Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Tirupati Dhar Renewable Power Pvt. Ltd. v. Madhya Pradesh Power Management Co. Ltd. And Others

Madhya Pradesh High Court
Sep 21, 2017

P.K. Jaiswal, J.:— As common question of law and facts are involved in these two writ petitions, therefore, the writ petitions were heard analogously and are being disposed of by this common order. For the sake of convenience, facts are taken from Writ Petition No. 855/2017.

2. The instant writ petition under Article 226 of the Constitution of India, has been preferred by M/s. Tirupati Dhar Renewable Power Pvt. Ltd., against the communication dated 30.4.2016 and 1.2.2017 issued by the respondent No. 1 and has also sought a direction to the respondents No. 1 and 4 to accept the date of commissioning of the wind power project as 31.3.2016 and thereby execute PPA as per the Wind Tariff Order, 2013 which was effective till 31.3.2016.

3. The petitioner is a company, who generates the renewable energy.

4. The respondent No. 1 is a State owned company for purchase and sale of power and also wind energy as per M.P. Electricity Regulatory Commission Tariff order on behalf of three distribution company of the State. The respondent No. 2 is the department of New and Renewable Energy, Government of M.P., nodal department meant for mooting renewable energy in the State of M.P. The respondent No. 3 is a Commissioner Department of New & Renewable Energy. The respondent No. 4 is the Chief General Manager (Commercial), M.P. Power Management Co. Ltd.

5. The Government of Madhya Pradesh announced various policies to promote generation of Electricity from various Renewable sources of Energy. One such Policy announced by the Government to exploit the rich wind energy potential in the State of Madhya Pradesh is “Wind Power Project Policy 2012”.

6. The Madhya Pradesh Electricity Regulatory Commission (in short, “MPERC”) has been issuing tariff orders for procurement of Power from Wind Electricity Generators since 2004 as per the provisions of Section 61 and Section 86 (1) (e) of the Electricity Act, 2003. In March, 2013 M.P.E.R.C. issued tariff order No. SMP-12/2013 and fixed a tariff of Rs. 5.92 per unit for all the new wind Electric generation Projects in the State of Madhya Pradesh commissioned on or after 01.04.2013. The Commission also said that the control period for the above tariff order shall start from 01.04.2013 and will end on 31.3.2016. The tariff decided in the above order shall apply to all the projects which come up during the above mentioned control period and shall remain valid for the project life of 25 years.

7. The petitioner—Tirupati Dhar Renewable Power (P) Ltd. applied for allotment of 6 MW (3 MW in Revenue land and 3 MW in private land) project in Dhar District as per the Provisions of the “Wind Power Project Policy 2012” and as per MERC tariff order No. SMP-12/2013 as per request for application floated by respondent No. 3 and got the same registered with the Nodal Agency “Madhya Pradesh New and Renewable Energy Department” vide letter dated 9.12.2014. The registered capacity was enhanced to 15 MW with Madhya Pradesh New and Renewable Energy Department comprising of 10 Wind Turbine Generator's of 1.5 MW each falling on 10 locations as per technical requirements.

8. In the month of October, 2014 a letter of understanding was signed with the petitioner company to provide all the possible support for development of wind power project. The petitioner - company received Power evacuation connectivity approval for the above 15 MW project from MPPKVVCL, Indore on 25.2.2016. The petitioner - Company received final Project approval from MPNRED for 12 MW on private land on 2.3.2016 and for 3MW on Revenue land on 15.3.2016. The petitioner - company completed all the construction for the project and made the project ready for commissioning. On 22.3.2016 the petitioner - company obtained the commissioning permission from the Chief Electrical Inspector to Government.

