Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

RABINDRA MAN VERMA v. JAIPRAKASH ASSOCIATES LTD.

National Consumer Disputes Redressal Commission
Feb 14, 2020
Smart Summary (Beta)

Case Summary: National Consumer Disputes Redressal Commission — Consumer Case No. 1869 of 2016

Factual and Procedural Background

The Complainant, Rabindra Man Verma, booked an apartment (Unit K-8/1003) with Jaiprakash Associates Ltd. by cheque dated 20.11.2010 and received a provisional allotment on 31.03.2011. The parties revised the payment plan (change from construction-linked to down payment) and multiple demands and payments followed (demand notices dated 31.03.2011, 28.04.2011, 30.06.2011; payments by cheques in April–July 2011). The Opposite Party admitted that the Complainant had paid substantial sums (including an admitted payment of Rs. 29,99,200/- excluding service tax towards basic price and Rs. 1,22,250/- towards IDC under the revised plan).

The Complainant alleged that despite making payments (more than 95% of the consideration by 19.07.2011 as pleaded) possession was not delivered within the contractual period (36 months plus 90 days grace — expiry 30.06.2014). The Opposite Party sent a letter dated 06.09.2014 advising possession would be in April 2016; no detailed reasons for continuing delay were provided in subsequent communications. The Complainant sought refund and other reliefs in a complaint filed before this Commission in November 2016. The unit remained incomplete as of August 2019 (as stated in the record).

Forum and panel: National Consumer Disputes Redressal Commission, New Delhi; Presiding Member: Deepa Sharma; Member: C. Viswanath. Dated 14 February 2020.

Legal Issues Presented

  1. Whether the Complainant is a "consumer" under the Consumer Protection Act, 1986 for the purchase of the apartment (i.e., whether the apartment was purchased for personal use or for speculation).
  2. Whether this Commission has pecuniary jurisdiction to entertain the complaint given the asserted value of the flat (and whether interest should be included in computing pecuniary jurisdiction).
  3. Whether the arbitration clause in the agreement bars the Complainant from approaching the Consumer Forum or requires arbitration as the first remedy.
  4. Whether the Opposite Party can be absolved of liability by invoking a force majeure clause (clauses 7.1 and 7.2 of the Standard Terms and Conditions) for the delay in possession.
  5. What reliefs are permissible (refund, interest, compensation, costs) if the Opposite Party is found to have committed deficiency in service by failing to deliver possession).

Arguments of the Parties

Complainant's Arguments

  • The apartment was booked for personal residence (the Complaint and written submissions state it was for the Complainant's personal use and for his residence).
  • The Complainant made payments (allegedly over 95% of the consideration by July 2011) yet possession was delayed well beyond the contractual period; demand notices later wrongly alleged outstanding sums and threatened cancellation.
  • The Complainant sought refund of amounts paid with interest and/or delivery of possession, free car parking (first parking free), compensation for mental agony and punitive damages, and litigation costs.

Opposite Party's Arguments

  • The Opposite Party contended the booking was for speculation in the real estate market so the Complainant is not a consumer under Section 2(d) of the Consumer Protection Act, 1986.
  • It argued the Commission lacked pecuniary jurisdiction because the value of the flat (admitted at Rs. 75,00,280/-) was less than Rs. 1 crore; the Complainant had attempted to inflate claims by claiming high interest to reach the jurisdictional threshold.
  • It raised non-joinder of a necessary party (Jaypee Infratech Ltd.) asserting the provisional allotment letter involved other entities.
  • The Opposite Party relied on an arbitration clause (Clause 10.8) and filed an application under Section 8 of the Arbitration & Conciliation Act, 1996, contending disputes should first be amicably resolved or referred to arbitration.
  • The Opposite Party invoked clauses 7.1 and 7.2 (force majeure and limitation of liability): alleged delays due to force majeure events (shortage of labour, scarcity of water, excavation restrictions, villager agitations and legal impediments) entitling it to extension of time and limiting compensation to stipulated rebate (Rs.5/- per sq. ft. per month) and excluding broader claims for consequential losses.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Ambrish Kumar Shukla & Ors. Vs. Ferrous Infrastructure Pvt. Ltd. The principle that interest should be taken into account when computing pecuniary jurisdiction of the Commission. The Commission relied on this authority to hold that after adding interest on the value of the flat, the present complaint fell within its pecuniary jurisdiction.
Anish Singhal vs. Jaiprakash Associates Ltd. (CC/2194/2016 decided on 01.10.2019) Authority addressing maintainability of complaints against Jaiprakash Associates Ltd. (in the context of parties and payments). The Commission applied this decision to find that the complaint against Jaiprakash Associates Ltd. was maintainable because payments were made into Jaiprakash Associates Ltd.'s account.
National Seeds Corporation Vs. M. Madhusudhan Reddy & Anr. (2012) 2 SCC 506 The principle that a consumer may approach consumer fora despite an arbitration clause; the Consumer Protection Act is in addition to and in derogation of other laws. The Commission cited this Supreme Court authority to hold that the existence of an arbitration clause did not bar the Complainant from approaching the Consumer Forum as an alternative remedy.

