Vishal Jain And Others v. Competent Authority And Others
Factual and Procedural Background
The present writ appeal arises from the order dated 05.12.2018 passed in W.P. No. 18451/2018. The learned Single Judge disposed of the writ petition relying on the judgment in Nirbhay Singh v. Competent Authority. The case concerns the acquisition of land under the National Highways Act, 1956, for the widening of National Highway Number 3. The petitioner owned land in Village Rojwas, Tehsil Tarana, District Ujjain, which was acquired by the Government of India through notifications issued under various sections of the National Highways Act, 1956. Compensation was assessed and awarded under the provisions of the National Highways Act, 1956, and the amount was deposited directly into the petitioner’s bank account.
Subsequently, the petitioner sought compensation under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the “Act of 2013”), relying on the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Removal of Difficulties) Order, 2015 (“Order 2015”), which extended certain benefits of the 2013 Act to land acquisitions under enactments listed in the Fourth Schedule, including the National Highways Act, 1956. The competent authority (SDO) rejected the petitioner’s representation for enhanced compensation under the 2013 Act, leading to the writ petition before the High Court.
Legal Issues Presented
- Whether the compensation awarded under the National Highways Act, 1956, can be enhanced or re-determined under the provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, as extended by the 2015 Removal of Difficulties Order?
- Whether the provisions of Section 24 of the 2013 Act apply to acquisition proceedings initiated and completed under the National Highways Act, 1956?
- Whether the petitioner can seek remedy under Section 3G(5) of the National Highways Act, 1956, for enhancement of compensation in light of the 2015 Order?
Arguments of the Parties
Petitioner’s Arguments
- The petitioner contended that since the 2015 Removal of Difficulties Order came into effect on 01.09.2015, the compensation award dated 18.12.2015 should have been made under the provisions of the 2013 Act rather than the National Highways Act, 1956.
- The petitioner relied on Section 24 of the 2013 Act, which provides that pending land acquisition proceedings are to be continued under the 2013 Act.
- Additionally, the petitioner placed reliance on judgments by the Bombay High Court in Vishwasrao Dattatray Kachare v. Union of India and the Karnataka High Court in Lalita v. Union of India supporting the applicability of the 2013 Act.
Respondents’ Arguments
- The respondents argued that the acquisition proceedings, including notifications and award, were initiated and completed under the National Highways Act, 1956, prior to the applicability of the 2013 Act provisions.
- Section 24 of the 2013 Act applies only to proceedings under the Land Acquisition Act, 1894, and not to those under the National Highways Act, 1956, which does not provide for lapse of proceedings.
- The respondents contended that enhancement of compensation under the 2013 Act provisions can only be considered by an arbitrator under Section 3G(5) of the National Highways Act, 1956, and not through the writ petition.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Nirbhay Singh v. Competent Authority | Clarification on the applicability of the 2015 Removal of Difficulties Order and the procedure for land acquisition compensation under the National Highways Act, 1956. | The Court relied on this judgment to confirm that the award passed under the National Highways Act, 1956, prior to the 2015 Order coming into force, could not be re-opened under the 2013 Act provisions. |
| Vishwasrao Dattatray Kachare v. Union of India, AIR 2017 Bombay 120 | Applicability of the 2015 Removal of Difficulties Order and the role of the arbitrator under Section 3G(5) of the National Highways Act, 1956. | The Court noted that enhancement of compensation claims pending before an arbitrator under Section 3G(5) may be governed by the 2013 Act as extended by the 2015 Order. |
| Lalita v. Union of India, 2003 (1) KarLJ 406 | Support for the petitioner’s contention regarding applicability of the 2013 Act provisions. | The Court acknowledged the reliance but distinguished the present case based on procedural facts and the statute under which acquisition was made. |
Court's Reasoning and Analysis
The Court analyzed the timeline and statutory framework of the land acquisition proceedings. It observed that the notifications and final award were issued under the National Highways Act, 1956, before the 2015 Removal of Difficulties Order came into force. The Court emphasized that Section 24 of the 2013 Act applies only to proceedings under the repealed Land Acquisition Act, 1894, and does not affect proceedings under the National Highways Act, 1956, which contains no provision for lapse or revival under the 2013 Act.
The Court further referred to the Bombay High Court’s decision in Vishwasrao Dattatray Kachare, which clarified that the 2015 Order applies only to enhancement claims pending before an arbitrator under Section 3G(5) of the National Highways Act, 1956, not to completed awards. Hence, the petitioner’s claim for compensation enhancement under the 2013 Act could only be pursued before such an arbitrator and not through a writ petition.
Holding and Implications
The Court dismissed the writ appeal and upheld the order of the learned Single Judge dismissing the writ petition.
