Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Power Grid Corporation Of India Ltd. v. Bihar State Power (Holding) Company Ltd. And Others (S).

Central Electricity Regulatory Commission
Jul 12, 2020
Smart Summary (Beta)

Factual and Procedural Background

The petition was filed by Power Grid Corporation of India Limited ("the Petitioner") seeking revision/truing-up/determination of transmission tariff for a 400 kV Biharsharif-Sasaram-Sarnath Transmission Line (with associated bays) under the Eastern-Northern inter-regional HVDC Transmission System. The Petitioner sought revision of transmission tariff for the 2001-04, 2004-09 and 2009-14 periods, truing-up for 2014-19 and determination of tariff for 2019-24 pursuant to Regulation 8 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 and 2019 (the 2014 and 2019 Tariff Regulations).

Administrative approval and expenditure sanction were initially accorded by the Ministry of Power on 4.9.1998, with an initial cost estimate and a scheduled commercial operation date (COD) by December 2001. The asset was put into commercial operation from 1.7.2001. Earlier tariffs for this asset had been determined/trued-up by the Commission in orders dated: 3.3.2005 (Petition No.55/2002) for 2001-04; 12.1.2011 (Petition No.216/2010) for 2004-09; 30.5.2011 and later truing-up by 4.12.2015 (Petition No.183/TT/2014) for 2009-14 and 2014-19 respectively.

The Petitioner invoked APTEL judgments (22.1.2007 in Appeal No.81/2005; 13.6.2007 in Appeal No.139/2006; and earlier 14.11.2006 in Appeal Nos.94 & 96 of 2005) to seek revision of computation of Interest on Loan (IOL), Interest on Working Capital (IWC), maintenance spares and depreciation for the earlier tariff periods. The Commission had earlier adjourned a related petition (No.121/2007) pending Civil Appeals before the Hon'ble Supreme Court. The Hon'ble Supreme Court dismissed those Civil Appeals on 10.4.2018. Thereafter, the Commission directed revival as appropriate and the Petitioner filed the instant petition (No.300/TT/2019).

The petition was heard on 13.2.2020 (along with related petitions). No public objections were received in response to the newspaper notice and none of the respondents filed reply. One intervenor (BSP(H)CL, adopting BRPL's reply in a related petition) objected to reopening earlier tariff periods on the ground that the Commission had become functus officio; the Petitioner replied that a combined order dated 6.11.2019 had rejected that contention.

Legal Issues Presented

  1. Whether the transmission tariff for the periods 2001-04, 2004-09 and 2009-14 can be revised in light of the APTEL judgments dated 14.11.2006, 22.1.2007 and 13.6.2007 and consequent dismissal of Civil Appeals by the Hon'ble Supreme Court on 10.4.2018.
  2. How the principles laid down by APTEL (on computation of interest on loan, treatment of refinancing, additional capitalization and maintenance spares, and depreciation) should be applied to the Petitioner’s transmission asset for the earlier tariff periods.
  3. Truing-up of annual fixed charges for the 2014-19 tariff period under Regulation 8(1) of the 2014 Tariff Regulations and determination of tariff for the 2019-24 tariff period under Regulation 8 of the 2019 Tariff Regulations, applying the respective regulations.
  4. Whether carrying cost should be allowed for differences between earlier allowed tariff and tariff as revised in this order and, if not, the manner of recovery of differences between prior orders and the instant order.

Arguments of the Parties

BSP(H)CL / BRPL (Intervenor) — Arguments

  • Objected to reopening the tariff of 2001-04, 2004-09 and 2009-14 periods on the ground that the Commission had become functus officio (i.e., no power to reopen earlier final orders).
  • Adopted the reply filed by BRPL in the related Petition No.288/TT/2019.

Petitioner — Arguments

  • Relied on the APTEL judgments dated 14.11.2006, 22.1.2007 and 13.6.2007 to seek revision of IOL, IWC, maintenance spares and depreciation for earlier tariff periods.
  • Submitted that the Commission, by a combined order dated 6.11.2019, had already rejected the contention that the Commission was functus officio and therefore revision was permissible.
  • Made specific prayers seeking (inter alia) approval of revised tariffs for 2001-04, 2004-09 and 2009-14; truing-up for 2014-19; determination for 2019-24; direct recovery of shortfall/refund of AFC on account of changes in tax rates; reimbursement of petition filing fee and publication expenses; separate recovery of licence fee and RLDC charges; recovery of impact of floating interest rates for 2019-24; recovery of FERV on foreign loans; filing separate petition for security expenses and IOWC thereon; claim of capital spares at end of tariff block; and separate billing/recovery of GST if levied in future.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
APTEL judgment dated 14.11.2006 (Appeal Nos. 94 & 96 of 2005) Set aside the Commission's methodology of computing loan repayment as "higher of actual or normative" and held that loan repayment must be computed on normative debt when financing plan adopts a normative 50:50 debt:equity. (Normative repayment methodology.) The Commission applied the APTEL direction to adopt normative debt repayment methodology and revised the computation of interest on loan for the period 01.04.1998 to 31.03.2001 and accordingly for the tariff periods 2001-04 and 2004-09 for the Petitioner’s asset.
APTEL judgment dated 22.1.2007 (Appeal No. 81 of 2005) Observed that Interest on Loan (IOL) for the period 1.4.1998 to 31.3.2001 shall be computed only on normative loan repayment as per the APTEL's 14.11.2006 decision (i.e., normative repayment to be used for computing IOL). The Commission revised the interest on loan allowed for the 2001-04 and 2004-09 periods on the basis of the normative debt repayment methodology as indicated by APTEL.
APTEL judgment dated 13.6.2007 (Appeal No.139 of 2006) Held that additional capitalization after COD should be considered for computation of maintenance spares (historical cost not to be frozen at COD); and clarified that depreciation is an expense and cannot be deployed as deemed repayment of loan. The Commission revised maintenance spares considered for IWC for 2001-04 and 2004-09 to take additional capitalization after COD into account, recomputed outstanding loan positions (since depreciation not to be treated as deemed loan repayment) and revised related tariff components accordingly.
Hon'ble Supreme Court judgment dated 10.4.2018 Dismissed Civil Appeals filed by the Commission and others against the APTEL judgments referred above. Following the dismissal, the Commission proceeded to list and decide the matters pending on account of APTEL directions; Petition No.121/2007 was revived and the instant petition (No.300/TT/2019) was heard and disposed of applying the APTEL principles.

Court's Reasoning and Analysis

The Commission's reasoning proceeded in a sequence tied to the APTEL rulings and the applicable tariff regulations for each tariff block:

  1. Applicability of APTEL judgments and Supreme Court decision:

    The Commission observed that APTEL had laid down specific principles on (a) computation of IOL, (b) consequences of refinancing, (c) depreciation treatment, and (d) consideration of maintenance spares with respect to additional capitalization. The Hon'ble Supreme Court dismissed appeals against those APTEL judgments on 10.4.2018. Consequently, the Commission applied those APTEL directions to the Petitioner’s asset.

  2. Interest on Loan (IOL) and normative loan repayment:

    Following APTEL (particularly the 14.11.2006 and 22.1.2007 rulings), the Commission adopted the normative debt repayment methodology (rather than the earlier practice of taking the higher of actual or normative repayment). This revision altered opening/closing loan balances and thereby affected IOL across the 2001-04 and 2004-09 periods and required consequential revision for 2009-14.

  3. Additional capitalization and maintenance spares:

    Applying APTEL (13.6.2007), the Commission held that additional capitalization after COD should be recognized for purposes of calculating maintenance spares (historical cost should reflect admitted additional capitalisation where appropriate). As a result, maintenance spares for IWC computation for 2001-04 and 2004-09 were revised to take such additional capitalization into account.

  4. Depreciation and outstanding loan recomputation:

    APTEL clarified that depreciation is an expense and not to be treated as deemed repayment of loan. Accordingly, the Commission recomputed outstanding loan positions without treating depreciation as loan repayment, and revised the outstanding loan for 2001-04 and 2004-09 periods for the asset.

  5. Use of applicable regulations for subsequent tariff blocks:

    For truing up 2014-19, the Commission applied the 2014 Tariff Regulations (Regulations 9, 19, 24–29 etc.)—using admitted capital cost as on 31.3.2014, the debt-equity ratio allowed for the period ending 31.3.2014 (79.94:20.06), MAT rates for grossing up ROE, SBI base rate plus 350 bps for IWC, and O&M norms of the 2014 Regulations.

    For determination of tariff for 2019-24, the Commission applied the 2019 Tariff Regulations (including Regulation 18 on debt-equity, Regulation 19 on capital cost, Regulation 30–34 on ROE, depreciation and IWC, and Regulation 35 on O&M norms). The Commission used the admitted capital cost as on 31.3.2019 (16557.13 lakh), the same debt-equity ratio as on 1.4.2019, MAT (for grossing up ROE) as applicable, and SBI 1-year MCLR plus 350 bps (as on 1.4.2019) to arrive at the IWC rate for 2019-24.

  6. Treatment of carrying costs and recovery period:

    Considering the facts and in view of consumer interest, the Commission held that beneficiaries should not be burdened with carrying cost for the difference between earlier allowed tariff and that determined in this order for the 2001-04, 2004-09 and 2009-14 periods. Therefore, no carrying cost would be claimed or paid by the Petitioner or beneficiaries, and the difference shall be recovered over a period of six months from the date of issue of the order.

