T.S. Singh v. State Of U.P.
Summary of Tribunal Opinion — Prevention of discharge of untreated sewage into Sai River at Pratapgarh (Uttar Pradesh)
Factual and Procedural Background
The issue before the Tribunal is prevention of discharge of untreated sewage into the Sai River at Pratapgarh, Uttar Pradesh. Pursuant to an order dated 05.08.2019, the Uttar Pradesh State Pollution Control Board (UPSPCB) and UP Jal Nigam were directed to file factual and action taken reports. UPSPCB filed a report on 30.08.2019 which, inter alia, stated that Pratapgarh city generates 8.95 MLD of sewage and that a city drain carrying this untreated sewage flows into the Sai River. An 8.95 MLD Sewage Treatment Plant (STP) based on Fluidized Aerobic Bed Reactor (FAB) technology was constructed near Belhamai Bridge (constructed in 2009), but at the time of inspection it was non-operational because sewer lines and connectivity to the STP were under construction; sewage continued to be directly discharged into the Sai River.
The report further stated that while approximately 95% of the STP work was completed and testing was done in 2010, sewer lines (total proposed length 12.472 km) remain partly unlaid (about 3.472 km under construction). Reasons for delay identified in the report include a public interest litigation (PIL) in the Allahabad High Court lodged by a nearby hospital owner, insufficient funds released compared to sanctioned amounts, repeated cancellation of tenders, and a Forest Department ban that required central clearance. The Sai River has been identified among the "polluted river stretches" and was included in a River Rejuvenation Action Plan approved by the River Rejuvenation Committee, U.P.
The Tribunal summarized these factual findings, expressed concern over public expenditure on largely idle infrastructure, and referred to statutory provisions and prior Tribunal directions addressing river pollution and interim remediation. Further action was directed and a compliance report was ordered to be furnished by 28.02.2020, with the matter listed for further consideration on 16.03.2020.
Legal Issues Presented
- Whether measures must be ordered to prevent discharge of untreated sewage from the Pratapgarh city drain into the Sai River, and what interim and long-term remedial steps should be mandated to stop such discharge and remediate pollution.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| O.A. No. 673/2018 (News item in The Hindu by Jacob Koshy) — order dated 06.12.2019 | Identifying 351 polluted river stretches; directions for 100% treatment of sewage, commencement of STP setting up/connectivity, and financial consequences for defaults (compensation regime). | The Tribunal observed Sai River is covered among the polluted stretches and held that directions and compensation regime from that order apply to the present case. |
| O.A. No. 200 of 2014 (River Ganga) — order dated 22.08.2019 | Zero tolerance for pollution of national rivers; interim measures such as immediate bio-remediation/phyto-remediation where STPs are not operating; specification of standards and norms and use of performance guarantees. | The Tribunal relied on this approach and reiterated that interim remediation (e.g., phytoremediation) and measures to avoid idle STP capacity should be used where STPs are not operational. |
| O.A. No. 593/2017, Paryavaran Suraksha Samiti v. Union of India — order dated 28.08.2019 | Enforcement of precautionary principle; that pollution of water is a criminal offence under the Water Act; mandate for 100% treatment of sewage; recovery of compensation under 'Polluter Pays' principle and enforcement timelines. | The Tribunal invoked these principles to emphasise enforcement, the need for 100% sewage treatment, interim measures, and that compensation regimes and enforcement must be applied. |
| O.A. No. 6 of 2012, Manoj Mishra v. Union of India (Yamuna) — order dated 11.09.2019 | Prioritisation to ensure no pollutant is discharged into rivers/drains; completion/upgradation of STPs, interceptors and sewer networks within strict timelines; interim bioremediation/phytoremediation measures pending completion. | The Tribunal cited this authority to reiterate priorities: prevent pollutant discharge, complete necessary infrastructure, and use interim remediation where required. |
| O.A. No. 125 of 2017, Court on its own Motion v. State of Karnataka — order dated 18.12.2019 | Exploration and development of wetlands and biodiversity parks as measures for reducing pollution load on recipient water bodies. | The Tribunal noted development of wetlands/biodiversity parks as an additional option for pollution reduction applicable to the present context. |
| CPCB Guidelines (July 2003): "CPCB Guidelines on Construction Operation and Application of Root Zone Treatment System for Treatment of Municipal and Industrial Waste Water" | Guidance on root zone treatment and related phytoremediation technologies for municipal/industrial wastewater treatment. | The Tribunal referenced these guidelines as an available, established interim remediation technology that could be employed in preference to allowing polluted drains to enter clean river stretches. |
Court's Reasoning and Analysis
The Tribunal proceeded from the factual findings in the UPSPCB/UP Jal Nigam report: Pratapgarh generates 8.95 MLD of sewage, which is presently discharged untreated into the Sai River via a city drain; an STP of 8.95 MLD capacity was constructed (2009) but remained non-operational due to incomplete sewer lines and connectivity despite the STP being approximately 95% complete and tested in 2010. The report identified causes for delay including a PIL, under-release of funds, repeated tender cancellations, and a Forest Department ban requiring central permission.
