Sadhna Kumari v. Bihar State Food & Civil Supplies Corporation Limited & Others

Patna High Court
Apr 19, 2017
Smart Summary (Beta)

Structured Summary of the Opinion

Factual and Procedural Background

Sixteen applications were filed under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking constitution of an Arbitral Tribunal to adjudicate disputes arising from execution of an agreement between the applicants and the Bihar State Food and Civil Supplies Corporation Limited. The agreement (Annexure-1 dated 14.2.2013) related to milling of paddy for the Kharif 2012-2013 season and included Clause 15 (providing for recovery of amounts as land revenue under the Bihar and Orissa Public Demands Recovery Act, 1914, by instituting certificate proceedings) and Clause 16 (providing that disputes should be settled by mutual discussion and, failing that, by reference to an arbitrator—the District Collector—whose decision would be final).

A dispute arose, the Board issued show-cause notices and initiated certificate proceedings under the Recovery Act. The petitioners challenged these proceedings by writ petitions; the Court granted liberty to raise objections before the Certificate Officer under Section 9 of the Recovery Act. The petitioners' objections were rejected and certificates for recovery were issued. Thereafter, the petitioners filed the Section 11(6) applications seeking constitution of an Arbitral Tribunal in terms of Clause 16.

Legal Issues Presented

  1. Whether Clause 16 of the agreement constitutes a valid arbitration agreement entitling the applicants to seek constitution of an arbitral tribunal under Section 11(6) of the Arbitration and Conciliation Act, 1996.
  2. Whether the certificate proceedings under the Bihar and Orissa Public Demands Recovery Act, 1914 (including issuance of recovery certificates) preclude or bar resort to arbitration (including the effect of Section 8 of the Arbitration and Conciliation Act, 1996).
  3. Whether the District Collector, who is named as the arbitrator in Clause 16 and who is an officer of the respondent Board and who conducted the certificate proceedings, can serve as arbitrator in view of Section 12(5) and the disqualifications listed in the Seventh Schedule to the Arbitration and Conciliation Act (i.e., neutrality, independence and ineligibility where a specified relationship exists).

Arguments of the Parties

Petitioners' Arguments

  • The petitioners contended that the recovery/certificate proceedings initiated without adjudication of the underlying dispute are unsustainable and that they are therefore entitled to have the dispute adjudicated by arbitration in terms of Clause 16 of the agreement.
  • Counsel argued that Clause 16 is an arbitration agreement but the named arbitrator (the District Collector) cannot act because, under Section 12(5) and the Seventh Schedule, a person who is an employee or has a business relationship or is otherwise disqualified cannot serve as an arbitrator; reliance was placed on Voestalpine Schienen GmbH v. Delhi Metro Rail Corporation Ltd. (AIR 2017 SC 939) and the amendments to Section 12 introduced with the 2015 Amendment Act, and on Law Commission recommendations supporting neutrality and independence of arbitrators.
  • It was argued that, because of the ineligibility of the named arbitrator, the court should appoint an independent arbitrator.

Respondents' Arguments

  • The respondents relied on Section 8 of the Arbitration and Conciliation Act, 1996, arguing that because a judicial authority (the Certificate Officer) had issued certificates under the Recovery Act, the petitioners' remedy is to challenge the recovery certificate by an appeal under the Recovery Act and not by seeking arbitration after a long delay (certificate proceedings were initiated in 2014).
  • The respondents contended that Clause 16 is not an arbitration agreement and therefore the Section 11(6) application is not maintainable; they relied on the Supreme Court judgment in P. Dasaratharama Reddy Complex v. Government of Karnataka and Anr. (AIR 2014 SC 168) to support that contention.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Voestalpine Schienen GmbH v. Delhi Metro Rail Corporation Ltd., AIR 2017 SC 939 Cited for the principle that arbitrators must be neutral, impartial and independent; discussion of Law Commission recommendations and the purpose of amendments to Section 12 (notably sub-section (5)) to ensure neutrality. The Court relied on this authority to emphasize the ineligibility of a named arbitrator who falls within categories specified in the Seventh Schedule and to support the conclusion that where the arbitration clause conflicts with Section 12(5)/Seventh Schedule the court may appoint an arbitrator permissible under the Act.
P. Dasaratharama Reddy Complex v. Government of Karnataka and Anr., AIR 2014 SC 168 ((2014) 2 SCC 201) Cited by respondents to argue that an agreement may not constitute an arbitration agreement (in that case because the words 'Arbitrator' or 'Arbitration' were not present). The Court held that this precedent was not applicable: in the present case Clause 16 explicitly refers to arbitration and an arbitrator (District Collector), whereas in P. Dasaratharama Reddy Complex the clause lacked those words and therefore was held not to be an arbitration agreement.