Court's Reasoning and Analysis

The Commission heard the Complainant's counsel and perused the record. Its reasoning proceeded in discrete steps reflecting the issues identified:

  1. Consumer status: The Commission examined the pleadings and found the Complainant had repeatedly stated the apartment was intended for personal residence (including post-marriage residence). The Opposite Party produced no evidence showing the booking was made for speculative profit. On this basis the Commission held the Complainant was a "consumer" within the meaning of the Act.
  2. Pecuniary jurisdiction: Although the admitted price of the flat was Rs. 75,00,280/-, the Commission relied on the Ambrish Kumar Shukla precedent that interest must be included for the purpose of computing pecuniary jurisdiction. After accounting for interest, the complaint fell within this Commission's pecuniary jurisdiction.
  3. Non-joinder: The Opposite Party's contention of non-joinder was examined against the documentary evidence of payments. Since payments were made to Jaiprakash Associates Ltd., and having regard to the Commission's earlier treatment in Anish Singhal vs. Jaiprakash Associates Ltd., the complaint against Jaiprakash Associates Ltd. was held maintainable.
  4. Arbitration clause: The Commission considered the arbitration clause in the Standard Terms and Conditions but observed that Section 3 of the Consumer Protection Act makes the Act in addition to and in derogation of other laws. Relying on the Supreme Court decision in National Seeds Corporation v. M. Madhusudhan Reddy & Anr., the Commission held that a consumer may still approach the Consumer Forum despite an arbitration clause, i.e., the existence of an arbitration clause did not automatically oust the forum's jurisdiction in the consumer context.
  5. Force majeure defence: The Opposite Party alleged delays due to force majeure (shortage of labour, scarcity of water, restrictions, villager agitations, legal impediments). The Commission observed that the Opposite Party did not place evidence on record substantiating these asserted events as unforeseen/unexpected with attributable time periods. Finding the force majeure contention unproven, the Commission rejected the Opposite Party's attempt to shelter under clauses 7.1 and 7.2 to deny liability for delay.
  6. Remedies: In light of the above findings (establishment of consumer status, jurisdiction, non-applicability of arbitration as a bar in the consumer forum, and rejection of force majeure), the Commission concluded the Complainant was entitled to relief for deficiency in service due to delay in possession. The Commission therefore directed refund of the amounts deposited/paid with interest (at a specified rate below the rate sought by the Complainant) together with compensation and costs.

Holding and Implications

Holding: The Commission directed the Opposite Party to refund the amount deposited/paid by the Complainant with simple interest at the rate of 10% per annum from the respective dates of each payment until the date of refund, together with compensation. The Opposite Party was also ordered to pay Rs. 25,000/- towards cost of litigation. Payments were to be made within three months from the date of the order.