The Tribunal examined the legal framework: the Water (Prevention and Control of Pollution) Act, 1974 prohibits disposal of polluting matter in streams (Sections 24–25), empowers State Boards to issue prohibitory orders and recovery of compensation (Section 33A), and prescribes offences and punishments (Sections 41–49). The Tribunal noted that despite these statutory provisions, statutory regulators and public authorities have shown insufficient enforcement and implementation.
Given the failure to operationalize the STP despite public expenditure, the Tribunal emphasised readily available interim remediation steps that do not require large funds — specifically phytoremediation/root-zone treatment and bioremediation — to reduce pollution load before sewage reaches the river. The Tribunal reasoned that tapping the polluted drain before it meets the river or treating the effluent near the river mouth could prevent mixing of polluted and clean waters and avoid higher treatment costs later.
The Tribunal also relied on its prior orders and principles (including 'Polluter Pays' and precautionary principle) requiring 100% treatment of sewage, interim remedial measures pending completion of full sewerage/STP works, and allowing imposition of compensation for defaults. It concluded that failure to take at least minimum interim remediation steps should attract personal accountability (disciplinary action and 'Polluter Pays' compensation) against the Principal Secretary, Urban Development Department, Chief Executives of the local body and Jal Nigam, and other officers entrusted with the functions, including making entries in their ACRs.
In light of these findings and reasoning, the Tribunal directed action consistent with its prior orders and required a compliance report by a specified date.
Holding and Implications
Holding: The Tribunal directed that further action in the present case be taken in the light of the Tribunal's prior directions (including those in O.A. No. 673/2018 and other cited orders). A compliance report was ordered to be furnished by 28.02.2020 by e-mail to judicial-ngt@gov.in. A copy of the order was to be sent to the Chief Secretary, UP; Secretary, Urban Development Department; UP Jal Nigam; UPSPCB; and the Committee headed by Justice S.K. Singh. The matter was listed for further consideration on 16.03.2020.
Implications:
- The directions and compensation regime from the Tribunal's earlier orders addressing polluted river stretches (including requirements for 100% sewage treatment and interim remediation) apply to Pratapgarh/Sai River.
- Interim remediation options such as phytoremediation/root-zone treatment and bioremediation are endorsed as practicable steps to reduce pollution load pending completion of sewer networks and STP connectivity.
- Public authorities and officers responsible for implementation may face disciplinary action and civil recovery (compensation on 'Polluter Pays' principle) and entries in their ACRs for failure to take at least minimum remediation measures.
- The order directly requires submission of a compliance report and further adjudication at the next listed date; no new legal precedent beyond the application of existing Tribunal directions was created in this instant order.
Note: This summary is based exclusively on the information contained in the provided Tribunal opinion and does not add facts or inferences beyond the text.
