Factual and Procedural Background
The Revision Petition was filed by Defendant No. 5, M/s. I. Square Infrastructure & Developers, challenging the trial Court's order dated 31.03.2018 in Civil Suit No. 118-A/2014. The trial Court had held that the suit was to be treated as instituted from the date when leave for its institution was accorded while deciding Issue No. 8 under Section 91 of the Code of Civil Procedure, 1908 (CPC).
The Plaintiff, a registered society, instituted a suit for declaration of civil rights and for mandatory injunction to protect a 0.42 acre area designated as a garden/children's park in Khasra No. 406 at village Risali, Durg. The park had been left in a development plan sanctioned on 13.12.1990; the Municipal Corporation sanctioned funds for its development on 14.05.2008. Defendant No. 5 applied to reduce the park area, and the Joint Director, Town and Country Planning reduced the park by 50% by order dated 14.10.2010. The Plaintiff revised that action under statutory provisions and, after administrative dismissal on 26.03.2012, filed WP(PIL) No. 42/13; the Division Bench permitted the Plaintiff to file a civil suit by order dated 11.11.2014. The civil suit was instituted on 24.12.2014 invoking Section 94 CPC.
The defendants contested the suit. The trial Court framed issues on 17.02.2016, including Issue No. 8: "Whether the mandatory provision prescribed under Section 91(1) of CPC has been complied with?" On 31.03.2018 the trial Court observed that although no formal leave application had been filed at the outset, an application for leave was made during pendency and, by allowing that application under Section 151 CPC, the trial Court treated the suit as instituted from the date leave was granted. Defendant No. 5 impugned that order by filing the present revision petition.
Legal Issues Presented
- Whether the mandatory provision of Section 91(1) CPC (requiring leave of the Court to institute a suit for public nuisance or other wrongful acts affecting the public) had been complied with in this suit.
- What is the legal effect when a suit under Section 91 CPC is instituted without prior leave but the leave is granted by the trial Court during the suit's pendency—i.e., whether the suit can be deemed instituted on the date the leave was granted and whether interlocutory proceedings before grant of leave are valid.
- Whether the trial Court committed illegality by allowing an application under Section 151 CPC and treating the suit as instituted from the date leave was granted.
Arguments of the Parties
Applicant / Defendant No. 5 (Shri Sunil Pillai, counsel)
- Submitted that a suit under Section 91 CPC can only be instituted with the leave of the Court, and the mandatory leave requirement is a condition precedent to maintainability.
- Contended that no application seeking leave accompanied the plaint initially, and no order granting leave was passed prior to institution; therefore the suit as framed was not maintainable for non-compliance with the mandatory provision.
- Challenged the trial Court's allowance of the Plaintiff's later application under Section 151 CPC to treat the suit as instituted from the date leave was granted, arguing this constituted a serious illegality.
- Relied upon Supreme Court decisions including A.C. Muthiah v. Board of Control for Cricket in India (cited in the opinion) for the proposition that leave is required and the absence thereof affects maintainability.
Plaintiff
The opinion does not contain a detailed account of the Plaintiff's legal arguments presented before the Court; it records that the Plaintiff filed an application during pendency under Section 151 CPC seeking to regularize institution of the suit and that the trial Court allowed that application.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| A.C. Muthiah v. Board of Control for Cricket in India, reported in (2011) 6 SCC 617; also cited Civil Appeal No(s).6067/2010 decided on 18.09.2019 (SCC OnLine SC 1296) (as referenced in the opinion) | Confirms that leave is necessary to maintain a suit under provisions like Section 91 CPC; illustrates circumstances where leave-application issues arose and parties led evidence without an order on leave. | The Court distinguished this authority: in Muthiah an application for leave had been filed and parties led evidence; because an objection was not raised, the Supreme Court's observation was not to be treated as a precedent applicable to the present facts. The opinion held Muthiah was not helpful to Defendant No. 5. |
| Bansidhar Sankarlal v. Md. Ibrahim, (1970) 3 SCC 900 : AIR 1971 SC 1292 | Principle that proceedings initiated without required leave may be regarded as ineffective until leave is granted, but once leave is granted, the proceeding will be deemed to be instituted on the date leave is granted. | The Court relied on this principle to support the view that a suit instituted without leave can be treated as instituted from the date leave is subsequently granted, rendering earlier proceedings ineffective until the leave is obtained. |
