Anand Karunakaran v. Union Of India

National Green Tribunal
Jan 7, 2019

During the course of hearing of the case, we have been informed that EAC(Violation Committee) has observed that the SEIAA Haryana has already taken cognizance and issued show cause notice to the project proponent on 04.12.2017. Therefore the Committee has decided that the proceedings before the SEIAA be concluded.

The Learned Counsel for SEIAA submits that prosecution has already been recommended against the project proponent. Further he submits that an application for revising the Environment Clearance has already been submitted by the project proponent. The Haryana State Pollution Control Board has also issued a show cause notice to the project proponent on 05.12.2018.

In view of the above facts and circumstances, we deem it proper to direct the aforesaid authorities i.e. SEIAA, Haryana/HSPCB to conclude the proceedings, after considering all the alleged violation which are said to have been committed by the project proponent. This exercise shall be completed at the earliest, preferably, with a period of two months.

Accordingly, the original application (602/2016) stands disposed of, with no order as to cost.

M.A. Nos. 1147/2016 and 1474/2017

These misc. applications do not survive for consideration as the main application itself stands disposed of.

Accordingly, misc. application nos. 1147/2016 & 1474/2017 stand disposed of.