Biju K. Varghese v. Geologist Mining And Geologist Department And Others

Kerala High Court
Nov 5, 2020
Smart Summary (Beta)

Structured Summary of the Opinion

Factual and Procedural Background

The petitioner is the owner of a parcel of land. The third respondent, the Village Officer, forwarded Ext.P1 report to the first respondent (a Geologist) alleging that the petitioner had removed 2520 cubic meters of ordinary earth from the property. Following an inspection, the first respondent issued a show cause notice dated 11.06.2019 alleging removal of 2520 cubic meters of ordinary earth in violation of the Kerala Minor Mineral Concession Rules, 2015 and directing the petitioner to show cause.

The petitioner replied denying the allegation, explaining that flood-related accumulation of earth had occurred on his property and that he merely levelled that earth for agricultural operations and had not removed earth from the property. Despite the reply, the first respondent issued Ext.P3, styled as a demand notice, stating the petitioner's explanation was not acceptable and calling upon the petitioner to pay Rs.4,40,800/- towards royalty, price and fine. The petitioner challenged Ext.P3 by filing the present writ petition.

The Court heard arguments of the petitioner and the learned Government Pleader. The Government Pleader supplied the show cause notice and the petitioner’s reply at the Court’s request. The matter turned on whether Ext.P3 constituted an adjudicatory order and whether the proceedings complied with principles of natural justice.

Legal Issues Presented

  1. Whether Ext.P3 was merely a demand notice or an adjudicatory order by the first respondent determining liability for removal of ordinary earth.
  2. Whether, before issuing Ext.P3, there had been an adjudication of the dispute raised by the petitioner (i.e., whether the petitioner had removed ordinary earth as alleged).
  3. Whether Ext.P3 and the preceding notice complied with the principles of natural justice, in particular audi alteram partem (adequacy and particulars of notice, opportunity to be heard, requirement of mahazar and specification of quantity and power invoked).
  4. Whether the writ petition was maintainable in view of an alternative remedy of appeal under the Rules, particularly where an allegation of breach of natural justice is raised.

Arguments of the Parties

Petitioner's Arguments

  • The petitioner denied the allegation of removal of earth and contended that there should have been an adjudication on that dispute before Ext.P3 (i.e., a proper decision-making process determining whether removal occurred).
  • The quantification of 2520 cubic meters was made without basis; specifically, there was no mahazar prepared by the first respondent to support such quantification.
  • The first respondent lacked authority to impose a fine on the petitioner under the Rules.
  • There was no effective hearing of the matter by the first respondent prior to issuing Ext.P3.

Respondent's (Government Pleader) Arguments

  • Ext.P3 was passed under Rule 108 of the Kerala Minor Mineral Concession Rules, 2015, and an appeal is available under the Rules; therefore the writ petition was not maintainable because an effective alternative remedy existed.
  • The absence of a mahazar does not automatically render the quantification incorrect.
  • The Ext.P1 report of the Village Officer was categoric, provided property particulars and supported the first respondent’s issuance of Ext.P3.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Canara Bank v. Debasis Das, (2003) 4 SCC 557 Used to illustrate the test whether a notice is sufficient: whether the party received the order by surprise or shock. The Court referred to this principle to test adequacy of the notice issued by the first respondent and whether the petitioner was put on sufficient notice of the case to be met.
Commissioner of Central Excise, Bangalore v. Brindavan Beverages (P) Ltd., (2007) 5 SCC 388 Similarly cited for the principle that sufficiency of notice is measured by whether the party was taken by surprise; an aspect of audi alteram partem. The Court applied this precedent as part of the legal yardstick for evaluating whether the show cause notice and the proceedings afforded a reasonable opportunity to the petitioner.
Smt. Ambika Devi v. State, AIR 1988 Patna 258 Cited in support of the proposition that a party should not receive adjudicatory orders by surprise; an authority on adequacy of notice. The Court invoked the principle from this case in concluding that particulars required in notice (quantity, action proposed, power invoked) are necessary to satisfy natural justice.