| Kintali China Jaganadham v. K. Laxmi Naidu, AIR 1988 Ori 100 | Held that if a suit is instituted without leave and presentation is granted thereafter, the suit is deemed instituted on the date leave was granted; interlocutory orders passed prior to grant of leave are invalid and non est. | The Court cited and followed this approach, treating interlocutory proceedings prior to grant of leave as potentially invalid and endorsing that the suit is to be deemed instituted on the date of grant of leave. |
| Bhupendra Singh Babara v. Municipal Council Ambikapur, (2001) 3 M.P.H.T. 80 (CG) | Stated that a suit of the nature under Section 91 CPC can be held duly instituted only after leave is granted or permission is accorded. | The Court relied on this local authority to support the proposition that leave/permission is essential and that institution is effective only upon grant of leave. |
Court's Reasoning and Analysis
The Court began by examining Section 91 CPC, reproducing the statutory text and observing that the provision allows suits for public nuisance or other wrongful acts affecting the public to be instituted by the Advocate-General or, "with the leave of the Court, by two or more persons," thereby making leave of the Court a condition precedent to a valid suit under that provision. The Court concluded from a plain reading that "for the institution of a valid suit, leave of the Court is a condition precedent and there would be no properly instituted suit under the aforesaid provision before the leave is granted."
The Court then considered the authorities cited. It identified the principle in Bansidhar Sankarlal that proceedings initiated without required leave may be ineffective until leave is obtained, but once leave is obtained the proceedings are deemed to have been instituted on the date the leave was granted. The Court also referred to the High Court of Orissa's decision in Kintali China Jaganadham, which expressly held that the suit shall be deemed instituted on the date leave was granted and that interlocutory orders passed prior to grant of leave are invalid.
The Court distinguished the A.C. Muthiah decision relied upon by the Applicant. In Muthiah there had been an application for leave and parties had led evidence without the trial Court passing an order on leave; no initial objection was taken and the matter was decided on merits, so the Supreme Court's factual observation in that case was not to be treated as a controlling precedent for the present factual matrix. On that basis the Court found Muthiah unhelpful to the Applicant.
Applying these principles to the present case, the Court observed that although the suit was initially filed without seeking leave as required under Section 91 CPC, the Plaintiff during pendency made an application (under Section 151 CPC) for leave and the trial Court allowed it and treated the suit as instituted from the date the leave was granted. Given the cited authorities that permit a proceeding initiated without leave to be regarded as instituted from the date leave is later granted, the Court found no infirmity in the trial Court's approach in deciding Issue No. 8.
Holding and Implications
Holding: The revision petition filed by Defendant No. 5 is DISMISSED.
Implications:
- The trial Court's order dated 31.03.2018 — treating the suit as instituted from the date on which leave was granted and allowing the Plaintiff's application under Section 151 CPC to that effect — is upheld.
- The direct effect on the parties is that the trial Court's decision stands and the revision petition does not succeed; the Court recorded "No order as to costs."
- The opinion applies established principles (as in Bansidhar Sankarlal and Kintali China Jaganadham) that a proceeding commenced without required leave may be ineffective until the leave is granted, and that once leave is granted the proceeding is deemed instituted from that date. The Court did not purport to lay down any new, broader precedent beyond applying those authorities to the facts of this case.
Sanjay S. Agrawal, J.:— This Revision Petition has been preferred by Defendant No. 5 M/s. I. Square Infrastructure & Developers questioning the legality and propriety of the order dated 31.03.2018 passed by the trial Court in Civil Suit No. 118-A/2014, whereby the suit as framed has been held to be instituted from the date when the leave for its institution has been accorded, while entertaining the issue No. 8, under Section 91 of the Code of Civil Procedure, 1908 (hereinafter referred to as the ‘CPC’). The parties to this petition shall be referred hereinafter as per their description in the Court below.
