C & C Constructions Ltd. v. Ircon International Ltd. .

Delhi High Court
Mar 1, 2021
Smart Summary (Beta)

Factual and Procedural Background

This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 challenges the dismissal of an application filed by the appellant under Section 34 of the Act. The Section 34 application (OMP(COMM) No.566/2020) pertained to an arbitral award dated 21st December, 2019, wherein a three-member Arbitral Tribunal dismissed all the appellant's claims in exercise of powers under Section 16 of the Act. These claims concerned monetary compensation/damages related to a contract for the construction of Road Over Bridges (ROBs) and related works entered into between the appellant and the respondent. The respondent had filed an application under Section 16 of the Act, which resulted in the summary dismissal of the appellant's 15 monetary claims on the basis that they were barred by Clause 49.5 of the General Conditions of Contract.

Legal Issues Presented

  1. Whether the Arbitral Tribunal was correct in summarily dismissing the appellant's monetary claims under Section 16 of the Arbitration and Conciliation Act, 1996, invoking Clause 49.5 of the General Conditions of Contract.
  2. Whether the appellant was denied the opportunity to lead evidence, thus violating principles of natural justice and public policy under Section 34(b)(ii) of the Arbitration Act.
  3. Whether Clause 49.5 of the General Conditions of Contract was valid and binding or waived/novated by the respondent.
  4. The scope of interference by this Court under Section 37 of the Arbitration Act with respect to the arbitral award.

Arguments of the Parties

Appellant's Arguments

  • The Arbitral Tribunal erred in summarily dismissing all 15 monetary claims without granting an opportunity to prove that the claims were not barred by Clause 49.5.
  • All claims fall under Clause 49.4 of the General Conditions of Contract, which deals with delays not attributable to the employer or contractor but caused by third parties or court orders, thus entitling the appellant to compensation.
  • Denying the opportunity to lead evidence violates the principles of natural justice and public policy of India under Section 34(b)(ii) of the Arbitration Act.
  • Clause 49.5 was waived by the respondent, as evidenced by correspondence between the parties dated 19th June, 2013 and 14th October, 2013.
  • Reliance on a Single Judge judgment in Simplex Concrete Piles (India) Ltd. vs. Union of India, which held a clause similar to Clause 49.5 to be barred by Section 28 of the Indian Contract Act, 1872.
  • Reference to Asian Techs Ltd. vs. Union of India, where a similar clause was disregarded.

Respondent's Arguments

  • The claims were correctly dismissed as barred by Clause 49.5 of the General Conditions of Contract, which precludes entitlement to damages except for reasonable extensions of time granted by the engineer.
  • Clause 49.5 was not waived; the correspondence relied upon does not demonstrate any waiver or novation of the contract clause.
  • Clause 54 of the General Conditions of Contract prescribes the manner in which the contract or any part thereof can be novated, which was not followed.
  • Reliance on Supreme Court decisions in General Manager Northern Railways vs. Sarvesh Chopra and Oil and Natural Gas Corporation vs. Wig Brothers Builders and Engineers Pvt. Ltd. affirming the validity of clauses similar to Clause 49.5.
  • The appeal against the Single Judge judgment in Simplex Concrete Piles is pending before the Division Bench.
  • Clause 49.4 protects the contractor (appellant) from claims of delay by the respondent if delays are caused by third parties and does not entitle the appellant to claim compensation for delay from the respondent.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Municipal Corporation of Delhi vs Jagannath Ashok Kumar (1987) 4 SCC 497 Procedural fairness and principles of natural justice in arbitral proceedings. Referenced to clarify that opportunity to lead evidence is not absolute if claims are evidently barred by contract terms.
Sohan Lal Gupta vs Asha Devi Gupta (2003) 7 SCC 492 Principles of natural justice and evidence in arbitration. Used to support the limited scope of procedural fairness in arbitration.
Jagjeet Singh Lyallpuri vs Unitop Apartments and Builders Ltd. (2020) 2 SCC 279 Scope of arbitration tribunal powers and procedural requirements. Reinforced the tribunal’s discretion in summary dismissal where claims are contractually barred.
Centrotrade Minerals and Metals Ink vs Hindustan Copper Ltd. MANU/SC/0464/2020 Standards for interference with arbitral awards. Supported the narrow scope of judicial interference under Section 37.
Simplex Concrete Piles (India) Ltd. vs Union of India MANU/DE/4538/2010 Validity of contract clauses under Section 28 of the Indian Contract Act, 1872. Mentioned by appellant; court noted appeal pending and did not apply it as binding.
General Manager Northern Railways vs. Sarvesh Chopra (2002) 4 SCC 45 Validity of contract clauses similar to Clause 49.5. Relied upon by respondent to uphold the validity of Clause 49.5.
Oil and Natural Gas Corporation vs. Wig Brothers Builders and Engineers Pvt. Ltd. (2010) 13 SCC 377 Validity of contractual clauses limiting claims for damages. Supported respondent’s position on Clause 49.5’s validity.
Asian Techs Ltd. vs. Union of India (2009) 10 SCC 354 Disregard of contractual clauses similar to Clause 49.5. Distinguished by the court as not applicable to the present facts.
Deep Industries Ltd. vs Oil and Natural Gas Corporation Ltd. 2019 SCC Online SC 1602 Narrow scope of judicial interference under Section 37 of the Arbitration Act. Emphasized by the court to limit interference with arbitral awards.
MMTC Ltd. vs Vedanta Ltd. (2019) 4 SCC 163 Scope of interference with arbitral awards under Section 37. Reinforced the principle that courts should not act as appellate forums in arbitration matters.

