- Bookmark
- Share
- CaseIQ
D.B. Power Ltd. v. Tamil Nadu Generation And Distribution Corporation Ltd. .
Factual and Procedural Background
The Petitioner, DB Power Ltd., a generating company under the Electricity Act, 2003, established a 1200 MW coal-based thermal power plant in Chhattisgarh. The Respondent is a Distribution Licensee in Tamil Nadu. On 19.8.2013, the Petitioner entered into a Power Purchase Agreement (PPA) to supply 208 MW of electricity to the Respondent, with supply commencing on 1.8.2015.
The PPA required the Respondent to pay monthly bills within 30 days of receipt. Failure to pay on time attracted a Late Payment Surcharge (LPS) at the rate of SBI-PLR per annum on outstanding amounts, calculated daily and compounded monthly. The Petitioner raised LPS claims accumulated as on 20.1.2016, acknowledged by the Respondent on 7.2.2017, who expressed inability to pay due to financial difficulties and requested waiver of the surcharge. Communications continued without resolution.
The Petition was filed seeking directions for payment of LPS up to December 2018, citing financial distress caused by non-payment, including difficulties in loan repayments and risk of project becoming a Non-Performing Asset (NPA) leading to operational shutdown.
The Commission admitted the Petition on 5.3.2019 and directed the Respondent to file a reply, which was not submitted. The matter was disposed based on the available record.
Legal Issues Presented
- Whether the Respondent is liable to pay the Late Payment Surcharge along with interest as claimed by the Petitioner under the terms of the Power Purchase Agreement?
Arguments of the Parties
Petitioner's Arguments
- The PPA explicitly provides for payment of monthly bills by the due date and imposes a Late Payment Surcharge at SBI-PLR rate for delayed payments, calculated daily and compounded monthly.
- The Respondent delayed payments and acknowledged the LPS liability but failed to discharge it due to financial constraints.
- Repeated requests and supplementary bills were issued by the Petitioner seeking payment of LPS, which the Respondent refused or requested waiver for.
- Non-payment of dues caused financial stress, forcing the Petitioner to borrow additional working capital loans, increasing costs and risking default on project loans.
- The Petitioner's project is listed as a stressed asset, and continued non-payment threatens shutdown and further financial harm.
- The Petitioner seeks payment of Rs. 95,99,76,788.87 towards LPS up to December 2018, along with interest at 18% p.a. from due dates till actual payment, or at least an interim payment of Rs. 71.49 crores.
Respondent's Position
- The Respondent did not dispute the liability for Late Payment Surcharge under the PPA.
- Due to acute financial difficulties, the Respondent expressed inability to pay the dues and requested waiver of the surcharge.
- The Respondent paid Rs. 20 crore as directed by the Commission but did not file a formal reply to the Petition.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Commission examined the terms of the PPA, which clearly stipulated payment of monthly bills by the due date and imposed a Late Payment Surcharge at SBI-PLR per annum on delayed payments, calculated daily and compounded monthly. The Respondent acknowledged the surcharge liability but failed to pay due to financial constraints.
The Commission noted the Respondent’s failure to file a reply despite directions and the partial payment of Rs. 20 crore. It found the Respondent in default of payment of the Late Payment Surcharge as per the PPA terms.
The Commission held that the interest on unpaid Late Payment Surcharge is governed by the PPA provisions, which already provide for compounding at SBI-PLR rate monthly. The claim for additional interest at 18% p.a. was not accepted separately since the PPA terms cover the interest component.
The Commission also observed that repeated defaults by the Respondent entitle the Petitioner to regulate the power supply under the CERC (Regulation of Power Supply) Regulations, 2010.
Accordingly, the Commission directed the Respondent to pay the remaining Late Payment Surcharge within three months after reconciliation of bills.
Holding and Implications
The Commission disposed of Petition No. 22/MP/2019 directing the Respondent to pay the outstanding Late Payment Surcharge within three months from the date of the order after reconciliation with the Petitioner.
