Power Grid Corporation Of India Limited v. Rajasthan Rajya Vidyut Prasaran Nigam Limited And Others

Central Electricity Regulatory Commission
Mar 7, 2019
Smart Summary (Beta)

Structured Summary of the Opinion — Petition No. 62/TT/2018

Factual and Procedural Background

The petition was filed by Power Grid Corporation of India Ltd. (PGCIL) seeking approval of transmission tariff for the asset described as "400 kV D/C Kishenpur - New Wanpoh Line alongwith associated bays at both ends" under Northern Region System Strengthening Scheme XVI for the 2014-19 tariff period under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (the 2014 Tariff Regulations).

Petitioner’s prayers included approval of transmission tariff for 2014-19, admission of claimed capital cost and additional capitalization, allowance of tariff for inclusion in PoC charges, condonation of delay in commissioning, recovery/refund on account of changes in tax rates (MAT/CIT) under Regulation 25, reimbursement of petition filing and publication expenses, separate recovery of license fee and RLDC charges, adjustment for floating interest changes, revision in O&M norms for wage hike, and recovery of GST if transmission ceases to be exempt.

The Investment Approval for NRSS-XVI was given by PGCIL's Board (IA dated 6 July 2010) and a Revised Cost Estimate-II (RCE-II) was approved on 31 March 2017. The instant petition concerns Asset-I (the 400 kV D/C Kishenpur-New Wanpoh line) with claimed COD of 31.07.2017. The petition was considered with affidavits and additional information filed by the petitioner and replies by respondents (notably BRPL and UPPCL). The Commission issued queries (order dated 15.10.2018) and received further affidavits; the present order follows consideration of these materials.

Legal Issues Presented

  1. Whether the Commission should approve the transmission tariff for the Asset (400 kV D/C Kishenpur - New Wanpoh Line) for the 2014-19 tariff period under the 2014 Tariff Regulations.
  2. Whether the capital cost claimed, including Additional Capitalization (ACE), Interest During Construction (IDC), Incidental Expenditure During Construction (IEDC) and initial spares, should be admitted after prudence check under Regulation 9 and related provisions.
  3. Whether the delay in commissioning (claimed 49 months) should be condoned as being beyond the control of the petitioner and thus not attract disallowance of tariff under the Regulations.
  4. Whether and how IDC, IEDC and initial spares should be treated, including any assumptions about floating-rate loans and truing-up at the time of future proceedings.
  5. Whether the petitioner is entitled to recover filing and publication expenses, license fee and RLDC fees and charges, and how taxes (MAT, service tax, GST) should be treated for the tariff period.
  6. Whether the normative debt:equity ratio, return on equity (grossed up for tax), depreciation, interest on loan, interest on working capital and O&M expenses should be computed and allowed as per the 2014 Tariff Regulations.

Arguments of the Parties

Petitioner (PGCIL)

  • Sought approval of tariff for Asset-I for 2014-19 and admission of capital cost and ACE as claimed (including IDC, IEDC and initial spares within the scope and ceilings in the regulations).
  • Requested condonation of delay in commissioning on the ground that delays were due to factors beyond its control (forest & wildlife clearances, ROW issues, court cases) in line with Regulations and prior Commission practice.
  • Provided COD support (self-declaration, CEA certificates, RLDC certificate) and submitted CPM and PERT charts in response to objections.
  • Claimed IEDC and IDC and submitted statements of IDC discharge; sought direction on treatment of floating-rate interest for truing-up.
  • Requested recovery of filing/publication expenses, separate recovery of license fee and RLDC charges, and prospective recovery of GST/service tax if tax treatment changes in future.
  • Sought permission to bill and adjust interest-on-loan impacts arising from floating rate changes during 2014-19 and to approach Commission for revision of O&M norms for wage hike effects.

Respondent — BSES Rajdhani Power Limited (BRPL)

  • Filed objections (affidavit dated 11.09.2018) raising issues on cost over-run, Transmission Service Agreement (TSA), reasons for delay, absence of CPM/PERT initially, DPR, initial spares, wage revision, reimbursement of filing fee, license fee, etc.
  • Specifically contended that the time overrun was attributable to the petitioner's slackness in project management and that the petitioner had not submitted CPM & PERT charts (the petitioner later furnished these).

Respondent — UP Power Corporation Limited (UPPCL)

  • Filed reply (affidavit dated 19.03.2018) raising issues including time over-run, cost over-run, initial spares, additional capitalization, rate of interest on loan, etc.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Commission's analysis proceeded by applying the relevant provisions of the 2014 Tariff Regulations to the facts and submissions in the petition and replies. Key steps in the reasoning are summarized below, based strictly on the materials in the order:

  1. Commercial Operation Date (COD): The petitioner produced a self-declaration of COD (12.8.2017), CEA certificates (30.4.2016 and 20.4.2017), and an RLDC certificate (21.8.2017) in accordance with relevant regulations. The Commission accepted the COD as 31.07.2017 for tariff computation from COD to 31.03.2019.
  2. Capital Cost and Prudence Check (Regulation 9): The Commission noted the Investment Approval (IA) and Revised Cost Estimate-II (RCE-II). It compared the apportioned approved cost (per FR) of ₹53,126.60 lakh, RCE-II apportioned approved cost of ₹57,293.14 lakh, and the petitioner's estimated completion cost as on 31.03.2019 of ₹55,905.10 lakh. The Commission observed that the estimated completion cost was within RCE-II and concluded there was no cost overrun for the asset.
  3. Causes and Treatment of Cost Variation: The petitioner explained increases and decreases in various cost heads (e.g., increase in preliminary investigation/right-of-way/forest clearance costs, increase in tower steel costs due to route change; decreases due to competitive bidding). The Commission found these variations largely attributable to route changes, forest/wildlife clearances and prevailing market conditions beyond petitioner’s control, and accepted the explanation for the cost variation within RCE-II.
  4. Time Over-run and Condonation of Delay: The Commission analyzed the approved schedule (36 months from IA dated 2.7.2010, so scheduled completion ~1.7.2013) versus actual COD (31.7.2017), i.e., delay of approximately 49 months. The petitioner attributed the delay mainly to forest & wildlife clearances (periods running from late 2010 to 2017 including multiple procedural events and approvals), ROW issues (including refusals by J&K PDD to provide corridor and later route finalization), and court cases. The Commission considered documentary chronology supplied by the petitioner and the CPM/PERT charts filed in rejoinder, and concluded that the delay of 49 months was primarily due to forest & wildlife clearances, ROW issues and court cases which were beyond the control of the petitioner; accordingly the delay of 49 months was condoned.
  5. IEDC and IDC: The petitioner claimed IEDC of ₹2,520.32 lakh and IDC of ₹11,216.42 lakh. The Commission allowed the IEDC claimed as it was within the percentage on hard cost shown in the abstract cost estimate (less than 5% of hard cost). For IDC, the Commission examined the statement of IDC discharge and noted the petitioner did not indicate floating interest rates for SBI loans. The Commission computed IDC on a cash basis using certain assumptions for floating-rate SBI loans (specified rates and mid-quarter drawal assumption) and allowed IDC as on COD subject to truing-up at the time of actual truing-up upon submission of detailed floating-rate loan information. The Commission also noted a portion of IDC discharged after COD was considered in additional capital expenditure.
  6. Initial Spares: Under Regulation 13, the ceiling for transmission line initial spares is 1.00% of plant & machinery. The petitioner claimed ₹717.25 lakh; the Commission worked the ceiling and allowed initial spares up to the applicable limit (allowable initial spares of ₹405.34 lakh) and deducted the excess from capital cost considered for tariff. The petitioner submitted that initial spares discharged as on COD amounted to ₹645.52 lakh; the Commission presumed allowable portion had been discharged by COD.
  7. Capital Cost Considered: After adjustments (IEDC allowed, portions of IDC disallowed as undisclosed/un-discharged, and excess initial spares disallowed), the capital cost considered as on COD for tariff computation was ₹51,406.18 lakh.
  8. Additional Capital Expenditure (ACE) & Cut-off Date: The Commission applied Regulation 14 and the definition of cut-off date (Regulation 3(13)) — cut-off date for the asset is 31.03.2020. The petitioner claimed ACE for 2017-18 and 2018-19 (₹1,793.30 lakh and ₹1,196.65 lakh respectively) and the Commission allowed ACE up to 31.03.2019 (allowed amounts reported in the order: 2017-18 ₹2,880.09 lakh and 2018-19 ₹1,306.92 lakh — the latter includes discharged IDC and initial spare added in the respective year as ACE). The estimated completion cost as on 31.03.2019 used for tariff computation was ₹55,593.19 lakh.
  9. Debt-Equity Ratio: The Commission followed Regulation 19 and adopted the normative debt:equity ratio of 70:30 for both COD and 31.03.2019 capital cost figures (debt and equity amounts and percentages are recorded in the order).
  10. Return on Equity (RoE): In accordance with Regulation 24 and Regulation 25, the RoE was grossed up for tax. The petitioner stated it pays MAT; the Commission applied the MAT rate applicable in 2013-14 (20.961%) to gross up the base RoE of 15.50% resulting in a pre-tax RoE rate of 19.610% which is subject to truing-up under Regulation 25(3). The Commission computed RoE (pre-tax) amounts for the pro-rata 2017-18 and 2018-19 periods (amounts shown in the order).
  11. Interest on Loan (IOL): The Commission applied Regulation 26 methodology: considered gross normative loan, repayments (taken equal to depreciation allowed for the year), and weighted average rate of interest on actual average loan to compute interest on loan for the years. The order contains the loan, repayment, average loan, weighted average interest rate and IOL figures used in arriving at allowed interest.
  12. Depreciation: Depreciation was calculated on a straight-line method as per Appendix-II to the 2014 Tariff Regulations; the order provides depreciation rates and amounts for the years.
  13. O&M Expenses: The Commission applied the normative O&M provisions (Clause 29(4)(a)) and worked out O&M for the asset pro-rata for 2017-18 and for 2018-19. The petitioner had argued for possible revision in norms to address wage revision; BRPL objected that beneficiaries should not bear extra burden beyond regulatory provisions. The Commission allowed O&M as per the 2014 Tariff Regulations and noted the petitioner may approach the Commission for revision of norms if appropriate.
  14. Interest on Working Capital (IWC): Pursuant to Regulation 28 proviso 3, the Commission used SBI base rate plus 350 bps as on 01.04.2017 (12.60%) as the rate for working capital interest. The order tabulates components of working capital (maintenance spares, O&M, receivables), totals and interest amounts for the years.
  15. Annual Transmission Charges and Tariff: Combining depreciation, IOL, RoE, IWC and O&M, the Commission summarized the allowable annual transmission charges for Asset-I: 2017-18 (pro-rata) total ₹6,384.91 lakh and 2018-19 total ₹9,713.75 lakh (figures provided in the order).
  16. Filing Fee, Publication Expenses, License Fee and RLDC Charges: The Commission held the petitioner is entitled to reimbursement of filing fee and publication expenses from beneficiaries on a pro-rata basis under Regulation 52(1). It also allowed reimbursement of license fee and RLDC fees/charges in accordance with Regulation 52(2)(b) and 52(2)(a), respectively.
  17. Service Tax and GST: The petitioner’s prayer to recover service tax on transmission charges was considered premature/infructuous because service tax is not levied on transmission (and service tax has been subsumed by GST). The prayer for prospective recovery of GST was held to be premature as GST is not levied on transmission service at present.
  18. Sharing and Recovery: The Commission directed that transmission charges be recovered monthly in accordance with Regulation 43 of the 2014 Tariff Regulations and shared by beneficiaries and long-term customers as per the 2010 Sharing Regulations (as amended).

Holding and Implications

Core Ruling: The Commission allowed the petition in the terms set out in the order: it approved the COD as 31.07.2017; after prudence checks admitted capital cost (subject to specified adjustments and future truing-up on IDC and tax); condoned the delay of 49 months as being due to factors beyond the control of the petitioner; allowed IEDC, portions of IDC (with conditions for truing-up), initial spares up to the regulatory ceiling, ACE up to 31.03.2019; applied normative debt:equity (70:30), grossed-up RoE (using MAT rate for gross-up) subject to truing-up; computed and allowed depreciation, interest on loan, O&M, interest on working capital and, hence, annual transmission charges (2017-18 pro-rata and 2018-19 amounts as shown in the order).

Direct Consequences for the Parties:

  • The tariff components and annual transmission charges for the Asset were computed and allowed as set out in the order (2017-18 pro-rata total: ₹6,384.91 lakh; 2018-19 total: ₹9,713.75 lakh).
  • The petitioner is entitled to reimbursement of filing fee and publication expenses directly from beneficiaries on pro-rata basis, and to recover license fee and RLDC fees/charges in accordance with Regulation 52.
  • The petitioner's request to separately recover service tax or GST at present was not allowed; the Commission found the prayers premature since service tax is not levied and has been subsumed by GST, and GST is not levied on transmission at present.
  • The delay in commissioning was condoned, so no penal disallowance was applied on that basis in the order.

No New Precedent: The order applies the 2014 Tariff Regulations and regulatory principles to the facts. The opinion does not purport to lay down a novel legal principle or to set a binding judicial precedent beyond application of the applicable regulations to the petitioner's facts.

Disposition

This order disposes of Petition No. 62/TT/2018.

Source: Extracted and summarized solely from the provided text of the Commission's order in Petition No. 62/TT/2018. No additional sources or inferences were used.

Show all summary ...

The present petition has been filed by the petitioner, Power Grid Corporation of India Ltd. (PGCIL) seeking approval of transmission tariff for the Asset: 400 kV D/C Kishenpur - New Wanpoh Line alongwith associated bays at both ends (hereinafter referred to as the Asset) under Northern Region System Strengthening Scheme XVI in Northern Region (hereinafter referred to as transmission system) for 2014-19 tariff period under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (hereinafter referred to as the 2014 Tariff Regulations).

2. The petitioner has made the following prayers:-

i) Approve the Transmission Tariff for the tariff block 2014-19 for the asset covered under this petition. ii) Admit the capital cost as claimed in the Petition and approve the Additional Capitalization incurred / projected to be incurred and allow the cost overrun. iii) Allow tariff up to 90% of the Annual Fixed Charges in accordance with clause

7 (i) of Regulation 7 of CERC (Terms and Conditions of tariff) Regulations,2014 for purpose of inclusion in the POC charges. iv) Condone the delay in completion of subject assets on merit of the same being out of the control of Petitioner in line with CERC Regulations2014 12(2)(i) Page 4 of 33 Order in Petition No. 62/TT/2018 uncontrollable factors

v) Allow the petitioner to recover the shortfall or refund the excess Annual Fixed Charges, on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before the Commission as provided under clause 25 of the Tariff Regulations 2014. vi) Approve the reimbursement of expenditure by the beneficiaries towards petition filing fee, and expenditure on publishing of notices in newspapers in terms of Regulation 52 Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014, and other expenditure ( if any) in relation to the filing of petition. vii) Allow the petitioner to bill and recover License fee and RLDC fees and charges, separately from the respondents in terms of Regulation 52 Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014. viii) Allow the petitioner to bill and adjust impact on Interest on Loan due to change in Interest rate on account of floating rate of interest applicable during 2014-19 period, if any, from the respondents. ix) Allow to approach the Honble Commission for suitable revision in the norms for O&M expenditure for claiming the impact of wage hike from 01.01.2017 onwards

x) Allow the petitioner to bill and recover GST on Transmission charges separately from the respondents, if GST on Transmission of electricity is withdrawn from the exempted (negative) list at any time in future. Further any taxes and duties including cess, etc. imposed by any Statutory/Govt./Municipal Authorities shall be allowed to be recovered from the beneficiaries. and pass such other relief as Honble Commission deems fit and appropriate under the circumstances of the case and in the interest of justice.

