Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Power Grid Corporati... v. Karnataka Power Tran...

Central Electricity Regulatory Commission
Feb 25, 2021
Smart Summary (Beta)

Order Summary: Petition No.248/TT/2019 (CERC)

Factual and Procedural Background

The petition was filed by Power Grid Corporation of India Ltd. (PGCIL) seeking determination of transmission tariff for specified elements of the Sub-station works associated with the Additional Inter-regional AC link for import of power into Southern Region (Warora-Warangal and Chilakaluripeta-Hyderabad-Kurnool 765 kV Link) for the 2014-19 tariff period under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (the 2014 Tariff Regulations).

The assets for which tariff was sought principally comprised 2x240 MVAR, 765 kV Switchable Line Reactors (6x80 MVAR, 765 kV, 1-Ph Shunt Reactor), associated reactor bays and two 765 kV line bays at 765/400 kV Kurnool Sub-station (excluding PLCC, telecom equipment and certain line terminal equipment). The petitioner listed a set of reliefs including approval of tariff, admission of capital cost and additional capitalisation (ACE), permissions to bill various items (license/RLDC fees, taxes, interest variations), and recovery/refund mechanisms.

Investment Approval was accorded on 10.3.2017. The petitioner claimed Commercial Operation Date (COD) as 11.3.2019 (earlier than the scheduled COD of 9.11.2019 per Investment Approval). Notices under Section 64 were published and replies were filed by TANGEDCO and Warora-Kurnool Transmission Limited (WKTL). The matter was heard (last on 29.6.2020) and the Commission reserved and then issued the order disposing of the petition.

Legal Issues Presented

  1. Whether the early declaration of COD (claimed as 11.3.2019) for the line reactors at Kurnool Sub-station was approved by the Southern Region Power Committee (SRPC) and hence should be accepted for tariff purposes.
  2. Whether the capital cost claimed by the petitioner (excluding specified PLCC/telecom/line terminal equipment) and the Additional Capitalisation (ACE) for 2018-19 (to the extent within the tariff block) are admissible for tariff computation under the 2014 Tariff Regulations.
  3. Determination of regulatory components required to compute tariff for 2018-19 (pro-rata) — including Interest During Construction (IDC), Incidental Expenditure During Construction (IEDC), initial spares, debt-equity ratio, depreciation, Interest on Loan (IOL), Return on Equity (ROE), Operation & Maintenance (O&M) expenses, and Interest on Working Capital (IWC) — in accordance with the 2014 Tariff Regulations.
  4. Who should bear the transmission charges in the period from the COD of the transmission asset to the COD or scheduled COD of the associated transmission line executed by WKTL (i.e., the question of sharing of transmission charges and application of the 2010 Sharing Regulations).

Arguments of the Parties

Petitioner (PGCIL)

  • Claimed COD as 11.3.2019 based on SRPC's agreement for early commissioning of line reactors at Kurnool (for voltage control), CEA energisation certificate (4.2.2019) and RLDC charging certificate (19.3.2019).
  • Explained exclusion of PLCC, telecom equipment and line terminal equipment (LA, CVT, Wave Trap) from the charged portion of line bays, because these items cannot operate/usefully without the associated transmission line; therefore they were excluded from the petitioned assets and costs.
  • Asserted capital cost, IDC, IEDC, initial spares and ACE (2018-19) as claimed and sought tariff computation on those bases in accordance with 2014 Tariff Regulations; requested permission to seek revision of O&M norms for wage revision impact.
  • Requested reimbursement of petition filing fee and publication expenses and permission to bill/recover license fee, RLDC charges and GST (if levied in future).

TANGEDCO (Respondent No.4)

  • Contended that as the associated transmission line under WKTL did not achieve COD, the transmission charges in respect of the transmission asset should be borne by WKTL and beneficiaries should not be burdened.
  • Observed that although voltage issues were discussed in SRPC, there was no clear approval for using the transmission asset for controlling voltage at Kurnool — challenging the petitioner's reliance on SRPC minutes for early COD.
  • Invoked an earlier Commission order (25.1.2016 in Petition No.253/TT/2015) that delays caused by commissioning issues of upstream/downstream systems may render the concerned DIC liable to bear charges, to support allocation of charges to WKTL.

Warora-Kurnool Transmission Limited (WKTL) (Respondent No.18)

  • Submitted that scheduled COD of the line under WKTL's scope was in November 2019; delays were due to force majeure events beyond WKTL's control (ROW issues, overlapping route alignment with another project, heavy rainfall, objections by TSIIC, directions by WCL and SCCL, NHAI issues, etc.).
  • Stated WKTL had filed Petition No.334/MP/2020 seeking extension of scheduled COD under the TSA's force majeure provisions and argued it should not be liable for transmission charges for the period 11.3.2019 to 9.11.2019 because commissioning fell within its scheduled COD (November 2019) and/or deserved extension.
  • Explained that some delays are being handled through separate process and that force majeure relief had been sought in the separate petition already before the Commission.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Appellate Tribunal for Electricity (APTEL) judgment dated 2.12.2019 (Appeal Nos. 95 of 2018 & 140 of 2018) Directions concerning reconsideration of Incidental Expenditure During Construction (IEDC) treatment at the time of truing up. The Commission allowed IEDC now but recorded that IEDC will be reconsidered at the time of true up in light of the APTEL directions dated 2.12.2019.
Commission order dated 25.1.2016 in Petition No.253/TT/2015 Principle that delay in commissioning of concerned generating station or upstream/downstream transmission system may render the Designated ISTS Customer (DIC) causing delay liable to bear transmission charges. TANGEDCO relied on this order to argue WKTL should bear transmission charges; the Commission considered this submission in paras 64–66 when addressing sharing of charges and ultimately directed inclusion in PoC pool for the relevant period while directing administrative follow-up with SCM/RPC for post-SCOD usage.
Commission order dated 7.2.2021 in Petition No.334/MP/2020 Treatment of force majeure extension requests and the Commission's approach where force majeure events are continuing and COD is uncertain (liberty to approach after completion); findings on inability to quantify likely COD. The Commission recorded that WKTL's prayer for extension had already been decided in that order and therefore refrained from re-deciding force majeure issues in this tariff order; it relied on the order's reasoning to decline re‑adjudication here and directed the petitioner to pursue SCM/RPC for continuation of reactor use post scheduled COD and treatment of charges beyond scheduled COD.