  7. Ancillary and miscellaneous claims:

    The Commission addressed the Petitioner’s prayers as follows: reimbursement of filing fee and publication expenses is allowed to be recovered directly from beneficiaries (Regulation 70(1) of 2019 Regulations); licence fee and RLDC fees and charges can be billed separately (Regulations 70(3) & 70(4)); security expenses were not claimed in the instant petition and the Petitioner was directed to file separate petition(s) for security expenses and IOWC as appropriate (such applications to be considered per 2019 Regulations); GST on transmission was not levied at present and the Commission regarded the Petitioner’s prayer for prospective GST recovery as premature.

Holding and Implications

Holding (core ruling): THE PETITION (No. 300/TT/2019) IS DISPOSED OF by the Commission with revision/truing-up/determination of tariffs for the transmission asset in accordance with the APTEL judgments and the applicable tariff regulations for each tariff block.

Principal orders and direct effects on the parties (as stated in the opinion)

  • The Commission revised transmission charges for the 2001-04, 2004-09 and 2009-14 tariff periods applying APTEL directions (normative repayment methodology, maintenance spares for additional capitalization, and depreciation treatment) and adjusted loan balances and related components accordingly. (Numerical revised figures for these periods are set out in the order.)
  • The Commission trued up annual fixed charges for the 2014-19 tariff period and allowed the trued-up annual fixed charges as presented in the order (annual totals allowed for 2014-15 through 2018-19 are recorded in the order).
  • The Commission determined the annual fixed charges for the 2019-24 tariff period in accordance with the 2019 Tariff Regulations and allowed the annual fixed charges for 2019-20 through 2023-24 as set out in the order.
  • No carrying cost is allowed on the difference between earlier allowed tariff and that allowed in this order for the 2001-04, 2004-09 and 2009-14 periods; the difference shall be recovered over six months from the date of issue of the order.
  • The Petitioner is entitled to recover filing fee and publication expenses directly from beneficiaries on a pro-rata basis (Regulation 70(1) 2019 Tariff Regulations), and also is entitled to recover licence fee and RLDC fees and charges separately in accordance with the 2019 Tariff Regulations.
  • Security expenses were not claimed in the instant petition; the Petitioner may file separate petition(s) claiming security expenses and related IOWC, which will be considered in accordance with the 2019 Tariff Regulations.
  • The Petitioner’s request to bill and recover GST on transmission charges prospectively was held premature as GST was not levied on transmission service at present.

Broader implications:

The order implements and applies the APTEL judgments (and the subsequent dismissal of appeals by the Hon'ble Supreme Court) to the Petitioner’s asset and applies the respective tariff regulations for each tariff block. The opinion does not announce any novel legal principle beyond applying those existing precedents and the applicable regulations; it addresses the direct tariff consequences and related recovery mechanisms for the parties involved.

Disposition

The order concludes with an explicit statement that Petition No. 300/TT/2019 is disposed of. The order is signed and authenticated by the Chairperson and a Member of the Commission as recorded in the text.

Show all summary ...

The present petition has been filed by Power Grid Corporation of India Limited (hereinafter referred to as the Petitioner) for revision of transmission tariff of 2001-04, 2004-09 and 2009-14 tariff periods and truing up of the tariff of the 2014-19 tariff period under Regulation 8 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (hereinafter referred to as the 2014 Tariff Regulations) and for determination of tariff of the 2019-24 tariff period under Regulation 8 of Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 (hereinafter referred to as the 2019 Tariff Regulations) of

400 kV Biharsharif-Sasaram-Sarnath Transmission Line along with associated bays under Eastern-Northern Inter-regional HVDC Transmission System in Eastern Region (hereinafter referred to as the transmission asset). Order in Petition No.300/TT/2019 Page 3 of 36

2. The Petitioner has made the following prayers:-

1). Approve the revised Transmission Tariff for 2001-04 block, 2004-09 block and transmission tariff for 2009-14 block for the assets covered under this petition, as per para 8 above.

2) Approve the trued up Transmission Tariff for 2014-19 block and transmission tariff for 2019-24 block for the assets covered under this petition, as per para 9 and 10 above.

3) Allow the petitioner to recover the shortfall or refund the excess Annual Fixed Charges, on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before the Commission as provided in Tariff Regulation 2014 and Tariff regulations 2019 as per para 9 and 10 above for respective block.

4) Approve the reimbursement of expenditure by the beneficiaries towards petition filing fee, and expenditure on publishing of notices in newspapers in terms of Regulation 70 (1) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019, and other expenditure ( if any) in relation to the filing of petition.

5) Allow the petitioner to bill and recover Licensee fee and RLDC fees and charges, separately from the respondents in terms of Regulation 70 (3) and (4) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019.

6) Allow the petitioner to bill and adjust impact on Interest on Loan due to change in Interest rate on account of floating rate of interest applicable during 2019-24 period, if any, from the respondents.

7) Allow the petitioner to recover FERV on the foreign loans deployed as provided under clause 68 of the Tariff Regulations,2019

8) Allow the petitioner to file a separate petition before Honble Commission for claiming the overall security expenses and consequential IOWC on that security expenses as mentioned at para 10.5 above.

9) Allow the petitioner to claim the capital spares at the end of tariff block as per actual. 10) Allow the Petitioner to bill and recover GST on Transmission Charges separately from the respondents, if GST on transmission is levied at any rate in future. Further, any taxes including GST and duties including cess etc. imposed by any statutory/Govt./municipal authorities shall be allowed to be recovered from the beneficiaries. and pass such other relief as Honble Commission deems fit and appropriate under the circumstances of the case and in the interest of justice Order in Petition No.300/TT/2019 Page 4 of 36 Background

3. The brief facts of the case are as follows: a. The administrative approval and expenditure sanction for the transmission project was initially accorded by the Ministry of Power, Government of India vide its letter dated 4.9.1998 at an estimated cost of 67156.00 lakh, including IDC of 9219.00 lakh, based on 3rd quarter 1997 price level. As per the investment approval, the project was scheduled to be put into commercial operation within 39 months from date of approval, i.e. by December 2001. Subsequently, there was a change in the scope of work based on system studies. Accordingly, the revised cost estimate for 59310.00 lakh including IDC of 4607.00 lakh and financing charges of 464.00 lakh was approved by CEA. b. The initial transmission tariff for the period from 1.7.2001 to 31.3.2004 was determined by the Commission vide order dated 3.3.2005 in Petition No. 55/2002; tariff for the period from 1.4.2004 to 31.3.2009 was determined vide order dated 12.1.2011 in Petition No. 216/2010; and tariff for the period from 1.4.2009 to 31.3.2014 was trued up and tariff for the period from 1.4.2014 to 31.3.2019 was determined vide order dated 4.12.2015 in Petition No. 183/TT/2014. c. The Petitioner has sought revision of transmission tariff approved by the Commission for the 2001-04 and 2004-09 tariff periods on account of change in Interest on Loan (IOL) and Interest on Working Capital (IWC) to the extent of revision in IOL and in Maintenance Spares in terms of the judgement of Appellate Tribunal for Electricity (APTEL) dated 22.1.2007 and 13.6.2007 in Appeal Nos. 81/2005 and 139/2006 respectively. The Petitioner has further sought consequential revision of tariff allowed for the 2009-14 tariff period, truing up of tariff of 2014-19 tariff period and determination of tariff for 2019-24 tariff period for 400 kV Biharsharif-Sasaram-Sarnath Transmission Line along with associated bays under Eastern-Northern Inter-regional HVDC Transmission System in Eastern Region. Order in Petition No.300/TT/2019 Page 5 of 36 d. APTEL, vide judgement dated 22.1.2007 in Appeal No. 81/2005 and other related Appeals, and vide judgement dated 13.6.2007 in Appeal No. 139/2006 pertaining to generating stations of NTPC decided on mainly the following issues:-

(i) Computation of interest on loan

(ii) Consequences of refinancing of loan

(iii) Depreciation as deemed repayment

(iv) Admissibility of depreciation upto 90% of the value of the assets

(v) Consideration of maintenance of spares for working capital

(vi) Depreciation of assets. e. The Commission and certain beneficiaries filed appeals against the APTELs judgments before the Honble Supreme Court in 2007. The Appeals were admitted and initially stay was granted by the Honble Supreme Court. Subsequently, on an assurance by NTPC that the issues under appeal would not be pressed for implementation during the pendency of the appeals, the stay was vacated by the Honble Supreme Court. f. PGCIL, based on the APTELs judgments dated 22.1.2007 and 13.6.2007, sought re-determination of tariff of its transmission assets for the tariff periods 2001-04 and 2004-09 in Petition No. 121/2007. The Commission after taking into consideration the pending appeals before the Honble Supreme Court adjourned the matter sine die and directed to revive the same after the disposal of the Civil Appeals by the Honble Supreme Court. g. The Honble Supreme Court, vide its judgement dated 10.4.2018, dismissed the said Civil Appeals filed by the Commission and others against the APTELs said judgments. h. Consequent to the Honble Supreme Courts judgment dated 10.4.2018 in NTPC matters, the Petition No. 121/2007 was listed for hearing on 8.1.2019. The Commission, vide order dated 18.1.2019 in Petition No. 121/2007, directed the Petitioner to submit its claim separately for the assets at the time of filing Order in Petition No.300/TT/2019 Page 6 of 36 truing up petitions for the period 2014-19 in respect of concerned transmission assets. Accordingly, the Petitioner has filed the instant petition.

i. The instant petition was heard on 13.2.2020 and in view of APTELs judgments dated 22.1.2007 and 13.6.2007 and the judgement of Honble Supreme Court, tariff is being revised. Period-wise tariff is being re-worked based on the Tariff Regulations applicable for the respective tariff periods and suitable assumptions have been made at certain places and applied, which are indicated. j. The instant transmission asset was put under commercial operation from 1.7.2001. The tariff from 1.7.2001 was worked out based on the admitted capital cost of 17950.00. Accordingly, considering the admitted capital cost of 17950.00 lakh, tariff is being revised for the 2001-04, 2004-09, 2009-14 tariff periods in terms of APTELs judgement dated 22.1.2007 and 13.6.2007.