3. The Investment Approval (IA) for implementation of Northern Region System Strengthening Scheme XVI (NRSS-XVI) was accorded by Board of Directors of the petitioner vide Memorandum dated 6th July 2010 at an estimated cost of `75264 lakh including Interest During Construction (IDC) of `6331 lakh based on 1st Quarter 2010 price level. Further, the Revised Cost Estimate-II (RCE-II) of the project was approved by Board of Directors of the petitioner vide Memorandum dated 31st March 2017 at an estimated cost of `75794 lakh including IDC of `12622 lakh based on October 2016 price level. Page 5 of 33 Order in Petition No. 62/TT/2018

4. The system strengthening scheme in Northern Region (NR) was discussed and agreed in 23rd Standing Committee Meeting dated 16.02.2008 and 8th NRPC meeting dated 25.04.2008. The details of the transmission elements covered under the transmission system are broadly as follows:- Transmission Lines:

(i) LILO of both circuits of Kishenpur - Wagoora 400 KV D/C line at New Wanpoh.

(ii) Kishenpur-New Wanpoh 400 KV D/C Line Sub-Stations:

(i) New 2x315 MVA (7x105 MVA Single Phase Units considered), 400/220 KV New Wanpoh Substation.

(ii) Extension of 400/220 KV Kishenpur sub-station. Reactive Compenstaion:

(i) 1x125 MVAR bus reactor at New Wanpoh.

5. The status of assets under the transmission system submitted by the petitioner, are as below:- Name of Asset COD Petition No.

1 Asset-I: 400 kV D/C Kishenpur- New Wanpoh Line alongwith associated bays at both ends 31.07.2017 Current petition

2 400/220 KV 315 MVA ICT-II along with associated bays at New Wanpoh S/s 03.07.2014 111/TT/2013

3 400 KV 125 MVAR Bus Reactor along with associated bays at New Wanpoh S/s 16.06.2014 111/TT/2013

4 LILO of both circuits of Kishenpur- Wagoora 400 KV D/C line at New Wanpoh and 400/220 KV 315 MVA ICT-I along with associated bays at New- Wanpoh S/s 01.10.2013 34/TT/2013 Page 6 of 33 Order in Petition No. 62/TT/2018

6. The details of the transmission charges claimed by the petitioner are as under:- (` in lakh) Particulars Asset-I 2017-18 (pro-rata) 2018-19 Depreciation 1861.75 2890.59 Interest on Loan 2083.42 3025.42 Return on Equity 2093.27 3250.45 Interest on Working Capital 144.63 219.89 O&MExpenses 248.57 383.67 Total 6431.64 9770.02

7. The details of the interest on working capital claimed by the Petitioner are as under:- (` in lakh) Particulars Asset-I 2017-18 (pro-rata) 2018-19 Maintenance Spares 55.70 57.55 O&M expenses 30.95 31.97 Receivables 1601.45 1628.34 Total 1688.10 1717.86 Interest 144.63 219.89 Rate of Interest 12.80% 12.80%

8. Annual Fixed Charges under the first proviso to Regulation 7(7) of the 2014 Tariff Regulations for inclusion in the PoC charges were granted vide order dated 15.10.2018 .

9. No comments or suggestions have been received from the general public in response to the notices published by the petitioner under Section 64 of the Electricity Act. BSES Rajdhani Power Limited (BRPL), Respondent No. 12, has filed reply vide affidavit dated 11.09.2018. BRPL has raised issues of Cost Over-run, TSA, Delay reason, CPM, PERT, DPR, initial spare, wage revision, Page 7 of 33 Order in Petition No. 62/TT/2018 reimbursement of expenditure towards filing fee, license fee etc. The petitioner has filed rejoinder dated 14.09.2018 to the reply of BRPL. UP Power corporation limited (UPPCL), Respondent No. 09, has filed reply vide affidavit dated 19.03.2018. UPPCL has raised issues of time over-run, Cost Over-run, initial spare, add-cap, rate of interest on loan etc. The petitioner has filed rejoinder dated 14.09.2018 to the reply of UPPCL. The objections raised by the respondents and the clarifications given by the petitioner are addressed in the relevant paragraphs of this order.

10. Commission had sought replies to certain queries vide order dated 15.10.2018, which were replied to by the petitioner vide affidavit dated 29.10.2018. This order has been issued after considering the submissions of the petitioner in the original petition and subsequent additional information vide affidavits dated 20.02.2018, 21.03.2018, 11.09.2018, 14.09.2018 and 29.10.2018 and respondents affidavits dated 11.09.2018 and 19.03.2018. Commercial Operation Date (COD)

11. The petitioner has claimed date of commercial operation of Asset-I as 31.7.2017. In support of COD, petitioner has submitted self-declaration of COD letter dated 12.8.2017, CEA certificate dated 30.4.2016 and 20.4.2017 under regulation 43 of CEA (Measures relating to safety and Electric Supply) Regulations, 2010, RLDC certificate dated 21.8.2017 in accordance with Regulation 6.3.A(5) of CERC (Indian Electricity Grid Code) and CMD Certificate required under Grid Code. Accordingly, taking into consideration these certificates, the COD of the asset is approved as 31.7.2017 and has been considered for the purpose of tariff computation from COD till 31.3.2019. Page 8 of 33 Order in Petition No. 62/TT/2018 Capital Cost

12. Clause (1) and Clause (2) of Regulation 9 of the 2014 Tariff Regulations provide as follows:- (1) The Capital cost as determined by the Commission after prudence check in accordance with this regulation shall form the basis of determination of tariff for existing and new projects. (2) The Capital Cost of a new project shall include the following: (a) The expenditure incurred or projected to be incurred up to the date of commercial operation of the project; (b) Interest during construction and financing charges, on the loans (i) being equal to 70% of the funds deployed, in the event of the actual equity in excess of 30% of the funds deployed, by treating the excess equity as normative loan, or (ii) being equal to the actual amount of loan in the event of the actual equity less than 30% of the funds deployed; (c) Increase in cost in contract packages as approved by the Commission; (d) Interest during construction and incidental expenditure during construction as computed in accordance with Regulation 11 of these regulations; (e) Capitalized Initial spares subject to the ceiling rates specified in Regulation 13 of these regulations; (f) Expenditure on account of additional capitalization and de- capitalisation determined in accordance with Regulation 14 of these regulations; (g) Adjustment of revenue due to sale of infirm power in excess of fuel cost prior to the COD as specified under Regulation 18 of these regulations; and (h) Adjustment of any revenue earned by the transmission licensee by using the assets before COD.

13. The details of apportioned approved cost, capital cost as on the date of commercial operation and estimated additional capital expenditure incurred or projected to be incurred during 2017-18 and 2018-19 along with estimated completion cost for the asset covered in the petition as claimed Page 9 of 33 Order in Petition No. 62/TT/2018 by the petitioner and considered for the purpose of computation of tariff are as under:- (`in lakh)

14. We have considered the submissions of the petitioner. It is observed that the petitioner has submitted the Revised Cost Estimate-II (RCE-II) and that the estimated completion cost, as on 31.03.2019, claimed for the Asset is within the RCE-II. Cost Over-Run/Variation

15. The apportioned approved cost of the asset as per FR of the project is `53127 lakh and as per RCE-II is `57293 lakh against which the estimated completion cost of the asset as on 31.03.2019 is `55905 lakh. Hence, there is no cost overrun in case of the asset covered in instant petition. However, there is cost variation in RCE-II as compared with apportioned approved cost. The petitioner has submitted the following reasons of cost variation along with Form-5:

(i) Increase of about `3569 lakh in the costs associated with Preliminary Investigation, Right of Way, forest clearance, PTCC, general civil works etc. and is as per actual.