Court's Reasoning and Analysis

The Court's analysis proceeded in sequential steps, applying the agreement text, statutory provisions and the cited authorities:

  1. Admission and Agreement Text: The Court noted an admission by the respondents in earlier proceedings before this Court that an alternate remedy of arbitration was available. A reading of Clause 16 showed it to be an arbitration agreement because it expressly contemplated settlement by arbitration and named the District Collector as the arbitrator.
  2. On Applicability of P. Dasaratharama Reddy: The Court found the respondents' reliance on P. Dasaratharama Reddy inapplicable because that case involved an agreement which lacked the words 'Arbitrator' or 'Arbitration'—a distinguishing factual feature absent in the present Clause 16.
  3. On Section 8 of the Arbitration Act: The Court rejected the respondents' contention that Section 8 precluded arbitration because a "judicial authority" had issued certificates. The Court held that the certificate proceedings under the Recovery Act are execution proceedings before a statutory authority and not proceedings "before a judicial authority" for the purpose of Section 8; accordingly, Section 8 did not bar a resort to arbitration.
  4. Preservation of Arbitration Right Despite Certificates: The Court observed that issuance of recovery certificates did not extinguish the petitioners' contractual right to seek arbitration. The legality of the certificate proceedings (including whether recovery could proceed without adjudication of the dispute) was a matter that could be considered by the arbitrator or the appellate authority under the Recovery Act.
  5. Eligibility of the Named Arbitrator: The Court examined whether the District Collector (the named arbitrator) could act in light of Section 12(5) and the Seventh Schedule. It found that the Collector was an officer of the Board, had conducted the certificate proceedings, and thus fell within the categories (employee/consultant/advisor or having a business relationship) contemplated by Entry 1 to the Seventh Schedule. Multiple prohibitions in the Seventh Schedule were attracted.
  6. Application of Voestalpine and Section 12(5): Relying on the Supreme Court's emphasis in Voestalpine and the object of the 2015 amendment (to ensure neutrality and independence of arbitrators), the Court concluded that when an arbitration clause conflicts with Section 12(5)/Seventh Schedule the clause cannot be given effect to the extent of permitting the ineligible person to serve; the court may then appoint an arbitrator permissible under the Act.
  7. Relief Granted: On that basis, the Court held that the named arbitrator (Collector) could not be appointed and that an independent arbitrator should be appointed. Consequently, the Section 11(6) applications were allowed and the Court appointed an independent arbitrator.
  8. Scope Left Open: The Court expressly stated that it did not decide the merits of objections concerning maintainability in view of the certificate proceedings, limitation, or other substantive issues; those questions were left to be canvassed before the arbitrator or the appropriate appellate forum under the Recovery Act.

Holding and Implications

Holding:

All applications under Section 11(6) of the Arbitration and Conciliation Act, 1996 are allowed, and an independent arbitrator is appointed in place of the named District Collector who is ineligible to serve.

Immediate Consequences for the Parties:

  • An arbitral tribunal will be constituted to adjudicate the disputes under Clause 16 of the agreement. The Court appointed Justice (Retired) R.K. Datta as the arbitrator to adjudicate the disputes.
  • The District Collector, though named in the agreement, is disqualified from acting as arbitrator in view of Section 12(5) and the Seventh Schedule because of his relationship to the respondent Board and his role in the certificate proceedings.
  • The Court did not adjudicate substantive objections (for example, maintainability in light of certificate proceedings, limitation and other merits). Those issues remain open for the parties to raise before the arbitrator or pursue under the appellate provisions of the Recovery Act.

Broader Legal Impact: The Court applied existing principles (including the requirement of neutrality under Voestalpine and the effect of Section 12(5) and the Seventh Schedule) to the facts at hand. The opinion resolved appointment and eligibility issues for this dispute; it did not purport to lay down a novel legal principle beyond applying the cited authorities and statutory provisions.

Show all summary ...

1. These are sixteen applications filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking constitution of an Arbitral Tribunal for adjudication of the dispute that has arisen between the parties in execution of an agreement and, as questions of law and fact are similar in all the cases, they are being disposed of by this common order.

2. For the sake of convenience, the documents and pleadings in the record of Request Case No.8 of 2016 are being referred to in this order.

3. The applicants herein and the Bihar State Food and Civil Supplies Corporation Limited, the respondents, entered into agreement for milling of paddy for Kharif marketing for the seasons 2012-2013. Annexure-1 dated 14.2.2013 is the agreement available on record and Clauses 15 and 16 of the agreement, which are identical in all the cases read as under:

"15. The second party agrees that in case, any amount found recoverable on account of default, loss, damage on the part of the second party, the said recoverable amount with interest will be recovered as Land Revenue under Bihar and Orissa Public Demands Recovery Act, 1914 by instituting Certificate case before the concerned District Certificate Officer.