4. Further, as provided under Regulation 8(1) of the 2014 Tariff Regulations, the tariff allowed for the period 1.4.2014 to 31.3.2019 is trued-up and the tariff for the 2019-24 period is determined under Regulation 8 of the 2019 Tariff Regulations in the subsequent paragraphs.

5. The respondents are distribution licensees and power departments, who are procuring transmission service from the Petitioner, mainly beneficiaries of Eastern Region.

6. The Petitioner has served the petition on the respondents and notice of this application has been published in the newspaper in accordance with Section 64 of the Electricity Act 2003. No comments/objections have been received from the public in response to the notice in newspaper. Further, none of the respondents have filed any reply in the matter. Order in Petition No.300/TT/2019 Page 7 of 36

7. The matter was heard on 13.2.2020 alongwith Petition Nos. 288/TT/2019, 301/TT/2019 and 305/TT/2019. The learned counsel for BSP(H)CL, who was also appearing for BRPL in Petition No.288/TT/2019 submitted that BRPL has filed reply in the said petition and that the same is adopted by BSP(H)CL in this petition. He objected to the reopening of the tariff of 2001-04, 2004-09 and 2009-14 periods based on the APTELs judgements stating that the Commission has become functus officio. The learned counsel for the Petitioner submitted that the Commission, by a combined order dated 6.11.2019, has already rejected the contentions of BRPL and BSP(H)CL regarding revision of the tariff for the periods 2001-04, 2004-09 and 2009-14 on the ground that the Commission has become functus officio.

8. Having heard the representatives of the Petitioner and perused the material on record, we proceed to dispose of the petition.

9. The Petitioner has sought revision of the computation of the interest on loan, maintenance spares for working capital and depreciation allowed for the 2001-04 and 2004-09 period on the basis of the judgements of the APTEL dated 22.1.2007 in Appeal No.81 of 2005 and 13.6.2007 in Appeal No.139/2006. The APTEL while dealing with the issue of computation of interest on loan in judgement dated 22.1.2007 observed that IOL for the period from 1.4.1998 to 31.3.2001 shall be computed only on normative loan repayment as per its judgement dated 14.11.2006 in Appeal Nos.94 and 96 of 2005. APTEL in its judgement dated 14.11.2006 set aside the Commissions methodology of computation of loan on the actual repayment basis or normative repayment whichever is higher. The relevant portions of the judgement of APTEL dated 14.11.2006 is as follows:-

12 We have heard the arguments of the Senior Counsel(s) of appellant and respondents. We notice that the appellant has not challenged the formula for Order in Petition No.300/TT/2019 Page 8 of 36 computing the annual repayment amount as provided in Appeal No. 96 of 2005 & IA No.117 of 2006 in Appeal No. 94 of 2005 para-22 of the impugned order and has only challenged the provisions at para 23 specifying that the amount of annual repayment for calculation of interest on loan is chosen higher of the normative debt and actual debt.

13. As mentioned earlier the servicing of the capital (equity or debt) is financed by the recovery of interest on debt capital and through earning of return on equity capital. The actual loan repayment has been normalized to 50% of the total capital by the formula in para 22 of the impugned order given in para 11 above. Once it has been decided and agreed that the financing plan would be based on normative debtequity ratio of 50:50 and not the actual debt-equity ratio, the same normative basis should be adopted for recovery of cost of servicing the capital.

14. In the instant case since the normative debt-equity ratio of 50:50 has been adopted in the financing plan, the loan repayment should be computed based on normative debt. This is to ensure that whatever normative debt has been considered, tariff should ensure the recovery of the same normative debt and interest thereon.

18. In its Tariff Regulation of 2004 the Central Commission perhaps recognizing the aforesaid anomaly has dispensed with the practice of adopting higher of actual or normative repayment and has corrected the method of determination of quantum of debt repayment only on the basis of the normative debt with effect from 01.04.2004

19. In view of the above, the Central Commission is required to adopt normative debt repayment methodology for working out the interest on loan liability for the period 01.04.1998 to 31.03.2001. In view of the above, the interest allowed for the 2001-04 and 2004-09 periods is revised on the basis of the normative debt repayment methodology.

10. The APTEL in its judgement dated 13.6.2007 in Appeal No.139 of 2006 and others held that additional capitalisation after the date of commercial operation should also be considered for computation of maintenance spares as under:- Analysis and Decision We are not inclined to agree with the contention of the respondents that escalation of 6% will take care of the additional capitalization. Escalation is meant to factor inflation and is allowed as per CERC Regulations whether or not additional capitalization takes place. Question before us is that: can the historical cost be frozen with the Commissioning of the station. It is quite normal and prudent to ensure earliest operation of the plant without necessarily 100% completion of plants and works, of course not at the cost of safety of the plant. Adding some of the plants and works after the commercial operation will reduce interest during construction. If technically it is possible to delay some of the plants or works, it is only prudent to do so. For example it is common to build redundancies in the plant at a little later stage. CERCs own regulations rightly recognized additional capitalization. It is pertinent to set out excerpts pertaining to Order in Petition No.300/TT/2019 Page 9 of 36 additional capitalization from CERC (Terms & Conditions of Tariff) Regulation, 2004 Clause 18 as below:- Additional capitalization (1) The following capital expenditure within the original scope of work actually incurred after the date of commercial operation and up to the cut off date may be admitted by the Commission, subject to prudence check:

(i) Deferred liabilities

(ii) Works deferred for execution

(iii) Procurement of initial capital spares in the original scope of work, subject to ceiling specified in regulation 17.

(iv) Liabilities to meet award of arbitration or for compliance of the order or decree of a court; and

(v) On account of change in law. Provided that original scope of work along with estimates of expenditure shall be submitted along with the application for provisional tariff. Provided further that a list of the deferred liabilities and works deferred for execution shall be submitted along with the application for final tariff after the date of commercial operation of the generating station. It is clear from the abovementioned Clause 18 of the CERC Regulations that additional capitalization after the date of commercial operation is recognized as part of the capital expenditure Historical cost does not literally mean that the cost on the date of the commercial operation. The term historical cost is used so as to distinguish it from book value or the replacement cost. The cost of maintenance spares limited to 1% of the historical cost corresponds to the plant and equipment and installations which are required to be maintained. If the cost of additional equipment is not included in the historical cost, how spares for the additional equipment be procured for maintenance of the additional equipment. In this view of the matter, the CERC needs to examine afresh in the light of the aforesaid observations.

11. In view of the above, the maintenance spares to be considered for computation of working capital for the 2001-04 and 2004-09 periods are also required to be revised taking into consideration the additional capitalisation after the date of commercial operation.

12. As regards depreciation, APTEL in its judgement dated 13.6.2007 in Appeal No.139 of 2006 observed that depreciation is an expense and it cannot be deployed for deemed repayment of loan and accordingly directed the Commisison to compute the outstanding loan afresh. The relevant portion of the judgement is as under:- Order in Petition No.300/TT/2019 Page 10 of 36 Analysis and Decision In the orders of this Tribunal dated November 14, 2006 and January 24, 2007 it has been laid down that the computation of outstanding loan will be on normative basis only (instead of normative or actual whichever is higher). In view of this there is no question of any adjustment of the depreciation amount as deemed repayment of loan. It is to be understood that the depreciation is an expense and not an item allowed for repayment of loan. If a corporation does not borrow, it would not mean that the corporation will not be allowed any depreciation. Depreciation is an expense it represents a decline in the value of asset because of use, wear or obsolescence. The Accounting Principles Board of USA defines depreciation as under:- The cost of a productive facility is one of the costs of the service it renders during its useful economic life. Generally accepted accounting principles require that this cost be spread over the expected useful life of the facility in such a way as to allocate it as equitably as possible to the periods during which services are obtained from the use of the facility. This procedure is known as depreciation accounting, a system of accounting which aims to distribute the cost or other basic value of tangible capital assets, less salvage (if any), over the estimated useful life of the unit (which may be a group of assets) in a systematic and rational manner. It is a process of allocation, not of valuation It is well established that the depreciation is an expense and therefore, itcannot be deployed for deemed repayment of loan. In this view of the matter the CERC shall need to make a fresh computation of outstanding loan in the light of the aforesaid observations.

13. Accordingly, in view of the above directions, the outstanding loan allowed for the instant transmission asset for the 2001-04 and 2004-09 period is revised in the instant order.