(ii) Increase of `2332 lakh in the cost of tower steel is due to change in route of portion of line from Multicircuit to D/C at Pir-Panjal which resulted in quantity variation and also there is price variation based on price quoted by the bidder in competitive bidding. Apportion Approved Cost(FR) Apportion Approved Cost (As per RCE-II) Cost as on COD Estimated additional capital expenditure Estimated Completion Cost as on 31.03.2019 2017-18 2018-19 53126.60 57293.14 52915.15 1793.30 1196.65 55905.10 Page 10 of 33 Order in Petition No. 62/TT/2018

(iii) Decrease of `783 lakh in the cost of Conductor is due to price variation based on price quoted by the bidder in competitive bidding. Decrease of `534 lakh in Insulator cost is due to quantity variation as some of the insulator were diverted from other projects.

(iv) Increase of `431 lakh in transmission line spare cost and is as per site requirement and price quoted by the bidder in competitive bidding.

(v) Decrease of `5026 lakh in Erection, Stringing & Civil works cost including cost of foundation of Transmission line and is as per actual site condition and low price quoted in competitive bidding.

(vi) Decrease of `1741 lakh in taxes and duties of transmission line material and is on actual basis.

(vii) Decrease of `973 lakh in establishment cost and Increase of `6738 lakh in IDC is on actual basis

(viii) There is increase/decrease in award cost received in competitive bidding compared to initial estimates (FR cost).

16. We have considered the submissions of the petitioner. The total estimated completion cost of the asset is within the revised apportioned approved cost of the asset. We are of the view that cost variation in RCE-II as compared with apportioned approved cost is mainly due to increase in costs of preliminary investigation, Right of Way, forest clearance, PTCC, general civil works , increase in tonnage of tower steel due to change in route of portion of line from Multi-circuit to D/C at Pir- Panjal which resulted in quantity variation and the reduction in cost is mainly because of prevailing market condition which were beyond the control of the petitioner. Time over-run

17. As per the investment approval, the schedule completion date was within 36 months from the date of investment approval. The date of Investment Approval was 2.7.2010. Hence, the commissioning schedule comes to 1.7.2013, against which the subject asset has been commissioned and Page 11 of 33 Order in Petition No. 62/TT/2018 declared under commercial operation w.e.f. 31.7.2017 with a delay of 49 months approximately. Reasons of time over-run

18. The petitioner has submitted the following reasons for delay in commissioning of the asset:

(i) Forest and Wildlife Clearance:-

a) Major part of the line is traversing through hilly and tedious terrain which has posed challenges in routing the transmission line over Pir - Panjaal with very high altitudes, extremely rugged mountains, and tough climatic conditions. During Survey of the Transmission Line, efforts were made to through the line without any wild life involvement as well as with minimum Forest involvement. Out of total line length of 135.02 km, forest area covers around 48.32 sq km and wildlife covers around 0.51 sq km. A large length of transmission line is passing through forest and wildlife for which approval and tree cutting took considerable time and has lead to overall delay in commissioning of the asset.

b) In 28th Standing Committee on Transmission System Planning of Northern Region held on 23rd February, 2010; Power Development Department (PDD) of Jammu and Kashmir (J&K) agreed, in principle, to provide corridor for 400 kV Kishenpur - New Wanpoh D/C line for crossing Pir-Panjal mountain range by dismantling their existing 132 kV line section (approximately 8 km). However, the decision to construct 400 kV D/C line or Multi-circuit line for crossing Pir - Panjal, was to be taken as per the outcome of discussion with Government of J&K. Further in 29th Standing Page 12 of 33 Order in Petition No. 62/TT/2018 Committee on Transmission System Planning of Northern Region held on 29th December, 2010, the Chief Engineer PDD informed that Government of J&K had agreed, in-principle, for the proposal of providing Multi - circuit line in Pir- Panjal area with a provision of 2 nos. of 220 kV circuits for J&K. However, PDD of Government of J&K vide letter dated 16.4.2011 refused to provide their 132 kV corridor. Since, this refusal came at a later stage after Investment Approval of the said line, the final route finalization for forest stretch also got delayed.

c) The 48.32 sq km of forest stretch covers around 222.28 Hactare of forest land passing through Jammu, Udhampaur, Batote, Ramban & Anantnag division and 0.51 sq km of wildlife reserve covers around 2.35 Hactare in Chakore reserve in Chenab Division. Total number of trees, poles and saplings involved in these divisions where around 8234. The forest department was approached for work vide letter dated 18.1.2011. Final Order by J&K Government cabinet was released on 17.5.2013 for using forest land which further required approval from the Wildlife Division. The case of wildlife was discussed in various standard committee meeting of wildlife and further passed by CEC (Central Empowered Committee) and the Honble Supreme Court of India. Final approval of wildlife was accorded on 30.10.2015. Subsequent to final order, tree felling process was carried out in all the five Forest Divisions which was completed by 21.2.2017 after final payment was made as requested by J&K State Forest Corporation vide letter dated 21.2.2017. Since large no of trees were involved in this division with rough terrain, tree cutting took considerable time. The total time taken for forest and wildlife clearances with approval of tree cutting in these areas Page 13 of 33 Order in Petition No. 62/TT/2018 was around 61 months. Chronology of events pertaining to above events is summarized below: HINDRANCE / COMMUNICATION DATE From To

1 MoM 28thSCM 23.2.2010 Extract of minute

2 MoM 29thSCM 29.12.2010 Extract of minute

3 Permission of work in Forest Land 18.1.2011 GM, Projects , NR-II CCF

4 Permission of work in Forest Land 28.1.2011 CCF GM, Projects , NR-

5 Regarding Forest Proposal 8.2.2011 Manager, TL Batote CCF

6 Proposal Map/ Intend reply from FCA 12.2.2011 CCF DFO

7 Joint Inspection Letter to Range officer, Batote 1.3.2011 DFO Batote Range officer , Batote

8 PDD letter 16.4.2011 Under Secretary ED, Powergrid

9 query raised in Forest Case 4.5.2012 CF, Chenab Circle DFO, Ramban

10 Handing over of compartment

46 and 47 banihal to wildlife from forest 17.7.2012 Range officer,Banihal Range officer wildlife, Rambanbatote

11 Proposal forwarded for diversion of land after handing over charge from forest to wildlife for Chakore Reserve coming under wildlife 28.7.2012 DFO Ramban CF, Doda

12 Letter regarding fresh propsal for wildlife or the same submitted before valid 6.8.2012 CM, New Wanpoh Chief Wildlife Warden, Srinagar

13 Joint Inspection Letter to DFO, Ramban 8.8.2012 Range officer, Batote DFO, Ramban

14 Proposal for Line crossing through Jawahar tunnel Conservation 9.8.2012 Chief Wildlife Warden, Srinagar CF, Wildlife Jammu

15 Proposal of forest case for Ramban & Banihal 28.9.2012 DFO, Ramban CF, Doda

16 Proposal forwarded for wildlife clearance 30.8.2012 CCF Chief Wildlife Warden, J&K

17 Proposal to allow use of land in anantag District by PGCIL 3.9.2012 CF, Warden Srinagar CF, Wildlife, Kashmir

18 Wildlife area in Kishanpur - New Wanpoh Line 19.9.2012 CF, Jammu CWW, Srinagar

19 Proposal for diverison of Land 5.10.2012 CF, Doda CCF

20 Proposal for Jammu, Udhampur&Batote 27.11.2012 CCF, Jammu Pr. CCF

21 Regarding satutory Forest Clearance 23.1.2013 CM, TLO Batote CCF, Jammu

22 75th Forest Advisory Committee Meeting MOM 30.3.2013 To all members CCF, Member Secretary

23 Inspection report 26.4.2013 Wildlife warden, Kistwar CF, Wildlife Kistwar

24 Govt. order for use of forest 17.5.2013 Civil secretariat Page 14 of 33 Order in Petition No. 62/TT/2018 land forest dept.