Court's Reasoning and Analysis

The Court first addressed whether Ext.P3 was an adjudicatory order or merely a demand notice. Ext.P3 recited the earlier show cause notice, recorded that the petitioner’s explanation was not acceptable, and directed payment of Rs.4,40,800/- as royalty, price and fine for removal of 2520 cubic meters of ordinary earth. Rule 108 of the Rules vests authority to recover such amounts. On these facts the Court held that Ext.P3 was a formal expression of the first respondent’s decision on the dispute and therefore constituted an adjudicatory order (even though it was styled a demand notice).

Recognising that Ext.P3 is an order against which an appeal lies under the Rules, the Court nevertheless noted that it may exercise writ jurisdiction under Article 226 where there is a breach of principles of natural justice. The petitioner specifically alleged denial of an effective hearing.

The Court explained the core natural justice requirement of audi alteram partem: notice must apprise the party of the case to be met and provide adequate time and particulars. The notice should mention particulars of the act/omission constituting the breach, the action proposed, the power under which action is proposed, and, where relevant, details such as the quantity of mineral removed and reference to any mahazar so that the party is not taken by surprise.

On the facts, the show cause notice dated 11.06.2019 failed to disclose the quantity of earth alleged to have been removed and did not indicate the particulars of the action proposed or the precise power proposed to be invoked. The Court stated that in cases of this nature there should be an inspection with notice to the prima facie indictee, preparation of a mahazar specifying sufficient particulars (including quantity), and reference to the mahazar in the notice. Because those particulars were absent, the Court found the notice did not conform to the requirements of natural justice.

The Government Pleader argued that because the petitioner submitted a reply to the show cause notice he could not now complain of insufficiency of notice and that further particulars could have been sought. The Court rejected that submission, holding that a defective notice that fails to comply with principles of natural justice cannot be cured merely because a reply was filed; the proper remedy is issuance of a fresh, legally compliant notice.

Holding and Implications

HOLDING: The writ petition is allowed and Ext.P3 is set aside.

Implications and direct effects:

  • The impugned communication Ext.P3 (though styled a demand notice) was treated as an adjudicatory order and has been quashed for non-compliance with principles of natural justice (insufficient particulars in the notice: absence of quantity, mahazar reference and specification of the power/action proposed).
  • The Court made clear that the first respondent remains free to initiate fresh proceedings for recovery in accordance with the Rules after issuing a notice that conforms to the legal requirements identified by the Court.
  • The Registry was directed to forward a copy of the judgment to the Secretary to Government, Department of Industry, Government of Kerala, for appropriate action.

The opinion does not state that a new binding precedent was laid down; the decision's direct effect is to quash Ext.P3 and to require any fresh proceedings to be initiated after issuance of a proper notice complying with natural justice.

Show all summary ...

1. Petitioner owns an item of property. The third respondent, the Village Officer concerned has forwarded Ext.P1 report to the first respondent, the Geologist, stating that the petitioner has removed 2520 cubic meters of ordinary earth from the property. On receipt of Ext.P1 report, the first respondent inspected the property and thereupon, issued a notice to the petitioner on 11.06.2019, alleging that it was revealed in the inspection that the petitioner has removed 2520 cubic meters of ordinary earth from the property, violating the Kerala Minor Mineral Concession Rules, 2015 (the Rules), and directing to show cause why action shall not be taken against him for the violation. According to the petitioner, the natural shape of the property was lost due to accumulation of ordinary earth in the property in the recent flood; that he had only levelled the accumulated earth in the property itself for the agricultural operations carried on therein and he has not removed ordinary earth from the property. The petitioner, in the circumstances, has sent a reply to the first respondent informing him the said stand and requesting him to drop the action proposed against the petitioner. Thereafter, the petitioner was issued Ext.P3 communication by the first respondent styling it as a demand notice and informing the petitioner that the explanation offered by him to the show cause notice is not acceptable; that the petitioner is, therefore, liable to pay a sum of Rs.4,40,800/- towards royalty, price and fine for the ordinary earth found to have been removed from the property, and calling upon the petitioner to pay the said amount. Ext.P3 is under challenge in the writ petition.