14. The revision of tariff allowed for 2001-04 and 2004-09 tariff periods necessitates the revision of tariff allowed for the 2009-14 period, which is also allowed in the instant order. The implementation of the directions of the APTEL in case of the Petitioner was kept pending in view of the Civil Appeals filed before the Honble Supreme Court. Taking into consideration the facts of the case and keeping in view the interest of the consumers, we are of the view that the beneficiaries should not be burdened with the carrying cost for the difference in the tariff allowed vide earlier orders and that allowed in the instant order for the period 2001-04, 2004-09 and 2009-

14 tariff periods. Therefore, the Petitioner will neither claim nor pay any carrying cost Order in Petition No.300/TT/2019 Page 11 of 36 from/to the beneficiaries for the difference in the tariff allowed vide earlier orders and that allowed in the instant order. Further, the said difference in tariff shall be recovered over a period of six months from the date of issue of this order. REVISION OF TRANSMISSION CHARGES ALLOWED FOR THE 2001-04, 2004-09 and 2009-14 TARIFF PERIOD 2001-04 Period

15. The Commission in order dated 3.3.2005 in Petition No.55/2002 had approved the following transmission charges for the instant transmission asset for the 2001-04 period: ( in lakh) Particulars 2001-02 2002-03 2003-04 Depreciation 359.90 479.86 479.86 RoE 398.27 530.06 530.06 O&M Expenses 342.36 483.84 512.85 AAD 0.00 0.00 0.00 IOL 525.12 897.98 840.63 IWC 49.62 71.69 73.30 Total 1675.27 2463.43 2436.70

16. The petitioner has claimed the following revised transmission charges for the instant transmission asset for the 2001-04 period in this petition: ( in lakh) Particulars 2001-02 2002-03 2003-04 Depreciation 359.90 479.86 479.86 RoE 398.27 530.06 530.06 O&M 342.36 483.84 512.85 AAD 0.00 0.00 0.00 IOL 525.12 897.98 840.92 IWC 49.62 71.69 72.89 Total 1675.27 2463.40 2436.58

17. We have considered the Petitioners claim. The tariff is allowed for the instant transmission asset on the basis of the following:- Order in Petition No.300/TT/2019 Page 12 of 36

a) Admitted capital cost as on 1.7.2001: 17950.00 lakh.

b) The loan repayment in tariff has now been modified as per the judgment of APTEL that has directed that normative repayment is to be considered and not higher of normative or actual repayment as was considered by the Commssion earlier. Therefore, now there is variation in the closing balance of loan vis--vis that in the order dated 3.3.2005. This closing balance of loan shall have impact on opening and closing loan balances of future tariff periods too.

c) Weighted Average Rate of Interest on actual loan derived/adopted from order dated 3.3.2005 in Petition No. 55/2002.

d) Weighted average rate of depreciation, Rate of IWC and O & M Expenses data as per order dated 3.3.2005 in Petition No. 55/2002.

e) There was de-capitalisation of 568.95 lakh during financial year 2002-03. The maintenance spares component for calculating IWC is adjusted w.r.t. this de-capitalisation.

f) As per the then prevailing methodology, the impact of additional capitalisation/de-capitalisation during 2001-04 has been considered during the next tariff period. However, the impact of additional capitalisation/de- capitalisation on maintenance spares has been considered in the same year in which additionali capitalisation/de-capitalisation has occurred.

18. In view of the above, the revised transmission charges allowed for the instant transmission asset for the 2001-04 tariff period is as follows: ( in lakh) Particulars 2001-02 2002-03 2003-04 Depreciation 359.45 479.27 479.27 Interest on Loan 525.12 897.98 874.57 Return on Equity 398.27 531.02 531.02 Advance against Depreciation 0.00 0.00 0.00 Interest on Working Capital 54.44 71.35 72.58 O&MExpenses 342.36 483.84 512.85 Total 1679.64 2463.46 2470.29 Order in Petition No.300/TT/2019 Page 13 of 36 2004-09 Period

19. The Commission vide order dated 12.1.2011 in Petition No. 216/2010 had approved the following transmission charges for the instant transmission asset for the 2004-09 period. ( in lakh) Particulars 2004-05 2005-06 2006-07 2007-08 2008-09 Depreciation 436.11 436.42 436.42 436.42 436.68 Interest on Loan 659.51 561.32 501.33 449.94 396.59 Return on Equity 464.14 464.48 464.48 464.48 464.68 Advance against Depreciation 0.00 0.00 0.00 94.08 635.26 Interest on Working Capital 55.14 55.00 55.61 58.09 68.42 Expenses 235.51 244.91 255.01 264.73 275.77 Total 1850.41 1762.13 1712.84 1767.74 2277.40

20. The petitioner has claimed the following revised transmission charges for the instant transmission asset for the 2004-09 period in this petition: ( in lakh) Particulars 2004-05 2005-06 2006-07 2007-08 2008-09 Depreciation 436.11 436.42 436.42 436.42 436.68 Interest on Loan 658.75 560.68 500.76 449.43 396.14 Return on Equity 464.14 464.48 464.48 464.48 464.68 Advance against Depreciation 0.00 0.00 0.00 62.18 634.03 Interest on Working Capital 54.88 54.74 55.34 57.71 68.10 Expenses 235.51 244.91 255.01 264.73 275.77 Total 1849.39 1761.23 1712.01 1734.48 2275.40

21. We have considered the Petitioners claim. The tariff is allowed for the instant transmission asset on the basis of the following:- Order in Petition No.300/TT/2019 Page 14 of 36

a) Admitted Capital cost as on 1.4.2004: 16518.54 lakh after adjusting FERV difference of 862.51 lakh.

b) Weighted Average Rate of Interest on actual loan derived/adopted from Order(s) dated 25.1.2006 and 28.4.2008 in Petition No. 51/2005.

c) Weighted average rate of depreciation, Rate of IWC and O & M Expenses data as per order dated 25.1.2006 in Petition No. 51/2005.

d) The maintenance spares component for calculating IWC is adjusted w.r.t. additional capital expenditure of 24.20 lakh and of 14.39 lakh during 2004-05 and 2008-09 respectively.

22. In view of the above, the revised transmission charges allowed for the instant transmission asset for the 2004-09 tariff period is as follows: ( in lakh) Particulars 2004-05 2005-06 2006-07 2007-08 2008-09 Depreciation 436.11 436.42 436.42 436.42 436.68 Interest on Loan 658.76 560.68 500.76 449.43 396.14 Return on Equity 464.14 464.48 464.48 464.48 464.68 Advance against Depreciation 0.00 0.00 0.00 63.85 634.04 Interest on Working Capital 54.56 53.50 54.98 56.89 67.71 O&MfExpenses 235.51 244.91 255.01 264.73 275.77 Total 1849.07 1760.89 1711.64 1735.80 2275.01 2009-14 Period

23. The Commission vide order dated 30.5.2011 in Petition No 10/2011 had approved the tariff for the instant transmission asset for the 2009-14 period as follows: ( in lakh) Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Depreciation 874.75 874.75 874.75 874.75 874.75 Interest on Loan 413.43 361.27 309.59 258.36 210.77 Return on Equity 580.47 580.47 580.47 580.47 580.47 Interest on Working Capital 52.69 52.39 52.14 51.95 51.89 O&M Expenses 274.72 290.47 307.11 324.65 343.11 Total 2196.05 2159.35 2124.06 2090.18 2060.98 Order in Petition No.300/TT/2019 Page 15 of 36

24. The Commission vide order dated 4.12.2015 in Petition No 183/TT/2014 had trued up the tariff for the instant transmission asset for the 2009-14 period as follows: ( in lakh)

25. The petitioner has claimed the following revised transmission charges for the instant transmission assets for the 2009-14 period in this petition: ( in lakh) Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Depreciation 874.75 874.75 874.75 874.75 874.75 Interest on Loan 345.55 262.57 216.51 181.98 129.59 Return on Equity 620.08 642.8 643.43 643.43 651.16 Interest on Working Capital 52.10 51.63 51.52 51.67 51.67 O&MExpenses 274.72 290.47 307.11 324.65 343.11 Total 2167.20 2122.22 2093.32 2076.49 2050.28

26. We have considered the Petitioners claim. The tariff is allowed for the instant transmission assets on the basis of the following:-

a) Admitted Capital cost as on 1.4.2009: 16557.13lakh

b) Weighted Average Rate of Interest on actual loan derived/adopted from order dated 4.12.2015 in Petition No. 183/TT/2014

c) Weighted average rate of depreciation as per order dated 4.12.2015 in Petition No. 183/TT/2014. In view of the above, the revised transmission charges allowed for the instant transmission asset for the 2009-14 tariff period are as follows: Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Depreciation 874.75 874.75 874.75 874.75 874.75 Interest on Loan 345.96 262.92 216.83 182.30 129.85 Return on Equity 620.08 642.80 643.43 643.43 651.16 Interest on Working Capital 52.11 51.64 51.52 51.68 51.67 O&M Expenses 274.72 290.47 307.11 324.65 343.11 Total 2167.62 2122.57 2093.64 2076.80 2050.55 Order in Petition No.300/TT/2019 Page 16 of 36 ( in lakh) Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Depreciation 874.75 874.75 874.75 874.75 874.75 Interest on Loan 345.55 262.57 216.51 181.98 129.59 Return on Equity 620.08 642.80 643.43 643.43 651.16 Interest on Working Capital 52.10 51.63 51.52 51.67 51.67 O&MExpenses 274.72 290.47 307.11 324.65 343.11 Total 2167.19 2122.22 2093.31 2076.48 2050.28 TRUING UP OF ANNUAL FIXED CHARGES FOR 2014-19 TARIFF PERIOD

27. The Petitioner has submitted the information as required under the 2014 Tariff Regulations for truing up of annual fixed charges for 2014-19 period. The tariff for 2014-19 period has been trued up as discussed in the subsequent paragraphs.