25 Payment for Forest clearance ramban 24.6.2013 CCF CAO

26 Invitation for 6th Meeting of Standing Committee of SBWL 22.7.2013 GM, Powergrid Secretory, SBWL

27 Addendum: Use of Forest Land for Non Forest Purposes. 26.8.2013 Commissioner /Secretary to Govt. J&K Forest

28 Minutes of 6th Meeting of Standing Committee of SBWL held on 25.7.2013, Case forwarded to NBWL 22.10.2013 Minutes

29 Felling of Forest Trees 6.11.2013 Project Manager, TL Batote DFO, Batote, Ramban, Udhampur, Jammu

30 Proposal for line passing through Wildlife area 2.12.2013 Chief wildlife warden, Jammu Commissioner/sec. Govt. of J&K Forest Dept.

31 Proposal for Chakore Reserve 6.1.2014 Under Secretary to JK Govt. Forest Dept. Inspector General of forest (Wildlife)

32 Proposal Documents for Chakore Reserve

29. 1.2014 DIG Forest (WL) CWW, Jammu

33 Proposal Documents for Chakore Reserve 4.2.2014 Wildlife warden Chief Engineer, New Wanpoh, PGCIL

34 Reply to Chief wildlife warden Jammu for copy of Proposal Documents for Chakore Reserve 6.2.2014 Project Manager, Batote T/L Office DIG Forest (WL)

35 Case listed before the CEC Committee & Notice for Hearing 21.4.2014 Chairman, PCB,Prin. CCF, JammuChief Wildlife warden Deputy Secretary, Forest Depptt.

36 Request for Felling of Forest Trees on top level priority 9.5.2014 Dy. Manager, Kishenpur, PGCIL DFO, Ramban

37 Joint inspection and request for requisite paper for ownership of section 13.6.2014 Tehsildar,Udhampur

38 Recommendation of CEC in application no1381 2.7.2014 Member Secretary, Registrar, Supreme Court of India,

39 Request for requisite paper for ownership of a section 24.7.2014 Dy. Manager, Powergrid DFO,Batote

40 Invitation for 31st Meeting of Standing Committee of NBWL 8.8.2014 Wildlife Warden Chief Engineer, New Wanpoh

41 Nishandehi of Nathatop Forest 9.8.2014 DFO, Batote Asst. Commissioner, Udhampur

42 31st meeting minutes regarding proposal recommendation 13.8.2014 Minutes

43 Batote Forest approval for 350 Trees 18.9.2014 DFO Batote Project Manager, PGCIL Page 15 of 33 Order in Petition No. 62/TT/2018

44 Payment for 22/Batote Compartment 20.10.2014 Chief Manager, T/L Batote DFO Batote

45 Acknowledgment of payment receipt 28.10.2014 DFO,Batote Forest Division CM, Powergrid

46 Regarding recommendation of wildlife proposal for chakore reserve by Supreme Court 3.12.2014 CM, TLC, Batote Prl. CCF, Jammu

47 List of trees for felling 9.12.2014 DFO,Jammu CF,Jammu

48 Technical Sanction of Trees in Batote forest Division 26.12.2014 CF Jammu Govt. Order

49 Marking List of trees 1.1.2015 CF, Jammu (East Circle) CF, Jammu

50 Administrative approval for Udhmpur&Batote Forest Area 4.2.2015 CCF, Jammu Govt. Order

51 Withdrawing of technical sanction of Udhampur and batote forest area 11.2.2015 CF,Jammu CCF,Jammu

52 Wildlife clearance for 2.3506 Ha. Chakore Reserve 25.2.2015 Chief Wildlife warden, Srinagar/Jammu Secretary to J&K Govt. Forest Dept.

53 Revised marking of trees in Ramban Forest division 8.4.2015 DFO, Ramban Range officer, Ramban/Banihal

54 Wildlife clearance for 2.3506 Ha. Chakore Reserve 13.4.2015 Nodal Officer, (FCA) Prl. Secretary to Govt. J&K Forest Dept.

55 Technical Sanction Batote 22a/Btt 6.7.2015 CF, Srinagar Govt. Order

56 Administrative approval for Batote&Ramban Forest Area 9.7.2015 CF, Chenab Circle CF, Srinagar

57 Administrative approval for Batote comptt. No 22a/Btt 28.7.2015 Office order,CCF Jammu

58 Administrative approval for Batote Forest Area 13.8.2015 Office order,CCF Jammu

59 Felling of remaining trees in Batote forest Division 20.8.2015 Chief Manager, T/L Batote Div Mgr. SFC Ramban

60 Chakore wildlife letter for deposit of amount 27.8.2015 CCF ED, NR-II

61 Technical Sanction for removal of marked trees in Ramban area 29.8.2015 CF, Srinagar Govt. Order

62 Letter to Div. Mgr. Forest Division Ramban for payment & felling of trees there off 8.9.2015 Manager, TL Batote Div Mgr. SFC Ramban

63 Administrative approval for Ramban Forest Area 19.9.2015 CCF, Jammu Govt. Order

64 Request to Issue of Sanction order for Chakore Reserve 15.10.2015 CCF, Srinagar Prin. Secretary to JK Govt. Forest Dept.

65 Letter to Chief Conv. Officer for felling of marked trees 15.10.2015 ED, NR-II CCF. Srinagar

66 Final Approval of Wildlife Proposals 30.10.2015 Secretary to J&K Govt. Forest Dept. Govt. order

67 Letter for deposit of payments for felling of trees 16.11.2015 Chief Manager, T/L Batote Div Mgr. SFC Ramban Page 16 of 33 Order in Petition No. 62/TT/2018

68 Felling of Trees bill 17.11.2015 Div Mgr. SFC Ramban Chief Manager, T/L Batote

69 Supplementary felling of trees 30.11.2015 Chief Manager, T/L Batote Nodal Officer, Jammu

70 Felling of trees in Ramban District 21.12.2015 Div. Manager, SFC Ramban/Batote CM, TLO Batote

71 Diversion of forest land instruction to DFO 22.12.2015 Administrative officer, CCF' office, Jammu CF, Jammu &Doda

72 Supplementary felling of trees in Batote Division 31.12.2015 DFO, Ramban Range officer Ramban, Banihal

73 Felling of conifer trees in Private and Govt. Land 1.4.2016 CM, TLO Batote DC, Ramban

74 Diversion of Forest Land and supplementary felling of trees 28.4.2016 Range officer, Batote DFO, Batote

75 Diversion of Land & Supplementary felling of trees in Batote division 25.5.2016 DFO,Batote Forest Division CF, Doda

76 Use of forestry land for non- forestry purpose 21.8.2016 Principal CCF,

77 Additional marking list of trees in Doda Division 24.8.2016 DFO, Ramban CF, Doda

78 Additional Marking List of trees in Banhal & Ramban 6.9.2016 CF, Doda CCF, Jammu

79 Supplementary administrative approval 02.12.2016 CCF,Jammu Govt. Order

80 letter from General Manager J&K State forest Corporation regarding Additional Tree felling charges 31.12.2016 GM, J&K SFC, Jammu Chief Manager, TL Batote