Court's Reasoning and Analysis

The Commission's analysis proceeded step-wise, applying the relevant provisions of the 2014 Tariff Regulations and examining the factual materials:

  1. COD determination: The Commission examined the minutes of the 35th SRPC meeting (2.2.2019), which recorded SRPC's agreement for early commissioning of the line reactors at Kurnool for voltage management, together with the petitioner's CEA energisation certificate (4.2.2019) and RLDC charging certificate (19.3.2019). On that basis the Commission held there was approval for early use of the line reactors for voltage control and approved the COD for the listed elements as 11.3.2019.
  2. Capital cost & scope exclusions: Applying Regulation 9(1)–(2) (capital cost components) the Commission accepted the petitioner's exclusion of PLCC, telecom equipment and certain line terminal equipment (LA, CVT, Wave Trap) from the charged portion because the petitioner had explained these items could not be usefully utilised without the associated transmission line. Consequently the Commission considered only the capital cost submitted in the petition for the assets actually included.
  3. Cost over-run and ACE: The Commission compared the estimated completion cost (including ACE) with the apportioned approved cost and found no cost over-run. ACE claimed for 2019-20 (beyond the 2014-19 tariff period) was not considered for this tariff block and would be dealt with under the 2019 Regulations during the next tariff period. ACE for 2018-19 (balance & retention payments) was allowed subject to truing up.
  4. IDC, IEDC and initial spares: IDC claimed was examined against provided loan documentation; some discrepancies were noted and the Commission allowed IDC on the basis of available information (subject to revision at truing up) and directed the petitioner to reconcile loan figures. IEDC was allowed as claimed, but subject to reconsideration at truing up in light of the APTEL directions. Initial spares were allowed since claimed amounts were within the ceilings in Regulation 13.
  5. Financial normative parameters: The Commission applied Regulation 19 to adopt a 70:30 debt‑equity ratio on normative basis. Depreciation was computed using weighted average rate of depreciation (WAROD) per Regulation 27. Interest on Loan (IOL) was computed as per Regulation 26, using loan details as presented and rates prevailing as on COD; any change in interest rate (floating rate effects) would be considered at truing up. Return on Equity (ROE) was grossed up in accordance with Regulations 24 and 25, using the MAT rate applicable for 2018-19 and subject to adjustment at truing up based on actual tax rate.
  6. O&M and IWC: O&M expenses were computed as per Regulation 29(4) norms for 765 kV bays; the petitioner may approach the Commission separately for revision of O&M norms to account for wage revision. Interest on Working Capital (IWC) components and rate were applied as per Regulation 28 (SBI base rate as on 1.4.2018 plus 350 bps).
  7. Sharing of transmission charges and allocation dispute: The Commission considered TANGEDCO's contention that WKTL should bear charges due to delay in its line commissioning and WKTL's force majeure defenses. The Commission noted that WKTL's separate petition on force majeure (No.334/MP/2020) had been decided (order dated 7.2.2021) and therefore declined to re‑adjudicate force majeure in this tariff order. Given SRPC's prior approval for early commissioning and the expectation that associated lines would be commissioned by November 2019, the Commission directed that the transmission charges approved in this order be included in the PoC pool from COD (11.3.2019) up to the scheduled COD/SCOD of the asset (the order references up to SCOD and directs further administrative action via SCM/RPC for post-SCOD use and treatment). The Commission also reiterated that billing/collection/disbursement shall follow the 2010 Sharing Regulations.

Holding and Implications

Core Ruling: Petition No.248/TT/2019 is disposed of.

Key determinations and direct consequences for the parties (as recorded in the order):

  • The COD of the following Kurnool elements was approved as 11.3.2019: 2x240 MVAR 765 kV Switchable Line Reactors (6x80 MVAR, 1-Ph Shunt Reactor), 2 Switchable Line Reactor Bays and 2 line bays (excluding PLCC/telecom/line terminal equipment as claimed and explained by the petitioner).
  • Capital cost as on COD allowed for tariff calculation (subject to truing up) was taken as 7,900.42 lakh with ACE for 2018-19 of 445.87 lakh and total for tariff period 2014-19 (up to 31.3.2019) of 8,346.29 lakh.
  • IDC, IEDC, initial spares and other cost components were allowed as set out in the order but subject to reconciliation and truing up where specifically indicated (IDC reconciliation, IEDC reconsideration per APTEL directions).
  • Financial parameters were applied as per the 2014 Tariff Regulations (70:30 debt-equity, depreciation using WAROD, IOL on rates as on COD with truing up for later changes, ROE grossed-up with MAT and subject to truing up).
  • O&M expenses were approved as per the normative rates under Regulation 29(4); the petitioner may file an application if seeking revision for wage revision impact.
  • Interest on Working Capital was computed as per the Regulations (rate taken as SBI base rate as on 1.4.2018 plus 350 bps = 12.20%).
  • The Annual Transmission Charges allowed for these assets for 2018-19 (pro‑rata for 21 days) are 102.58 lakh (breakdown: Depreciation 23.57; IOL 26.89; ROE 27.70; IWC 2.70; O&M 21.72).
  • Reimbursement items: The petitioner is entitled to recover filing fee and publication expenses directly from beneficiaries pro-rata in accordance with Regulation 52. The petitioner is also entitled to reimbursement of license fee and RLDC fees and charges per Regulation 52. The petitioner's request for recovery of GST was considered premature as GST is not levied on transmission at present.
  • On sharing of charges, the Commission directed that the approved transmission charges be included in the PoC pool from COD (11.3.2019) to up to the scheduled COD/SCOD of the instant asset (the order directs the petitioner to approach SCM/RPC to continue to use the reactor as a bus reactor post scheduled COD of the associated transmission line and to address treatment of charges beyond scheduled COD). Billing/collection/disbursement shall follow the Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, as amended.

Broader legal significance: The order applies existing provisions of the 2014 Tariff Regulations and prior CERC/APTEL pronouncements to the facts; it does not purport to lay down a novel legal principle beyond application of the existing regulatory framework. Several admitted items and figures are allowed subject to reconciliation and truing up, and the order directs administrative follow-up (SCM/RPC) for post-SCOD operational treatment.

This summary is prepared strictly on the basis of the provided opinion text and does not add or infer information beyond that text.

Show all summary ...

The present petition has been filed by Power Grid Corporation of India Ltd. (PGCIL) for determination of tariff for 2 Nos. of 240 MVAR, 765 kV Switchable Line Reactors ( 6x80 MVAR, 765 kV, 1-Ph Shunt Reactor), along with Reactor Bays & 2 Nos. 765 kV Line Bays excluding PLCC, Telecom equipment and Line Terminal equipment such as LA, CVT & Wave Trap at 765/400 kV Kurnool Sub-station under Sub-station works Associated with Additional Inter-regional AC link for Import of Power into Southern Region i.e., Warora- Warangal and Chilakaluripeta-Hyderabad -Kurnool 765 kV Link. (hereinafter referred to as the transmission asset) for 2014-

19 tariff period under Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (hereinafter referred to as the 2014 Tariff Regulations).

2. The Petitioner has made the following prayers:

1) Approve the Transmission Tariff for the tariff block 2014-19 block for the assets covered under this petition,

2) Admit the capital cost as claimed in the Petition and approve the Additional Capitalisation incurred / projected to be incurred.