Implications:

  • Direct effect on the parties: The Opposite Party must refund all amounts deposited/paid by the Complainant with simple interest at 10% per annum (from the respective dates of payment) and pay the specified litigation costs (Rs. 25,000/-). The order required payment within three months.
  • Scope as precedent: The opinion applied existing authorities (including treatment of interest for pecuniary jurisdiction and the principle that arbitration clauses do not necessarily bar consumer forum jurisdiction). The decision does not purport to set a new legal precedent beyond applying these existing principles as stated in the text.

Note: The Commission's order directed a refund with interest and compensation but did not specify a quantified amount of compensation in the operative portion reproduced in the provided opinion. The Complainant's original quantified claims (e.g., Rs. 68,31,679/- refund sought; Rs.5 lakh for mental agony; Rs.5 lakh punitive damages; Rs.2 lakh litigation costs) were part of the relief sought, but the operative order as recorded directed refund with 10% simple interest and Rs. 25,000/- costs as described above.

Show all summary ...

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

NEW DELHI

CONSUMER CASE NO. 1869 OF 2016

1. RABINDRA MAN VERMA

R/o 6/302, East End Apartments, Mayur Vihar, Phase-I Extension

New Delhi 110096 ...........Complainant(s) Versus

1. JAIPRAKASH ASSOCIATES LTD.

Jaypee Greens, Sector 128 Noida 201304

U.P. ...........Opp.Party(s)

BEFORE:

HON'BLE MRS. JUSTICE DEEPA SHARMA,PRESIDING MEMBER HON'BLE MR. C. VISWANATH,MEMBER

For the Complainant : Mr. K.K. Rai, Senior Advocate Mr. Manvendra Verma, Advocate

Mr. Ramkrishna Veerendra, Advocate

Mr. DPS Rajeshy, Advocate

Mr. Abhinav Verma, Advocate

For the Opp.Party : NONE

Dated : 14 Feb 2020

ORDER

C.VISWANATH

In the Complaint, it is stated that the Complainant,allured by the ready-to-move-in apartments being offered with world class amenities by the Opposite Party within a period of 39 months of allotment (inclusive of the additional grace period of 90 days, as per clause 7.1 of the Standard Terms and Conditions of the Opposite Party), sought to purchase an apartment, for his personal residence. Accordingly, Complainant booked K- 8/1003, two-bedroom unit with a covered area of approximately 1600 sq. ft., vide cheque bearing number 123865 dated 20.11.2010 forRs. 8,17,975/- . On 31.03.2011, the Complainant received provisional allotment pursuant to the aforesaid booking. Thereafter, the Opposite Party sent a demand notice dated 31.03.2011 for Rs. 16,14745/- and directed the Complainant to pay the amount before the due date of 30.04.2011, failing which he would be liable to pay interest @18% p.a. for the period of delay. The Complainant duly paid the said amount, vide cheque dated 22.04.2011. On 28.04.2011, the Opposite Party issued a fresh demand notice for Rs. 7,69,107/- . The same was also paid by the Complainant, vide cheque dated 17.05.2011. Pursuant to an incentive scheme dated 05.08.2011 announced by the Opposite Party, the Complainant, vide intimation dated 10.06.2011, applied for change of his payment plan from construction linked to

1.

1

down payment. Accordingly, the Opposite Party revised the payment plan to Rs. 75,00,280/-. As per revised payment plan, it was admitted by the Opposite Party that Rs. 29,99,200/- (excluding service tax) had already been paid by the Complainant towards basic price and Rs. 1,22,250/- towards IDC. Through demand notice dated 30.06.2011, Rs. 36,29,852/- (inclusive service tax) was demanded by the Opposite Party by 20.07.2011.The Complainant paid the aforesaid amount, vide cheques dated 18.07.2011 & 19.07.2011.It is relevant to mention here that the Opposite Party had also demanded Rs. 4,00,000/- for the car parking slot, contrary to well established law of this Commission and the Apex Court that first parking shall be free. Rs. 3,74,900/- was balance towards the basic price and the Complainantby 19.07.2011 had paid more than 95% of the due consideration.Despite making all the payments well before the due date,the Complainant was shockedto receive a notice dated 11.05.2012 that Rs. 58,42,205/- was outstanding against him and the Opposite Party demanded the same with interest @12% p.a. in 30 days, failing which they threatened to cancel the allotment. The Complainant promptly sent a reply vide an email dt. 11.05.2012 and also delivered a copy thereof at the office of the Opposite Party on 16.05.2012. However, the Opposite Party took six long months to admit payment of all dues without conceeding their fault, vide letter dated 23.11.2012. It was alleged that the possession of the unit K-8/1003 was not delivered within the promised 36 months plus a grace period of 3 months. The said period for handing over the possession expired on 30.06.2014. However, the Complainant was shocked and aggrieved to receive a letter dated 06.09.2014 wherein it was stated that the unit would be ready for possession in April 2016. No specific cause(s) of delay were given, except a bald statement that the delay was due to "various reasons beyond control". No other communication explaining the cause of continuing delay was ever received by the Complainant till the date of filing of the present Complaint in November 2016.A notice dated 22.10.2016 was sent to the Opposite Party for refund of the deposit with interest, vide speed post and email. It was submitted that the unit is still incomplete as on August, 2019.