2. Briefly stated the facts of the case are that the Plaintiff, a registered society, instituted a suit claiming declaration of civil rights and also for protection from public nuisance by way of injunction in a mandatory form with regard to the property in question admeasuring 0.42 acres of land forming part of Khasra No. 406 total admeasuring 5 acres situated at village Risali, Tehsil and District Durg. According to the Plaintiff, the owners of the said property, had applied for a development plan before the Director, Town and Country Planning, Durg and it was sanctioned by the Assistant Director, Town and Country Planning, Durg vide order dated 13.12.1990 under certain terms and conditions stipulated therein. In the said sanctioned order, an open space admeasuring 0.42 acres the suit land, was left for the purpose of garden/children Park and for its development, the Muncipal Corporation, Bhilai has sanctioned a sum of Rs. 5,04,651/- vide its order dated 14.05.2008.
3. Further claim of the Plaintiff is that the Joint Director, Town and Country Planning, Durg on the basis of an application made by Defendant No. 5, namely, M/s. I. Square Infrastructures and Developers, a partnership firm, has initiated the proceeding wherein the park area has been reduced to the extent of 50% vide its order dated 14.10.2010 and that by taking undue advantage of it, the said Defendant has started interfering with the said park area with an intention to convert the same into the plots for residential purposes, giving rise to the institution of the revision by the Plaintiff under Section 32 read with Section 72/74 of the Chhattisgarh Nagar tatha Gram Nivesh Adhiniya, 1973 before Defendant No. 1, who, in turn, has dismissed the same vide its order dated 26.03.2012 which led to the filing of the petition being WP(PIL) No. 42/13. The said petition was disposed of by the Division Bench of this Court vide order dated 11.11.2014 while granting permission to the Plaintiff for filing a civil suit and accordingly the suit in the instant nature for the protection of the children park as granted earlier by the competent authority vide order dated 13.12.1990, which has attained its finality, has been instituted on 24.12.2014 while taking recourse to the provision prescribed under Section 94 of the CPC.
4. The defendants have contested the claim and the trial Court vide order dated 17.02.2016 has framed the issues and one of the issues, namely, issue No. 8 was framed as under:—
“Whether the mandatory provision prescribed under Section 91(1) of CPC has been complied with?”
5. After considering the submissions of the parties with regard to the aforesaid issue, it was observed by the trial Court vide order impugned dated 31.03.2018 that although a formal application seeking leave to institute the suit has not been filed from its inception but as the matter was pending for a long upon its registration and also the interim orders were made therein and in view of the said background observed that the suit shall be deemed to be instituted with the date the leave is granted while allowing the application filed by the Plaintiff during its pendency under Section 151 of the CPC to this effect. The said issue has, thus, been decided accordingly which has been impugned by way of preferring this revision petition by Defendant No. 5.
6. According to Shri. Sunil Pillai, learned counsel appearing for the Applicant, the suit as instituted under Section 91 of CPC could have been instituted only with the leave of the Court and admittedly neither the application seeking leave to institute the suit was accompanied with the plaint nor any order to the said effect was passed. In such an eventuality, the suit as framed should have been held to be not maintainable for the non-compliance of the said mandatory provision. Having failed to do so, the trial Court has committed a serious illegality in proceeding ahead with the matter while allowing the application filed by the Plaintiff under Section 151 of the CPC by treating the suit to be instituted from the date the leave is granted. In support, he placed his reliance upon the decisions rendered by the Supreme Court in the matter of A.C. Muthiah v. Board of Control for Cricket in India reported in (2011) 6 SCC 617 and Civil Appeal No(s).6067/2010 decided on 18.09.2019 2019 SCC OnLine SC 1296 respectively.
7. No one appears on behalf of the contesting Non-applicants 5 to 7/Plaintiffs despite service of notice of this petiton.
8. I have heard learned counsel for the Applicant and perused the entire papers annexed with this petition carefully.
9. Before adverting to the aforesaid contention, it is necessary to examine the provision prescribed under Section 91 of the CPC, which reads as under:—
91. Public nuisances and other wrongful act affecting the public.- [(1) In the case of a public nuisance or other wrongful act affecting, or likely to affect, the public, a suit for a declaration and injunction or for such other relief as may be appropriate in the circumstances of the case, may be instituted,-
(a) by the Advocate-General, or
(b) with the leave of the Court, by two or more persons, even though no special damage has been caused to such persons by reason of such public nuisance or other wrongful act.]
(2) Nothing in this section shall be deemed to limit or otherwise affect any right of suit which may exist independently of its provisions.