1. Issue for consideration is prevention of discharge of untreated sewage into Sai River at Pratapgarh in Uttar Pradesh.
2. Vide order dated 05.08.2019, a factual and action taken report was sought from the Uttar Pradesh State Pollution Control Board (UPSPCB) and the UP Jal Nigam. Accordingly, a report was filed on 30.08.2019 by the SPCB as follows:
“1. District Pratapgarh has 9 towns out of them 7 are statutory towns and 2 Census towns. There are 533,546 households in the district accounting for 1.6 percent of the total households in the state. The average size of households in the district is 6.0 persons. Total population of the city Pratapgarh as per 2011 census is 76.133 and water consumption is 13.70 MLD. The total sewage generation of the city is 8.95 MLD.
2. In Pratapgarh city main drain named City drain originates from Prayagpur Aurehta joins Sai river at Bela Pratapgarh. Distance covered by city drain from Prayagpur Aurehta to its meeting point to Sai River is approx 0.44 Km. City drain carries domestic waste water of habitations settled along the course of river Sai. Total sewage discharge from city drain to river Sai is 8.95 MLD which is untreated in nature. The city drain with a flow of 8.95 MLD will be intercepted and routed to under construction STP of 8.95 MLD at Pratapgarh city near Belhamai Bridge.
3. Above mentioned STP of 8.95 MLD capacity is based on Fluidized Aerobic Bed Reactor (FAB) technology whose main units are Screen & grit chamber, FAB reactor I & 11, tube settler, chlorine contact tank, Sludge thickner. sludge drying bed etc. At the time of inspection STP was found non-operational due to under construction of sewer lines and its connectivity with STP. At present sewage is directly discharged into river Sai.
4. It has been informed that STP was constructed in year 2009 by Thermax Ltd. in Pratapgarh Jalotsaran Yojna Belha Pratapgarh city with total estimated cost of Rs. 1820.75 Crore in which 8.50 Crore for STP and rest for sewer line, main pumping station and intermediate pumping station. Summary of the Pratapgarh sewerage plan is attached herewith and marked as Annexure no.-1.
5. It has been informed by UP Jal Nigam, Pratapgarh that construction work of STP and main pumping station was started by July 2009 as the land for STP and MPS was made available by Nagar Palika Parishad, Pratapgarh. Later the work was delayed due to PIL in Lucknow bench of Allahabad high court lodged by Dr. R.K Singh owner of a hospital near STP campus.
6. It is informed by U.P. Jal Nigam Pratapgarh that the work of sewer laying etc. cannot be started timely because the funds released for construction was not equivalent to sanctioned amount, and the tender for construction was cancelled six times by competent authority due to different reasons. Later Forest Department imposed ban on laying of sewer and asked for permission of Govt. of India. Scheme where works are held up due to ban imposed by Forest Dept. Pratapgarh, is attached herewith and marked as Annexure no.-2.
7. It has been informed that total proposed sewer line for connection of drains to STP is 12.472 Kilometre in which approx. 9 Kilometres sewer line has been installed and rest 3.472 Km is under construction. Approximately 95% work of STP was completed in 2010 and its testing has been also done.
8. Regional office UPPCB Raebareli has been directed to EO Nagar Palika Parishad. Pratapgarh and Executive Engineer Jal Nigam Pratapgarh vide letter no. 1305/STP/2017-18 dated 18.01.2018 and 696/STP/P/18-19 dated 10.09.2018 for completion and operation of STP as soon as possible.
9. The river Sai is also covered in the identified “Polluted river stretches” as Priority —V. In compliance of order passed by Hon'ble NGT on 20-09-2018 in OA no. 673/2018 in the matter of NEWS ITEM PUBLISHED IN “THE HINDU’ AUTHORED BY SHRI JACOB KOSHY” titled More river stretches are now cr itic ally polluted: CPCB, in this regard Pollution Control Board has prepared an Action Plan for rejuvenation of river Sai which has been duly approved by ‘River Rejuvenation Committee, U.P.”
3. It is clear from above that the sewage is being directly discharged into the river. STP was constructed in the year 2009 at the estimated cost of Rs. 1820.75 crore, out of which cost of STP alone was Rs. 8.50 crore and rest of the cost was for sewer line and other incidental activities. Since the sewer line were not constructed, the STP never became operational even though 95% work of the STP was completed in the year 2010 itself and testing was also done. It is undisputed that Sai River is one of the polluted river stretches identified as such and remediation of which has been directed by this Tribunal in O.A. No. 673/2018.