Alleging deficiency on the part of Opposite Party, Complainantfiled a Complaint before this Commission under Section 21 of the Consumer Protection Act, 1986, praying relief as under:-

2.

Direct the Opposite Party to refund the amount deposited by the Complainant, i.e. Rs. 68,31,679/- along with interest @18% per annum from the date of deposit till the date of paymentas compensation for deficiency in services on account of delay. In the alternative,

Direct the Opposite Party to handover possession of the apartment to the Complainant, complete in all respects, in conformity with the Provisional Allotment Letter without the cost of car parking, additional super area along with interest @18% per annum beyond the period of 39 months i.e. from June, 2014 till the date of possession.

3.

Direct the Opposite Party to provide adequate car parking space in the project for the Complainant and desist from collecting any amount for the same.

4.

2

Direct the Opposite Party to pay the Complainant adequate compensation for causing him mental agony and physical harassment resulting from a waste of his time in making umpteen visits to their office quantified at Rs. 5 lakhs and in addition to the above the Opposite Partyshould be saddled with punitive damages quantified at Rs. 5 lakhs for threatening to cancel his allotment even when he had paid 90-95% of the cost of the apartment which was rectified only after 6 months without any apology.

5.

Direct the Opposite Party to bear the increase in service tax with effect from 01.06.2015.6. Direct the Opposite Party to pay a sum of Rs.2 lakhs to the Complainant towards cost of litigation.

7.

Pass such other and further orders which this Hon'ble Commission may think fit and proper, in the facts and circumstances of the case in favour of the Complainant and against the Opposite Party.

8.

3. The Opposite Party resisted the Complaint by filing Written Statement. The Opposite Party issued a provisional allotment letter dated 31.03.2011 allotting an apartment bearing unit Reference No. K 8-1003 in "Kalypso Court" project of the Opposite Party admeasuring a Super Area of 1630 sq. ft. (151.43 sq. mtrs.) in favour of the Complainant herein. The said Provisional Allotment letter provided the total consideration of the said unit as Rs. 80,85,450/-, excluding other charges and a payment plan was also provided therein. Further, as per the request made by the Complainant by e-mail dated 10.06.2011 regarding the amendment of Provisional Allotment letter, the Opposite Party vide letter dated 30.06.2011, revised the consideration of the unit to Rs. 75,00,280/- excluding other charges. The time period for possession was provided as 36 months in the said Provisional Allotment Letter, subject to a grace period of 90 days given in the standard terms and conditions as agreed by the Complainant.