3) Allow the Petitioner to approach Commission for suitable revision in the norms for O&M expenditure for claiming the impact of wage hike, if any, during period 2014- Order in Petition No.248/TT/2019 Page 4 of 28

4) Allow the Petitioner to recover the shortfall or refund the excess Annual Fixed Charges, on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before the Commission as provided under clause 25 of the Tariff Regulations 2014.

5) Approve the reimbursement of expenditure by the beneficiaries towards petition filing fee, and expenditure on publishing of notices in newspapers in terms of Regulation 52 Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014, and other expenditure (if any) in relation to the filing of petition.

6) Allow the Petitioner to bill and recover Licensee fee and RLDC fees and charges, separately from the respondents in terms of Regulation 52 Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014.

7) Allow the Petitioner to bill and adjust impact on Interest on Loan due to change in Interest rate on account of floating rate of interest applicable during 2014-19 period, if any, from the respondents.

8) Allow the Petitioner to bill and recover GST on Transmission Charges separately from the respondents, if GST on transmission is withdrawn from the exempted list at any time in future. Further, any taxes and duties including cess etc. imposed by any statutory/Govt./municipal authorities shall be allowed to be recovered from the beneficiaries.

9) Allow tariff up to 90% of the Annual Fixed Charges in accordance with clause 7 (i) of Regulation 7 Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 for purpose of inclusion in the PoC charges. 10) Allow the petitioner to bill Tariff from actual DOCO. and pass such other relief as Commission deems fit and appropriate under the circumstances of the case and in the interest of justice. Background

3. The Investment Approval (hereinafter referred to as "IA") for the transmission asset Sub-station Works Associated with Additional Inter-Regional AC Link for Import into Southern Region i.e., Warora-Warangal and Chilakaluripeta-Hyderabad- Kurnool 765 kV Link was accorded by Board of Directors of the Petitioner in its 338th meeting held on 10.3.2017 for 28372 lakh including an IDC of 1768 lakh based on October 2016 price level (communicated vide Memorandum No. C/CP/PA 1617-03-0AB-IA027 dated 11.4.2017).

4. The scope of the transmission asset was discussed and agreed in the 37th, 38th and 39th meetings of the Standing Committee on Power System Planning of Order in Petition No.248/TT/2019 Page 5 of 28 Southern Region held on 31.7.2014, 7.3.2015 and 29.12.2015, respectively. It was also agreed in 26th Meeting of SRPC held on 20.12.2014.

5. The Empowered Committee on Transmission in the 33rd and 35th meeting held on 30.9.2014 and 14.9.2015, respectively, decided the implementation of the transmission asset through Tariff Based Competitive Bidding (TBCB) route. The sub-station works for TBCB lines terminating at the Petitioners sub-stations including line bays and line reactors were brought under the scope of the Petitioner.

6. The scope of work covered under the transmission asset Sub-station works associated with additional inter-regional AC link for import of power into Southern Region i.e., Warora-Warangal and Chilakaluripeta-Hyderabad- Kurnool 765 kV Link'' in Southern Region is as follows: Sub-station

1. New 765/400 kV Hyderabad (Maheshwaram) GIS Sub-station (Extension)

765 kV

a) 4 nos. line bays (GIS)

2. 765/400 kV Kurnool Sub-station (Extension)

765 kV

a) 2x240 MVAR, 765 kV, Switchable Line Reactors (6x80 MVAR, 765 kV 1-Ph, Shunt Reactor)

b) 2 nos. Switchable Line Reactor Bays

c) 2 nos. Line Bays

3. 400/220 kV Warangal Sub-station (Extension)

400 kV

a) 2 nos. line bays

7. The transmission asset covered in the instant petition is as under: Order in Petition No.248/TT/2019 Page 6 of 28 Asset COD Asset-1:

a) 2X240 MVAR, 765 kV, Switchable Line Reactors (6X80 MVAR,

765 kV, 1-Ph Shunt Reactor)

b) 2 Nos Switchable Line Reactor Bays

c) 2 Nos Line bays* 11.3.2019 * Excluding PLCC, Telecom equipment and Line Terminal equipment such as LA, CVT & Wave Trap at 765/400 kV Kurnool Sub-station in the instant petition which are part of 2 Nos Line Bays.

8. The remaining scope of the work as per Investment Approval is covered in Petition No 169/TT/2020, where in the petitioner has also claimed the balance items of PLCC, Telecom equipment and Line Terminal equipment such as LA, CVT & Wave Trap at Kurnool 765/400 Sub-station which are part of Asset-I in the instant petition.

9. The petitioner has claimed 04 Nos Line Bays (GIS) at (Hyderabad) Maheshwaram 765/400 kV Sub-station, 02 Nos. Line Bays at Warangal 400/200 kV Sub-station in Petition No.169/TT/2020. Therefore, the complete scope of the work as per Investment Approval is covered in Petition Nos. 248/TT/2019 and 169/TT/2020.

10. The details of the Annual Transmission Charges claimed by the Petitioner are as under: ( in lakh) Particulars 2018-19 (Pro-rata) Depreciation 23.12 Interest on Loan 26.40 Return on Equity 26.98 Interest on Working Capital 2.67 O&M Expenses 21.72 Total 100.89

11. The details of the interest on working capital claimed by the Petitioner are as under: Order in Petition No.248/TT/2019 Page 7 of 28 ( in lakh) Particulars 2018-19 (Pro-rata) O&M Expenses 32.06 Maintenance Spares 57.71 Receivables 297.87 Total 387.65 Rate of Interest 12.20% Interest on working Capital 2.67

12. The Petitioner has served a copy of the petition upon the respondents and notice of this tariff application has been published in newspapers in accordance with Section 64 of the Electricity Act, 2003. No comments or suggestions have been received from the general public in response to the notices published by the Petitioner under Section 64 of the Electricity Act, 2003. Reply to the petition has been filed by the TANGEDCO (Respondent No.4) and Warora-Kurnool Transmission Limited (WKTL) (Respondent No.18), vide their affidavits dated 6.2.2020 and 18.6.2020, respectively. The Petitioner vide affidavit dated 13.5.2020 has filed its rejoinder to the reply of TANGEDCO.

13. The Petition was last heard on 29.6.2020 and the Commission reserved the order in the Petition. Having heard the representatives of the Petitioner present at the hearing and perused the material on record, we proceed to dispose of the petition.