9. The petitioner - company received the 33 KV line charging permission from Madhya Pradesh Power Transmission Company Limited (MPPTCL) vide letter dated 29.3.2016 and commissioned the 33 KV line on the same day in the presence of concerned Government officials. After completing the project the petitioner - company applied to State Load Despatch Centre (SLDC) vide letter dated 30.3.2016 for grant of power injection permission to the grid as required for commissioning of project. On 31.3.2016 the Company received the permission for injecting power into the grid from Madhya Pradesh Power Transmission Company Ltd. The petitioner - company deployed adequate staff and completed the process well within time and commissioned this 15MW wind power project in the presence of the competent authority, the Superintending Engineer (O & M), M.P. Paschim Kshetra Vidyut Vitaran Company Ltd., Dhar on 31.3.2016. All the readings were recorded by the Competent Authority and issued a commissioning certificate for the commissioning of the 15MW project on 31.3.2016. Reading from individual Wind Electric Generator (WEG) were recorded and snap shot was taken by the competent authority. The copy of commissioning certificate dated 31.3.2016 (Annexure P/14) issued by the Superintending Engineer reads as under:—

“COMMISSIONING CERTIFICATE

This is to Certify that 1.5 MW (1 × 1500 kw) ReGen. Powertech make Wind Turbine Generator (WTG) which is connected to 33/11 KV Jaitpura S/S has been installed at New Wind Power Project of M/s. D.J. Malpani (Develouper M/s. Tirupati Dhar Renewable Power Pvt. Ltd.) at Village Athar Tehsil Dhar has been successfully commissioned on dated 31.03.2016 as per approval of SE (Comm-HT) O/o MD MPPKVVCL Indore's Letter No/WZ/05/Com-HT/AK 2386.06.02.2016 MD/WZ/05/Com-HT/AK/3756 dated 25.02.2016, at the location ID No. TIR-11 through Tirupati Dhar feeder

Main Meter No. XD500605 & Check Meter No. XD500606

Format for commissioning of wind power project is enclosed herewith as per GCM (Comm) MPPMCL Jabalpur Letter No. 05-01/RE Project Commissioning/178 dated 18.3.2016.

This certificate is issued as reported by EE (O & M) Dhar Dn.”

10. The details of Wind Turbine Generator's (in short, “WTG”) meter i.e. initial reading and final reading are relevant which reads as under:—

Initial Reading (Location No. TIR-11)

ReGen Operation Status TIR-11 Active Power 0 KW Generator Speed 0 rpm Wind Speed 3 m/s Wind Deviation 3.2 deg Yaw Position 194.6 deg Blade Position 87.6 deg Energy Counter 0 kWh Operating Hours 0 h Time to Autostart 300 s Autostart Enable OFF Current Mode service

Final Reading (Location No. TIR-11)

ReGen Operation Status TIR-11 Active Power 89 KW Generator Speed 80 rpm Wind Speed 87 m/s Wind Deviation 84 deg Yaw Position 277.1 deg Blade Position 0.6 deg Energy Counter 30 kWh Operating Hours 0 h Time to Autostart 300 s Autostart Enable ON Current Mode Power production

11. After commissioning on 31.3.2016, the petitioner - company applied for execution of Power Purchase Agreement (PPA) to MPPMCL on 1.4.2016. Vide letter dated 30 April, 2016 the petitioner - company was denied PPA by the respondent No. 1 - MPPMCL on the ground that 15 MW capacity WEGs were not commissioned by 31.3.2016 and vide order dated 1.2.2017 (Annexure P/19) directed that if Company did not execute the PPA as per the tariff order dated 17.3.2016 by 10.2.2017 they will not enter into any PPA for the project and not allow injection of any power generated from the project capacity into the grid for supply to MPPMCL and the petitioner - company shall be required to make alternate arrangements. It is this action, which has been impugned in this writ petition on the ground that the petitioner generating company commissioned both the projects on 31.3.2016 and as per Clause 5.1 of MPERC tariff order, 2013, for procurement of powers from wind electric generator all projects which come up during the period from 1.4.2013 to 31.3.2016 the tariff decided in this order No. SMP-12/2013 shall apply and shall remain valid for the project life of 25 years. Clause 5.1, 11.2, 12.4, 12.11 and 12.30 of MPERC Tariff Order of 2013 reads, as under:—

“5.1 The control period to which this order shall apply shall start from 01.04.2013 and will end on 31.3.2016 (i.e. end of FY 2015-16). The tariff decided in this order shall apply to all projects which come up during the above mentioned control period and the tariff determined shall remain valid for the project life of 25 years.

