Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

State Of Jharkhand And Others v. Hss Integrated Sdn And Another

Supreme Court Of India
Oct 18, 2019
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The dispute arises out of a consultancy agreement dated 28-08-2007 between the petitioner-State and a consortium (respondents) for supervision of the six-lane Ranchi Ring Road project. The contract, originally for 36 months (01-10-2007 to 30-09-2010), was twice extended. Alleging deficiencies, the Executive Engineer issued a letter on 25-11-2011 warning of suspension of payments under Clause 2.8 of the General Conditions of Contract (GCC). After exchanges of correspondence, the State invoked Clause 2.8 on 12-12-2011, and later terminated the contract on 09-02-2012 (effective 12-03-2012) under Clauses 2.9.1(a) and (d).

The consortium treated the termination as illegal, served a legal notice on 10-03-2012, and invoked arbitration. An Arbitral Tribunal comprising party nominees and a retired High Court Judge as presiding arbitrator was constituted. The claimants sought ₹5,17,88,418 (13 heads); the State filed counter-claims of ₹6,00,78,736 (5 heads).

The Tribunal found the termination illegal, awarded ₹2,10,87,304 (plus interest) to the claimants, and rejected the State’s counter-claims. Challenges under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996 failed before the District Court and the Jharkhand High Court (Commercial Appeal No. 1 of 2018; judgment dated 30-01-2019, 2019 SCC OnLine Jhar 172). The State then filed the present Special Leave Petition (SLP) before the Supreme Court.

Legal Issues Presented

  1. Whether the Arbitral Tribunal’s finding that the contract termination was illegal and procedurally flawed warranted interference under Sections 34 and 37 of the Arbitration Act.
  2. Whether the concurrent awards and judgments upholding the respondents’ monetary claims and rejecting the State’s counter-claims suffered from perversity, patent illegality or breach of public policy so as to justify intervention by the Supreme Court in an SLP.

Arguments of the Parties

Petitioners’ Arguments (State)

  • The arbitral award was contrary to the material on record; the High Court failed to appreciate this error.
  • Clause 2.8 involved suspension of payments only, not suspension of work; hence the contractual sequence (suspension → termination) was properly followed and termination was valid.
  • The High Court wrongly affirmed the Tribunal’s conclusion that due procedure was not followed.

Respondents’ Arguments (Consortium)

  • All three forums—the Tribunal, the Section 34 court, and the High Court—returned concurrent factual findings that the termination was illegal.
  • Under settled law, courts cannot interfere with plausible arbitral findings unless they are perverse or violate public policy.
  • Reliance was placed on Associate Builders v. DDA, NHAI v. Progressive-MVR (JV), and MSEDCL v. Datar Switchgear to underline judicial restraint in reviewing arbitral awards.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Associate Builders v. Delhi Development Authority (2015) 3 SCC 49 Scope of interference with arbitral awards—limited to perversity, patent illegality, or conflict with public policy. Reaffirmed that none of these grounds existed in the present case, hence no interference was warranted.
NHAI v. Progressive-MVR (JV) (2018) 14 SCC 688 When two plausible views exist, the arbitral view should be respected under Section 34. Cited to support deference to the Tribunal’s plausible findings on contractual termination.
Maharashtra State Electricity Distribution Co. Ltd. v. Datar Switchgear Ltd. (2018) 3 SCC 133 Arbitral Tribunal is the master of evidence; factual findings are not to be re-appraised as on appeal. Relied upon to decline re-evaluation of evidence concerning performance and termination.

Court’s Reasoning and Analysis

The Supreme Court noted that the Tribunal, after examining contractual clauses and evidence (paras 17-36 of the award), concluded that the State failed to follow the prescribed procedure before termination. Both the Section 34 court and the High Court upheld this conclusion, resulting in concurrent findings of fact.

Drawing on Progressive-MVR and Datar Switchgear, the Court reiterated that arbitral findings which are plausible, evidence-based, and not perverse are immune from judicial interference. The Court further observed that:

  • The Tribunal’s analysis of the contract and sequence of suspension/termination steps was reasoned and supported by evidence.
  • The award partially allowed some claims and disallowed others, demonstrating careful application of mind.
  • No violation of public policy, patent illegality, or perversity was shown by the petitioners.

Consequently, there was no scope to upset the concurrent determinations under Sections 34 and 37.

Holding and Implications

SLP DISMISSED.

Immediate effect: the arbitral award of ₹2.10 crore (plus interest) in favour of the consortium stands, and the State’s counter-claims remain rejected. Broader implication: the judgment reinforces the Supreme Court’s consistent stance that it will not disturb well-reasoned arbitral awards upheld by lower courts unless statutory grounds of interference are clearly met; no new legal precedent was created.