28. The details of the transmission charges claimed by the Petitioner are as under:- ( in lakh) Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Depreciation 287.72 287.72 287.72 287.72 287.72 Interest on Loan 100.14 91.43 107.83 118.96 142.92 Return on Equity 651.66 654.65 654.32 654.32 656.08 Interest on working capital 41.18 41.62 42.58 43.45 44.67 O & M Expenses 312.20 322.70 333.35 344.40 355.85 Total 1392.90 1398.12 1425.80 1448.85 1487.24

29. The details of the IWC claimed by the Petitioner are as under: ( in lakh) Particular 2014-15 2015-16 2016-17 2017-18 2018-19 O & M Expenses 26.02 26.89 27.78 28.70 29.65 Maintenance Spares 46.83 48.41 50.00 51.66 53.38 Receivables 232.15 233.02 237.63 241.48 247.87 Total 305.00 308.32 315.41 321.84 330.90 Rate of Interest (%) 13.50 13.50 13.50 13.50 13.50 Interest on Working Capital 41.18 41.62 42.58 43.45 44.67 Order in Petition No.300/TT/2019 Page 17 of 36 Capital Cost as on 1.4.2014

30. The capital cost of the instant transmission asset has been calculated in accordance with the Regulation 9(3) and Regulation 9(6) of 2014 Tariff Regulations. The Commission vide order dated 4.12.2015 in Petition No.183/TT/2014 had approved the transmission tariff for the instant transmission asset for the 2014-19 period based on admitted capital cost of 16557.13 lakh as on 31.3.2014. The Petitioner has not claimed any additional capital expenditure during the 2014-19 tariff period. Accordignly, the capital cost of 16557.13 lakh has been considered for the purpose of truing up of the tariff of the 2014-19 tariff period. Debt-Equity ratio

31. The debt-equity ratio has been allowed in accordance with Regulation 19(3) of 2014 Tariff Regulations. As per Regulation 19(3) of the 2014 Tariff Regulations, the debt-equity ratio allowed by the Commission for determination of tariff for the period ending on 31.3.2014 shall be considered. Accordingly, the debt-equity ratio of 79.94:20.06 for the period ending on 31.3.2014, considered for the purpose of determination of tariff of the 2014-19 tariff period has been considered for the prupose of truing up of the tariff of the instant transmissionasset for the 2014-19 tariff period.The details of the debt-equity ratio as on 1.4.2014 and 31.3.2019 of the instant transmission asset is as follows:- Funding Capital cost as on 1.4.2014 ( in lakh) Total capital cost as 31.3.2019 ( in lakh) Debt 13236.56 79.94 13236.56 79.94 Equity 3320.57 20.06 3320.57 20.06 Total 16557.13 100.00 16557.13 100.00 Order in Petition No.300/TT/2019 Page 18 of 36 Interest on Loan (IoL)

32. The details of interest on loan allowed are as under:- ( in lakh) Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Gross Normative Loan 13236.56 13236.56 13236.56 13236.56 13236.56 Cumulative Repayment up to previous Year 8571.63 8859.35 9147.06 9434.78 9722.50 Net Loan-Opening 4664.93 4377.21 4089.50 3801.78 3514.06 Addition due to Additional Capitalization 0.00 0.00 0.00 0.00 0.00 Repayment during the year 287.72 287.72 287.72 287.72 287.72 Net Loan-Closing 4377.21 4089.50 3801.78 3514.06 3226.34 Average Loan 4521.07 4233.36 3945.64 3657.92 3370.20 Weighted Average Rate of Interest on Loan 2.2546% 2.1761% 2.7305% 3.2484% 4.2392% Interest on Loan 101.93 92.12 107.74 118.83 142.87 Return on Equity (ROE)

33. The Petitioner is entitled for Return on Equity for the instant transmission asset in terms of Regulation 24 and 25 of the 2014 Tariff Regulations. The Petitioner has submitted that it is liable to pay income tax at MAT rates and has claimed following effective tax rates for the 2014-19 tariff period: Year Claimed effective tax rate (in %) Grossed up ROE (Base Rate/1-t)(in %) 2014-15 21.018 19.624 2015-16 21.382 19.716 2016-17 21.338 19.705 2017-18 21.337 19.704 2018-19 21.549 19.758

34. We have considered the submissions of the Petitioner. The Commission in order dated 17.06.2020 in Petition No. 301/TT/2019 has arrived at the effective tax rate based on the notified MAT rates for the Petitioner and the same is given in the table below. The same MAT rates are considered for the purpose of grossing up of Order in Petition No.300/TT/2019 Page 19 of 36 rate of RoE for truing up of the tariff of the 2014-19 tariff period in terms of the provisions of the 2014 Tariff Regulations. Year Notified MAT rates (inclusive of surcharge & cess) (in %) Base rate of RoE (in %) Grossed up ROE (Base Rate/1-t) (in %) 2014-15 20.961 15.50 19.610 2015-16 21.342 15.50 19.705 2016-17 21.342 15.50 19.705 2017-18 21.342 15.50 19.705 2018-19 21.549 15.50 19.758

35. The Petitioner has claimed ROE for the 2014-19 period after grossing up the ROE of 15.50% with Effective Tax rates (based on MAT rates) each year as per the above said Regulation. The ROE is trued up on the basis of the MAT rate applicable in the respective years and is allowed as follows:- ( in lakh) Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Opening Equity 3320.57 3320.57 3320.57 3320.57 3320.57 Additions 0.00 0.00 0.00 0.00 0.00 Closing Equity 3320.57 3320.57 3320.57 3320.57 3320.57 Average Equity 3320.57 3320.57 3320.57 3320.57 3320.57 Return on Equity (Base Rate) (%) 15.50 15.50 15.50 15.50 15.50 MAT Rate for respective year (%) 20.961 21.342 21.342 21.342 21.549 Rate of Return on Equity (%) 19.610 19.705 19.705 19.705 19.758 Return on Equity 651.16 654.32 654.32 654.32 656.08 Depreciation

36. The depreciation has been worked out as per the methodology provided in Regulation 27 of the 2014 Tariff Regulations. The depreciation allowed is as follows:- ( in lakh) Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Opening Gross Block 16557.13 16557.13 16557.13 16557.13 16557.13 Additional Capitalisation 0.00 0.00 0.00 0.00 0.00 Closing Gross Block 16557.13 16557.13 16557.13 16557.13 16557.13 Average Gross Block 16557.13 16557.13 16557.13 16557.13 16557.13 Order in Petition No.300/TT/2019 Page 20 of 36 Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Rate of Depreciation (%) 1.7377% 1.7377% 1.7377% 1.7377% 1.7377% Depreciable Value 14901.42 14901.42 14901.42 14901.42 14901.42 Elapsed life 12 13 14 15 16 Weighted Balance useful life

22 21 20 19 18 Remaining Depreciable Value 6329.79 6042.07 5754.35 5466.64 5178.92 Depreciation 287.72 287.72 287.72 287.72 287.72 Operation & Maintenance Expenses (O&M Expenses)

37. As stated above, the instant transmission system consists of the 400 kV Biharsharif-Sasaram-Sarnath Transmission Line along with associated bays under Eastern Northern Inter-regional HVDC Transmission System in Eastern Region. Regulation 29(3) of the 2014 Tariff Regulations specifies the norms for O&M Expenses for the transmission system.

38. The Petitioner has claimed the O&M Expenses for the instant transmission system for the 2014-19 period as per the norms specified in the 2014 Tariff Regulations. The Petitioners claim is as per the norms specified in the 2014 Tariff Regulations. Hence, it is allowed and the details are as follows:- ( in lakh) Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Claimed by the Petitioner 312.20 322.70 333.35 344.40 355.85 Allowed after true-up in this order 312.20 322.70 333.35 344.40 355.85 Interest on Working Capital (IWC)

39. The Petitioner is entitiled for IWC as per Regulation 28 of the 2014 Tariff Regulations. The components of the working capital and the petitioners entitlement to interest thereon are discussed hereunder:-

(i) Receivables Order in Petition No.300/TT/2019 Page 21 of 36 Receivables as a component of working capital will be equivalent to two months fixed cost. The petitioner has claimed the receivables on the basis of 2 months' annual transmission charges. In the tariff being allowed, receivables have been worked out on the basis of 2 months' transmission charges.

(ii) Maintenance spares Regulation 28 of the 2014 Tariff Regulations provides for maintenance spares @ 15% per annum of the O&M Expenses. The value of maintenance spares has accordingly been worked out.

(iii) O & M expenses O&M Expenses have been considered for one month as a component of working capital. The petitioner has claimed O&M Expenses for 1 month of the respective year as claimed in the petition. This has been considered in the working capital.

(iv) Rate of IWC As per Proviso 3 of Regulation 28 of the 2014 Tariff Regulation, SBI Base rate 10.00% as on 1.4.2014 plus 350 Bps i.e. 13.50% has been considered for the asset, as the rate of interest on working capital.

40. The IWC allowed as per the methodology provided in Regulation 28 of the 2014 Tariff Regulations is as under:- ( in lakh) Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Maintenance Spares 46.83 48.41 50.00 51.66 53.38 O&M Expenses 26.02 26.89 27.78 28.70 29.65 Receivables 232.37 233.08 237.62 241.45 247.85 Total Working Capital 305.22 308.38 315.40 321.81 330.88 Interest of working capital 41.20 41.63 42.58 43.44 44.67 APPROVED ANNUAL FIXED CHARGES FOR 2014-19 TARIFF PERIOD

41. The trued up annual fixed charges for the instant transmission assets for the tariff period 2014-19 are as under:- Order in Petition No.300/TT/2019 Page 22 of 36 ( in lakh) Particulars 2014-15 2015-16 2016-17 201718 2018-19 Depreciation 287.72 287.72 287.72 287.72 287.72 Interest on Loan 101.93 92.12 107.74 118.83 142.87 Return on Equity 651.16 654.32 654.32 654.32 656.08 Interest on Working Capital 41.20 41.63 42.58 43.44 44.67 O & M Expenses 312.20 322.70 333.35 344.40 355.85 Total 1394.22 1398.49 1425.70 1448.71 1487.08 DETERMINATION OF ANNUAL FIXED CHARGES FOR 2019-24 TARIFF PERIOD

42. The Petitioner has claimed the following tariff charges for the instant assets for the 2019-24 tariff period:- ( in lakh) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Depreciation 287.72 287.72 287.72 287.72 287.72 Interest on Loan 143.66 129.56 114.39 97.10 84.51 Return on Equity 656.08 656.08 656.08 656.08 656.08 Interest on Working Capital 29.60 29.92 30.17 30.40 30.66 O&M Expenses 304.06 314.72 325.73 337.10 348.81 Total 1421.12 1418.00 1414.09 1408.40 1407.78