The Complainant booked the apartment in the project for speculating in the Real Estate Market, as there is no mention in the Complaint that he booked this unit for his personal use. The Complainant is not a consumer as defined in Section 2(d) of the Consumer Protection Act, 1986 and the present complaint is liable to be dismissed on this ground alone. The value of the flat booked by the Complainant was less than Rs. 1 Crore, as such this Commission did not have pecuniary jurisdiction to try this matter. Admittedly, the total value of the flat was Rs. 75,00,280/- only. Thus, the present matter did not fall within the pecuniary jurisdiction of this Commission. The Complainant had deliberately sought untenable prayers of interest to raise the claim to bring the Complaint within the pecuniary jurisdiction of this Commission. Instead, the present Complaint ought to have been filed by the Complainant before the State Commission. Thus, the Complaint be rejected on this ground alone. The present Complaint suffers with from the defect of Non-joinder of necessary and proper parties, as the present Complaint is filed against Jaiprakash Associates Ltd. only, though the Provisional Allotment Letter, is signed, executed and issued by the Jaiprakash Associate Ltd. and Jaypee Infratech Ltd.. Hence the present Complaint is liable to be dismissed on this ground also.

3

It was submitted that there is an arbitration clause No. 10.8 for amicable settlement in the agreed Standard Terms and Conditions of the Application form dated 20.11.2010 duly signed by the Complainant which provided as under:

"Dispute Resolution: any and all disputes arising out of or in connection with or in relation hereto shall so far as possible, in the first instance; be amicably settled between the company and the Applicant. In the event of disputes, claim and/or differences not amicably resolved such disputes shall be referred to sole arbitration of a person nominated for the purpose by Chairman of the Company. The proceedings of the Arbitration shall be conducted in accordance with the provisions of the Arbitration and conciliation Act 1996, as amended from time to time, or any rules made there under. The Applicant hereby gives his consent to the appointment of the sole arbitrator as specified herein above and waives any objections that he may have to such appointment or to the award that may be given by the Arbitrator. The venue for the arbitration shall be New Delhi, India". It is clarified that the applicants/complainant has to approach to amicably settle the instant issue, between the parties as provided in agreed standard terms and conditions. Therefore, the Complainant must invoke the arbitration clause after trying to amicably settle the dispute at the first instances. The Opposite Party also filed an Application under section 8, "Arbitration & Conciliation Act 1996", however the present reply has been filed to comply with the limitation provided, without prejudice to the application u/s 8, filed along with the present reply.

After issuing the Provisional Allotment Letter dated 31.03.2011, the Opposite Party carried out the development work on the said project. However for reasons beyond the control of the Opposite party i.e. due to force majeure events, such as -shortage of labour, scarcity of water, restrictions in excavations, villager agitations as well as legal impediments which continued to exist some time. The progress of the project got slow down. These facts were duly brought to the notice of Complainant, vide letter dated 06.09.2014. Due to such events the delivery of project got rescheduled. At the time of booking of subject matter apartment, it was agreed between the parties (clause 7.1 of the Standard Terms and Conditions) that in case of force majeure events, the Opposite Party would be entitled to extension of time without incurring any liability.

Clause 7.1 and 7.2 of the Standard Terms and Conditions as agreed by the prospective buyers/customers/complainant provided that:

"7.1 The Company shall make best efforts to deliver possession of the said Premises to the Applicant within the period more specifically described in the Provisional Allotment Letter with a further grace period of 90 days. If the completion of the Said Premises is delayed by reason of non-availability or scarcity of steel and/or cement and/or other building materials and/or water supply and/or electric power and/or slow down, strike and/or due to dispute with the construction agency employed by the Company, lock-out or civic commotion or any militant action or by reason of war, or enemy action, or earthquake or any act of God or if non-delivery of possession is as a result of any Law or as a result of any restrictions imposed by a Governmental Authority or delay in the sanction of building/zoning plans/grant of completion/occupation certificates by any Governmental Authority or for any other reason beyond the control of the Company (hereinafter referred to as "Force Majeure Event") the Company shall be entitled to a reasonable extension of time for delivery of possession of the said premises."

4

"7.2 Nothing contained herein shall be construed to give raise to any right to a claim by way of compensation/damages loss of profit or consequential losses against the Company on account of delay in handing over possession for any of the aforesaid conditions beyond the control of the Company. If, however, the Company fails to deliver possession of the said Premises within the stipulated period as mentioned herein above, and within the further grace period of 90 days thereafter, the Applicant shall be entitled to compensation for delay thereafter @Rs.5/- per sq. ft. (Rs. 54/- per sq. mtr.) per month for the Super area of the Said Premises ('Rebate"). The time consumed by the occurrence of Force Majeure Events shall be excluded while computing the time delay for the delivery of possession of the Said Premises".

