the Petitioner’s non-performance of contractual payment obligations.
- Whether the Court can grant relief beyond the scope of G.O.(D) No.298 (which waived fees for 1.4.2020 to 31.5.2020) and, if so, on what legal basis.
Arguments of the Parties
Petitioner's Arguments
- The Petitioner sought complete waiver of license fee for the period of total lockdown (24.3.2020 to 6.9.2020) because the Bus Stand and the shop were closed pursuant to government orders and he was prevented from accessing and operating the shop.
- For the period after partial relaxation, the Petitioner requested proportionate reduction/re-fixation of license fee in accordance with the limited opening times permitted.
- The Petitioner submitted a representation to the local body seeking the above reliefs and contended that he should not be made to suffer for a period when performance was prevented by government directives beyond his control.
Respondents' Arguments
- The Respondents contended the contractual obligation to pay monthly license fee was absolute and not excused by any supervening event; performance obligations under the license remained binding.
- They relied on the Government Order G.O.(D) No.298 dated 2.9.2020 which directed waiver of lease/rental for 1.4.2020 to 31.5.2020, and noted that the Petitioner had not challenged that G.O.; accordingly, the Court could grant relief only within the terms of that G.O. and not beyond.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Davis Contractors Ltd. v. Fareham Urban District Council (1956) A.C. 696 | Classic formulation of the Doctrine of Frustration: frustration occurs when performance becomes radically different from what was undertaken so as to discharge parties from obligations. | The judgment was cited to explain the conceptual difference between frustration and force majeure and to define frustration as a legal doctrine that terminates contractual obligations where performance becomes impossible in the fundamental sense. |
| South East Asia Marine Engg. & Constructions Ltd. (SEAMEC Ltd.) v. Oil India Ltd., 2020 (5) SCC 164 | Interpreting Section 56 of the Indian Contract Act: on occurrence of an event rendering performance impossible, the contract becomes void thereafter; effect of frustration under Indian law and interplay with restitution under Section 65. | The Court relied on SEAMEC to state that under Indian law frustration discharges parties from future obligations and to note the limited restitution mechanism under Section 65 for advantages received under a void contract. |
| Jamshed Hormusji Wadia v. Board of Trustees, Port of Mumbai, 2004 (3) SCC 214 | State and its instrumentalities must act justly, fairly and reasonably in contractual and landlord-tenant contexts; actions tested against Article 14. | Cited to support the proposition that when one contracting party is a State instrumentality (here, the municipal corporation), contractual terms must be interpreted and applied in a manner consistent with fairness and reasonableness under Article 14. |
| Bharat Petroleum Corpn. Ltd. v. Maddula Ratnavalli, 2007 (6) SCC 81 | Entities that are State within Article 12 are enjoined to act fairly and reasonably; statutory orders and discretion must be exercised bona fide and not arbitrarily. | Applied to reinforce that the local body (a State instrumentality) must exercise contractual and statutory powers reasonably and that the Court may scrutinize such actions under constitutional principles. |
Court's Reasoning and Analysis
The Court commenced by characterizing the parties’ relationship as contractual, with performance and rights generally determined by the contract. It considered two principal doctrines for post-contractual supervening events: the Doctrine of Frustration and the concept of force majeure (as explained in authorities and texts).
The Court analyzed frustration (as in Davis Contractors and embodied in Section 56, Indian Contract Act) and observed that frustration has the effect of terminating the contract and discharging parties from future obligations. Relying on SEAMEC, the Court noted that under Indian law frustration discharges parties and Section 65 provides limited restitution for advantages received. The Court concluded frustration could not apply because the contractual relationship continued: after lockdown was lifted the Petitioner resumed occupation and business and the license remained in force.
Turning to force majeure and related principles, the Court noted there was no force majeure clause in the parties' agreement; the tender contained a stipulation that the licensee would not be excused from payment under any circumstance. Nonetheless, the Court examined statutory and contractual principles that govern reciprocal promises.
The Court relied upon Sections 51 and 54 of the Indian Contract Act (reciprocal promises and simultaneous performance) to reason that where a contract consists of reciprocal promises, one party need not perform if the other is not in a position to perform. The Local Body had a reciprocal obligation to keep the Bus Stand open and permit the licensee to operate. Where the Local Body, by its directives (based on central and state orders), prevented the licensee from accessing and operating the shop, the Court found it would be inequitable to compel the licensee to pay fees for the enforced closure.