2. Heard the learned counsel for the petitioner as also the learned Government Pleader.

3. Since the petitioner did not produce the show cause notice and the reply sent by him to the show cause notice, as required by the court, the learned Government Pleader has made available the said documents.

4. The learned counsel for the petitioner contended that insofar as the petitioner has denied the allegation in the notice that he has removed ordinary earth from the property, there should have been an adjudication as to whether the petitioner has removed ordinary earth from the property as alleged in the notice, before issuing Ext.P3 demand notice. Alternatively, it was contended by the learned counsel that the quantification of the ordinary earth alleged to have been removed by the petitioner has been made by the first respondent without any basis, for there is not even a mahazar of the property prepared by him for the said purpose. It was also contended by the learned counsel that at any rate, the first respondent has no authority to impose fine on the petitioner for the alleged breach of the Rules. It was contended by the learned counsel that there was no effective hearing of the matter by the first respondent before issuing Ext.P3 demand notice.

5. The learned Government Pleader submitted that Ext.P3 being an order passed by the first respondent invoking the powers under Rule 108 of the Rules, the writ petition is not maintainable, as the petitioner has an effective alternative remedy by way of appeal against orders in the nature of Ext.P3 under the Rules. It was also contended by the learned Government pleader that merely for the reason that mahazar was not prepared by the first respondent, it cannot be said that the quantification of the ordinary earth made by the first respondent is incorrect. It was further contended by the learned Government Pleader that Ext.P1 report of the Village Officer is categoric in its terms, and since it gives the particulars of the property from where the petitioner has removed ordinary earth, the first respondent cannot be found fault with for having issued Ext.P3 order.

6. As noted, in the reply sent to the show cause notice, the petitioner has denied violation of the Rules alleged against him. The specific case of the petitioner is that despite denial of the violation of the Rules, without adjudicating that dispute, proceedings have been initiated for recovery of the amounts on the premise that the petitioner has violated the Rules. The first and foremost question to be examined, therefore, is as to whether there has been an adjudication of the dispute by the first respondent before Ext.P3 communication was issued to the petitioner. It is seen that in Ext.P3 communication, the first respondent refers to the show cause notice issued by him to the petitioner. The first respondent also recites in Ext.P3 communication that the explanation sent by the petitioner to the show cause notice is not acceptable and therefore, the petitioner is liable to pay royalty, price and fine for having removed 2520 cubic meters of ordinary earth from his property. It was on that premise that the first respondent has called upon the petitioner to pay a sum of Rs.4,40,800/-towards royalty, price and fine in respect of the ordinary earth alleged to have been removed by the petitioner from his property. Rule 108 of the Rules confers authority on the first respondent to recover the royalty, price and fine in respect of the minor minerals removed in violation of the Rules. It is thus evident that there has been an adjudication of the dispute raised by the petitioner. Whether the said adjudication conforms to the requirements of law is a different issue altogether. In so far as there has been an adjudication of the dispute raised by the petitioner, it cannot be contended that Ext.P3 communication is a demand notice, though it is styled as a demand notice. Ext.P3 communication being a formal expression of the decision of the first respondent on the dispute raised by the petitioner, the same should have been styled by the first respondent as an order, instead of a demand notice, and it was unnecessary at all for the first respondent to style it as a demand notice, for an adjudication order in respect of a liability of the instant nature would always take within its scope a demand notice as well. In this context, I am constrained to mention that this practice is being followed by the competent authorities under the Rules throughout the State and several writ petitions have come up before this court raising similar contention. Needless to say, the practice aforesaid needs to be changed for avoiding misconceived litigations.

7. The next question is as to whether Ext.P3 order conforms to the requirements of law. I am conscious of the fact that Ext.P3 being an order against which an appeal is provided under the Rules, this Court may not entertain a challenge against the same, unless there are circumstances justifying interference, in exercise of the jurisdiction under article 226 of the Constitution. As noted, one of the contentions raised by the petitioner in the writ petition is that there was no effective opportunity of hearing before the impugned order was passed. The said contention being one relating to compliance of the principles of natural justice, this Court would be certainly justified in examining the same, for if it is found that the order is vitiated for non-compliance of the principles of natural justice, this Court would be justified in interfering with the same, despite the alternative remedy available to the party.