4. Heard the Learned Counsel for the Complainant. Also carefully perused the record.

5. The Opposite Party contested that the Complainant had booked the Apartment in the project for speculating in the Real Estate Market and hence is not a Consumer as defined under the Act.

The Complainant has clearly stated in his Complaint that he was "tempted to own an apartment for his personal residence". The Complainant has also stated in his written arguments that he purchased the said Apartment "for self after marriage as his residence". No evidence has been adduced by the Opposite Party that the Complainant has generated any profit by way of trading, except the bald allegation that he brought the apartment for speculation in the Real Estate Market. The Complainant is a consumer as he sought to purchase the apartment for his personal use.

The Opposite Party further contended that as the value of booked flat was less than Rs. 1 Crore, this Commission did not have any pecuniary jurisdiction to entertain this matter. The Complainant had booked the Flat in the year 2010. The Opposite Party had itself admitted in the written statement that the total value of the flat was Rs. 75,00,280/-. The Complainant paid Rs. 68,31,679/- till the date of filing the Complaint. Approximately 10 years has already elapsed, but till date possession of the Flat has not been delivered. In Ambrish Kumar Shukla & Ors. Vs. Ferrous Infrastructure Pvt. Ltd., this Commission held that interest has to taken into account in computing pecuniary jurisdiction. After adding interest on the value of the Flat, the present Complaint would lie within the pecuniary jurisdiction of this Commission. Another point of contention is that the present Complaint suffers with the defect of Non- joinder of necessary and proper parties, as it was filed against Jaiprakash Associates Ltd. only, though the Provisional Allotment Letter is signed, executed and issued by Jaiprakash Associate Ltd. and Jaypee Infratech Ltd. As per the payment plan and receipts placed on record, it is found that all payments were made in the account of Jaiprakash Associates Ltd. only. The issue of non-joinder of parties came up before this Commission in Anish Singhal vs. Jaiprakash Associates Ltd. CC/2194/2016 decided on 01.10.2019 wherein it was held that the complaint against Jaiprakash Associates was maintainable.

The contention that as per Standard Terms and Conditions, the Complainant must invoke the arbitration clause in the first instance, Section 3 of the Consumer Protection Act provides that the Act is in addition to and in derogation of the provisions of any other law being in force. The Consumer Protection Act is a socially beneficial legislation which is in addition to the rights of a Consumer. The Complainant can, therefore, come to this Commission as an

5

alternative remedy. This issue also came up for consideration of the Hon'ble Supreme Court in National Seeds Corporation Vs. M. Madhusudhan Reddy & Anr. (2012)2SCC 506 whereby it was held that the Complaint filed by a s Consumer before the Consumer Fora would be maintainable, despite there being an arbitration clause in the agreement to refer the dispute to the Arbitrator.

The Opposite Party also contended that at the time of booking of the apartment, it was agreed between the parties that in case of force majeure events, the Opposite Party would be entitled to extension of time without incurring any liability. Possession of the flat has not yet been delivered to the Complainant. The Opposite Party has not provided any evidence in support of the reasons adduced by the Opposite Party. There being no evidence as to unforeseen and unexpected events which prevented the development of the allotted unit, the Opposite Party cannot take shelter of the force majeure clause. A person cannot be made to wait indefinitely for the possession of the flats allotted to him/her. The reasons stated for force majeure conditions are only delay tactics to handover possession of the Apartment. The Complainant is, therefore, entitled to seek the refund of the amount paid by him along with compensation.

6. In view of the above, the Opposite Party is directed to refund the amount deposited/paid by the Complainant with simple interest of 10% per annum with effect from the respective date of each payment, till the date of refund with compensation. Further, the Opposite Party is directed to pay Rs. 25,000/- towards cost of litigation. Payments in terms of this order shall be made within three month from today.

......................J

DEEPA SHARMA

PRESIDING MEMBER

......................

C. VISWANATH

MEMBER

6