14. This order has been issued after considering the main petition dated 22.7.2019, the Petitioners affidavits dated 20.3.2020, 13.5.2020 and 16.7.2020 and replies dated 6.2.2020 and 18.6.2020 of TANGEDCO and Warora-Kurnool Transmission Limited (WKTL) respectively. Order in Petition No.248/TT/2019 Page 8 of 28 Date of Commercial Operation (COD)

15. The Petitioner has claimed COD for the transmission asset as 11.3.2019. The Petitioner has submitted that as per IA, the transmission asset was scheduled to be put into commercial operation on 9.11.2019. However, it was put into commercial operation before the scheduled COD. The reasons submitted by the petitioner for early COD and subsequent utilisation of the transmission asset are as under:

a) In the 35th meeting of SRPC held on 2.2.2019, it was intimated that due to over-voltage, there are occurrences of frequent tripping of 765 kV Nizamabad-Maheswaram, 765 kV Kurnool-Kadapa and 765 kV Kadapa- Thiruvalam lines, causing stress on EHV equipment due to frequent switching.

b) SRLDC issued codes on daily basis for taking these 765 kV lines (765 kV Nizamabad-Maheswaram, 765 kV Kurnool-Kadapa and 765 kV Kadapa- Thiruvalam lines) out of service during night and taking back into service early morning.

c) Accordingly, in order to reduce the voltage at Kurnool, early COD of the line reactors at Kurnool Sub-station under instant project, intended for Hyderabad- Kurnool 765 kV D/C Line, was agreed.

16. TANGEDCO, vide affidavit dated 6.2.2020, while referring to the submissions of the Petitioner regarding the decision taken in the 35th meeting of SRPC to prepone COD of the transmission asset, submitted that since Warora Kurnool Transmission Ltd. (WKTL) did not achieve COD of its entire scope of the project, the transmission charges in respect of the transmission asset should be borne by WKTL.

17. In response, the Petitioner vide affidavit dated 13.5.2020 has submitted that the transmission asset is being implemented by the Petitioner, whereas the associated transmission lines are being executed by WKTL, a subsidiary of Essel Infra, under TBCB route. The Petitioner has further reiterated the submissions made Order in Petition No.248/TT/2019 Page 9 of 28 earlier in the petition and submitted that it was agreed in the 35th SRPC that the transmission asset is being utilized for voltage control in Southern Region.

18. We have considered the submissions of the Petitioner and TANGEDCO. It is observed that as per the Investment Approval dated 10.3.2017, the transmission asset was scheduled to be put into commercial operation on 9.11.2019 while the Petitioner has claimed COD of the transmission asset as 11.3.2019. The Petitioner has submitted that the constituents of SR agreed in the 35th SRPC meeting held on 2.2.2019 for early declaration of COD of the transmission assets to control the voltage issues in Kurnool Sub-station. TANGEDCO has submitted that as the transmission line under the scope of WKTL has been delayed, WKTL has to bear the transmission charges for the period from COD of the transmission assets to the COD of the transmission line under the scope of WKTL and the beneficiaries should not be burdened with the same. TANGEDCO has further submitted that though the issue of voltage was discussed in the 35th SRPC meeting, there was no clear approval for using the transmission asset for controlling the voltage in Kurnool Sub- station. In view of the rival contentions, we would like to decide first whether the SRPC has approved early declaration of COD and use of the transmission assets to control the voltage at Kurnool Sub-station as contended by the Petitioner. The relevant portion of the Minutes of the 35th Meeting of SRPC held on 2.2.2019 is as follows: SRPC deliberations SRPC noted the above. ED, SR-I, PGCIL stated that the nodes at Maheswaram and Kurnool were experiencing high voltages and for effective management of the system POSOCO was instructing closing and opening of the lines on a daily basis. For the TBCB line coming from Warora, PGCIL was carrying out the works of bay extension at Warangal, Maheswaram and Kurnool. The contractual schedule was around February/March 2019 while the lines were expected by November 2019. However, PGCIL was ready with bays at Kurnool with two reactors (2 x 240 MVAR) which could be energized by end of February 2019 or first week of March 2019. The reactors were Order in Petition No.248/TT/2019 Page 10 of 28 likely to reduce the voltages of 765 kV node by 10-11 kV and about 4-5 kV of 400 kV node at Kurnool, if the reactors are permitted to be commissioned by the forum. CTU as well as SRLDC supported this proposal of SR-I. SRPC agreed for early commissioning (end of February 2019/first week of March 2019) of the line reactors at Kurnool for voltage management.

19. It is observed from the minutes of meeting of SRPC that the issue of high voltage at Maheswaram and Kurnool Sub-station was discussed and it was agreed for early declaration of COD of the line reactors at Kurnool Sub-station for voltage management. Thus, there is approval of the 35th SRPC for using the line reactors at Kurnool Sub-station for voltage control. TANGEDCOs contention regarding the sharing of transmission charges is dealt in paras 64 and 65 of this order.

20. The Petitioner has submitted CEA energisation certificate dated 4.2.2019 for 6 Nos. 765 kV 80 MVAR Shunt Reactors and 765 kV D/C Hyderabad-I&II Line Bays (Bays No. 714, 715, 715R, 716, 717, 718 & 718R) and the Petitioner has submitted RLDC charging certificate dated 19.3.2019. Accordingly, taking into consideration the minutes of the 35th SRPC meeting, CEA energisation certificate and the RLDC certificate, the COD of the following elements has been approved as 11.3.2019. 765/400 kV Kurnool Sub-station (Extn).

765 kV

a) 2X240 MVAR, 765 kV, Switchable Line Reactors (6X80 MVAR, 765 kV, 1-Ph Shunt Reactor)

b) 2 Nos Switchable Line Reactor Bays

C) 2 Nos Line bays. Capital Cost

21. Clauses (1) and (2) of Regulation 9 of the 2014 Tariff Regulations provide as follows: (1) The Capital cost as determined by the Commission after prudence check in accordance with this regulation shall form the basis of determination of tariff for existing and new projects Order in Petition No.248/TT/2019 Page 11 of 28 (2) The Capital Cost of a new project shall include the following: (a) The expenditure incurred or projected to be incurred up to the date of commercial operation of the project; (b) Interest during construction and financing charges, on the loans (i) being equal to 70% of the funds deployed, in the event of the actual equity in excess of 30% of the funds deployed, by treating the excess equity as normative loan, or (ii) being equal to the actual amount of loan in the event of the actual equity less than 30% of the funds deployed; (c) Increase in cost in contract packages as approved by the Commission; (d) Interest during construction and incidental expenditure during construction as computed in accordance with Regulation 11 of these regulations; (e) Capitalised Initial spares subject to the ceiling rates specified in Regulation 13 of these regulations; (f) Expenditure on account of additional capitalization and de-capitalisation determined in accordance with Regulation 14 of these regulations; (g) Adjustment of revenue due to sale of infirm power in excess of fuel cost prior to the COD as specified under Regulation 18 of these regulations; and (h) Adjustment of any revenue earned by the transmission licensee by using the assets before COD.