11.2 Considering the above parameters, the Commission sets the levelized tariff @ Rs. 5.92 per unit for generation from new wind energy projects to be commissioned after issue of this order for its project life of 25 years.

12.4 The energy generated by the wind generating units will be procured centrally by the M.P. Power Management Co. Ltd. at the rates specified in this order. The energy so procured will be allocated by M.P. Power Management Co. Ltd. to the three distribution licensees on the basis of actual energy input in the previous financial year. Accordingly, the Power Purchase Agreements will be signed between the developer and the M.P. Power Management Co. Ltd. The M.P. Power Management Company Limited, Jabalpur, in turn, will have back to back power supply agreement with the Distribution Licensees. The agreements will be for exclusive sale of electricity for a period of 25 years from the date of commissioning of plant or for a shorter period in case the developer opts to supply to the licensees after consuming the electricity for self use/third party sale for some years. The developer may execute agreement with M.P. Power Management Company Limited before commissioning of plants and the Commissioning Certificate may from a part of the agreement. The M.P. Power Management Company Limited, Jabalpur is directed to develop the model agreement accordingly.

12.11 The metering arrangement is to be done at site as per the provisions of the Government of M.P. “Wind Energy Project Policy-2012” notified on 30.01.2012 as amended from time to time.

12.30 All existing projects i.e. projects commissioned before 01.04.2013 shall continue to be governed by the terms and conditions applicable at the time of their commissioning.”

12. Clause 12.29 of March, 2016 tariff order dated 17.03.2016 of MPERC reads as under:—

“12.29 All existing projects i.e. projects commissioned before 00.00 hrs. of 01.04.2016 shall continue to be governed by the terms and conditions applicable at the time of their commissioning.”

13. According to the petitioner, the company has invested more than Rs. 200 crores and the projects stand commission post issuance of Commissioning Certificate issued on 31.3.2016 (Annexure P/14) and hence, the petitioner - company, is covered by clause 12.30 of MPERC Tariff Order, 2013. The impugned notice denying the petitioners their legitimate claim of Power Procurement @ of Rs. 5.92 without any cogent reason or logic is also bad in eyes of law.

14. Learned Senior Counsel for the petitioner has submitted that a valid commissioning certificate (Annexure P/14) was issued in favour of the petitioner - company and the same is still in existence and hence, by no stretch of imagination it can be presumed or anyone can reach to a conclusion that the project was not commissioned as per Tariff Order dated 26.3.2013 and prayed that the impugned order be quashed.

15. The stand of respondent Nos. 1 and 4 is that as of 31.3.2016 the Wind Power Project of the petitioner did not inject any power into the Grid and therefore the Wind Power Project of the petitioner was not commissioned as of 31.3.2016. The Commissioning Certificate issued to the petitioner by the Official of Madhya Pradesh Paschim Kshetra Vidyut Vitran Company (MPPKVV) was issued without due diligence and verification. Under the provisions of Electricity Act, 2003 it is the State Load Despatch Centre which manages and records the power flow into the grid. The State Load Despatch Centre vide its letter dated 18.4.2016 specifically highlighted the disparity in the injection data recorded in the Main ABT (Availability Based Tariff) Meters. It was specifically mentioned by the SLDC that the WPP of the petitioner has not injected any power into the grid as of 31.3.2016. The SLDC is an expert statutory body under the Electricity Act, 2003 to regulate, manage and control the electricity load in the State and it regularly coordinates and interacts with the National and Regional Load Despatch Centres. The SLDC has specialized techniques and technologies to determine, control and manage the power flow into the Grid. The stand of the respondent Nos. 1 and 4 is that the Wind Power Project of the petitioner was not commissioned as per required norms as of 31.3.2016 and no power was injected into the grid as of 31.3.2016.