The Court further applied constitutional principles of reasonableness and fairness. It relied on Supreme Court decisions (Jamshed Wadia and Bharat Petroleum) to emphasize that State instrumentalities must act fairly and reasonably, and contractual terms involving a State party must be scrutinized under Article 14. The Court observed that the Government itself recognized lockdown as a force majeure event by issuing G.O.(D) No.298 waiving lease/rental for 1.4.2020–31.5.2020, and concluded that the rationale for that waiver would equally apply to the entire period of total lockdown.
Considering the factual finding that Vadaseri Bus Stand remained closed from 24.3.2020 to 6.9.2020 and that the Respondents had directed the Petitioner not to open the shop till 6.9.2020, the Court treated the lock down as a force majeure event for purposes of equitable relief. It held the Petitioner entitled to complete waiver for the period of total lockdown and to seek reconsideration of fee quantum for the subsequent partial-relaxation period by fresh representation. The Court did not enter into detailed re-fixation itself but directed administrative reconsideration in accordance with law.
Holding and Implications
Holding:
The Writ Petition is allowed. In particular, the Court ordered that the Petitioner is totally relieved from the obligation to pay the license fee for the period of total lockdown (24.3.2020 to 6.9.2020), i.e., the Petitioner is entitled to a complete waiver for that period.
For the period after 6.9.2020 (when restrictions were partially relaxed), the Court permitted the Petitioner to submit a fresh representation projecting grievances and seeking revision of the quantum of license fee; the Fourth Respondent will forward the representation and proposals to Respondents 1 and 2, who shall consider and pass appropriate orders in accordance with law expeditiously.
Implications:
- Direct effect on parties: The Petitioner obtains full waiver of license fees for the period 24.3.2020–6.9.2020. For the subsequent period, administrative reconsideration is ordered rather than judicial re-fixation.
- Legal principle applied: The Court treated government-imposed lockdown as a force majeure type event for equitable relief, applied reciprocal-promise principles (Sections 51 and 54) and constitutional standards of fairness/reasonableness where one contracting party is a State instrumentality.
- Scope of relief: The Court did not apply the Doctrine of Frustration (which would have terminated the contract) because the license continued and the Petitioner resumed business; instead it granted equitable relief consistent with government orders and constitutional norms.
- Precedential effect: The opinion applies and interprets established statutory and judicial authorities in the facts of this case; the Court did not state that it was creating or declaring a new, broader precedent beyond the described decision. The direct consequence is limited to the parties and the administrative directions ordered by the Court.
Order as to costs: No costs. Connected miscellaneous petitions closed.
(Prayer: Petition filed under Article 226 of the Constitution of India to issue a Writ of Mandamus, forbearing the Respondents from demanding License fee from the Petitioner for the period from 24.3.2020 to 6.9.2020 and to reduce, revise and re-fix the License fee in a manner proportionate with the opening time permitted for the period from 7.9.2020 onwards for Municipal Shop No.12-A, Phase I, Vadasery Christoper Bus Stand, Nagercoil, in view of COVID-19 Pandemic Government Total Lockdown Regulations.)
1. Nagercoil Municipal Corporation constructed a number of Shops within the premises of Vadaseri Christopher Bus Stand. Licenses to occupy them were brought for Public Tender cum Auction Sale on 16.10.2019. The Petitioner herein was the successful bidder for Shop No.12-A (Phase I). Accepting his offer to pay a sum of Rs.1,15,000 towards monthly fee, the Corporation issued License in his favour vide Proceedings, dated 31.10.2019. The License was for a period of three years commencing from 1.11.2019. The Petitioner paid a sum of Rs.13,80,000 towards refundable deposit and also a sum of Rs.10.00 lakhs towards Security Deposit. In other words, the Corporation had collected one year License fee from the Petitioner in advance.
2. Following the outbreak of Covid-19, the National Disaster Management Authority exercising its powers under Section 6(2) of the Disaster Management Act, 2005 issued Order, dated 24.3.2020 directing all the Authorities to take effective measures to prevent the spread of the pandemic in the country. Pursuant thereto, the State Government of Tamil Nadu issued G.O.(Ms) No.152, Health and Family Welfare (P1) Department, dated 23.3.2020 imposing restrictions. As a result, Vadaseri Bus Stand and all the Shops located within its premises came to be closed. The Petitioner was prevented from accessing the Shop. The business could not run. Such a complete lock down was in force from 24.3.2020 to 6.9.2020. Thereafter, there was partial lifting and relaxation of the restrictions.