81 Release of Payments to JKSFC 21.2.2017 DivMgr, J&K SFC, Ramban Asset, Gen Mgr,, T/L Batote

(ii) ROW and Court Cases:-

a) There were continuous ROW issues and court cases at various locations which started from AprIl, 2013 and continued till October, 2016. Major disturbed locations were Tower location 73,74,75 and 76 for which letters were written by petitioners representative to various authorities such as Tehsildar, SDM, Deputy Commissioner etc. requesting for administrative measure to carry out the work. Also there were court cases which further delayed the execution of the asset. Court case was filed by Bidya Ram of Tehsil Sana on 28.6.2013 for which the judgment was issued on 30.9.2015. Further case was filed by Mohan Singh Jamwal and Chursingh Page 17 of 33 Order in Petition No. 62/TT/2018 on 29.12.2015 and 5.6.2015 respectively for which the orders were issued on 8.9.2016 and 18.1.2016 respectively.

b) The ROW issue had started from 2013, because work could not be started in Banihal before the finalization of route in Pir- Panjal. PDD refused to follow the originally envisaged 132 kV corridor after which a new route was surveyed which was further diverted by SASE (Snow and Avalanche Study Establishment), a Ministry of Defence establishment in Pir- Panjal. The final route could only be finalized in late 2012 and only after that the work could be started at Banihal and other places.

c) Further, the ROW issue at four locations in Banihal, which is prone to extreme winter conditions like sub-zero temperature, heavy snowfall and avalanches, was resolved in October, 2016. The work could be restarted thereafter in April, 2017 after the winter. Also, two of the towers were special towers viz DD+18 which took time to erect and the whole work was done manually as no machinery could reach these hilly sites. The chronology of event is as under:- HINDRANCE / COMMUNICATION Date From To

1 Request for administrative measures at Tower Loc-68/0 to 77/0 6.4.2013 CM, Powergrid Tehsildar, Banihal

2 Demand of high compensation from land owners 17.4.2013 CM, Powergrid Deputy Commissioner, Udhampur

3 Request to expedite the land acquisition cases. 14.5.2013 CM, Powergrid Land collector, Narwal

4 Land acquisition in Udhampur district 28.5.2013 Deputy manager , Powergrid The collector land acquistaion, Udhampur

5 RoW problem in banihal area 17.6.2013 CM, Powergrid The SDM, Banihal

6 Regarding Inordinate delay in the construction activities 18.2.2014 CM, Powergrid The wing commander

7 RoW problem in banihal area 12.3.2014 CM, Powergrid The tehsildar, Ramban Page 18 of 33 Order in Petition No. 62/TT/2018

8 Row Problem in village Kembal Danga 19.5.2014 Deputy manager , Powergrid The assistant commissioner (Revenue), Udhampur

9 Regarding preparation of Revenue paper 24.6.2014 CM, Powergrid The SDM, Banihal

10 Regarding release of land acquisition payment 5.9.2014 Deputy manager , Powergrid The collector land acquisition, Udhampur

11 Payment of compensation 15.9.2014 The collector,Land Acquisition, Jammu The tehsildar, Udhampur

12 Regarding construction activities stopped 22.10.2014 The ED, Jammu The Deputy Commissioner, Jammu

13 Request for administrative measures for location under village Tethar 19.11.2014 CM, Powergrid Deputy Commissioner, Ramban

14 Request for joint visit of revenue and forest officials 23.12.2014 CM, Powergrid The assistant commissioner (Revenue), Udhampur

15 Regarding RoW issue in village Mansar, Udhampur 17.4.2015 CM, Powergrid The Addl. DM, Udhampur

16 Request for Private negotiation meeting to solve the issue 17.4.2015 CM, Powergrid Divisional Commissioner , Udhampur

17 RoW problem in Banihal 28.4.2015 CM, Powergrid Deputy Commissioner , Udhampur & Jammu

18 Request for administrative measures for location under village Tethar 5.5.2015 ED, Powergrid Divisional Commissioner , Jammu

19 Request for administrative measures for location under village Tethar 19.6.2015 ED, Powergrid Divisional Commissioner , Jammu

20 Request for administrative measures for 4 Nos. pending location at Tethar 18.8.2015 CM, Powergrid Deputy Commissioner, Ramban

21 Request for administrative measure for Row at LoC- 73,74,75,76 18.8.2015 AGM, Powergrid DC,Jammu

22 To sort the RoW issue 21.8.2015 DC, Jammu DC,Ramban

23 Request for administrative measures at Row locations 31.8.2015 CM, Powergrid Deputy Commissioner, Ramban

24 Request for administrative measures at Row locations 4.9.2015 Manager, Powergrid Asst. Commissioner Rev.,Ramban

25 Request for administrative measures at Row locations 27.10.2015 CM, Powergrid DC,Ramban

26 Request for administrative measures at Row locations 27.11.2015 CM, Powergrid grid SDM,Banihal

27 Request for administrative measures at Row locations 30.12.2015 CM, Powergrid DC,Ramban Page 19 of 33 Order in Petition No. 62/TT/2018

28 Request for administrative measures at Row locations 30.12.2015 CM, Powergrid DC,Ramban

29 Request for administrative measures at Row locations 6.2.2016 CM, Powergrid SDM,Banihal

30 Request for administrative measures at Row locations 26.3.2016 CM, Powergrid Tehsildar,Banihal

31 Request for administrative measures at Row locations 28.4.2016 CM, Powergrid SDM,Banihal

32 Request to direct SHO for security 15.5.2016 CM, Powergrid Tehsildar,Banihal

33 For deployment of Police 31.5.2016 Addl. DC, Ramban SP,Ramban

34 Request for administrative measures 10.6.2016 CM, POWERGRID Tehsildar,Banihal

35 For deployment of Police including CRPF 27.6.2016 Addl. DC, Ramban SP,Ramban

36 Request for administrative measures 14.10.2016 Asst GM, Powergrid SDM,Banihal

37 Row at LoC-73/0 to 76/0 17.10.2016 Asst GM, Powergrid ID Asst. Commissioner Rev.,Ramban

38 Row at LoC-73/0 to 76/0 17.10.2016 Asst GM, Powergrid Asst. Commissioner Rev.,Ramban Court cases Court Case Start date End date

1 Court Case by Inhabitants of Sahan 7.7.2012 25.9.2012

2 Court Case at Sana Ramban by Bidya Ram S/o Masu 28.6.2013 30.9.2015

3 Court Case at Sana Ramban by Chur Singh and Others 5.6.2015 18.1.2016

4 Court Case at by Mohan Singh Jamwal and others 29.12.2015 8.9.2016

19. BRPL, Respondent No. 12, has made submissions vide affidavit dated 11.9.2018. BRPL has submitted that time overrun is entirely attributable to the slackness of the petitioner in the project management for which petitioner is solely responsible and that the petitioner has also not submitted CPM & PERT Chart. In response, petitioner, vide affidavit dated 14.9.2018, has submitted CPM & PERT Chart and further submitted the detailed explanation of schedule vs actual as below: Activity Schedule Actual Remarks, if any From To From To

1 Investment approval by board - 2.7.2010

2 LoA 2.8.10 2.8.10 26.7.10 26.7.10 No delay/within schedule

3 Supplies 29.11.10 29.11.12 10.12.10 27.5.17 This activity is not critical.

4 Forest 8.10.10 10.10.11 8.2.11 2.12.16 Initially J&K agreed to Page 20 of 33 Order in Petition No. 62/TT/2018 clearance provide corridor for 400 kV Kishenpur-New Wanpoh D/c line for crossing Pir Panjal mountain range by dismantling their existing

132 kV line section (about 7-8km). But at later stage Power development department (PDD), Govt. of J&K refused to provide their 132kV corridor. Since PDD refused to provide the corridor at the later stage after Investment approval of the said line, the final route finalization for forest stretch also got delayed and first letter for Permission of work in Forest Land was communicated vide letter dated 18.1.2011.