16. The second objection of the respondent Nos. 1 and 4 is that any dispute between a licensee and a generating company has to be adjudicated by the Appropriate Commission. The petitioner is having alternative remedy under Section 86 (1) (f) of the Electricity Act, 2003. Learned Counsel submits that only in cases where the validity of the regulations framed by the Appropriate Commission is challenged, only in such cases a writ petition is maintainable and in all other cases which pertain to adjudication of disputes or interpretation of the Electricity Act, 2003 the appropriate remedy as available under the Electricity Act, 2003 has to be availed. One more objection regarding territorial jurisdiction has been raised on the ground that the respondent No. 1 is having its head Office at Jabalpur and, therefore, the Principal Seat of M.P. High Court at Jabalpur Bench is having jurisdiction to try the issue and prayed for dismissal of the writ petition.

17. We have heard the learned Senior counsel for the appellant and the learned counsel for the respondents No. 1 and 4 and have deeply gone through the material available on record.

18. It is not in dispute that Wind Power Project is installed at Dhar District, which comes within the territorial jurisdiction of High Court of M.P., Bench at Indore. By mere filing of Caveat application at Jabalpur does not ousts the jurisdiction of Bench at Indore to hear a matter in which cause of action wholly or partly has arisen in District Dhar.

19. As per Clause (2) of Article 226 of the Constitution of India, un-disputedly even if a small fraction of cause of action arose within the jurisdiction of the court, the court will have the jurisdiction in the matter. In the present case, the plant of the petitioner is in District Dhar and, therefore, we are of the view that the part of cause of action arose within the territorial jurisdiction of Indore Bench and thus, this court will have jurisdiction in the matter and thus we reject the objection of the respondent Nos. 1 and 4 that this Court has no jurisdiction to try the writ petition.

20. In the present case, till today no PPA has been executed. As per State Load Despatch Centre report, the stand of the respondent Nos. 1 and 4 is that the Wind Power Project of the petitioner did not inject any power into the Grid, (Main ABT Meter) and, therefore, the WPP of the petitioner was not commissioned as of 31.3.2016. The State Load Despatch Centre maintains Power injections from the Wind Farms into grid recorded in ABT Meters. In case of Tirupati Dhar, Energy injection started from 10 block of 1.4.2016 and continued up to 96 block except for 60 and 61 block. The injection of power into the grid is a necessary requirement for commissioning of the Wind Power Project.

21. As per Guidelines issued by Ministry of New and Renewable Energy, Government of India, for implementation of “Scheme for Setting up of 1000 MW ISTS - connected Wind Power Projects”, definition of “Project Commissioning” is given that the Project will be considered as commissioned if all equipment as per rated project capacity has been installed and energy has flown into grid, in line with the Commissioning procedures defined in the Guidelines. The respondent Nos. 1 and 4 on 18.3.2016 had also issued a letter to all the Power Companies in the State of Madhya Pradesh that actual injection of power into the grid is required to establish commissioning of WEG/Unit. The denial of Tariff Policy, 2013 to the petitioner - company is only on the ground that the petitioner has not injected energy into the grid as of 31.3.2016 and, therefore, it is not entitled to the rates in Tariff Order, 2013. The said stand of respondents No. 1 and 4 is contrary to Clause 12.29 of the Tariff Order, 2013.

22. The following contentions have been made on behalf of the writ petitioner wherein the process of commissioning of Wind Power Project in the State of Madhya Pradesh involves following steps:—

“Step1. Chief Electrical Inspector to Government's clearance for commissioning of wind turbine generator (WTG).

Step 2. Commissioning of tele-metering.

Step 3. Line charging permission from State Load Dispatch Centre (SLDC).

Step 4. Power Injection into the grid, permission from SLDC.

Step 5. Commissioning of each WTG involving following in presence Superintending Engineer (O & M), the competent designated authority:

a) Synchronization of WTG with grid frequency.

b) Power generation from WTG.

c) Meter reading record of WTG.

d) Certifying of meter reading of WTG.