3. The Petitioner has suffered considerable financial loss. He has made up his mind not to seek renewal of the License even though there is a Clause providing for it. Since the deposits made by the Petitioner are with the Local Body, it is about to adjust the same against the License fee arrears. The demand of the Petitioner is that the local body should grant total waiver of payment of License fee for the period from 24.3.2020 to 6.9.2020 and partial waiver for the subsequent period. In this regard, the Petitioner has submitted a representation.
4. In the Writ Petition, the Government as well as the Local Body have been arrayed as Respondents. The stand of the Respondents is that the contractual obligation to pay the Monthly License-fee is absolute and that it is not excused by any supervening event. However, considering the hardship experienced by the Licensees, the Government had issued G.O.(D) No.298, Municipal Administration and Water Supply (MA.IV) Department, dated 2.9.2020 ordering to waive payment of Lease/Rental amount for the period from 1.4.2020 to 31.5.2020. The Petitioner has not challenged the said G.O. Therefore, this Court can grant relief to the Petitioner only in terms of the said G.O. and cannot travel beyond.
5. I carefully considered the rival contentions and went through the materials on record. The relationship between the parties is contractual in nature. The rights of the parties will normally have to be determined in terms of the Contract. But when the performance of a Contract is affected by post-Contract events, the situation will have to be resolved either by invoking the Doctrine of frustration or the Principle of Force Majeure. "Frustration occurs whenever the law recognises that without default of either party a Contractual obligation has become incapable of being performed because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the Contract. Non haec in foedera veni. [It was not this that I promised to do]" (Lord Radcliffe's classic formulation in Davis Contractors Ltd. V. Fareham Urban District Council (1956) A.C. 696. "Force majeure" is defined as an event outside the control of the parties and which prevents one or both of the parties from performing their Contractual obligations. Force majeure Clause is a Clause in a Contract specifying certain events which would excuse the non-performance of a contractual obligation (P. Ramanatha Aiyar's Advanced Law Lexicon (5th Edition). The distinction between the two has been brought out in "Goode on Commercial Law" as follows:
"A Contract is said to be frustrated when a supervening event occurs, which so fundamentally affects the performance of the Contract that in the eyes of the law the Contract comes to an end and both parties are discharged from any future duty to perform. The English law Doctrine of Frustration is quite different from, say, the French law concept of force majeure. Frustration operates as a matter of law to bring the Contract to an end, whether or not the parties wish it and, indeed, whether or not they are aware of the frustrating event or its legal effect on the Contract. By contrast, force majeure under French law is a Doctrine under, which the impediment excuses a party from non-performance of a particular obligation without as such affecting the continuance of the Contract. It is for the party complaining of the non-performance to seek rescission of the Contract and for the Court to decide whether to grant rescission or to adjust the rights and obligations of the parties to take account of the effect of the impediment. The party invoking the force majeure event is required to give notice of it as soon as practicable. Force majeure Clauses are common in Contracts governed by English law, which, however, does not possess any legal Concept of Force Majeure. Accordingly, the events constituting force majeure, the impact of force majeure and the conditions in which it may be invoked stem entirely from the terms of the Contract. English law knows no tertium quid between frustration and non-frustration. If the Contract is frustrated it automatically comes to an end. If it is not, the parties must perform, however burdensome the Contract may have become and however much the circumstances may have changed. There is no duty on the parties to renegotiate the Contract terms, nor does the Court have power to modify the Contract on the ground of hardship or change in the economic equilibrium of the Contract, which may be particularly difficult to envisage or take into account in the negotiation of long-term Contracts. It is, thus, left to the parties to provide in hardship clauses for renegotiation.“
6. It is true that there is no”force majeure“Clause in the Agreement between the parties. On the other hand, in the Tender Notification, there is a stipulation that the Licensee will not be excused from his payment obligation under any circumstance.