The Commission held that the interest on unpaid surcharge is governed by the PPA at SBI-PLR rate compounded monthly and rejected the claim for 18% p.a. interest separately.
The decision enforces the contractual obligation of the Respondent to pay delayed surcharge and provides the Petitioner with a remedy for recovery, including the option to regulate power supply in case of continued default. No new legal precedent was established; the ruling is confined to enforcement of existing contractual and regulatory provisions.
The Petitioner, DB Power Ltd., is a generating company within the meaning of clause (2) of Section 28 of the Electricity Act, 2003 (the Act). The Petitioner has set up Order in Petition No. 22/MP/2019 Page 2 of 8 a 1200 MW (2600 MW) coal based Thermal Power plant at village Badadarha, in District Janjgir Champa, Chhattisgarh. The Respondent is a Distribution Licensee in the State of Tamil Nadu within the meaning of clause (17) of section 2 of the Act. On 19.8,2013, the petitioner entered into agreement to supply 208 MW of electricity to the Respondent and has been supplying power with effect from 1.8.2015. Background
2. The brief facts of the case are as follows:
a) That PPA provides for payment of Monthly Bills to the Petitioner for the power supplied to the Respondent, by due date which is 30th day after a Monthly Bill or a Supplementary Bill is received and duly acknowledged by the Procurer (Respondent);
b) PPA further provides remedy on failure to make monthly payment by due date that a Late Payment Surcharge shall be payable by the Respondent to the Petitioner at the rate equal to SBI-PLR per annum, on the amount of outstanding payment, calculated on day to day basis (and computed with monthly rest), for each day of delay;
c) In the instant case, the petitioner has raised Late Payment Surcharge accumulated as on 20.1.2016 which was acknowledged by the Respondent on 7.2.2017 but the Respondent expressed its inability on account of its acute financial position and requested the Petitioner to withdraw the demand. Subsequently, communications were exchanged between the petitioner and the Respondents.
d) The petitioner has also submitted the difficulty in its loan repayment to the project lenders which has caused the project non-performing assets leading to shutdown of operations. Order in Petition No. 22/MP/2019 Page 3 of 8
e) The present petition is filed by the petitioner seeking directions to the Respondent for making late payment surcharge up to December, 2018.
3. The main prayers of the Petitioner are as under: a. Direct the Respondent to pay an amount of Rs. 95,99,76,788.87 due towards the Late Payment Surcharge up to December, 2018 to the Petitioner along with interest @18% p.a. from the Due Dates of payment of the respective Monthly Bills till the date of actual payment by the Respondent; b. In the interim, pending final adjudication of the present Petition, direct the Respondents to forthwith make payment of Rs. 71.49 crores i.e. 75% of the amount due towards the Late Payment Surcharge uptil December, 2018; c. Pass any such other and further reliefs as this Honble Commission deems just and proper in the nature and circumstances of the present case.
4. The Petition was admitted on 5.3.2019. The Commission directed respondent to file its reply vide Record of proceedings dated 5.3.2019, 7.5.2019 and 21.8.2019. However, the Respondent has not filed its reply. Accordingly, we proceed to dispose the petition based on available information on record. Submission of the Petitioner
5. The petitioner vide affidavit dated 21.1.2019 submitted as under:
a) That Article 8.3 of the PPA provides for payment of Monthly Bills by the Due Date to the Petitioner which is defined in Article 1.1 of the PPA. Article 8.3.5 of the PPA provides that in the event of delay in payment of a Monthly Bill by the Respondent beyond its Due Date, a Late Payment Surcharge shall be payable by the Respondent to the Petitioner at the rate equal to SBI-PLR per annum, on the amount of outstanding payment, calculated on day to day basis (and computed with monthly rest), for each day of delay.