22. The Petitioner was directed to submit the reasons for excluding the PLCC, telecom equipment and line terminal equipment such as LA, CVT and Wave Trap. In response, the Petitioner, vide affidavit dated 16.7.2020, has submitted that in order to reduce the voltage issues at Kurnool, early declaration of COD of the line reactors at Kurnool Sub-station intended for Hyderabad-Kurnool 765 kV D/C Line was agreed. Therefore, in order to utilize the line reactors as bus reactors, the line reactors are connected to the bus bars through line bays. The line reactors are being utilized as bus reactors and have to be connected to both the buses for charging. Thus, in order to charge line reactor bays (715R and 718R), the associated Line bays (715 and 718) have to be charged. Further, in order to utilize the line reactors as bus reactors, the line side isolators were to be opened. Therefore, LA, CVT and Wave Trap are excluded and are not part of the charged portion of the line bays. The line side equipment can be charged only when the associated Transmission Line is charged/ ready for charging/ put into commercial operation. Hence, it is not possible to operate this equipment without the transmission line. Further, PLCC and Telecom equipment are required for transmission line protection and data transfer application and thus cannot be utilized Order in Petition No.248/TT/2019 Page 12 of 28 in absence of transmission line. As the utilization of PLCC, telecom equipment and line terminal equipment such as LA, CVT and Wave Trap is not possible without the transmission line, it is excluded from the scope of the transmission asset.

23. The Petitioner has claimed following capital cost incurred as on COD and projected ACE, in respect of the transmission asset covered in the instant petition: ( in lakh) Apportioned Approved Cost (FR) Cost up to Proposed ACE in FY Estimated Completion Cost 2018-19 2019-20 11488.19 7931.20 445.87 1007.13 9384.20

24. As the Petitioner has excluded the cost of PLCC, telecom equipment and Line Terminal equipment such as LA, CVT & Wave Trap at Kurnool 765/400 kV Sub- station, the capital cost as submitted by the Petitioner is considered for the purpose of computation of tariff in respect of the transmission asset covered in the instant petition. Since the Petitioner has voluntarily excluded the PLCC, Telecom equipment and Line Terminal equipment such as LA, CVT & Wave Trap at 765/400 kV Kurnool Sub-station which is part of 2 Nos Line Bays and their capital cost in the instant petition, the same would not be considered in the Petition No. 169/TT/2020. Cost Over-run

25. The Petitioner has submitted that against the total apportioned approved cost of 11488.19 lakh, the estimated completion cost is 9384.20 lakh and it has prayed to allow the capital cost and tariff as claimed under instant petition.

26. We have considered the submissions of the Petitioner. It is observed that the estimated completion cost including ACE is within the FR apportioned approved cost. Therefore, there is no cost over-run. Order in Petition No.248/TT/2019 Page 13 of 28 Interest During Construction (IDC)

27. The Petitioner has claimed Interest During Construction (IDC) of 192.12 lakh for the transmission asset and submitted the Auditors Certificate dated 9.5.2019 in support of the same. The Petitioner has submitted computation of IDC along with year-wise details of the IDC discharged which is summarized as under: ( in lakh) IDC as per Auditors Certificate IDC discharged up to COD IDC un-discharged up to COD IDC to be discharged during 2019-20 192.11 161.34 30.78 30.78

28. The Petitioner has submitted IDC computation statement which consists of the name of the loan, drawl date, loan amount, interest rate and interest claimed. IDC is worked out based on the details given in the IDC statement. Further, the loan amount as on COD has been mentioned in Form 6 and Form 9C. While going through these documents, certain discrepancies have been observed such as mismatch in loan amount between IDC statement and in Form 6 and Form 9C. The allowable IDC has been worked out based on the available information and relying on loan amount as per Form 9C. However, the Petitioner is directed to submit the detailed IDC statement by rectifying the above-mentioned deviation, at the time of true up of capital cost for 2014-19 period. Accordingly, details of IDC considered for tariff computation, subject to revision at the true up is as follows: ( in lakh) IDC claimed IDC disallowed as on COD Allowable IDC as on (Cash basis) IDC to be discharged during 2019-20 Computational Difference Un-discharged liability 192.12 0.31 30.47 161.34 30.47 Incidental Expenditure During Construction (IEDC)

29. The Petitioner has claimed IEDC of 113.61 lakh for the transmission asset and submitted Auditors Certificate dated 9.5.2019 in support of the same. The Order in Petition No.248/TT/2019 Page 14 of 28 Petitioner has submitted that entire IEDC has been discharged up to COD. IEDC claimed is within the percentage of hard cost as indicated in the abstract cost estimate. Hence, IEDC of 113.61 lakh has been allowed, subject to true up.

30. IEDC allowed for the subject asset will be reconsidered in the light of the directions of Appellate Tribunal for Electricity (APTEL) in judgment dated 2.12.2019 in Appeal No. 95 of 2018 and Appeal No 140 of 2018, at the time of truing up. Initial Spares

31. This has been dealt in line with Regulation 13 of the 2014 Tariff Regulations. The Petitioner has claimed initial spares corresponding to brownfield substation under for transmission asset and has submitted Auditors Certificate dated 9.5.2019 in support of the same. The Petitioner vide affidavit dated 20.3.2020 has submitted details of year-wise capitalisation and initial spares discharged up to COD. The Petitioner has further submitted that the expenditure incurred towards initial spares up to COD have been considered in COD cost. The amount towards balance initial spares liabilities have been considered in additional capital expenditure of the respective year and the Petitioner has prayed to allow the entire initial spares claimed under the instant petition. The details of initial spares claimed by the Petitioner is as follows: ( in lakh) Element Total Capital Cost (Plant and machinery Cost excluding IDC, IEDC, Land cost and cost of Civil works) up to Cut-off date Initial Spares Claimed Expenditur e up to Additiona l Capital Expendit ure in 2019-20 Additional Capital Expenditure in 2020-21 (a) (b) (c) (d) (e) Sub-station (Brownfield) 7705.38 237.67 217.59 7.15 12.93

32. We have considered the submissions made by the Petitioner. The initial spares claimed by the petitioner are within ceiling specified in the 2014 Tariff Regulations. The initial spares are allowed considering the Plant and Machinery cost Order in Petition No.248/TT/2019 Page 15 of 28 excluding IDC, IEDC and land expenses up to 31.3.2019. Accordingly, the initial spares allowed is as under: ( in lakh) Element Plant and Machinery Cost excluding IDC, IEDC and Land expenditure up to cut- off date (31.3.2019) Initial spares claimed Ceiling prescribed in the 2014 Tariff Regulations Initial spares allowed Sub-station (Brownfield) 7705.38 237.67 6% 237.67 Capital cost as on COD

33. Accordingly, the capital cost allowed as on COD under Regulation 9(2) of the 2014 Tariff Regulations is as under: ( in lakh) Capital Cost as on COD as per Auditors Certificate Less: Un-discharged Less: Computational difference in IDC Capital Cost as on COD considered for tariff calculation

1 2 3 4=1-2-3 7931.20 30.47 0.31 7900.42 Additional Capital Expenditure (ACE)

34. As per Regulation 3 (13) of the 2014 Tariff Regulations, the cut-off date for transmission assets is 31.3.2022. The Petitioner has claimed ACE for the period 2018-19 and 2019-20 as under: ( in lakh) Additional Capital Expenditure claimed 2018-19 2019-20 445.87 1037.91

35. Since 2019-20 falls beyond the tariff period 2014-19 and is not covered under provisions of the 2014 Tariff Regulations, the projected ACE claimed beyond 2018-

19 has not been taken into consideration and the same shall be dealt during the next tariff period as per the provisions of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019.