43. The details of the IWC claimed by the Petitioner are as under: ( in lakh) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 O & M Expenses 25.34 26.23 27.14 28.09 29.07 Maintenance Spares 45.61 47.21 48.86 50.57 52.32 Receivables 174.73 174.83 174.34 173.64 173.09 Total 245.68 248.27 250.34 252.30 254.48 Rate of Interest (%) 12.05% 12.05% 12.05% 12.05% 12.05% Interest on Working Capital 29.60 29.92 30.16 30.40 30.66

44. The tariff for 2019-24 period is allowed as discussed in the subsequent paragraphs. Capital Cost

45. Regulation 19 of the 2019 Tariff Regulations provides as follows:-

19. Capital Cost (1) The Capital cost of the generating station or the transmission system, as the case may be, as determined by the Commission after prudence check Order in Petition No.300/TT/2019 Page 23 of 36 in accordance with these regulations shall form the basis for determination of tariff for existing and new projects. (2) The Capital Cost of a new project shall include the following: (a) The expenditure incurred or projected to be incurred up to the date of commercial operation of the project; (b) Interest during construction and financing charges, on the loans (i) being equal to 70% of the funds deployed, in the event of the actual equity in excess of 30% of the funds deployed, by treating the excess equity as normative loan, or (ii) being equal to the actual amount of loan in the event of the actual equity less than 30% of the funds deployed; (c) Any gain or loss on account of foreign exchange risk variation pertaining to the loan amount availed during the construction period; (d) Interest during construction and incidental expenditure during construction as computed in accordance with these regulations; (e) Capitalised initial spares subject to the ceiling rates in accordance with these regulations; (f) Expenditure on account of additional capitalization and de-capitalisation determined in accordance with these regulations; (g) Adjustment of revenue due to sale of infirm power in excess of fuel cost prior to the date of commercial operation as specified under Regulation 7 of these regulations; (h) Adjustment of revenue earned by the transmission licensee by using the assets before the date of commercial operation;

(i) Capital expenditure on account of ash disposal and utilization including handling and transportation facility; (j) Capital expenditure incurred towards railway infrastructure and its augmentation for transportation of coal upto the receiving end of the generating station but does not include the transportation cost and any other appurtenant cost paid to the railway; (k) Capital expenditure on account of biomass handling equipment and facilities, for co-firing;

(l) Capital expenditure on account of emission control system necessary to meet the revised emission standards and sewage treatment plant; (m) Expenditure on account of fulfilment of any conditions for obtaining environment clearance for the project; (n) Expenditure on account of change in law and force majeure events; and (o) Capital cost incurred or projected to be incurred by a thermal generating station, on account of implementation of the norms under Perform, Achieve and Trade (PAT) scheme of Government of India shall be considered by the Commission subject to sharing of benefits accrued under the PAT scheme with the beneficiaries. (3) The Capital cost of an existing project shall include the following: (a) Capital cost admitted by the Commission prior to 1.4.2019 duly trued up by excluding liability, if any, as on 1.4.2019; (b) Additional capitalization and de-capitalization for the respective year of tariff as determined in accordance with these regulations; (c) Capital expenditure on account of ash disposal and utilization including handling and transportation facility; (d) Capital expenditure on account of ash disposal and utilization including handling and transportation facility; (e) Capital expenditure incurred towards railway infrastructure and its augmentation for transportation of coal up to the receiving end of generating station but does not include the transportation cost and any other appurtenant cost paid to the railway; and Order in Petition No.300/TT/2019 Page 24 of 36 (f) Capital cost incurred or projected to be incurred by a thermal generating station, on account of implementation of the norms under Perform, Achieve and Trade (PAT) scheme of Government of India shall be considered by the Commission subject to sharing of benefits accrued under the PAT schemewith the beneficiaries. (4) The capital cost in case of existing or new hydro generating station shall also include: (a) cost of approved rehabilitation and resettlement (R&R) plan of the project in conformity with National R&R Policy and R&R package as approved; and (b) cost of the developers 10% contribution towards Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) and Deendayal Upadhyaya Gram JyotiYojana (DDUGJY) project in the affected area. (5) The following shall be excluded from the capital cost of the existing and new projects: (a) The assets forming part of the project, but not in use, as declared in the tariff petition; (b) De-capitalised Assets after the date of commercial operation on account of replacement or removal on account of obsolescence or shifting from one project to another project: Provided that in case replacement of transmission asset is recommended by Regional Power Committee, such asset shall be decapitalised only after its redeployment; Provided further that unless shifting of an asset from one project to another is of permanent nature, there shall be no de-capitalization of the concerned assets. (c) In case of hydro generating stations, any expenditure incurred or committed to be incurred by a project developer for getting the project site allotted by the State Government by following a transparent process; (d) Proportionate cost of land of the existing project which is being used for generating power from generating station based on renewable energy; and (e) Any grant received from the Central or State Government or any statutory body or authority for the execution of the project which does not carry any liability of repayment.

46. The capital cost of 16557.13 lakh has been considered by the Commission for the instant transmission asset as on 31.3.2019. The Petitioner has not claimed any additional capital expenditure during 2019-24 period. Therefore, the capital cost of 16557.13 lakh as on 31.3.2019 has been considered for the purpose of determination of transmission tariff for 2019-24 period in accordance with Regulation

19 of the 2019 Tariff Regulations. Order in Petition No.300/TT/2019 Page 25 of 36 Debt-Equity ratio

47. Regulation 18 of the 2019 Tariff Regulations provides as under:-

18. Debt-Equity Ratio: (1) For new projects, the debt:equity ratio of 70:30 as on date of commercial operation shall be considered. If the equity actually deployed is more than 30% of the capital cost, equity in excess of 30% shall be treated as normative loan: Provided that:

i. where equity actually deployed is less than 30% of the capital cost, actual equity shall be considered for determination of tariff:

ii. the equity invested in foreign currency shall be designated in Indian rupees on the date of each investment:

iii. any grant obtained for the execution of the project shall not be considered as a part of capital structure for the purpose of debt: equity ratio. Explanation-The premium, if any, raised by the generating company or the transmission licensee, as the case may be, while issuing share capital and investment of internal resources created out of its free reserve, for the funding of the project, shall be reckoned as paid up capital for the purpose of computing return on equity, only if such premium amount and internal resources are actually utilised for meeting the capital expenditure of the generating station or the transmission system. (2) The generating company or the transmission licensee, as the case may be, shall submit the resolution of the Board of the company or approval of the competent authority in other cases regarding infusion of funds from internal resources in support of the utilization made or proposed to be made to meet the capital expenditure of the generating station or the transmission system including communication system, as the case may be. (3) In case of the generating station and the transmission system including communication system declared under commercial operation prior to 1.4.2019, debt: equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2019 shall be considered: Provided that in case of a generating station or a transmission system including communication system which has completed its useful life as on or after 1.4.2019, if the equity actually deployed as on 1.4.2019 is more than 30% of the capital cost, equity in excess of 30%shall not be taken into account for tariff computation; Provided further that in case of projects owned by Damodar Valley Corporation, the debt: equity ratio shall be governed as per sub-clause (ii) of clause (2) of Regulation

72 of these regulations. (4) In case of the generating station and the transmission system including communication system declared under commercial operation prior to 1.4.2019, but where debt: equity ratio has not been determined by the Commission for determination of tariff for the period ending 31.3.2019, the Commission shall approve the debt: equity ratio in accordance with clause (1) of this Regulation. (5) Any expenditure incurred or projected to be incurred on or after 1.4.2019 as may be admitted by the Commission as additional capital expenditure for determination of tariff, and renovation and modernisation expenditure for life extension shall be serviced in the manner specified in clause (1) of this Regulation. Order in Petition No.300/TT/2019 Page 26 of 36

48. The debt-equity ratio for the 2019-24 period is allowed as per Regulation 18(3) of the 2019 Tariff Regulations. The details of the debt-equity ratio considered for the purpose of tariff for 2019-24 tariff period is as follows:- Particulars Capital cost as on 1.4.2019 ( in lakh) Capital cost as on 31.3.2024 ( in lakh) Debt 13236.56 79.94 13236.56 79.94 Equity 3320.57 20.06 3320.57 20.06 Total 16557.13 100.00 16557.13 100.00 Return on Equity (ROE)

49. Regulation 30 and Regulation 31 of the 2019 Tariff Regulations specify as under:-

30. Return on Equity: (1) Return on equity shall be computed in rupee terms, on the equity base determined in accordance with Regulation 18 of these regulations. (2) Return on equity shall be computed at the base rate of 15.50% for thermal generating station, transmission system including communication system and run- of river hydro generating station, and at the base rate of 16.50% for the storage type hydro generating stations including pumped storage hydro generating stations and run-of river generating station with pondage: Provided that return on equity in respect of additional capitalization after cut- off date beyond the original scope excluding additional capitalization due to Change in Law, shall be computed at the weighted average rate of interest on actual loan portfolio of the generating station or the transmission system; Provided further that:

i. In case of a new project, the rate of return on equity shall be reduced by 1.00% for such period as may be decided by the Commission, if the generating station or transmission system is found to be declared under commercial operation without commissioning of any of the Restricted Governor Mode Operation (RGMO) or Free Governor Mode Operation (FGMO), data telemetry, communication system up to load dispatch centre or protection system based on the report submitted by the respective RLDC;

ii. in case of existing generating station, as and when any of the requirements under (i) above of this Regulation are found lacking based on the report submitted by the concerned RLDC, rate of return on equity shall be reduced by 1.00% for the period for which the deficiency continues;

iii. in case of a thermal generating station, with effect from 1.4.2020:

a) rate of return on equity shall be reduced by 0.25% in case of failure to achieve the ramp rate of 1% per minute; Order in Petition No.300/TT/2019 Page 27 of 36

b) an additional rate of return on equity of 0.25% shall be allowed for every incremental ramp rate of 1% per minute achieved over and above the ramp rate of 1% per minute, subject to ceiling of additional rate of return on equity of 1.00%: Provided that the detailed guidelines in this regard shall be issued by NationalLoad Dispatch Centre by 30.6.2019.