Step 6. Issuance of commissioning certificate by competent authority i.e. Superintending Engineer (O & M).”

23. The above commissioning steps were completed as under:—

“a) After erection of wind turbine generator (WTG) and completing its electrical network, Chief Electrical Inspector to Government granted clearance for commissioning of turbines on 22.03.2016. Thus Step 1 of commissioning was completed.

b) Electrical feeder line, was constructed from 33 KV sub-station at Jaitpura Dhar. Each WTG is connected to this feeder at 33 KV voltage level. In between the last WTG and Discom substation, a meters yard is constructed. In this metering yard two meters are installed. First meter is “multi function meter (MFM)” which sends data to SLDC for its load scheduling and other power planning purpose, and second common billing meter.

c) After completion of feeder and connecting each WTG with it, charging of feeder with electrical current was required to be taken from State Load Dispatch center (SLDC) when they confirm that data from MFM is getting transferred to them and Supervisory Control and Data Acquisition (SCDA) system is established. Charging permission of line granted by SLDC vide letter dated 29.3.2016. Thus step 2 and step 3 of commissioning were completed.

d) After charging of feeder line petitioner need to apply to SLDC for grant of permission for injecting the power to grid generated from WTGs. Petitioner applied for the permission vide letter dated 30.3.2016. Permission for injection of power was granted by SLDC at 6.33 PM on 31.3.2016. Thus Step 4 of commissioning was completed.

e) WTGs are synchronized with the grid frequency. Power generated from WTG and energy injected into the grid is recorded. As proof snap shot of meter installed in WTG was taken. The generation is recorded and certified by the designated authority i.e. Superintending Engineer (O & M) Dhar of MP Madhya Kshetra Vidyut Vitaran Co. Ltd. Thus step 5 of commissioning was completed. The certified meter reading Annexure P-15 suffices the core view that commissioning is completed once generation starts. The generation from each of WTG started before 24.00 hours of 31 March 2016.

f) After completing all the above steps, commissioning certificate for each WTG was issued by the Superintending Engineer (O & M) Dhar, the competent authority for the purpose. Thus the step 6, the final step of commissioning of WTG was completed. The petitioner has marked & enclosed copy commissioning certificates dated 31.3.2016 as Annexure P-14.

g) As per MFM data obtained from service provider of SCDA system to SLDC and showing that power is read to some quantity in this meter before 24.00 hours of 31 March 2016.”

24. Learned Counsel for the petitioner has drawn our attention to the commissioning certificates of WTGs of Tamil Nadu and Gujrat. In both these states, for commissioning of WTGs reading of meter installed at WTG is taken as data to demonstrate that WTG has started generation. Annexure P-25 and Annexure P-26 Commissioning Certificate of WTGs of Tamil Nadu and Gujrat reads as under:—

“Certificate of Commissioning

This is to certify that M/s. Satidham Industries Pvt. Ltd.having registered office at 56A, Danudyog, Pipatia, Silvasa, UT of Dadra and Nagar Haveli - 396 230, have commissioned 1,500 MW capacity windfarm consisting of 1 (One) number of new Wind Turbine Generator (WTG) as per the WTG ID no and date of commissioning given below

Make of each Wind Turbine Generator (WTG): M/s. ReGen Powertech Pvt. Ltd.

Capacity of each Wind Turbine Generator: 1500 KW No of Wind Turbine Generator(s): 1 (One) Total Capacity of the Windfarm: 1,500 MW

Sr. No. Details of site of installation Survey No. Date of Commissioning WTG ID number Name of village Taluka District 1 Khakhrechi Maliya Miyana Morbi 1584 pl 16/2/2017 RISPL/1500/1 6-17/4059

This windfarm is connected by 33 KV grid line to 33/66 KV ReGen Powertech Pvt. Ltd.'s site sub-station at Vejalpar. The ReGen's site Sub Station is connected to 66KV GETCO Sub Station at Vejalpar, Dist. Morboi.