Court's Reasoning and Analysis

The court analyzed the appellant’s claims and the contractual provisions, particularly Clause 49.5, which excludes entitlement to damages or compensation for delays attributable to the respondent or the engineer, except for reasonable extensions of time. The Arbitral Tribunal dismissed the claims summarily under Section 16 of the Arbitration Act, finding them barred by Clause 49.5. The appellant's contention that all claims fall under Clause 49.4, which deals with delays caused by third parties or court orders, was found unpersuasive because Clause 49.4 primarily protects the contractor from claims by the employer, not the other way around.

The court held that the principles of natural justice do not mandate an absolute right to lead evidence if the claim is evidently barred by the contract, especially since arbitration proceedings are not bound by the procedural strictures of the Civil Procedure Code or Indian Evidence Act. The correspondence relied upon by the appellant did not establish any waiver or novation of Clause 49.5, which requires formal novation under Clause 54 of the contract. The court distinguished the appellant’s reliance on certain precedents, noting that some were either not applicable or were pending appeal.

Further, the court emphasized the narrow scope of interference permissible under Section 37 of the Arbitration Act, which does not allow the court to act as an appellate forum to re-examine factual or legal findings of the arbitral tribunal. The parties, having agreed to arbitration, are bound by the arbitrators’ decisions and cannot use arbitration as a preliminary step to litigation.

Consequently, the court found no grounds to interfere with the arbitral award or the dismissal of the Section 34 application.

Holding and Implications

The appeal under Section 37 of the Arbitration and Conciliation Act, 1996 is dismissed.

The court upheld the arbitral award dismissing the appellant’s claims as barred by Clause 49.5 of the contract and confirmed the limited scope of judicial interference under Section 37. The decision binds the parties to the arbitral award, emphasizing that arbitration awards are final and not subject to re-litigation on the merits in court. No new precedent was set; the ruling reinforces established principles limiting judicial review of arbitral awards and affirms the contractual validity of Clause 49.5 in this context.

Show all summary ...

HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW HON'BLE MR. JUSTICE AMIT BANSAL [VIA VIDEO CONFERENCING] RAJIV SAHAI ENDLAW, J. CM No.8193/2021 (for exemption)

1. Allowed, subject to just exceptions and as per extant rules.

2. The application is disposed of. FAO(OS) (COMM) No.36/2021

3. This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 impugns the judgment/order dated 15th December, 2020 of the Commercial Division of this Court of dismissal of application of the appellant under Section 34 of the said Act. FAO(OS)(COMM) 36/2021 Page 2 of 6

4. The application under Section 34 of the Act, being OMP(COMM) No.566/2020, was filed with respect to arbitral award dated 21st December, 2019 (of three Arbitrators, with the appellant and the respondent having nominated one Arbitrator each and the third Arbitrator having been appointed by this Court) of dismissal, in exercise of powers under Section

16 of the Act, of all the claims of the appellant.

5. It is the contention of the counsel for the appellant that the Arbitral Tribunal, on an application under Section 16 of the Act having been preferred by the respondent, has summarily dismissed all the 15 monetary claims for recovery of compensation/damages, of the appellant against the respondent, with respect to the Contract for Construction of Road Over Bridges (ROBs) & its approaches as per Specifications, Drawing & Design, Maintaining all Quality Control Standards etc. complete under ROB Cluster Package in Lieu of various LCs at Jaipur entered into by the respondent with the appellant.

6. The counsel for the appellant has drawn our attention to Clause 49.5 of the General Conditions of Contract, invoking which the application under Section 16 of the Act was filed by the respondent. As per the said clause, in the event of any failure or delay on the part of the respondent or the engineer in fulfilling their obligations under the contract, such failure or delay on the part of the respondent or the engineer was not to in any way affect or vitiate the contract or alter the character thereof or entitle the appellant to damages or compensation therefor except that the engineer shall grant such extension or extensions of time to complete the work as in his opinion was reasonable. It was the plea of the respondent in its application under Section 16 of the FAO(OS)(COMM) 36/2021 Page 3 of 6 Act, that all the 15 monetary claims of the appellant were barred and/or not maintainable under Clause 49.5 of the General Conditions of Contract.