36. ACE approved are summarized below which is subject to true up: Order in Petition No.248/TT/2019 Page 16 of 28 ( in lakh) Particulars Regulation 2018-19 ACE to the extent of Balance & Retention Payment 14 (1)(i) 445.87 Capital cost for the tariff period 2014-19

37. Accordingly, the capital cost considered for the tariff period 2014-19, subject to truing up, is as follows: ( in lakh) Capital Cost as on COD considered for tariff calculation ACE allowed during 2018-19 Total Estimated Completion Cost up to 31.3.2019 7900.42 445.87 8346.29 Debt-Equity Ratio

38. Debt-Equity Ratio is considered as per Regulation 19 of the 2014 tariff Regulations. The financial package up to COD as submitted in form 6 has been considered to determine the debt-equity Ratio. Accordingly, the capital cost allowed as on the date of commercial operation have been considered in the debt-equity ratio of 70.00:30.00. The debt-equity as on dates of commercial operation and 31.3.2019 considered on normative basis are as under: Particulars As on COD As on 31.03.2019 Amount ( in lakh) Percentage Amount ( in lakh) Percentage Debt 5530.29 70.00 5842.40 70.00 Equity 2370.13 30.00 2503.89 30.00 Total 7900.42 100.00 8346.29 100.00 Depreciation

39. Depreciation has been dealt with in line of Regulation 27 of 2014 Tariff Regulations. The transmission asset was put under commercial operation during 2018-19. Accordingly, it will complete 12 years beyond the tariff period 2014-19. The Gross Block during 2018-19 has been depreciated at weighted average rate of depreciation (WAROD) (as placed in Annexure-1). WAROD has been worked out after taking into account the depreciation rates of assets as prescribed in the 2014 Tariff Regulations and depreciation allowed during the 2018-19 is as under: Order in Petition No.248/TT/2019 Page 17 of 28 ( in lakh) Particulars 2018-19 (Pro-rata) (21 Days) Opening Gross Block 7900.42 Additional Capitalisation 445.87 Closing Gross Block 8346.29 Average Gross Block 8123.36 Weighted Average Rate of Depreciation (WAROD) 5.0421% Depreciable Value 6981.65 Depreciation during the year 23.57 Remaining Depreciable Value at the end of the year 6958.08 Interest on Loan (IOL)

40. The IOL has been calculated as per the provisions of Regulation 26 of the 2014 Tariff Regulations as detailed below:

(i) Gross amount of loan, repayment of instalments and rate of interest on actual loans have been considered as per petition including additional information.

(ii) The yearly repayment for the tariff period 2014-19 has been considered to be equal to the depreciation allowed for that year.

(iii) Weighted average rate of interest on actual average loan worked out as per (i) above is applied on the notional average loan during the year to arrive at the interest on loan.

41. The Petitioner has submitted that IOL has been claimed on the basis of rate prevailing as on COD and the change in interest due to floating rate of interest applicable, if any, needs to be claimed/ adjusted over the tariff block 2014-19. We have calculated IOL on the basis of rate prevailing as on the date of commercial operation. Any change in rate of interest subsequent to the date of commercial operation will be considered at the time of truing-up. IOL is allowed considering all the loans submitted in Form-9C. The Petitioner is directed to reconcile the total Gross Loan for the calculation of weighted average Rate of Interest and for the calculation of IDC, which would be reviewed at the time of truing-up.

42. The details of IOL approved for the transmission asset are as follows: Order in Petition No.248/TT/2019 Page 18 of 28 ( in lakh) Particulars 2018-19 (Pro-rata) (21 Days) Gross Normative Loan 5530.29 Cumulative Repayment upto previous Year 0.00 Net Loan-Opening 5530.29 Addition due to Additional Capitalization 312.11 Repayment during the year 23.57 Net Loan-Closing 5818.84 Average Loan 5674.56 Weighted Average Rate of Interest on Loan 8.24% Interest on Loan 26.89 Return on Equity (ROE)

43. The Petitioner has submitted that ROE has been calculated at the rate of 19.61% after grossing up ROE with MAT rate of 20.961% as per provisions of Regulations 24 and 25 of the 2014 Tariff Regulations. The Petitioner has further submitted that the grossed up ROE is subject to truing up based on the effective tax rate of respective financial year applicable to the Petitioner Company.

44. We have considered the submissions made by the Petitioner and the Respondents. Regulation 24 read with Regulation 25 of the 2014 Tariff Regulations provides for grossing up of return on equity with the effective tax rate for the purpose of return on equity. It further provides that in case the generating company or transmission licensee is paying Minimum Alternative Tax (MAT), the MAT rate including surcharge and cess will be considered for the grossing up of return on equity. Accordingly, the MAT rate applicable during 2018-19 has been considered for the purpose of return on equity, which shall be trued up with actual tax rate in accordance with Regulation 25(3) of the 2014 Tariff Regulations.

45. Accordingly, ROE allowed is as follows: ( in lakh) Particulars 2018-19 (Pro-rata 21 days) Opening Equity 2370.13 Addition due to Additional Capitalization 133.76 Closing Equity 2503.89 Order in Petition No.248/TT/2019 Page 19 of 28 Particulars 2018-19 (Pro-rata 21 days) Average Equity 2437.01 Return on Equity (Base Rate ) 15.50% MAT rate for the Financial year 21.549% Rate of Return on Equity (Pre-tax) 19.758% Return on Equity (Pre-tax) 27.70 Interest on Loan (IOL)

46. IOL has been calculated as per the provisions of Regulation 26 of the 2014 Tariff Regulations as detailed below:

(iv) Gross amount of loan, repayment of instalments and rate of interest on actual loans have been considered as per petition including additional information.

(v) The yearly repayment for the tariff period 2014-19 has been considered to be equal to the depreciation allowed for that year.

(vi) Weighted average rate of interest on actual average loan worked out as per (i) above is applied on the notional average loan during the year to arrive at the interest on loan.