8. That takes me to the question whether there has been any violation of the principles of natural justice in the matter of the first respondent passing Ext.P3 order. When a quasi-judicial body embarks on determining the rights of parties, adherence to the principles of natural justice is of supreme importance. The first and foremost among the said principles is the principle commonly known as audi alteram partem, viz, that no man should be condemned unheard. Notice is the first limb of that principle. The purpose of notice is to apprise the party the case he has to meet. The time given to the party for showing cause against the action proposed shall also be adequate. The aforesaid are not to be complied with technically, but shall be complied with, so as to enable the party to get a reasonable opportunity to present his case. Coming to the notice again, it must be mentioned that the notice shall necessarily mention the particulars of the act or omission which constitutes the breach of law attracting adverse action, it shall mention the action proposed with necessary particulars, so that the party shall not be taken by surprise, if the competent authority chooses to take the action proposed after compliance of the principles of natural justice and the source of power under which the action is proposed. To be precise, when multiple action is provided for under the Rules in respect of a violation, the party concerned shall certainly be informed as to the particulars of the action proposed against him, for the defence may vary from action to action. The surest test for determining the issue as to whether the notice was sufficient is to ascertain whether the party received the order by surprise and shock [See Canara Bank v. Debasis Das, (2003) 4 SCC 557, Commissioner of Central Excise, Bangalore v. Brindavan Beverages (P) Ltd., (2007)5 SCC 388) and Smt.Ambika Devi v. State, AIR 1988 Patna 258].

9. Reverting to the facts, notice dated 11.06.2019 issued by the first respondent to the petitioner before Ext.P3 order reads thus:

“LANGUAGE”

As evident from the notice, though the same refers to the act which constitutes the breach of law attracting adverse action, the first respondent has not disclosed the quantity of ordinary earth stated to have been removed by the petitioner from the land. The notice does not indicate the particulars of the action proposed against the petitioner, precisely the power that is proposed to be invoked for the same. As regards the action proposed, the notice is vague and ambiguous inasmuch as it only says that action will be taken against the petitioner under law. In a case of this nature, according to me, there shall be an inspection of the property by the competent authority with notice to the indictee. A mahazar of the land from where earth was removed, with sufficient particulars so as to enable one to ascertain the quantity of the earth removed shall be prepared. The notice should certainly refer to the mahazar. It should state the quantity of the earth removed, the nature of the action proposed, the particulars of the dues to be recovered and also the power invoked for the same. If the aforesaid particulars are not furnished to the party concerned in the notice, I have no doubt that in our social scenario, the orders would be received by surprise by the party concerned. Insofar as the notice aforesaid does not contain the necessary particulars, it has to be found necessarily that the same does not conform to the requirements of the principles of natural justice.

10. The learned Government Pleader contended that the petitioner has submitted a reply to the show cause notice, and having submitted a reply to the show cause notice, the petitioner cannot be heard to contend that he was not given sufficient notice. It was the contention of the learned Government Pleader that if as a matter of fact, the petitioner wanted any more particulars as to the action proposed against him, he should have sought that information from the first respondent and had the petitioner sought that information from the first respondent, the same would have been made available to him. I do not agree. If the notice issued in a proceedings is not proper, there would be breach of the principles of natural justice and the said defect in the proceedings cannot be cured except by issuing a proper notice.

In the result, the writ petition is allowed. Ext.P3 order is set aside. It is, however, made clear that this judgment will not preclude the first respondent from initiating a fresh proceedings against the petitioner for recovery of the amounts payable by him in terms of the Rules, after issuing a notice conforming to the requirements of law. Registry is directed to forward a copy of this judgment to the Secretary to Government, Department of Industry, Government of Kerala, for appropriate action.