31. Tax on Return on Equity:(1) The base rate of return on equity as allowed by the Commission under Regulation 30 of these regulations shall be grossed up with the effective tax rate of the respective financial year. For this purpose, the effective tax rate shall be considered on the basis of actual tax paid in respect of the financial year in line with the provisions of the relevant Finance Acts by the concerned generating company or the transmission licensee, as the case may be. The actual tax paid on income from other businesses including deferred tax liability (i.e. income from business other than business of generation or transmission, as the case may be) shall be excluded for the calculation of effective tax rate. (2) Rate of return on equity shall be rounded off to three decimal places and shall be computed as per the formula given below: Rate of pre-tax return on equity = Base rate / (1-t) Where t is the effective tax rate in accordance with clause (1) of this Regulation and shall be calculated at the beginning of every financial year based on the estimated profit and tax to be paid estimated in line with the provisions of the relevant Finance Act applicable for that financial year to the company on pro-rata basis by excluding the income of non-generation or non-transmission business, as the case may be, and the corresponding tax thereon. In case of generating company or transmission licensee paying Minimum Alternate Tax (MAT), t shall be considered as MAT rate including surcharge and cess. (3) The generating company or the transmission licensee, as the case may be, shall true up the grossed up rate of return on equity at the end of every financial year based on actual tax paid together with any additional tax demand including interest thereon, duly adjusted for any refund of tax including interest received from the income tax authorities pertaining to the tariff period 2019-24 on actual gross income of any financial year. However, penalty, if any, arising on account of delay in deposit or short deposit of tax amount shall not be claimed by the generating company or the transmission licensee, as the case may be. Any under-recovery or over-recovery of grossed up rate on return on equity after truing up, shall be recovered or refunded to beneficiaries or the long term customers, as the case may be, on year to year basis.

50. The Petitioner has submitted that MAT rate is applicable to the Petitioner's company. Accordingly, the MAT rate applicable in 2019-20 has been considered for the purpose of ROE, which shall be trued up with actual tax rate in accordance with Regulation 31(3) of the 2019 Tariff Regulations. The ROE has been allowed as follows:- Order in Petition No.300/TT/2019 Page 28 of 36 ( in lakh) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Opening Equity 3320.57 3320.57 3320.57 3320.57 3320.57 Additions 0.00 0.00 0.00 0.00 0.00 Closing Equity 3320.57 3320.57 3320.57 3320.57 3320.57 Average Equity 3320.57 3320.57 3320.57 3320.57 3320.57 Return on Equity (Base Rate) (%) 15.50% 15.50% 15.50% 15.50% 15.50% MAT Rate for respective year (%) 17.472% 17.472% 17.472% 17.472% 17.472% Rate of Return on Equity (%) 18.780% 18.780% 18.780% 18.780% 18.780% Return on Equity 623.60 623.60 623.60 623.60 623.60 Interest on Loan (IoL)

51. The details of IOL allowed are as under:- ( in lakh) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Gross Normative Loan 13236.56 13236.56 13236.56 13236.56 13236.56 Cumulative Repayment up to previous Year 10010.22 10297.93 10585.65 10873.37 11161.09 Net Loan-Opening 3226.34 2938.63 2650.91 2363.19 2075.47 Addition due to Additional Capitalization 0.00 0.00 0.00 0.00 0.00 Repayment during the year 287.72 287.72 287.72 287.72 287.72 Net Loan-Closing 2938.63 2650.91 2363.19 2075.47 1787.76 Average Loan 3082.48 2794.77 2507.05 2219.33 1931.61 Weighted Average Rate of Interest on Loan 5.4930% 5.1558% 4.5528% 4.3757% 4.3757% Interest on Loan 169.32 144.09 114.14 97.11 84.52 Depreciation

52. Regulation 33 of the 2019 Tariff Regulations provides as under:- "33. Depreciation: (1) Depreciation shall be computed from the date of commercial operation of a generating station or unit thereof or a transmission system or element there of including communication system. In case of the tariff of all the units of agenerating station or all elements of a transmission system including communication system for which a single tariff needs to be determined, the depreciation shall be computed from the effective date of commercial operation of the generating station orthe transmission system taking into consideration the depreciation of individual units: Provided that effective date of commercial operation shall be worked out by considering the actual date of commercial operation and installed capacity of all theunits of the generating station or capital cost of all elements of the transmission system, for which single tariff needs to be determined. Order in Petition No.300/TT/2019 Page 29 of 36 (2) The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the Commission. In case of multiple units of a generating station or multiple elements of a transmission system, weighted average life for the generating station ofthe transmission system shall be applied. Depreciation shall be chargeable from the firstyear of commercial operation. In case of commercial operation of the asset for part ofthe year, depreciation shall be charged on pro rata basis. (3) The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up to maximum of 90% of the capital cost of the asset: Provided that the salvage value for IT equipment and software shall be considered as NIL and 100% value of the assets shall be considered depreciable; Provided further that in case of hydro generating stations, the salvage value shall be as provided in the agreement, if any, signed by the developers with the State Government for development of the generating station: Provided also that the capital cost of the assets of the hydro generating station for the purpose of computation of depreciated value shall correspond to the percentage of sale of electricity under long-term power purchase agreement at regulated tariff: Provided also that any depreciation disallowed on account of lower availability of the generating station or unit or transmission system as the case may be, shall not be allowed to be recovered at a later stage during the useful life or the extended life. (4) Land other than the land held under lease and the land for reservoir in case of hydro generating station shall not be a depreciable asset and its cost shall be excluded from the capital cost while computing depreciable value of the asset. (5) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-I to these regulations for the assets of the generating station and transmission system: Provided that the remaining depreciable value as on 31st March of the yearclosing after a period of 12 years from the effective date of commercial operationof the station shall be spread over the balance useful life of the assets. (6) In case of the existing projects, the balance depreciable value as on 1.4.2019 shall be worked out by deducting the cumulative depreciation as admitted by the Commission upto 31.3.2019 from the gross depreciable value of the assets. (7) The generating company or the transmission licensee, as the case may be, shall submit the details of proposed capital expenditure five years before the completion of useful life of the project along with justification and proposed life Order in Petition No.300/TT/2019 Page 30 of 36 extension. The Commission based on prudence check of such submissions shall approve the depreciation on capital expenditure. (8) In case of de-capitalization of assets in respect of generating station or unit thereof or transmission system or element thereof, the cumulative depreciation shall be adjusted by taking into account the depreciation recovered in tariff by the decapitalized asset during its useful services.

53. The depreciation has been worked out considering the admitted capital cost of 16557.13 lakh as on 31.3.2019 and accumulated depreciation up to 31.3.2019. The detailed calculations for depreciation for the transmission asset are worked out and allowed as follows:- ( in lakh) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Opening Gross Block 16557.13 16557.13 16557.13 16557.13 16557.13 Additional Capitalisation 0.00 0.00 0.00 0.00 0.00 Closing Gross Block 16557.13 16557.13 16557.13 16557.13 16557.13 Average Gross Block 16557.13 16557.13 16557.13 16557.13 16557.13 Rate of Depreciation (%) 1.7377% 1.7377% 1.7377% 1.7377% 1.7377% Depreciable Value 14901.42 14901.42 14901.42 14901.42 14901.42 Elapsed life 17 18 19 20 21 Weighted Balance useful life

17 16 15 14 13 Remaining Depreciable Value 4891.20 4603.48 4315.77 4028.05 3740.33 Depreciation 287.72 287.72 287.72 287.72 287.72 Operation & Maintenance Expenses (O&M Expenses)

54. Regulation 35(3)(a) of the 2019 Tariff Regulations specifies the norms for the O&M Expenses for the transmission system as follows:- (3) Transmission system: (a) The following normative operation and maintenance expenses shall be admissible for the transmission system: Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Norms for sub-station Bays ( Lakh per bay)

765 kV 45.01 46.60 48.23 49.93 51.68

400 kV 32.15 33.28 34.45 35.66 36.91

220 kV 22.51 23.30 24.12 24.96 25.84

132 kV and below 16.08 16.64 17.23 17.83 18.46 Norms for Transformers ( Lakh per MVA) Order in Petition No.300/TT/2019 Page 31 of 36 Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

765 kV 0.491 0.508 0.526 0.545 0.564

400 kV 0.358 0.371 0.384 0.398 0.411

220 kV 0.245 0.254 0.263 0.272 0.282

132 kV and below 0.245 0.254 0.263 0.272 0.282 Norms for AC and HVDC lines ( Lakh per km) Single Circuit (Bundled Conductor with six or more sub-conductors) 0.881 0.912 0.944 0.977 1.011 Single Cir uit (Bundled conductor with four sub-conductors) 0.755 0.781 0.809 0.837 0.867 Single Circuit (Twin & Triple Conductor) 0.503 0.521 0.539 0.558 0.578 Single Circuit (Single Conductor) 0.252 0.260 0.270 0.279 0.289 Double Circuit (Bundled conductor with four or more sub- conductors) 1.322 1.368 1.416 1.466 1.517 Double Circuit (Twin & Triple Conductor) 0.881 0.912 0.944 0.977 1.011 Double Circuit (Single Conductor) 0.377 0.391 0.404 0.419 0.433 Multi Circuit (Bundled Conductor with four or more sub-conductor) 2.319 2.401 2.485 2.572 2.662 Multi Circuit (Twin & Triple Conductor) 1.544 1.598 1.654 1.713 1.773 Norms for HVDC stations HVDC Back-to-Back stations (Rs Lakh per