16. In case of disputes both parties agree to settle the issue(s) on mutual discussion. Failure to reach agreement the matter will be referred to arbitrator. It has been also agreed that the arbitrator will be District Collector of the concerned District whose decision shall be final, concerning the dispute referred to him."

4. It seems that certain dispute arose and the Board issued show-cause notices and initiated certificate proceedings under the Bihar and Orissa Public Demands Recovery Act, 1914 (for short, Recovery Act) under Clause 19.

5. Petitioners challenged these proceedings by filing writ petitions before this Court and the petitioners were granted liberty to raise objections before the Certificate Officer-cum-Sub-divisional Officer under Section 9 of the Recovery Act. The petitioners raised the claim. Their objections were rejected and when the certificates for recovery of the amount were issued, they filed these applications, inter alia seeking constitution of an Arbitral Tribunal in accordance to the requirement of Clause-16 reproduced hereinabove.

6. It is the case of the petitioners that the recovery proceedings initiated without adjudication of the dispute is unsustainable and, as the recovery proceedings under the Certificate Act, proceedings is unsustainable, they are not liable to pay the amount. They want resolution of the dispute by taking recourse to Clause-16 of the agreement.

7. Learned counsel for the petitioners argued that Clause-16 is an arbitration agreement and even though in the arbitration agreement the District Collector is nominated as a named arbitrator, but in view of Section-12(5) of the Arbitration and Conciliation Act and the provisions of Schedule-7, Clause-1 thereof , the Collector being an employee of the organization and a person having business relationship and interested in the dispute, cannot act as an arbitrator and, therefore, an independent arbitrator should be appointed. In support of the aforesaid contention, a reasoned judgment of the Supreme Court in the case of Voestalpine Schienen Gmbh v. Delhi Metro Rail Corporation Limited ., reported in AIR 2017 SC 939 is relied upon.

8. Learned senior counsel for the petitioners took us through various aspects of the matter, the principle laid down by the Supreme Court, the recommendations made by the Law Commission, the amendment to the provisions of Section 12 and argues that it is a fit case where the independent arbitrator should be appointed. Learned Counsel invites our attention to the views recorded by the Supreme Court at para-17, in the case of M/s. Voestalpine (supra) various judgments of the Supreme Court on the subject in question with regard to independent and impartial arbitrator being appointed discussed in 18 of the judgment and argues that this is a fit case where independent arbitrator should be appointed.

9. Learned counsel for the respondents refuted the aforesaid contention, placed reliance on Section 8 of the Arbitration and Conciliation Act, 1996 and argues that as a judicial authority, namely, the Certificate Officer, has issued the certificate under the Bihar and Orissa Public Demands Recovery Act, 1914. Now the only remedy available to the petitioners is to challenge the recovery certificate by filing an appeal under the aforesaid statutory provision and no application for arbitration is now maintainable after such a long period of time as the certificate proceedings were initiated in the year 2014. He further argues that Clause-16 is not an arbitration agreement and, therefore, this application under Section-11(6) is not maintainable and in support of the aforesaid contention, invites my attention to a judgment of the Supreme Court in the case of P. Dasaratharama Reddy Complex v. Government of Karnataka and Anr., reported in (2014) 2 SCC 201 : (AIR 2014 SC 168).

10. Shri Y.V. Giri, appearing for one of the applicants in Request Case No.34 of 2016, invites my attention to an admission made by the respondents in a proceedings held before this Court in C.W.J.C. Nos. 9113 of 2014, 12355 of 2014 and 12356 of 2014 on 25.2.2014 when certain admissions were made by counsel for the respondent Board, detailed in para 12 of the order passed by a Division Bench of this Court on 22.7.2014, in that petition when a claim was made for quashing the demand notice issued, a plea of alternate remedy being available was made by arguing that an arbitration clause being available, the writ petition is not maintainable.