The direct consequence is that the petitioner is not entitled to compensation under the 2013 Act provisions by way of writ petition since the acquisition and award were completed under the National Highways Act, 1956. The petitioner retains an alternative remedy to seek enhancement of compensation through arbitration under Section 3G(5) of the National Highways Act, 1956, where the 2015 Order’s provisions may be considered. No new precedent was set by this decision.
1. Present writ appeal is arising out of the order dated 05.12.2018 passed in W.P. No. 18451/2018.
2. Learned Single Judge has disposed of the writ petition in light of the judgment deliverd in the case of Nirbhay Singh v. Competent Authority. The judgment delivered in the case of Nirbhay Singh (supra) reads as under:—
“W.P. No. 8648/2018
Nirbhay Singh v. Competent Authority
Indore, Dated: 01.05.2018
Shri Devashish Singh, learned counsel for the petitioner.
Shri Koustubh Pathak, learned GA for the respondents/State.
Heard on the question of admission.
The petitioner has filed the present petition being aggrieved by the award dated 18.12.2015, passed by the Competent Authority and SDO, Tehsil - Tarana, District Ujjain under the provisions of the National Highways Act, 1956 and order dated 29.12.2017, passed by the SDO and Land Acquisition Officer (Revenue) Tehsil - Tarana, District Ujjain whereby representation has been rejected.
The petitioner is owner of Survey No. 162/2 (Area 0.400 hectares) and 163/2 (Area 0.020 hectares), situated in Village Rojwas, Tehsil - Tarana, District Ujjain. Government of India issued a notification in exercise of power conferred under Section 3 of National Highways Act, 1956 for acquisition of the land of various survey numbers situated in Village Rojwas, Tehsil - Tarana, District Ujjain for widening of the National Highway Number 3 from Shivpuri to Dewas (516.315KM to 532.420 KM). For the aforesaid purpose, the land of various survey numbers measuring 1.004 hectares of Gram Rojwas were liable to be acquired and for which a notification under Section 3A of the National HighwaysAct 1956 was issued on 26.02.2011. Thereafter, notification under Section 3B was issued w.e.f. 19.12.2012. Thereafter, objections were invited from the land owners. That the notification under Section 3D(2) was issued on 18.12.2013 whereby all the lands have vested into the Government of India free from all encumbrances. The notification was published in the local newspaper but the authorities did not receive any objection. The land acquisition officer has assessed the compensation for the irrigated land @ Rs. 22,40,000/- per hectare and for unirregated land @ Rs. 14,00,000/- per hectare. After assessment, the amount of compensation has directly been deposited in the bank account of owners through E-transaction. The Competent Authority-cum-SDO has passed the final award on 18.12.2015.
The amount has been credited in the account of the petitioner as well. In the year 2017, the petitioner submitted an application before the competent authority i.e. SDO that he ought to have been paid the compensation for his land under the provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (in short the “Act of 2013”) because the acquisition of land under the NHAI Act has been brought within the purview of of Act of 2013 by virtue of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Removal of difficulties) Order 2015 w.e.f. 01.09.2015 (in short “Order 2015”) which is reproduced below:
“The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Removal of Difficulties) Order, 2015
And whereas, the Central Government considers it necessary to extend the benefits available to the land owner under the RFCTLARR Act to similarly placed land owners whose lands are acquired under the 13 enactments specified in the Fourth Schedule; and accordingly the Central Government keeping in view the aforesaid difficulties has decided to extend the beneficial advantage to the land owners and uniformly apply the beneficial provisions of the RFCTLARR Act, relating to the determination of compensation and rehabilitation and resettlement as were made applicable to cases of land acquisition under the said enactments in the interest of the land owners;
Now, therefore, in exercise of the powers conferred by sub-section (1) of Section 113 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (30 of 2013), the Central Government hereby makes the following Order to remove the aforesaid difficulties, namely:—
1. (1) This Order may be called the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Removal of Difficulties) Order, 2015.
(2) It shall come into force with effect from the 1st day of September, 2015.
2. The provisions of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, relating to the determination of compensation in accordance with the First Schedule, rehabilitation and resettlement in accordance with the Second Schedule and infrastructure amenities in accordance with the Third Schedule shall apply to all cases of land acquisition under the enactments specified in the Fourth Schedule to the said Act.“
The SDO vide order dated 29.12.2017 has rejected such representation, hence, present petition before this Court. Learned counsel for the petitioner submits that Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Removal of difficulties) Order 2015 came into force w.e.f. 01.09.2015, therefore, the SDO ought not to have passed the award on 18.12.2015 under the National Highways Act, 1956. He further submits that under Section 24 of the Act of 2013 all the pending proceedings of the land acquisition are liable to be continued under the provisions of Act of 2013. In support of his contention, he has placed reliance over the judgment passed by the Bombay High Court in Vishwasrao Dattatray Kachare v. Union of India, reported in AIR 2017 BOMBAY 120 & judgment passed by the Karnataka High Court in case of Lalita v. Union of India, reported in 2003 (1) KarLJ 406.