Show all summary ...

M.R. Shah, J.— Aggrieved by the impugned judgment and order dated 30-1-2019 2019 SCC OnLine Jhar 172 passed by the High Court of Jharkhand at Ranchi in Commercial Appeal No. 1 of 2018, by which the High Court has dismissed the said appeal preferred by the petitioners herein under Section 37 of the Arbitration and Conciliation Act, 1996 (for short “the Arbitration Act”) and has confirmed the award declared by the learned Arbitral Tribunal, confirmed by the first appellate court, the original appellants have preferred the present special leave petition.

2. This special leave petition arises out of the contractual dispute between the petitioner State and the respondents in relation to a consultancy agreement over construction of six lane divided carriage way of certain parts of Ranchi Ring Road. Respondents 1 and 2 acted as a consortium for providing such consultancy and supervisory services. An agreement was entered into between the parties on 28-8-2007. The original work period under the said agreement was for 36 months i.e. from 1-10-2007 to 30-9-2010. There was a dispute with respect to the non-performance and unsatisfactory work done by the respondents. However, the respondents were granted extension of contract twice. Thereafter, a letter dated 25-11-2011 was issued by the Executive Engineer to the respondents and other contractors entrusted with the task of construction, granting a second extension of time of contract for construction work. The respondents were called upon to make compliances with the issues pointed out, at the earliest. In the said communication dated 25-11-2011, it was stated that if the deficiencies are not removed and/or complied with, in that case, there shall be suspension of payment under Clause 2.8 of the General Conditions of Contract (for short “GCC”). On 5-12-2011, a review meeting was held between the parties, followed by a letter dated 7-12-2011 issued by the respondent-original claimants in reply to compliance with the aforesaid letter dated 25-11-2011. It was the case on behalf of the respondent-original claimants that without properly considering the said letter of the respondent-original claimants dated 7-12-2011, the petitioners herein issued letter dated 12-12-2011 invoking Clause 2.8 of GCC for suspension of payment, alleging certain deficiencies. It was the case on behalf of the respondent-original claimants that by letter dated 27-12-2011, they replied to the suspension notice and complied with the deficiencies. In reply to the aforesaid letters, the petitioners issued letters dated 23-12-2011 and 28-12-2011 asking the claimants to ensure compliance with the pending issues. That by letter/communication dated 9-2-2012, the petitioners served a notice upon the respondents terminating the contract with effect from 12-3-2012. The said termination notice was issued under Clauses 2.9.1(a) and (d) of GCC. The respondent-original claimants replied to the said termination notice by letters dated 16-2-2012 and 24-2-2012 and requested the petitioners to re-consider the matter. However, the dispute between the parties was not resolved. The respondent-original claimants served a legal notice dated 10-3-2012 and invoked Arbitration Clause 2.9.1(a). Pursuant to the order passed by the High Court, the Arbitral Tribunal was constituted.

2.1. The Arbitral Tribunal comprised of nominees of the rival parties and a retired Judge of the Jharkhand High Court as the presiding arbitrator. The respondent-original claimants claimed a total sum of Rs 5,17,88,418 under 13 different heads, excluding interest. The petitioners also filed a counterclaim for Rs 6,00,78,736 under five heads. The claim of the original claimants primarily involved the unpaid amount in respect of the work executed under the contract, loss of profit and overhead charges, apart from other consequential claims arising out of termination. It was the specific case on behalf of the original claimants that the termination was absolutely illegal and not being in accordance with the terms of the contract. The counterclaim filed by the petitioner State was for reimbursement on account of unsatisfactory performance by the respondents.

2.2. That, on appreciation of evidence, the learned Arbitral Tribunal gave a specific finding that the termination of the contract was illegal and without following the procedure as required under the contract (paras 17 to 36). That, thereafter the learned Arbitral Tribunal proceeded to consider the claims on merits and ultimately allowed the claims to the extent of Rs 2,10,87,304 under different heads as under:

Claims Amount Allowed Comments Claim 1-A — Claim unpaid bills from 1-11-2011 to 28-2-2012 53,37,294 50,59,957 Partly allowed Claim 1-B — Claim due/Unpaid against bills from Oct 2007 to Oct 2011 79,04,819 67,07,032 Partly allowed Claim 1-C — Claim against design of bridges 8,30,000 8,30,000 Allowed Total Claim 1 1,40,72,113 1,25,96,989 Claim 2 — Invoice for the month of March 2012 (month of termination) 11,05,954 11,05,954 Allowed Claim 3 — Claim towards shifting of office from Ranchi to site 1,57,000 - Disallowed Claim 4 — Claim towards laboratory set up at site 4,41,000 - Disallowed Claim 5 — Demobilisation of staff 5,00,000 - Disallowed Claim 6 — Bank guarantee charge for extended period 33,730 - Disallowed
Claim 7 — Claim towards cost incurred to submit record to EE in person 1,28,500 - Disallowed Claim 8 — Loss of profit (for 24 months extension period) 1,18,54,639 19,75,733 Partly allowed Claim 9 — Claim against encashment of BG 14,08,765 13,90,000 Partly allowed Claim 10 — Claim towards solicitor and advocates payments 3,06,200 Claim 11 — Claim towards arbitration cost 10,00,000 10,00,000 Partly allowed Claim 12 — Staff maintenance fee (3 months' notice pay only) 17,97,084 - Disallowed Claim 13 — Claim towards inability to bid for projects bad reputation 50,00,000 - Disallowed Interest claimed as per contract beyond 60 days of invoice submission 1,39,89,633 30,18,588 Interest @ 12% from the date when Tribunal got constituted. Total of claims & allowed (Indian Rupees) 5,17,94,618 2,10,94,304 % amount allowed 40.71

2.3. In view of the finding arrived at by the learned Arbitral Tribunal that the termination of the contract was illegal and without following due procedure as required under the contract and in view of allowing the claims of the claimants partly, the Arbitral Tribunal dismissed the counterclaims submitted by the petitioners.

2.4. The award declared by the learned Arbitral Tribunal has been confirmed by the first appellate court in a proceeding under Section 34 of the Arbitration Act. The same has been further confirmed by the High Court by the impugned judgment and order 2019 SCC OnLine Jhar 172 in an appeal under Section 37 of the Arbitration Act.

2.5. Feeling aggrieved and dissatisfied with the impugned judgment and order 2019 SCC OnLine Jhar 172 passed by the High Court dismissing the appeal under Section 37 of the Arbitration Act and consequently confirming the award passed by the learned Arbitral Tribunal, the original respondent State and others have preferred the present special leave petition.

3. The learned counsel appearing on behalf of the petitioners has vehemently submitted that the High Court has materially erred in dismissing the appeal under Section 37 of the Arbitration Act and has materially erred in not properly appreciating the fact that the arbitral award was passed contrary to the materials on record.

3.1. It is vehemently submitted by the learned counsel appearing on behalf of the petitioners that the High Court has materially erred in not properly considering that the suspension under the agreement was not the suspension of work per se, rather was suspension of all payments to the consultants and therefore there was no question of dilution/go-by of the suspension letter. It is further submitted by the learned counsel appearing on behalf of the petitioners that the High Court has not properly appreciated/considered the scheme of the contract. It is submitted that in case of non-performance of the contract satisfactorily, the first step was suspension of payment and if the failure in performance is not remedied, then the consequence which follows is the next step that being notice of termination by issuing 30 days' notice. It is submitted that suspension is either operative or revoked by resuming the payments, for, suspension is suspension of payment and not suspension of work/contract. It is submitted that therefore the High Court has materially erred in confirming the findings recorded by the learned Arbitral Tribunal that the termination of the contract was illegal and without following due procedure as required under the contract.

4. While opposing the present special leave petition, the learned counsel appearing on behalf of the respondent-original claimants has vehemently submitted that, as such, there are concurrent findings of fact recorded by all the courts below on the illegal termination of the contract. It is submitted that, on appreciation of evidence, the learned Arbitral Tribunal (in paras 17 to 36) gave the specific findings by giving cogent reasons that the termination of the contract was illegal and without following due procedure as required under the contract. It is submitted that once the findings recorded by the learned Arbitral Tribunal are on appreciation of evidence and considering the materials on record, the same is rightly not interfered with by the courts below in the proceedings under Sections 34 and 37 of the Arbitration Act.

4.1. Making the above submissions and relying upon the decisions of this Court in Associate Builders v. DDA (2015) 3 SCC 49, NHAI v. Progressive-MVR (JV) (2018) 14 SCC 688 and Maharashtra State Electricity Distribution Co. Ltd. v. Datar Switchgear Ltd. (2018) 3 SCC 133, it is prayed to dismiss the present special leave petition.

5. Heard the learned counsel appearing on behalf of the respective parties at length.

6. The main controversy is with respect to the termination of the contract vide letter/communication dated 9-2-2012 terminating the contract with effect from 12-3-2012 invoking Clauses 2.9.1(1) and (d) of GCC. That, on appreciation of evidence and considering the various clauses of the contract, the learned Arbitral Tribunal has observed and held by giving cogent reasons that the termination of the contract was illegal and contrary to the terms of the contract and without following due procedure as required under the relevant clauses of the contract. The said finding of fact recorded by the learned Arbitral Tribunal is on appreciation of evidence. The said finding of fact has been confirmed in the proceedings under Sections 34 and 37 of the Arbitration Act. Thus, there are concurrent findings of fact recorded by the learned Arbitral Tribunal, first appellate court and the High Court that the termination of the contract was illegal and without following due procedure as required under the relevant provisions of the contract.