Electricity generation report for the purpose of commissioning of windfarm.

Sr. No. WTG ID No. Date Time (Hrs.) Meter (KWh) From To Initial Final Difference 1. RISPL/1500/16-17/4059 16/2/2017 15.30 16.30 110 158 48

TAMILNADU GENERATION AND DISTRIBUTION CORPORATION LTD.

FromTo,

Er. M. SAHARBAN, B.E.,M/s. Hatsun Agro Product Ltd.,

Executive Engineer,Door, No:1/20A,

TANGEDCORajiv Gandhi Salai (OMR),

Kovilpatti—628 501.Karapakkam Chennai 600 097.

Lr. No: EE/D/KPT/DM/F, WEG HTSC, 283/D.No:595/2017, Dt:/4.02.2017.

Dear Sir,

Sub: WEG HTSC No:283 dt. 07.02.2017, Commissioning Certificate reg.

1 No. 2000 KW capacity Wind Electric Generator of M/s. Hatsun Agro Product Ltd., has been commissioned satisfactorily on 7.2.2017 and tied up with TANGEDCO 230 KV grid. The particulars of generation are as below.

SI. No. SF. No. and Village Capacity HT. SC. No. & Date of Commissioning Generated Units 1. 491/3,518/1 (P), 2A (P) of Pasuvanthanai Village 1 X 2000 KW WEG WEG HTSC No:283 dt. 07.02.17 9600 Units From:07.02.1 7 To: 09.02.17

25. As per clause 11.2 of tariff order for procurement power from wind electric generators (SMP-12/13) the Commission/State reveals the tariff as 5.92 per unit for generation from new wind generator project to be commissioned after issuance of tariff order for its period life of 25 years. As per commission certificate issued by the Superintending Engineer on 31.3.2016, the petitioner has successfully commissioned on wind power project on 31.3.2016. The data of wind turbine generator meter also certify the aforesaid fact. The petitioner has applied MFM data obtained from service provider from SCDAV system to SLDC which demonstrate that WTG has started generation.

26. Clause 12.29 of the Tariff Order very specifically lays down that all projects commissioned before 00.00 hours of 01.04.2016 shall continue to be governed by the terms and conditions applicable at the time of their commissioning. From the certificate issued by the Superintending Engineer, after verification to assail it on the ground that it was not issued by due diligence, is wholly misconceived. The terms and conditions are applicable at the time of their commissioning and as such, the Tariff Order, 2013 shall become applicable once a commissioning certificate has been issued. Further contention that the power was not recorded in the meter of respondent, is immaterial because applicability of Tariff Order, 2013 very clearly states that the Tariff Order will apply from the date of commissioning. The reading in WTG Meter clearly shows that the power stood generated and the plant was in operation. It is relevant to point out that generation of power in a wind project is dependent on the velocity of the wind. Wind acts like a fuel generation of power and as such, whether power has been received by the Distribution Company or not, is irrelevant for the purpose of entering into PPA as per the Tariff Order, 2013.

27. In this case, only interpretation of the document is involved. The certificate issued very clearly says that the commissioning has been done and once this position is evident from the record and certificate, no further question is required to be decided. There is no technical question regarding electricity generation etc. involved in this case. The course adopted by the respondents No. 1 and 4 is wholly arbitrary, unreasonable and in violation of Article 14 of the Constitution of India and as such, the writ petition is maintainable. The contention of alternative remedy to lay the challenge before the Tribunal does not arise.

28. For these reasons, we quash the communication dated 30.04.2016 and 01.02.2017 issued by the respondent No. 1 and direct the respondent No. 1 to take appropriate steps as per Tariff Order No. MP-12/2013, in accordance with law.

29. In the result, Writ Petition No. 855/2017 and Writ Petition No. 857/2017 are allowed, without any order as to costs. Original order be retained in Writ Petition No. 855/2017 and a copy thereof be retained in Writ Petition No. 857/2017.