7. The counsel for the appellant has contended that the Arbitral Tribunal ought to have granted the appellant an opportunity to prove that the claims of the appellant were not barred by Clause 49.5 of the General Conditions of Contract. Attention is drawn to Clause 49.4 of the General Conditions of Contract which deals with delays not due to employer/contractor but on the part of the third parties or on the part of the Court orders. The contention of the counsel for the appellant is that all the 15 claims of the petitioner fall under Clause 49.4. On further enquiry, as to under which clause of Section

34 of the Arbitration Act the appellant justifies setting aside of the award, it is contended that the claim of the appellant falls under Section 34(b)(ii), whereunder an arbitral award is liable to be set aside if is in conflict with the public policy of India. It is argued that opportunity to lead evidence is the public policy of India and summary dismissal of claims under Section 16, as barred by Clause 49.5, is in denial of principles of natural justice.

8. Though according to us there is no absolute component of the principles of natural justice, that an opportunity to lead evidence will be granted, if it is otherwise evident from the pleadings and the documents that the claim is barred, and the Arbitral Tribunal is not bound by the procedure prescribed in the Code of Civil Procedure, 1908 (CPC) or the Indian Evidence Act, 1872 but we have proceeded to hear the counsels. Reference in this regard may be made to Municipal Corporation of Delhi vs Jagannath Ashok Kumar (1987) 4 SCC 497, Sohan Lal Gupta vs Asha Devi Gupta (2003) 7 SCC 492, Jagjeet Singh Lyallpuri vs Unitop FAO(OS)(COMM) 36/2021 Page 4 of 6 Apartments and Builders Ltd. (2020) 2 SCC 279 and Centrotrade Minerals and Metals Ink vs Hindustan Copper Ltd. MANU/SC/0464/2020. If it was the case of the appellant itself before the Arbitral Tribunal that the compensation/damages sought were caused to the appellant on account of delay of the respondent, there was no need for the Arbitral Tribunal to given an opportunity to lead evidence to the appellant, since the claim, on the own plea of the appellant, was barred by the contract between the parties.

9. We have enquired from the counsel for the petitioner, that even if it were to be believed that the claims of the petitioner fell under Clause 49.4 and not under Clause 49.5 of the General Conditions of Contract, how could the delay on the part of the third parties to the contract entitle the appellant to make monetary claims for delay against the respondent. Clause 49.4 appears to have been inserted, only to protect the contractor i.e. the appellant herein from claims of the respondent of delay, if such delay were to be on account of third parties.

10. The counsel for the appellant does not controvert the same and on the contrary now contends that Clause 49.5 was waived by the respondent and has in this regard drawn our attention to the letter of the appellant dated 19th June, 2013 at page 754 of the electronic file and the response of the respondent dated 14th October, 2013 at page 831 of the file thereto.

11. However a perusal of the said communication and response also does not demonstrate any plea of waiver of Clause 49.5, even if it was possible in such manner. The letter dated 19th June, 2013 of the appellant has the subject of Requisition for extension of time. The respondent, in its response thereto asked the appellant for its claim, only for the purposes of FAO(OS)(COMM) 36/2021 Page 5 of 6 deciding, whether to grant extension of time or not and it can by no stretch of imagination be said that from the said correspondence, Clause 49.5 stood waived. A contract arrived at in a formal manner cannot be novated in the manner suggested by the counsel for the appellant. The counsel for the respondent has also drawn our attention to Clause 54 of the General Conditions of Contract which provides the manner in which any part of the contract was to be novated.

12. The counsel for the appellant has also referred us to a judgment of a Single Judge of this Court in Simplex Concrete Piles (India) Ltd. Vs. Union of India MANU/DE/4538/2010, to contend that a clause as Clause 49.5 has been held to be barred by Section 28 of the Indian Contract Act, 1872.

13. The counsel for the respondent states that the appeal thereagainst is pending before the Division Bench. He has also drawn our attention to the dicta of the Supreme Court in General Manager Northern Railways Vs. Sarvesh Chopra (2002) 4 SCC 45, where a clause as Clause 49.5 has been held to be valid. Reference is also made to the dicta in Oil and Natural Gas Corporation Vs. Wig Brothers Builders and Engineers Pvt. Ltd. (2010) 13 SCC 377.

14. The counsel for the appellant has drawn our attention to Asian Techs Ltd. Vs. Union of India (2009) 10 SCC 354 to contend that therein a similar clause as Clause 49.5 was held to have been given a go-by.

15. However the same is not the case here.

16. Moreover, this Court, while exercising powers under Section 37 of the Arbitration Act has to remember that as held in Deep Industries Ltd. vs FAO(OS)(COMM) 36/2021 Page 6 of 6 Oil and Natural Gas Corporation Ltd. 2019 SCC Online SC 1602, MMTC Ltd. vs Vedanta Ltd. (2019) 4 SCC 163, the scope of interference with the Arbitral Award, under Section 37, is much narrower and more limited than even under Section 34 of the Act and this Court is not to hear and adjudicate as in second appeal under the CPC, to see whether any substantial question of law arises. The parties agreeing to arbitration have to remember that they are thereby binding themselves to the decision of the arbitrator/s on facts as well as law and cannot use arbitration as a first step in litigation.

17. No case for interference is made out.

18. Dismissed. RAJIV SAHAI ENDLAW, J. AMIT BANSAL, J. MARCH 1, 2021