4. Based on above report as well as general experience of this Tribunal in dealing with such matters, it is seen that huge amount of public money is being wasted without fruitful results without study of ground situation, ignoring directions of this Tribunal to identify and notify standards of technology, cost and service providers at national/state levels. While it is for the administration to take action against the persons responsible for wastage of the public money, mandate of the Water (Prevention and Control of Pollution) Act, 1974 (The Water Act), prohibiting disposal of polluting matter in a stream or well under Sections 24 - 25 of the Water Act cannot be ignored. Section 33A of the Water Act provides for orders by a State Board to prohibit such activity and pass any order for this purpose, which has been interpreted to include recovery of compensation on ‘Polluter Pays’ principle for restoration of damage to the environment. Sections 41 to 49 provide for punishment for such offences, which included imprisonment.
5. In spite of such stringent provisions, no serious concern is shown by the statutory regulators in enforcing the Statute nor by the concerned public authorities in carrying out the mandate of law. Least which should have been done, without requirement of substantial funds, is Phyto-remediation or other such interim remediation to reduce the pollution load created by discharge of sewage in a drain, before such drain is connected to the river system carrying clean water. It may be preferable that such drain carrying polluted water is not allowed to enter river carrying clean water. After treatment by Phytoremediation, etc. as mentioned above, the water can be used for secondary purposes as per norms on the subject instead of polluted water mixing with the clean water and thereafter the same being treated at high cost. The other alternative is to tap the drain before it joins the river and proper treatment is carried out at an appropriate place near the mouth of the river itself by way of an appropriate treatment system to save huge cost which may have to be incurred after sewage is mixed with clean water. In this regard, we may note that CPCB has laid down guidelines as far back as in July, 2003 being “CPCB Guidelines on Construction Operation and Application of Root Zone Treatment System for Treatment of Municipal and Industrial Waste Water”.
6. Any failure to follow atleast the above minimum course which is easily available, the Principal Secretary, Urban Development Department as well as Chief Executive Officers of the concerned Local Body and Jal Nigam or any other officers entrusted with this function must be held accountable personally by way of disciplinary action as well as requirement of payment of compensation on ‘Polluter Pays’ principle and making of entry in their ACRs to enforce the rule of law and to enforce citizens' right to clean environment.
7. This Tribunal has dealt with the matter while dealing with the pollution of rivers. Vide order dated 22.08.2019, in O.A. No. 200 of 2014 (River Ganga), it was observed:—
“16……. As already observed by this Tribunal including in the order dated 14.05.2019 that River Ganga being National River with distinct significance for the country, even a drop of pollution therein is a matter of concern. All the authorities have to be stringent and depict zero tolerance to the pollution of River Ganga. Wherever STPs are not operating, immediate bioremediation and/or phyto-remediation may be undertaken if feasible. To avoid procedural delay of tender processes, etc. specifications and norms for undertaking such activities may be specified in consultation with the CPCB as was earlier directed in our order dated 29.11.2018. Performance guarantees may be required to be furnished for ensuring timely performance. It needs to be ensured that setting up of STPs and sewerage network to be completed and carried out so as to avoid any idle capacities being created. Performance guarantees may be taken for preventing such defaults.
8. Vide order dated 28.08.2019 in O.A. No 593/2017, Paryavaran Suraksha Samiti v. Union of India, (dealing with Water pollution for compliance of order of Hon'ble Supreme Court in (2017) 5 SCC 326) it was observed:—
“17. As already noted, prevention of pollution of water is directly linked to access to potable water as well as food safety. Restoration of pristine glory of rivers is also of cultural and ecological significance. This necessitates effective steps to ensure that no pollution is discharged in water bodies. Doing so is a criminal offence under the Water Act and is harmful to the environment and public health. ‘Precautionary’ principle of environmental law is to be enforced. Thus, the mandate of law is that there must be 100% treatment of sewage as well as trade effluents. This Tribunal has already directed in the case of river Ganga that timelines laid down therein be adhered to for setting up of STPs and till then, interim measures be taken for treatment of sewage. There is no reason why this direction be not followed, so as to control pollution of all the river stretches in the country. The issue of ETPs/CETPs is being dealt with by an appropriate action against polluting industries. Setting up of STPs and MSW facilities is the responsibility of Local Bodies and in case of their default, of the States. Their failure on the subject has to be adequately monitored. Recovery of compensation on ‘Polluter Pays’ principle is a part of enforcement strategy but not a substitute for compliance. It is thus necessary to issue directions to all the States/UTs to enforce the compensation regime, latest with effect from 01.04.2020. We may not be taken to be the States/UTs themselves have to pay the requisite amount of compensation to be deposited with the CPCB for restoration of environment. The Chief Secretaries of all the States may furnish their respective compliance reports as per directions already issued in O.A. No. 606/2018.