47. The Petitioner has submitted that IOL has been claimed on the basis of rate prevailing as on COD and the change in interest due to floating rate of interest applicable, if any, needs to be claimed/ adjusted over the tariff block 2014-19. We have calculated IOL on the basis of rate prevailing as on the date of commercial operation. Any change in rate of interest subsequent to the date of commercial operation will be considered at the time of truing-up. IOL is allowed considering all the loans submitted in Form-9C. The Petitioner is directed to reconcile the total Gross Loan for the calculation of weighted average Rate of Interest and for the calculation of IDC, which would be reviewed at the time of truing-up.

48. The details of IOL approved for the transmission asset are as follows: ( in lakh) Particulars 2018-19 (Pro-rata for

21 days) Gross Normative Loan 5530.29 Cumulative Repayment upto previous Year 0.00 Net Loan-Opening 5530.29 Addition due to Additional Capitalization 312.11 Repayment during the year 23.57 Order in Petition No.248/TT/2019 Page 20 of 28 Particulars 2018-19 (Pro-rata for

21 days) Net Loan-Closing 5818.84 Average Loan 5674.56 Weighted Average Rate of Interest on Loan 8.24% Interest on Loan 26.89 Depreciation

49. Depreciation has been dealt with in line of Regulation 27 of 2014 Tariff Regulations. The transmission asset was put under commercial operation during 2018-19. Accordingly, it will complete 12 years beyond the tariff period 2014-19. The Gross Block during 2018-19 has been depreciated at weighted average rate of depreciation (WAROD) (as placed in Annexure-1). WAROD has been worked out after taking into account the depreciation rates of assets as prescribed in the 2014 Tariff Regulations and depreciation allowed during the 2018-19 is as under: ( in lakh) Particulars 2018-19 (Pro-rata for

21 days) Opening Gross Block 7900.42 Additional Capitalisation 445.87 Closing Gross Block 8346.29 Average Gross Block 8123.36 Weighted Average Rate of Depreciation (WAROD) 5.0421% Depreciable Value 7735.09 Depreciation during the year 23.57 Remaining Depreciable Value at the end of the year 7711.53 Operation and Maintenance Expenses (O&M Expenses)

50. The Petitioner has claimed the following O&M Expenses for the transmission asset: ( in lakh) Asset Particulars 2018-19

2 nos. 240 MVAR, 765kV Switchable Line Reactor Bays & 2 Nos 765 kV Line Bays O&M Expenses 21.72

51. The Petitioner in the instant petition has submitted that O&M Expenses norms provided in the 2014 Tariff Regulations for the tariff period 2014-19 had been arrived on the basis of normalized actual O&M Expenses during the period 2008-09 Order in Petition No.248/TT/2019 Page 21 of 28 to 2012-13. The Petitioner has further submitted that the wage revision of the employees is due during 2014-19 and actual impact of wage hike effective from a future date has not been factored in fixation of the normative O&M rates specified for the tariff block 2014-19. The Petitioner has submitted that it would approach the Commission for suitable revision in norms for O&M Expenses for claiming the impact of wage hike during 2014-19, if any.

52. We have considered the submissions of Petitioner. The O&M Expenses norms specified for the transmission asset under Regulation 29(4) of the 2014 Tariff Regulations are as follows: Element 2018-19 Sub-station: 765 kV bay ( in lakh per bay) 96.20

53. The O&M Expenses have been worked out as per the norms specified in the 2014 Tariff Regulations. As regards the impact of wage revision, any application filed by the Petitioner in this regard will be dealt with in accordance with the appropriate provisions of the 2014 Tariff Regulations. The Petitioner has computed normative O&M Expenses as per Regulation 29(4)(a) of the 2014 Tariff Regulations. Accordingly, the O&M Expenses approved is given below: ( in lakh) Asset 2018-19 (Pro rata for 21 days

2 nos. 240 MVAR, 765kV Switchable Line Reactors Bays and 2 nos. 765 kV Line bays 21.72 Total O&M Expenses Allowed 21.72 Interest on Working Capital (IWC)

54. As per the 2014 Tariff Regulations the components of the working capital and the interest thereon are discussed hereinafter:

a) Maintenance spares: Order in Petition No.248/TT/2019 Page 22 of 28 Maintenance spares @15% Operation and maintenance expenses specified in Regulation 29.

b) O & M expenses: Operation and maintenance expenses have been considered for one month of the O&M expenses.

c) Receivables: The receivables have been worked out on the basis of 2 months of annual fixed cost as worked out above.

d) Rate of interest on working capital: As per Clause 28 (3) of the 2014 Tariff Regulations, SBI Base Rate as on 1.4.2018 (8.70%) plus 350 bps i.e. 12.20% has been considered as the rate of interest on working capital.

55. Accordingly, the interest on working capital approved for the transmission is summarized hereunder: ( in lakh) Particulars 2018-19 (Pro-rata for

21 days) Maintenance Spares 56.63 O&M Expenses 31.46 Receivables 297.15 Total 385.24 Rate of Interest 12.20% Interest on working Capital 2.70 Annual Transmission charges

56. Accordingly, the annual transmission charges allowed for the transmission assets are as under: ( in lakh) Particulars 2018-19 (Pro-rata for

21 days) Depreciation 23.57 Interest on Loan 26.89 Return on Equity 27.70 Interest on Working Capital 2.70 O&M Expenses 21.72 Total 102.58 Order in Petition No.248/TT/2019 Page 23 of 28 Filing fee and the publication expenses

57. The Petitioner has sought reimbursement of fee paid by it for filing the petition and publication expenses in terms of Regulation 52 of the 2014 Tariff Regulations. The Petitioner shall be entitled for reimbursement of the filing fees and publication expenses in connection with the present petition, directly from the beneficiaries on pro-rata basis in accordance with clause (1) of Regulation 52 of the 2014 Tariff Regulations. License fee and RLDC Fees and Charges

58. The Petitioner has prayed to allow the Petitioner to bill and recover License fee and RLDC fees and charges, separately from the respondents. We are of the view that the Petitioner shall be entitled for reimbursement of license fee and RLDC fees and charges in accordance with Clause (2)(b) and (2)(a) of Regulation 52 in the 2014 Tariff Regulations. Goods and Services Tax

59. The Petitioner has prayed for reimbursement of tax, if any, on account of implementation of GST. GST is not levied on transmission service at present and we are of the view that Petitioners prayer is premature. Sharing of transmission charges

60. The Petitioner has submitted that the billing, collection and disbursement of transmission charges and shall be governed by provision of the Central Electricity Regulatory Commission (Sharing of inter-State Transmission Charges and Losses) Regulations, 2010 (2010 Sharing Regulations) as per Regulation 43 of 2014 Tariff Regulations.