5 Foundation 31.12.10 1.1.13 27.1.11 27.3.17 There is delay on account of forest & wildlife clearance and ROW issue.

6 Tower Erection 3.3.11 25.3.13 10.5.11 20.7.17

7 Stringing 1.7.11 29.05.13 6.1.12 25.7.17

8 Testing & Commissioning 30.5.13 1.7.13 25.7.17 29.7.17

20. We have considered the submissions made by the petitioner and respondents. The delay of 49 months in commissioning is mainly because of forest & wildlife clearance and ROW issue at various locations and due to Court cases. After investment approval dated 2.7.2010, LOA was issued on 26.7.2010 i.e. before the scheduled date of 2.8.2010. Thus, there is no delay on part of LOA. Further, in the 28th SCM and 29th SCM held on 23.2.2010 and 29.12.2010 respectively, PDD J&K agreed to provide corridor for 400 kV Kishenpur - New Wanpoh D/C line for crossing Pir - Panjal mountain range by dismantling their existing 132 kV line section and accordingly, permission of work in Forest Land was communicated vide letter dated 18.1.2011. However, at a later stage, PDD vide letter dated 16.4.2011 refused to provide their 132 kV corridor, which resulted in delay Page 21 of 33 Order in Petition No. 62/TT/2018 of the final route finalization for forest stretch. Thus, the variation in time period from 29.12.2010 to 21.2.2017 (63 months 24 days, excluding 10 months timeline as per MOEF guidelines) was due to forest & wildlife clearance which was beyond the control of the petitioner. Further, delay due to ROW issues from 6.4.2013 to 17.10.2016 (42 months 12 days) and due to Court cases from 7.7.2012 to 8.9.2016 (50 months 2 days) are subsumed in time duration of forest & wildlife clearance and were also beyond the control of the petitioner. The summary of facts as discussed above is given hereunder: Reason for time over- Duration Period Remarks

1 Forest & wildlife clearance 29.12.2010 to 21.2.2017

63 months 24 days excluding 10 months timeline as per MOEF guidelines

2 Row issues 6.4.2013 to 17.10.2016 _ Time period from 6.4.2013 to 17.10.2016 ( 42 months

12 days) subsumed in S.no-1

3 Court cases 7.7.2012 to 8.9.2016 _ Time period from 7.7. 2012 to 8.9.2016 (50 months 2 days) subsumed in s.no-1

4 Total delay incurred due to various factors such as Forest & wildlife clearance, Row issues and court cases.

63 months 24 days

5 Total delay corresponding to the Asset 49 months . The total delay incurred due to various factors such as forest & wildlife clearance, ROW issues and court cases is of 63 months 24 days, while there has been delay of 49 months in commissioning the asset under consideration. Accordingly, the delay of 49 months is condoned. Incidental Expenditure During Construction (IEDC) & Interest During Construction (IDC) Page 22 of 33 Order in Petition No. 62/TT/2018

21. The petitioner has claimed IEDC of `2520.32 lakh for the asset. The petitioner has claimed IEDC as on COD, which is within the percentage on hard cost as indicated in the abstract cost estimate. In the instant petition, less than 5% of hard cost is indicated as IEDC in the abstract cost estimate. Hence, the entire IEDC claimed by the petitioner is allowed.

22. The petitioner has claimed IDC of `11216.42 lakh for the asset. The petitioner has submitted the statement showing discharge of IDC liability as on COD. However, in the Statement showing IDC discharged up to COD, the petitioner has not indicated the floating rate of interest of SBI loans deployed. The IDC on cash basis up to the COD has been worked out on the basis of the loan details given in the Statement showing discharge of IDC and Form-9C for the asset. The petitioner is directed to submit information on interest rates, corresponding to the quarterly loans as depicted in the Statement showing IDC discharged up to COD, at the time of truing-up. Further, the petitioner has submitted that there is no default in the payment of interest.

23. Following assumptions have been made to work out the IDC on cash basis as on COD in the instant case: A. Rate of Interest for all the SBI loans having floating rate of interests has been considered as 8.90% i.e. for loans of SBI (2013-14) (Q1), SBI (2014-15) (Q1), SBI (2015-16) (Q2), SBI (2015-16) (Q4), SBI (2016-17) (Q4) and 7.95% for SBI (2017-2018) (Q1). B. Dates of drawl of all the SBI loans have been considered as mid of the respective quarters to simplify the IDC working. Page 23 of 33 Order in Petition No. 62/TT/2018

24. The IDC claimed and considered as on COD and summary of discharge of IDC liability up to COD and thereafter for the purpose of tariff determination subject to revision at the time of truing up is as below: (` in lakhs) claimed as certificate considered as on COD Discharged upto COD Discharged in 2017-18 Discharged in 2018-19 11216.42 11216.42 10019.36 1086.80 110.26

25. The balance portion of IDC discharged after COD has been considered in additional capital expenditure. The allowed/capitalized IDC shall be reviewed at the time of truing up, on submission of details regarding floating Interest rates of SBI loans. Initial spares

26. Regulation 13(d) of the 2014 Tariff Regulations provides that initial spares shall be capitalized as a percentage of plant and machinery cost upto cut-off date, subject to following ceiling norms:- (d) Transmission System Transmission line: 1.00% Transmission sub-station (Green Field): 4.00% Transmission sub-station (Brown Field): 6.00%

27. The petitioner has claimed `717.25 lakh as initial spares for the asset corresponding to Transmission Line. Detailed calculation of excess Initial spares claimed in respect of the above mentioned asset has been deducted Page 24 of 33 Order in Petition No. 62/TT/2018 to arrive at the Capital Cost considered for the purpose of tariff in the present petition, is as below: (` in lakhs)

28. Further, the petitioner, vide affidavit dated 29.10.2018, has submitted that the petitioner has discharged Initial Spare as on COD is `645.52 lakh. Hence, it is presumed that the total allowable Initial Spare of `405.34 lakh, as indicated above, would have been discharged as on COD.

29. The following capital cost as on COD, after taking into account the allowable IEDC, IDC and initial spares, is considered for the computation of tariff for the asset :- (` in lakh) Capital Cost Claimed as on COD Less: IDC disallowed (Excess claim) Less: IDC disallowed (Un- discharged) Less: Excess Initial spare Capital Cost considered as on 52915.15 0.00 1197.06 311.91 51406.18 Additional Capital Expenditure (ACE)

30. Clause (1) of Regulation 14 of the 2014 Tariff Regulations provides as under:- Plant & Machine ry Cost as on cut-off date Total capital after IDC/IED deductio Spares claime Propo rtionat Spare claime Ceiling limit Spares worked Excess claimed a b c d=b*c/ f=((b-

d)*e)/(100 -e)%

1 40845.68 40845.68 717.25 717.25 1.00% 405.34 311.91 Page 25 of 33 Order in Petition No. 62/TT/2018 (1) The capital expenditure in respect of the new project or an existing project incurred or projected to be incurred, on the following counts within the original scope of work, after the date of commercial operation and up to the cut-off date may be admitted by the Commission, subject to prudence check:

(i) Un-discharged liabilities recognized to be payable at a future date;

(ii) Works deferred for execution;

(iii) Procurement of initial capital spares within the original scope of work, in accordance with the provisions of Regulation 13;

(iv) Liabilities to meet award of arbitration or for compliance of the order or decree of a court; and

(v) Change in Law or compliance of any existing law: Provided that the details of works asset wise/work wise included in the original scope of work along with estimates of expenditure, liabilities recognized to be payable at a future date and the works deferred for execution shall be submitted along with the application for determination of tariff.

31. Clause (13) of Regulation 3 of the 2014 Tariff Regulations defines cut-off date as under:- cut-off date means 31st March of the year closing after two years of the year of commercial operation of whole or part of the project, and in case the whole or part of the project is declared under commercial operation in the last quarter of the year, the cut-off date shall be 31st March of the year closing after three years of the year of commercial operation.