7. The Doctrine of Frustration is embodied in Section 56 of the Indian Contract Act, 1872. Section 56 reads as follows:
“56. Agreement to do impossible act.-“An agreement to do an act impossible in itself is void. Contract to do act afterwards becoming impossible or unlawful.” A Contract to do an act which, after the Contract is made, becomes impossible, or, by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful.“
The jurisprudential aspects of this provision have been recently dealt with by the Hon'ble Supreme Court of India in South East Asia Marine Engg. & Constructions Ltd. (SEAMEC Ltd.) v. Oil India Ltd., 2020 (6) CTC 644 (SC): 2020 (5) SCC 164. It was held therein as follows:
“19. ....Under Indian Contract law, the consequences of a force majeure event are provided for under Section 56 of the Contract Act, which states that on the occurrence of an event which renders the performance impossible, the Contract becomes void thereafter.
20. ... ... ...
21. ... ... ...
22. ... ... ...
23. In India, the Contract Act, 1872 had already recognised the harsh consequences of such frustration to some extent and had provided for a limited mechanism to ameliorate the same under Section 65 of the Contract Act, 1872. Section 65 provides as under:
“65. Obligation of person who has received advantage under void Agreement, or Contract that becomes void.”When an agreement is discovered to be void, or when a Contract becomes void, any person who has received any advantage under such Agreement or Contract is bound to restore it, or to make Compensation for it, to the person from whom he received it. “The aforesaid clause provides the basis of restitution for “failure of basis”. We are cognizant that the aforesaid provision addresses limited circumstances wherein an agreement is void ab initio or the Contract becomes subsequently void.
26. ....under the Indian Contract law, the effect of the Doctrine of Frustration is that it discharges all the parties from future obligations.”
8. Since the consequence of invoking the Doctrine of Frustration is that it puts an end to the Contract, the same cannot be applied to the case on hand. Both the parties are proceeding on the premise that the contractual relationship is very much holding good. After the lockdown was lifted, the Petitioner was permitted to occupy the Shop and he is presently carrying on his business. The License is in force though it will expire shortly. Hence, invocation of Doctrine of frustration is ruled out.
9. The question is whether notwithstanding the stipulation of absolute performance cast on the Licensee, this Court would be justified in treating the “lock down” as a force majeure event, which will relieve the Licensee from performing his obligation to the corresponding extent.
10. My answer is in the affirmative. Section 51 of the Indian Contract Act, 1872 states that when a Contract consists of reciprocal promise to be simultaneously performed, no promisor need perform his promise unless the promisee is ready and willing to perform his reciprocal promise. As per Section 54, performance cannot be claimed till the other has been performed. The Local Body must keep the Bus Stand open and in good repair. The Licensee must be permitted to keep the licensed Shop open. If the local body had directed the Licensee to close down the Shop, it cannot demand fee from the Licensee for the period when the Shop remained closed. Of course, the Licensee must be free of any wrong doing. If the Licensee is made to suffer for no fault of his by direction to close down the Shop, then, the question of payment of fee will not arise. This is clearly an implied term in the Contract.
11. There is a greater reason too. The Petitioner has Contracted not with a private party but with Nagercoil Corporation. It is a State instrumentality. local bodies have been given Constitutional status. In the case on hand, their actions have been governed by the directives issued by the Central and State Governments. When one party to the Contract is the local body, then this Court would be justified in applying the Principles of Reasonableness and Fairness.
12. The Hon'ble Supreme Court in the Jamshed Hormusji Wadia v. Board of Trustees, Port of Mumbai, 2004 (3) SCC 214, held that the State and its Authorities including Instrumentalities of States have to be just, fair and reasonable in all their activities including those in the field of Contracts. Even while playing the role of a Landlord or a Tenant, the State and its Authorities remain so and cannot be heard or seen causing displeasure or discomfort to Article 14 of the Constitution of India. A State cannot be seen to be indulging in rack-renting, profiteering and indulging in whimsical or unreasonable evictions or bargains. The validity of their actions in the field of Landlord-Tenant relationship is available to be tested not under the Rent Control legislation but under the Constitution. The Rent Control legislations are temporary, if not seasonal; the Constitution is permanent and all time law.
13. In Bharat Petroleum Corpn. Ltd. v. Maddula Ratnavalli, 2007 (6) SCC 81, it was held that where an entity is a State within the meaning of Article 12 of the Constitution of India, it is enjoined with a duty to act fairly and reasonably. The State acting whether as a landlord or a Tenant is required to act bona fide and not arbitrarily, when the same is likely to affect prejudicially the right of others. A Statute must be construed justly. An unjust law is no law at all. A Statutory Order or discretion exercised by a Statutory Authority must be tested on the anvil of the Constitutional scheme. The action on the part of the State must be reasonable even in Contractual matters.