b) The Respondent has delayed the payment of Petitioners Monthly Bills beyond their respective Due Dates and the petitioner vide its letter dated 22.1.2016 pointed out the delay in making payment of Monthly Invoices by the Respondent and gave the details of interest (Late Payment Surcharge) accumulated as on Order in Petition No. 22/MP/2019 Page 4 of 8 20.1.2016 and subsequent letters dated 17.3.2016, 14.10.2016, 21.11.2016 and 30.11.2016.
c) Respondent vide its letter dated 7.2.2017 responded to the petitioner and expressed its inability to pay the dues on account of its acute financial position and requested the Petitioner to withdraw the demand. The Petitioner vide its letter dated 13.2.2017 to the Respondent, sought payment of late payment surcharge. The Petitioner provided the details of the Supplementary Bills for Late Payment Surcharge for the period from March, 2016 to January, 2017. The petitioner wrote various letters dated 18.1.2017, 29.8.2017 and 12.10.2017 seeking payment of late payment surcharge. The Respondent vide letter dated 27.11.2017 again expressed its inability to discharge its liability and requested the Petitioner for waiver of late payment surcharge.
d) The Petitioner pointed out that delay in payment of Bills by the Respondent was compelling the Petitioner to avail higher borrowing from the lenders towards working capital thereby increasing the burden of interest and associated cost on the Petitioner and causing financial stress to the Petitioner.
e) The petitioner vide its letters dated 12.2.2018, 10.4.2018 to the Respondent giving updated details of the Supplementary Bills raised by the Petitioner for Late Payment Surcharge on the Respondent totaling to an amount of Rs. 53,45,58,384.00, requested the Respondent to clear the dues so as to enable the Petitioner to pay the interest bearing working capital loan taken by the Petitioner from the Banks. Vide its letter dated 4.1.2019, the Petitioner submitted details of pending Late Payment Surcharge amounting to Rs. 95,99,76,788.87 and Order in Petition No. 22/MP/2019 Page 5 of 8 requested the Respondent for reconciliation of bills and payments from 1.8.2015 till 4.1.2019.
f) The petitioner submits that though the Respondent has clearly acknowledged the said liability, but has refused to discharge the same. Therefore, the Respondent is liable to be directed by this Commission to forthwith discharge its admitted liability by making payment of the outstanding dues to the Petitioner, as per the details furnished by the Petitioner vide its letter dated 4.1.2019.
g) The petitioner submits that the Petitioners asset is on the verge of becoming a Non-Performing Asset due to non-servicing of the debt to the Project lenders. On account of non-payment by the Respondent, the Petitioner is further constrained to borrow funds from banks/institutions, working capital loans for payment of the said taxes and duties and increased price of coal on account of change in law in order to operate and run the plant to supply electricity to the Respondent.
h) According to petitioner, the claim made by the Petitioner under this Petition, in terms of the PPA entered between the parties has been admitted by the Respondent. If the Respondent does not clear the dues in the terms of the PPA, the Petitioner will continue to suffer irreparable harm and injury and would default in its loan repayment to the project lenders resulting in its project being declared as a Non-Performing Asset. This would then result in shutting down the operations of the Petitioners Company leading to further cascading effects and dire consequences. The Petitioners project is in the list of stressed projects submitted by the Ministry of Finance, Government of India in July, 2018.
6. The learned counsel of the Respondent has not objected to the liability of Late Payment Surcharge in terms of PPA. On 7.5.2019, the Commission directed the Order in Petition No. 22/MP/2019 Page 6 of 8 Respondent to pay part amount of Rs 20 Cr in two weeks. The counsel of the Respondent submitted that due to financial crunch, it is not able to pay the outstanding dues but the Respondent will pay Rs. 20 Cr to the Petitioner within two weeks. Therefore, the issue whether the Respondent is liable for late payment surcharge as per PPA is not under dispute.
7. Thus, the issue which is required to be examined is: Issue: Whether the Respondent is liable for Late Payment Surcharge along with the interest as claimed by the Petitioner in terms of the PPA?