500 MW) (Except Gazuwaka BTB)

834 864 894 925 958 HVDC Back-to-Back station ( Lakh per 500 MW) 1,666 1,725 1,785 1,848 1,913

500 kV Rihand-Dadri HVDC bipole scheme (Rs Lakh) (1500 MW) 2,252 2,331 2,413 2,498 2,586

500 kV Talcher- Kolar HVDC bipole scheme (Rs Lakh) (2000 MW) 2,468 2,555 2,645 2,738 2,834

500 kV Bhiwadi-Balia HVDC bipole scheme (Rs Lakh) (2500 MW) 1,696 1,756 1,817 1,881 1,947

800 kV, Bishwanath- Agra HVDC bipole scheme (Rs Lakh) (3000 MW) 2,563 2,653 2,746 2,842 2,942 Provided that the O&M expenses for the GIS bays shall be allowed as worked out by multiplying 0.70 of the O&M expenses of the normative O&M expenses for bays; Provided further that:

i. the operation and maintenance expenses for new HVDC bi-pole Order in Petition No.300/TT/2019 Page 32 of 36 schemes commissioned after 1.4.2019 for a particular year shall be allowed pro-rata on the basis of normative rate of operation and maintenance expenses of similar HVDC bi-pole scheme for the corresponding year of the tariff period;

ii. the O&M expenses norms for HVDC bi-pole line shall be considered as Double Circuit quad AC line;

iii. the O&M expenses of 500 kV Mundra-Mohindergarh HVDC bipole scheme (2000 MW)shall be allowed as worked out by multiplying 0.80 of the normative O&M expenses for 500 kV Talchar-Kolar HVDC bi-pole scheme (2000 MW);

iv. the O&M expenses of 800 kV Champa-Kurukshetra HVDC bi-pole scheme (3000 MW) shall be on the basis of the normative O&M expenses for 800 kV, Bishwanath-Agra HVDC bi-pole scheme;

v. the O&M expenses of 800 kV, Alipurduar-Agra HVDC bi-pole scheme (3000 MW)shall be allowed as worked out by multiplying 0.80 of the normative O&M expenses for 800 kV, Bishwanath-Agra HVDC bi-pole scheme; and

vi. the O&M expenses of Static Synchronous Compensator and Static Var Compensator shall be worked at 1.5% of original project cost as on commercial operation which shall be escalated at the rate of 3.51% to work out the O&M expenses during the tariff period. The O&M expenses of Static Synchronous Compensator and Static Var Compensator, if required, may be reviewed after three years. (b) The total allowable operation and maintenance expenses for the transmission system shall be calculated by multiplying the number of sub-station bays, transformer capacity of the transformer (in MVA) and km of line length with the applicable norms for the operation and maintenance expenses per bay, per MVA and per km respectively. (c) The Security Expenses and Capital Spares for transmission system shall be allowed separately after prudence check: Provided that the transmission licensee shall submit the assessment of the security requirement and estimated security expenses, the details of year-wise actual capital spares consumed at the time of truing up with appropriate justification. (4) Communication system: The operation and maintenance expenses for the communication system shall be worked out at 2.0% of the original project cost related to such communication system. The transmission licensee shall submit the actual operation and maintenance expenses for truing up.

55. The O&M Expenses claimed by the Petitioner are as per the norms specified in the 2019 Tariff Regulations and hence, they are allowed as claimed as under: Order in Petition No.300/TT/2019 Page 33 of 36 ( in lakh) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Claimed by the Petitioner 304.06 314.72 325.73 337.10 348.81 Allowed after true-up in this order 304.06 314.72 325.73 337.10 348.81 Interest on Working Capital (IWC)

56. Regulation 34(1)(c), Regulation 34(3), Regulation 34(4) and Regulation 3(7) of the 2019 Tariff Regulations specify as follows:

34. Interest on Working Capital (c) For Hydro Generating Station (including Pumped Storage Hydro Generating Station) and Transmission System:

i. Receivables equivalent to 45 days of fixed cost;

ii. Maintenance spares @ 15% of operation and maintenance expenses including security expenses; and

iii. Operation and maintenance expenses, including security expenses for one month (3) Rate of interest on working capital shall be on normative basis and shall be considered as the bank rate as on 1.4.2019 or as on 1st April of the year during the tariff period 2019-24 in which the generating station or a unit thereof or the transmission system including communication system or element thereof, as the case may be, is declared under commercial operation, whichever is later: Provided that in case of truing-up, the rate of interest on working capital shall be considered at bank rate as on 1st April of each of the financial year during the tariff period 2019-24. (4) Interest on working capital shall be payable on normative basis notwithstanding that the generating company or the transmission licensee has not taken loan for working capital from any outside agency. 3.Definitions (7) Bank Rate means the one year marginal cost of lending rate (MCLR) of the State Bank of India issued from time to time plus 350 basis points;

57. The Petitioner has submitted that it has computed IWC for 2019-24 period considering the SBI Base Rate plus 350 basis points as on 1.4.2019. The Petitioner has considered the rate of IWC as 12.05%. The IWC is worked out in accordance with Regulation 34 of the 2019 Tariff Regulations. The rate of IWC considered is Order in Petition No.300/TT/2019 Page 34 of 36 12.05% (SBI 1 year MCLRapplicable as on 1.4.2019 of 8.55% plus 350 basis points). The components of the working capital and interest allowed thereon are as follows:- ( in lakh) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 O&M Expenses 25.34 26.23 27.14 28.09 29.07 Maintenance Spares 45.61 47.21 48.86 50.57 52.32 Receivables 176.82 175.01 172.64 171.97 171.90 Total Working Capital 244.77 248.44 248.65 250.62 253.29 Interest on Working Capital 29.86 29.94 29.96 30.20 30.52 Rate of Interest (%) 12.05% 12.05% 12.05% 12.05% 12.05% ANNUAL FIXED CHARGES FOR THE 2019-24 TARIFF PERIOD

58. The transmission charges allowed for the instant transmission assets for the 2019-24 period are summarised below:- ( in lakh) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Depreciation 287.72 287.72 287.72 287.72 287.72 Interest on Loan 169.32 144.09 114.14 97.11 84.52 Return on Equity 623.60 623.60 623.60 623.60 623.60 Interest on Working Capital 29.86 29.94 29.96 30.20 30.52 O & M Expenses 304.06 314.72 325.73 337.10 348.81 Total 1414.56 1400.07 1381.15 1375.73 1375.17 Filing Fee and the Publication Expenses

59. The Petitioner has sought reimbursement of fee paid by it for filing the petition and publication expenses. The Petitioner shall be entitled for reimbursement of the filing fees and publication expenses in connection with the present petition, directly from the beneficiaries on pro-rata basis in accordance with Regulation 70(1) of the 2019 Tariff Regulations. Licence Fee & RLDC Fees and Charges

60. The Petitioner shall be entitled for reimbursement of licence fee in accordance with Regulation 70(4) of the 2019 Tariff Regulations for 2019-24 period. The Petitioner Order in Petition No.300/TT/2019 Page 35 of 36 shall also be entitled for recovery of RLDC fee and charges in accordance with Regulations 70(3) of the 2019 Tariff Regulations for 2019-24 period. Security Expenses

61. The petitioner has submitted that security expenses for the instant transmission asset are not claimed in the instant petition and it would file a separate petition for claiming the overall security expenses and the consequential Interest on Working Capital. The petitioner has requested to consider the actual security expenses incurred during 2018-19 for claiming estimated security expenses for 2019-20 which shall be subject to true up at the end of the year based on the actuals. The petitioner has submitted that similar petition for security expenses for 2020-21, 2021-22, 2022-

23 and 2023-24 shall be filed on a yearly basis on the basis of the actual expenses of previous year subject to true up at the end of the year on actual expenses. The petitioner has submitted that the difference, if any, between the estimated security expenses and actual security expenses as the audited accounts may be allowed to be recovered from the beneficiaries on a yearly basis.

62. We have considered the submissions of the Petitioner. Any application filed by the petitioner in this regard will be dealt with in accordance with the appropriate provisions of the 2019 Tariff Regulations. Goods and Services Tax

63. The Petitioner has submitted that, if GST is levied at any rate and at any point of time in future on Charges of Transmission of Electricity, the same shall be borne and additionally paid by the Respondents to the Petitioner and the same shall be charged and billed separately by the Petitioner. Further additional taxes, if any, are to Order in Petition No.300/TT/2019 Page 36 of 36 be paid by the Petitioner on account of demand from Government / Statutory authorities, the same may be allowed to be recovered from the beneficiaries.

64. We have considered the submissions of the Petitioner. GST is not levied on transmission service at present and we are of the view that Petitioners prayer is premature. Capital Spares

65. The Petitioner has sought reimbursement of capital spares at the end of tariff period. The Petitioners claim, if any, shall be dealt with in accordance with the provisions of the 2019 Tariff Regulations. Sharing of Transmission Charges

66. The billing, collection and disbursement of the transmission charges approved shall be governed by the provisions of Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, as amended from time to time as provided in Regulation 43 of 2014 Tariff Regulations for the 2014-19 tariff period and Regulation 57 of the 2019 Tariff Regulations for the 2019-24 tariff period.

67. This order disposes of Petition No. 300/TT/2019. sd/- sd/- (I. S. Jha) (P. K. Pujari) Member Chairperson