61. TANGEDCO has submitted that the work of Additional inter-regional AC link for import of power into Southern Region i.e. Warora-Warangal and Chilakaluripeta- Hyderabad-Kurnool 765 kV Link (line) was awarded to WKTL, a subsidiary of Essel Order in Petition No.248/TT/2019 Page 24 of 28 Infra under TBCB route. The execution of the line was stalled because of the objections of Western Coal Field Limited (WCL) and Singareni Collieries Company Limited (SCCL) as the Warora-Warangal Transmission Line was crossing the proposed coal fields. The issue is being taken up by Ministry of Power (MoP) with Ministry of Coal (MoC). TANGEDCO has submitted that in the present case, WKTL has completely stalled the project and there is no possibility of putting the assets into beneficial use. Hence, even if COD of the transmission assets is approved by the Commission in anticipation, WKTL is liable to pay the transmission charges as per the 2010 Sharing Regulations. TANGEDCO has submitted that the Commission in order dated 25.1.2016 in Petition No. 253/TT/2015 has held that in case of delay on account of commissioning of the concerned generating station or in COD of the upstream or downstream transmission system, the DIC causing delay shall bear the transmission charges. TANGEDCO has further submitted that as WKTL has not commissioned its entire scope of the project, the transmission charges are to be borne by WKTL till commissioning of the assets in their scope.

62. WKTL has submitted that the scheduled COD of the line under its scope for import of power into Southern Region as per TSA is 6.11.2019. However, there is time over-run in case of the line due to certain force majeure events that are beyond WKTLs reasonable control. The cumulative impact of such force majeure events on the critical path of the line, has led to delays in the completion of the foundation, erection and stringing works of the line. The time over-run in case of the line is due to ROW, overlapping of route alignment of the Petitioners 800 kV HVDC Raigarh- Pugalur Transmission Line with the transmission lines of WKTL, unprecedented heavy rainfall in the States of Telangana and Andhra Pradesh, objections raised by the Telangana State Industrial Infrastructure Corporation (TSIIC) on the ground that TSIIC was in the process of acquiring the land over which the said lines were being Order in Petition No.248/TT/2019 Page 25 of 28 constructed, for development of industries, directions issued by Western Coalfields Ltd. (WCL) and Singareni Collieries Company Ltd. (SCCL) to stop construction of tower and Prof. Jayashankar Open Cast project, crossing of proposed wayside amenity and helipad on the Project line raised by National Highway Authority of India (NHAI), etc.

63. WKTL has further submitted that WKTL has filed Petition No. 334/MP/2020 for extension of the scheduled COD under Article 4.4.2 of the TSA. WKTL has submitted that in terms of Article 4.4.2 of the TSA, if an element or the project is not put into commercial operation within the scheduled COD on account of force majeure events, then such scheduled COD shall be extended. Therefore, WKTL is eligible for extension of the scheduled COD till the actual COD of the line in view of the afore-said force majeure events due to which WKTL was hindered from performing its obligations under the TSA. WKTL has further submitted that it is not liable to pay transmission charges for the period from 11.3.2019 to 9.11.2019 as the same is outside the scope of the terms and conditions of the TSA executed by WKTL as it was required to commission its transmission system only by November, 2019.

64. We have considered the submissions of the Petitioner, TANGEDCO and WKTL. WKTLs prayer for extension of scheduled COD of its transmission asset due to force majeure conditions has already been decided by the Commission vide order dated 7.2.2021 in Petition No. 334/MP/2020. As such, there is no necessity for us to dwell into the issue in this order. The relevant portion of the order dated 7.2.2021 is extracted hereunder:

35. During the course of hearing on 25.8.2020, in response to a specific query of the Commission regarding likely COD of the transmission Project, learned counsel for the Petitioner informed the Commission that since many of the force majeure events such as pending court proceedings, objections raised by TSIIC and pendency of wildlife approval are still continuing, the Petitioner is not in position to confirm the likely COD Order in Petition No.248/TT/2019 Page 26 of 28 of the Project. Learned counsel further submitted that lenders of the Petitioner are also in process of substituting Essel Infra project Limited with their nominee, Adani Transmission Limited (successful bidder) due to continuous defaults in debt payment.

36. It is observed that events cited above are still continuing and the Petitioner has approached the Commission for declaration of these events as force majeure events and requested for extension of SCOD of the Project, in advance. The Petitioner itself stated that it is unable to quantify and to confirm the likely COD of the Project as some of above events are still continuing. Therefore, we are of the view that since the project has not been completed by the Petitioner till date and is still under implementation with uncertainty about the likely COD, it would not be appropriate to take a view on the claimed force majeure issues and extension of SCOD at this stage. Accordingly, the Petitioner is granted liberty to approach the Commission to seek the appropriate relief for force majeure events, after completion of the Project.

65. TANGEDCO has contended that the transmission charges for the period from the COD of the transmission asset till the COD of the transmission lines under the scope of WKTL should be borne WKTL.

66. We have already approved the COD of the transmission asset as 11.3.2019 based on the recommendation of the 35th SRPC meeting for early commissioning of the line reactors at Kurnool Sub-station for controlling the voltage at Kurnool Sub- station. Therefore, we are of the view that the transmission charges approved in this order should be included in PoC pool from COD of the Asset i.e. 11.3.2019 to up to SCOD of the instant Asset i.e. 8.11.2019. It is observed from minutes of the 35th SRPC that RPC approved only for early commissioning of the line reactors at Kurnool Sub-station on the anticipation that the associated transmission lines will be expected to be commissioned in the month of November, 2019. The associated transmission line is scheduled to be commissioned on 9.11.2019. However, the associated transmission line has not achieved COD as anticipated. Therefore, the petitioner is directed to approach SCM/RPC for continuing to use the line reactor as bus reactor post scheduled COD of the associated transmission line and treatment of transmission charges beyond scheduled COD.

67. Accordingly, the billing, collection and disbursement of the transmission charges approved in this order shall be governed by the provisions of Central Order in Petition No.248/TT/2019 Page 27 of 28 Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, as amended from time to time as provided in Regulation 43 of the 2014 Tariff Regulations.

68. To summarise, annual transmission charges allowed for the instant transmission assets for the year 2018-19 (pro-rata for 21 days) are 102.58 lakh and the petitioner is directed to approach SCM/RPC for continuing to use the line reactor as bus reactor post scheduled COD of the associated transmission line and treatment of transmission charges beyond scheduled COD.

69. This order disposes of Petition No.248/TT/2019. sd/- sd/- sd/- (Arun Goyal) (I. S. Jha) (P. K. Pujari) Member Member Chairperson Order in Petition No.248/TT/2019 Page 28 of 28 Annexure-1 ( in lakh) Capital Expenditures as on COD Admissible Capital Cost as on COD for tariff purpose Projected Additional Capital Expenditure Rate of Depreciation as per Regulation Annual Depreciation as per Regulation 2018-19 Total 2018-19 Freehold Land 365.97 - - - - Sub-station Equipment 7534.45 445.87 445.87 5.28% 409.59 Total 7,900.42 445.87 445.87 409.66 Average Gross Block ( in lakh) 8,123.36 Weighted Average Rate of Depreciation 5.0421% CERC website S. No. 136/2021