9. In O.A. No. 6 of 2012, Manoj Mishra v. Union Of India (dealing with river Yamuna pollution) vide order dated 11.09.2019, the Tribunal observed:—
“13. Priorities need to be planned. The first step is to ensure that no pollutant is discharged into the river or drains connected thereto. Projects of setting up and upgradation of STPs including setting up of interceptors, laying of sewerage line network etc. have to be completed within strict timelines. Pending such action, immediate bioremediation and/or phytoremediation or any other alternative remediation measure may be undertaken as an interim measure. Pollution of river or water bodies is a criminal offence which needs to be checked by setting up ETPs/CETPs/STPs. The Hon'ble Supreme Court has directed1 that establishment and proper functioning of ETPs/CETPs/STPs in the country be ensured. This is to enforce the right of access to water. It has been noted by the Hon'ble Supreme Court that water pollution is the cause of various diseases and also affects food safety apart from affecting the environment as such. Following the said judgment, this Tribunal has directed2 that “All the local bodies have to ensure 100% treatment of the generated sewage and in default to pay compensation which is to be recovered by the States/UTs, with effect from 01.04.2020. In default of such collection, the States/UTs are liable to pay such compensation. The CPCB is to collect the same and utilize for restoration of the environment.”
10. Again, vide order dated 06.12.2019, in O.A. No. 673/2018, News item published in “The Hindu” authored by Shri Jacob Koshy Titled “More river stretches are now critically polluted: CPCB” (dealing with 351 polluted river stretches), the Tribunal observed:—
“47. We now sum up our directions as follows:
i) 100% treatment of sewage may be ensured as directed by this Tribunal vide order dated 28.08.2019 in O.A. No. 593/2017 by 31.03.2020 atleast to the extent of in-situ remediation and before the said date, commencement of setting up of STPs and the work of connecting all the drains and other sources of generation of sewage to the STPs must be ensured. If this is not done, the local bodies and the concerned departments of the States/UTs will be liable to pay compensation as already directed vide order dated 22.08.2019 in the case of river Ganga i.e. Rs. 5 lakhs per month per drain, for default in in-situ remediation and Rs. 5 lakhs per STP for default in commencement of setting up of the STP.”
11. We may also observe that apart from interim remediation as mentioned above, pending installation of STPs etc. another option is development of wetlands and bio-diversity parks for reducing the pollution loads on the recipient water bodies. Such directions have been issued by this Tribunal in dealing with the issue in other cases also. Reference may be made order dated 18.12.2019 in O.A. No. 125 of 2017, Court on its own Motion v. State of Karnataka:—
“28 (xii) Steps may be taken to explore development of wetlands and bio-diversity parks apart from other remedial action for reducing the pollution load on the recipient water bodies.”
12. Since the above matter is already covered by directions of this Tribunal dealing with 351 polluted river stretches vide order dated 06.12.2019, in O.A. No. 673/2018, the directions with regard to compensation etc. will apply to the present case.
13. Let further action in the present case be taken in the light of above directions and compliance report furnished by 28.02.2020 by e-mail at judicial-ngt@gov.in.
14. A copy of this order be sent to the Chief Secretary, UP, Secretary, Urban Development Department, UP Jal Nigam, UPSPCB and the Committee headed by Justice S.K. Singh, former Judge of Allahabad High Court by e-mail.
15. List for further consideration on 16.03.2020.