In the present case, the notification under Section 3 was issued on 15.04.2011 and further consequential notifications were issued on 19.12.2012 and 18.12.2013. Entire proceedings were initiated and completed under the provisions of National Highways Act, 1956, therefore, the SDO has passed the award on 18.12.2015 under the said Act. For passing the award under the Act of 2013 there has to be preliminary notification under Section 11 of the Act. Section 24 applies to the proceedings pending under the Land Acquisition Act, 1894. Section 24 specifically provides that despite anything contained in this Act in any case of land acquisition proceedings initiated under the Land Acquisition Act 1894 shall be deemed to have lapsed in certain cases. There is no provision of lapse of the proceedings under the National Highways Act, 1956, therefore, Section 24 would not apply in the proceedings pending under the National Highways Act, 1956.
The Division Bench of Bombay High Court in case of Vishwasrao Dattatray Kachare (supra) has held that the applicability of said Order 2015 can be considered by an Arbitrator in a proceedings under Section 3G(5) of National Highways Act, 1956. It has been further held that it would be for the Arbitrator to determine whether the application would be governed by the said notification dated 20.08.2015 issued by the Central Government. Relevant para of the aforesaid judgment is reproduced below:
“12. The 2013 Act was brought into force with effect from 1 January 2014 repealing the Land Acquisition Act, 1894. In the present context, Section 105 of the 2013 Act would become relevant, as it provides that the provisions of 2013 Act shall not apply to the enactments relating to the land acquisition as specified in the Fourth Schedule in which N.H. Act finds a place in the Fourth Schedule at item 7. However, sub-section 3 of Section 105 of the 2013 Act provides that the Central Government is empowered to issue a notification within one year from the date of commencement of the 2013 Act relating to the “determination of compensation in accordance with the First Schedule and rehabilitation and resettlement specified in the Second and Third Schedules”, as beneficial to the affected families, shall apply to the cases of land acquisition under the enactments specified in the Fourth Schedule or shall apply with such exceptions or modifications that do not reduce the compensation or dilute the provisions of the 2013 Act relating to compensation or rehabilitation and resettlement as may be specified in the notification.
13. On behalf of the National Highways Authority, it is brought to our notice that the Central Government by a notification dated 20 August 2015 issued under sub-section (3) of Section 105 of the 2013 Act has issued an order called as the “Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Removal of Difficulties) Order, 2015”, brought into force with effect from 1 September 2015. By clause (2) of the said order, the 2013 Act relating to ‘the determination of compensation in accordance with the First Schedule, rehabilitation and resettlement in accordance with the Second Schedule and infrastructure amenities in accordance with the Third Schedule’, is made applicable to all cases of land acquisition under the enactments specified in the Fourth Schedule in the said Act. By virtue of this order, the provisions of the 2013 Act pertaining to determination of compensation and other benefits as provided in the First Schedule, Second Schedule and the Third Schedule are made applicable to the N.H. Act.
14. On the above background, the legal consequence is that in regard to those applications where enhancement of compensation is sought for and the same are pending consideration of the arbitrators and to which the provisions of the above notification become applicable, then the provisions of the 2013 Act in regard to determination of compensation in accordancewith the First Schedule as also in regard to rehabilitation and resettlement in accordance with the Second Schedule and infrastructure amenities in accordance with the Third Schedule would become applicable in regard to acquisition under the N.H. Act. In such case the Arbitrator as appointed under Section 3G(5) of the N.H. Act, apart from the factors as provided under sub-section (7) of Section 3G, would also be required to take into consideration the provisions of the 2013 Act as made applicable by virtue of the said 2015 Order as issued under sub-section (1) of Section 113 of the 2013 Act. However, it would be for the arbitrator to determine whether a particular application would be governed by the said notification dated 20 August 2015 issued by the Central Government.”
Therefore, the order of 2015 would not apply in the present case as the acquisition proceedings have already been culminated and the award has been passed under the National Highways Act, 1956.
In view of the above discussion, no relief can be granted to the petitioner in this writ petition. He may claim the benefit of order of 2015 before the Arbitrator in a proceedings under Section 3 G of the National Highways Act.
Petition is dismissed in limine.”
3. In the present case, the petitioner is having an alternative remedy to take an appropriate action under Section 3(G)(5) of National Highway Authority Act, 1956, this Court does not find any reason to interfere with the order passed by the learned Single Judge.
4. Present writ appeal is, accordingly, dismissed.