8. In the present case the Petitioner has claimed pending dues towards Late Payment Surcharge amounting to Rs. 95,99,76,788.87/- (approximately rupees Ninety Six crores) from the date of Power supply started i.e. 1.8.2015 till 31.12.2018. The Power Purchase Agreement between the Petitioner and the Respondent was signed on 19.8.2013. The relevant extract of the PPA dated 19.8.2013 in regard to Late Payment Surcharge are as under: 8.3 Payment of Monthly Bills 8.3.1 The Procurer shall pay the amount payable under the Monthly Bill on the Due Date to such account of the Seller, as shall have been previously notified by the Seller in accordance with Article 8.3.4 below. 8.3.2 All payments made by the Procurer shall be appropriated by the Seller In the following order of priority:
i) towards Late Payment Surcharge, if any; ii) towards the earlier unpaid Monthly Bill(s), if any; and iii) towards the then current Monthly Bill. xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx 8.3.5 In the event of delay in payment of a Monthly Bill by the Procurer beyond its Due Date, a Late Payment Surcharge shall be payable by such Procurer to the Seller at the rate equal to SBI-PLR per annum, on the amount of outstanding payment, calculated on a day to day basis (and compounded with monthly rest), for each day of the delay. The Late Payment Surcharge shall be claimed by the Seller through the Supplementary Bill. Order in Petition No. 22/MP/2019 Page 7 of 8
9. It is evident from the Respondent letters dated 7.2.2017 and 27.11.2017 that though the Respondent was aware of the Petitioners claim towards Late Payment Surcharge, it could not pay the Late Payment Surcharge due to its financial crunch. Through the said letters, Respondent requested the Petitioner for waiver of the Surcharge claimed. The Commission, vide Record of Proceedings dated 5.3.2019, 7.5.2019 and 21.8.2019 directed the Respondent to file its reply. However, Respondent has not filed its reply inspite of Commissions direction. The Commission vide Record of Proceedings dated 7.5.2019 directed the Respondent to pay Rs. 20 Cr to the Petitioner, which has been paid and the same has been confirmed by the Petitioner on 21.8.2019.
10. In view of the above discussion, it is evident that Respondent is under default of payment towards Late Payment Surcharge in terms of the PPA. The extract of Article 8.8 of the PPA in regard to payment of Supplementary bills is as under: Payment of Supplementary Bill 8.8.1 Either Party may raise a bill on the other Party (Supplementary Bill) for payment on account of;
i) Adjustments required by the Regional Energy Accounts (If applicable); ii) Tariff Payment for change in parameters, pursuant to provisions in schedule 4; or iii) Change in Law as provided in Article 10, and such Supplementary Bill shall be paid by the other Party. 8.8.3 In the event of delay in payment of a supplementary Bill by either Party beyond its Due Date, a Late Payment Surcharge shall be payable at the same terms applicable to the Monthly Bill in Article 8.3.5.
11. Accordingly, Respondent is directed to pay the remaining amount under Late Payment Surcharge claimed by the Petitioner within three month from the date of issue of this order, after reconciliation of bills with the Petitioner. However, with regard to Petitioners prayer for directing the Respondent to pay the Late Payment Surcharge along with interest @18%, it is held that interest on non-paid Late Payment Surcharge is covered by the provisions of PPA as quoted above which takes care of compounding on Order in Petition No. 22/MP/2019 Page 8 of 8 monthly basis at the rate of SBI-PLR as quoted in PPA. Further, on repeated default of payment by the Respondent, Petitioner has the option to regulate the power of the Respondent in terms of CERC (Regulation of Power Supply) Regulations, 2010.
12. Petition No. 22/MP/2019 is disposed of in terms of above. Sd/- Sd/- Sd/- (I.S. Jha) (Dr. M. K. Iyer) (P. K. Pujari) Member Member Chairperson
Alert