10. By virtue of the aforesaid provision, a suit for declaration and injunction or for such other relief as may be appropriate in the circumstances of the case with regard to the public nuisance or other wrongful act affecting or likely to affect the public may be instituted with the leave of the Court, by two or more persons, even though no special damage has been caused to such persons by reason of such public nuisance or other wrongful act. The provision, thus, deals with public nuisance or other wrongful act which affects a considerable number of people. Under the said provision, the Advocate General or two or more persons with the leave of the Court may bring a suit either for a declaration or injunction or for any other relief irrespective of any special damage. It, thus, appears from a bare perusal of the aforesaid provision that for the institution of a valid suit, leave of the Court is a condition precedent and there would be no properly instituted suit under the aforesaid provision before the leave is granted.
11. According to the observations made in the matter of A.C. Muthiah v. Board of Control for Cricket in India (supra) as relied upon by Shri. Pillai, there is, however, no dispute that in order to maintain a suit under the said provision in the nature of public interest for removal of public nuisance or other wrongful act affecting or likely to affect the public at large, the Plaintiff has to obtain the leave of the Court before institution of such a suit and two or more persons must require to be joined as Plaintiffs in filing the same. But the question which falls for determination at this stage that what would be the effect where the trial Court, while entertaining the issue No. 8, has accorded its permission during its pendency?
12. In order to ascertain the proper interpretation of the aforesaid provision, the principles laid down by the Supreme Court in the matter of Bansidhar Sankarlal v. Md. Ibrahim reported in (1970) 3 SCC 900 : AIR 1971 SC 1292 are to be seen. In the said matter, a decree for ejectment of the company was put in execution without obtaining the leave of the Court as required to be obtained under Section 171 of the Indian Companies Act, 1913. It was observed in that factual scenario that if the proceeding for execution of a decree for ejectment is initiated without the leave of the Court, then it may be regarded as ineffective until the leave is granted, but once the leave is granted, the proceedings will be deemed to be instituted on the date when the leave is granted. The observation so made therein at paragraph 8 is relevant for the purpose at this juncture, which reads as under:—
8. …………………The suit or proceeding instituted without leave of the Court may, in our judgment, be regarded as ineffective until leave is obtained, but once leave is obtained the proceeding will be deemed instituted on the date granting leave.”
13. The High Court of Orissa in a similar situation in the matter of Kintali China Jaganadham v. K. Laxmi Naidu reported in AIR 1988 Ori 100, as happened in the instant matter, observed at paragraph 9, while following the aforesaid principles of law that in a suit when it was instituted without the leave of the Court and its presentation was granted thereafter, as under:—
“9. …………The suit shall be deemed to be instituted on the date the leave was granted and not on any earlier date. Proceeding prior to the grant of leave in the suit and any interlocutory order passed prior to the grant of leave shall be held as invalid and non est…………..”
14. Similar in the view taken by this Court in the matter of Bhupendra Singh Babara v. Municipal Council Ambikapur reported in (2001) 3 M.P.H.T. 80 (CG), wherein it has been observed that the suit of such a nature could be held to be duly instituted only after the leave is granted or permission is accorded.
15. Now, further reliance of Shri. Pillai on a decision rendered by the Supreme Court in the matter of A.C. Muthiah v. Board of Control for Cricket in India (supra) is, however, of no use and would not come as a rescue for him. That is the case where an application for leave to institute such a kind of suit was filed. However, no order in this regard was passed by the trial Court, nor the defendant had raised any objection regarding its maintainability for want of leave and instead, both the parties had led evidence and the matter was decided on merits. In that factual scenario, though observed that in every suit of such a nature, grant of leave is necessary under the said provision, but in a peculiar circumstances when an objection was not raised by the defendant initially, therefore, while declining to consider his objection, observed ultimately that the observation made herein, shall not be treated as a precedent.
16. Upon due consideration of the observations made in both the decisions as relied upon by Shri. Pillai, I am not impressed with the contention of him.
17. In the present matter, as observed herein above, although the suit in the instant nature was filed initially without seeking leave of the Court but an application to this effect as required under the law was made by the Plaintiff during its pendency and after allowing the same, the suit has been held to be instituted on the date when the same is granted. In view of the said background and in the light of the principles laid down in the above mentioned decisions, I do not find any infirmity in the approach of the Court below in deciding the issue no. 8 as such.
18. In view of above, the revision petition is accordingly dismissed. No order as to costs.