11. Heard learned counsel for the parties at length and perused the records. It is seen that after the certificate proceedings, the petitioners approached this Court and when the matter was pending before this Court, as pointed out by Shri Giri, the respondents admitted that an alternate remedy of settlement of dispute through arbitration is available. Apart from the aforesaid admission of the petitioners, a perusal of Clause-16 of the agreement in question clearly shows that it is an arbitration agreement. The judgment in the case of P. Dasaratharama Reddy Complex (AIR 2014 SC 168) (supra), relied upon by the learned counsel for the respondents, is not applicable in the present case. There the arbitration clause considered and reproduced by the Hon'ble Supreme Court in para 10 is entirely different and in para 15 it is clearly indicated that the words 'Arbitrator' or 'Arbitration' are not available in that agreement and that was the reason why it was held that there is no arbitration agreement. In this case, the arbitration agreement is clear in its term and there is no iota of doubt that there is an arbitration agreement. As far as the contention of the respondents that in view of the adjudication by the Certificate Officer and in view of Section 8, the arbitration cannot be resorted to is not correct. Section 8 empowers the judicial authority before whom an application is brought to refer the matter for arbitration, subject to an arbitration agreement. The certificate proceeding is not before a judicial authority. It is only an execution proceeding before a statutory authority who is not a judicial authority and, therefore, the objection of the respondents is unsustainable. That apart, merely because the certificate proceedings have been held and some certificates for recovery have been issued, it does not mean that the right of the petitioners to seek resolution of the dispute by arbitration and seek relief in terms of the agreement is taken away. The certificate proceedings are independent execution proceedings and the question as to whether the certificate proceedings held is legal without there being adjudication of the dispute is a question which would have to be considered by an appropriate authority, may be, the arbitrator or the appellate authority, under the Recovery Act.

12. For the present, in these proceedings, this Court is not required to go into all these aspects of the matter. These may be questions to be looked into either by the arbitrator or by the appellate authority, in case the petitioner takes recourse to the appellate proceedings under the Bihar and Orissa Public Demands Recovery Act, 1914. For the present, it is suffice to say that there is a dispute between the parties, on the matter of execution of the work in pursuance to the agreement in question which has to be adjudicated in terms of Clause-16, the arbitral agreement and, therefore, an arbitrator has to be appointed. However, as a named arbitrator is indicated in Clause-16, the further question would be as to whether in view of requirement of Section-12(5) and the provisions of Schedule-7, Entry-1, the Collector can be permitted to discharge the duties of an arbitrator.

13. Admittedly, the Collector is an officer of the Board. He is the person who conducted the certificate proceedings and, therefore, as contemplated in Entry-1 to the 7th Schedule, falls in the category of, may be, an employee, a consultant and advisor or has any other past or present business relationship with the parties. That apart, many of the prohibitions contained in the 7th Schedule are attracted in the case of the named arbitrator i.e. the Collector.

14. While discussing the matter in the case of M/s. Voestalpine Schienen GMBH (AIR 2017 SC 939) (supra), the Hon'ble Supreme Court has stressed upon the requirement of neutrality, impartiality and independence of the arbitrator, the recommendations of the Law Commission and has stressed upon the need to have an impartial arbitration. The question of appointing an independent and impartial arbitrator has been discussed and the requirement for doing so in paras 16 and 17 has been crystallized in the following manner:

"16. We may put a note of clarification here. Though, the Law Commission discussed the aforesaid aspect under the heading "Neutrality of Arbitrators", the focus of discussion was on impartiality and independence of the arbitrators which has relation to or bias towards one of the parties. In the field of international arbitration, neutrality is generally related to the nationality of the arbitrator. In international sphere, the 'appearance of neutrality' is considered equally important, which means that an arbitrator is neutral if his nationality is different from that of the parties. However, that is not the aspect which is being considered and the term 'neutrality' used is relatable to impartiality and independence of the arbitrators, without any bias towards any of the parties. In fact, the term 'neutrality of arbitrators' is commonly used in this context as well.

17. Keeping in mind the afore-quoted recommendation of the Law Commission, with which spirit, Section 12 has been amended by the Amendment Act, 2015, it is manifest that the main purpose for amending the provision was to provide for neutrality of arbitrators. In order to achieve this, sub-section (5) of Section 12 lays down that notwithstanding any prior agreement to the contrary, any person whose relationship with the parties or counsel or the subject-matter of the dispute falls under any of the categories specified in the Seventh Schedule, he shall be ineligible to be appointed as an arbitrator. In such an eventuality, i.e., when the arbitration clause finds foul with the amended provisions extracted above, the appointment of an arbitrator would be beyond pale of the arbitration agreement, empowering the court to appoint such arbitrator(s) as may be permissible. That would be the effect of non-obstante clause contained in sub-section (5) of Section 12 and the other party cannot insist on appointment of the arbitrator in terms of arbitration agreement."

15. It is a case where the named arbitrator as contemplated in Clause-16 cannot be appointed and an independent arbitrator has to be appointed and, therefore, overruling all the objections raised by the respondents, all these applications are allowed.

16. Justice (Retired) R.K. Datta is appointed as arbitrator to adjudicate the dispute. However, in these proceedings this Court has not gone into the merits of various objections raised with regard to maintainability of the dispute in view of the certificate proceedings held, the question of limitation and all other issues are left open to be canvassed by the parties before the arbitrator.