6.1. In Progressive-MVR (2018) 14 SCC 688, after considering the catena of decisions of this Court on the scope and ambit of the proceedings under Section 34 of the Arbitration Act, this Court has observed and held that even when the view taken by the arbitrator is a plausible view, and/or when two views are possible, a particular view taken by the Arbitral Tribunal which is also reasonable should not be interfered with in a proceeding under Section 34 of the Arbitration Act.

6.2. In Datar Switchgear Ltd. (2018) 3 SCC 133, this Court has observed and held that the Arbitral Tribunal is the master of evidence and the findings of fact which are arrived at by the arbitrators on the basis of the evidence on record are not to be scrutinised as if the Court was sitting in appeal. In para 51 of the judgment, it is observed and held as under:

“51. Categorical findings are arrived at by the Arbitral Tribunal to the effect that insofar as Respondent 2 is concerned, it was always ready and willing to perform its contractual obligations, but was prevented by the appellant from such performance. Another specific finding which is returned by the Arbitral Tribunal is that the appellant had not given the list of locations and, therefore, its submission that Respondent 2 had adequate lists of locations available but still failed to install the contract objects was not acceptable. In fact, on this count, the Arbitral Tribunal has commented upon the working of the appellant itself and expressed its dismay about lack of control by the Head Office of the appellant over the field offices which led to the failure of the contract. These are findings of facts which are arrived at by the Arbitral Tribunal after appreciating the evidence and documents on record. From these findings it stands established that there is a fundamental breach on the part of the appellant in carrying out its obligations, with no fault of Respondent 2 which had invested whopping amount of Rs 163 crores in the project. A perusal of the award reveals that the Tribunal investigated the conduct of the entire transaction between the parties pertaining to the work order, including withholding of DTC locations, allegations and counter-allegations by the parties concerning installed objects. The arbitrators did not focus on a particular breach qua particular number of objects/class of objects. Respondent 2 is right in its submission that the fundamental breach, by its very nature, pervades the entire contract and once committed, the contract as a whole stands abrogated. It is on the aforesaid basis that the Arbitral Tribunal has come to the conclusion that the termination of contract by Respondent 2 was in order and valid. The proposition of law that the Arbitral Tribunal is the master of evidence and the findings of fact which are arrived at by the arbitrators on the basis of evidence on record are not to be scrutinised as if the Court was sitting in appeal now stands settled by a catena of judgments pronounced by this Court without any exception thereto. (2015) 3 SCC 49, (1981) 3 SCC 260”

7. As held by this Court in a catena of decisions, the award passed by the Arbitral Tribunal can be interfered with in the proceedings under Sections 34 and 37 of the Arbitration Act only in a case where the finding is perverse and/or contrary to the evidence and/or the same is against the public policy. (See Associate Builders v. DDA (2015) 3 SCC 49, etc.)

7.1. In the present case, the categorical findings arrived at by the Arbitral Tribunal are to the effect that the termination of the contract was illegal and without following due procedure of the provisions of the contract. The findings are on appreciation of evidence considering the relevant provisions and material on record as well as on interpretation of the relevant provisions of the contract, which are neither perverse nor contrary to the evidence in record. Therefore, as such, the first appellate court and the High Court have rightly not interfered with such findings of fact recorded by the learned Arbitral Tribunal.

7.2. Once it is held that the termination was illegal and thereafter when the learned Arbitral Tribunal has considered the claims on merits, which basically were with respect to the unpaid amount in respect of the work executed under the contract and loss of profit. Cogent reasons have been given by the learned Arbitral Tribunal while allowing/partly allowing the respective claims. It is required to be noted that the learned Arbitral Tribunal has partly allowed some of the claims and even disallowed also some of the claims. There is a proper application of mind by the learned Arbitral Tribunal on the respective claims. Therefore, the same is not required to be interfered with, more particularly, when in the proceedings under Sections 34 and 37 of the Arbitration Act, the petitioners have failed.

8. Once the finding recorded by the learned Arbitral Tribunal that the termination of the contract was illegal is upheld and the claims made by the claimants have been allowed or allowed partly, in that case, the counterclaim submitted by the petitioners was liable to be rejected and the same is rightly rejected. No interference of this Court is called for.

9. In view of the above and for the reasons stated above, the present special leave petition deserves to be dismissed and is accordingly dismissed. However, in the facts and circumstances of the case, there will be no order as to costs.