14. Applying the ratio laid down by the Hon'ble Supreme Court in the aforesaid decisions, this Court holds that the terms of the License must be interpreted under the scanner of Article 14 of the Constitution of India. What applies to the Landlord-Tenant relationship when one party is State or its instrumentality, equally applies to the Licensee-licensor relationship also. This sermon to the State is absolutely unnecessary. This is because the Government itself had recognized the lockdown as a force majeure event and issued G.O.(D) No.298, Municipal Administration and Water Supply (MA.IV) Department, dated 2.9.2020 directing waiver for a period of two months from 1.4.2020 to 31.5.2020. There is absolutely no merit in the contention of the Respondents that this G.O. has not been challenged. There is no need to challenge the G.O. This is because it confers benefit on the Licensees/Lessees. The only stand of the Licensee is that the extent of conferment is inadequate. It is seen that the said G.O. was issued in response to the Letter, dated 18.6.2020 sent by the Commissioner of Municipal Administration. A Letter sent in the month of June 2020 will obviously cover only the preceding months of April and May. No one would have anticipated that the lockdown would continue for several more months. Therefore, when the G.O. was issued in September, it straightaway accepted the proposal which was confined only to April and May 2020. That is how bureaucracy functions. The Secretary to Government did not deem it necessary to go beyond the terms of the request made by the Commissioner of Municipal Administration. But a Constitutional Court cannot have a blinkered vision. It must take into account the position that prevails on the date when the lis is adjudicated.
15. The Respondents themselves have chosen to treat the lock down restrictions as a force majeure event. But they have relieved the Licensees from the obligation to pay the fees only for two months. The reason for granting waiver for the months of April and May would equally hold good for the entire “total lockdown” period. Vadaseri Bus Stand remained closed from 24.3.2020 to 6.9.2020. The Respondents had directed the Petitioner not to open the Shop till 6.9.2020. Therefore, I hold that the Petitioner is entitled to the benefit of complete waiver for the period from 1.6.2020 to 6.9.2020.
16. During early stages of the pandemic, I read an article in Business Line by R. Yashod Vardhan/P. Vinod Kumar. The article concluded as follows:
"The ICA does not profess to be a complete code on the subject of Contracts and cannot provide nuanced solutions to deal with the various problems caused by Covid-19. If the Central Government does not come out with an Ordinance and bridge the gaps in the law, what are we left with. In an old case, a Judge observed sagaciously:
"In administering the law, it is the duty of the Judge to amplify its remedies and without usurping jurisdiction, to apply its rules to the advancement of substantial justice."
G.O.(D) No.298, Municipal Administration and Water Supply (MA.IV) Department, dated 2.9.2020, endeavors to fill the gap. However, it is only a baby step, when giant strides are required. It is, therefore, left to the Court to cover the remaining distance.
17. I have no difficulty in coming to the conclusion that the Petitioner stands relieved of his obligation to pay the License-fee for the period from 24.3.2020 to 31.8.2020, when there was total lockdown. It is pointed out that for two more months thereafter, the Licensees were allowed to open their Shops only for short duration every day. In other words, lockdown was not lifted completely. The Bus stand was not operational fully.
18. Therefore, I am of the view that the Petitioner is entitled to call upon the Respondents to revisit the quantum of License-fee for the period subsequent to the lifting of total lockdown. It may not be open to this Court to enter into the finer details. I permit the Petitioner to submit a fresh representation projecting his grievances regarding the period commencing from 1.9.2020 onwards. The Fourth Respondent will forward the said representation along with their proposal to the Respondents 1 & 2, who shall consider the same and pass appropriate Orders in accordance with law as expeditiously as possible.
19. Let me summarise the reliefs granted. For the period when there was total lockdown that is from 24.3.2020 to 6.9.2020, the Licensee/Petitioner is totally relieved from the obligation to pay the License-fee. He is entitled to complete waiver. For the period subsequent to 6.9.2020 that is when there was partial relaxation and lifting of lock down restrictions, the Petitioner is permitted to move the Respondents for relief. This Court believes in the Principle of Nudging as propounded by Richard H. Thaler. This Court would expect the Authorities to take note of the ground realities and respond appropriately.
20. This Writ Petition is allowed as indicated above. No Costs. Consequently, connected Miscellaneous Petitions are closed.
Alert