32. The cut-off date for the instant asset is 31.3.2020. The petitioner, vide Auditor Certificate dated 8.12.2017, has claimed estimated Additional Capital Expenditure (ACE) projected to be incurred `1793.30 lakhs and `1196.65 lakh for year 2017-18 and 2018-19 respectively. Further the petitioner has claimed the entire ACE under Regulation 14(1). In addition, the petitioner has also claimed the discharge of IDC and initial spare liability during 2017-18 & 2018-19 in respect of the asset. Page 26 of 33 Order in Petition No. 62/TT/2018 Accordingly, the ACE claimed by the petitioner and allowed up to 31.03.2019 is summarized in the table below:- (` in lakh) 2017-18 2018-19 Claimed 1793.30 1196.65 Allowed** 2880.09 1306.92 **Discharged IDC and initial spare added in the respective year add cap.

33. The capital cost considered for the purpose of computation of tariff is as follows:- (` in lakh) Expenditure up to COD 2017-18 2018-19 Total Estimated Completion Cost up to 31.3.2019 51406.18 2880.09 1306.92 55593.19 Debt-Equity Ratio

34. This has been dealt with in line with Clause 1 and 5 of Regulation 19 of the 2014 Tariff Regulations.

35. The petitioner has claimed debt: equity ratio of 70:30 as on the date of commercial operation. Debt: equity ratio of 70:30 is considered as provided in Regulation 19 of the 2014 Tariff Regulations. The details of debt- equity ratio in respect of the Asset as on the date of commercial operation and as on 31.3.2019 are as under:- (` in lakh) Asset Particular Capital cost as on Capital cost as on 31.3.2019 Amount % Amount % Debt 35,984.32 70.00 38915.23 70.00 Equity 15,421.85 30.00 16677.96 30.00 Total 51406.18 100.00 55593.19 100.00 Page 27 of 33 Order in Petition No. 62/TT/2018 Return on Equity

36. This has been dealt with in line with Clause (1) and (2) of Regulation 24 and Clause (2) of Regulation 25 of the 2014 Tariff Regulations.

37. The petitioner has submitted that it is liable to pay income tax at MAT rate, the RoE has been calculated @ 19.610% after grossing up the RoE with MAT rate of 20.961% as provided under Regulation 25(2)(i) of the 2014 Tariff Regulations. As per Regulation 25(3) of the 2014 Tariff Regulations, the grossed up rate of RoE at the end of the financial year shall be trued up based on actual tax paid together with any additional tax demand including interest thereon duly adjusted for any refund of tax including interest received from the IT authorities pertaining to the 2014-19 period on actual gross income of any financial year.

38. We have considered the submissions made by the petitioner and respondent. Regulation 24 read with Regulation 25 of the 2014 Tariff Regulations provides for grossing up of return on equity with the effective tax rate for the purpose of return on equity. It further provides that in case the generating company or transmission licensee is paying Minimum Alternative Tax (MAT), the MAT rate including surcharge and cess will be considered for the grossing up of return on equity. Accordingly, the MAT rate applicable during 2013-14 has been considered for the purpose of return on equity, which shall be trued up with actual tax rate in accordance with Regulation 25 (3) of the 2014 Tariff Regulations. Accordingly, the RoE allowed is as follows:- (` in lakh) Page 28 of 33 Order in Petition No. 62/TT/2018 Asset-I Particulars 2017-18 (pro-rata) 2018-19 Opening Equity 15421.85 16285.88 Addition due to Additional Capitalization 864.03 392.08 Closing Equity 16285.88 16677.96 Average Equity 15853.87 16481.92 Return on Equity (Base Rate ) 15.50% 15.50% MAT rate for the Financial year 2013-14 20.961% 20.961% Rate of Return on Equity (Pre-tax) 19.610% 19.610% Return on Equity (Pre-tax) 2078.31 3232.10 Interest on loan (IOL)

39. This has been dealt with in line with Regulation 26 of 2014 Tariff Regulations.

40. IOL has been worked out as under:-

(i) Gross amount of loan, repayment of instalments and rate of interest on actual average loan have been considered as per the petition;

(ii) The yearly repayment for the tariff period 2014-19 has been considered to be equal to the depreciation allowed for that year; and

(iii) Weighted average rate of interest on actual average loan worked out as per (i) above is applied on the notional average loan during the year to arrive at the interest on loan.

41. Based on above, details of IOL calculated are as follows:- (` in lakh) Particulars Asset-I 2017-18 (pro-rata) 2018-19 Gross Normative Loan 35984.32 38000.39 Cumulative Repayment upto previous Year 0.00 1848.34 Net Loan-Opening 35984.32 36152.04 Addition due to Additional Capitalization 2016.06 914.84 Repayment during the year 1848.34 2874.12 Page 29 of 33 Order in Petition No. 62/TT/2018 Net Loan-Closing 36152.04 34192.77 Average Loan 36068.18 35172.41 Weighted Average Rate of Interest on Loan 8.5794% 8.5539% Interest on Loan 2068.60 3008.60 Depreciation

42. This has been dealt with in line with Regulation 27 of 2014 Tariff Regulations.

43. Depreciation has been calculated annually based on Straight Line Method at the rates specified in Appendix-II to the 2014 Tariff Regulations.

44. Details of the depreciation allowed are as under:- (` in lakh) Particulars Asset-I 2017-18 (pro-rata) 2018-19 Opening Gross Block 51406.18 54286.27 Additional Capital expenditure 2880.09 1306.92 Closing Gross Block 54286.27 55593.19 Average Gross Block 52846.22 54939.73 Rate of Depreciation 5.2321% 5.2314% Depreciable Value 46331.64 48148.41 Remaining Depreciable Value 46331.64 46300.07 Depreciation 1848.34 2874.12 Operation and Maintenance Expenses (O&M Expenses)

45. This has been dealt with in line with Clause 29(4)(a) of 2014 Tariff Regulations.

46. The O&M Expenses claimed by the petitioner are as under:- Page 30 of 33 Order in Petition No. 62/TT/2018 (` in lakh) 2017-18 2018-19 248.57 383.67

47. The petitioner has submitted that O&M Expenses for the tariff period 2014-

19 had been arrived at on the basis of normalized actual O&M Expenses during the period 2008-09 to 2012-13. The petitioner has further submitted that the wage revision of the employees is due during 2014-19 and actual impact of wage hike effective from a future date has not been factored in fixation of the normative O&M rates specified for the tariff block 2014-19. The petitioner has submitted that it would approach the Commission for suitable revision in norms for O&M Expenses for claiming the impact of wage hike during 2014-19, if any.

48. BRPL has submitted that any increase in employee cost, if any, due to wage revision must be taken care by increasing the productivity levels of the petitioner company and the beneficiaries should not be burdened over and above the provisions in the 2014 Tariff Regulations. In response, the petitioner filed its rejoinder dated 14.9.2018 and submitted that O&M for the tariff period 2014-19 had been arrived at on the basis of normalized actual O&M Expenses during the period 2008-09 to 2012-13. The petitioner has further submitted that the wage revision of the employees is due during 2014-19 and actual impact of wage hike effective from a future date has not been factored in fixation of the normative O&M rates specified for the tariff block 2014-19. The petitioner has submitted that it would approach the Page 31 of 33 Order in Petition No. 62/TT/2018 Commission for suitable revision in norms for O&M Expenses for claiming the impact of wage hike during 2014-19, if any. Analysis/Decision

49. We have considered the submissions of petitioner and the BRPL. The O&M Expenses have been worked out as per the norms specified in the 2014 Tariff Regulations. Accordingly, the O&M Expenses allowed is given as under: (` in lakh) Element 2017-18 (Pro-rata)* 2018-19

4 nos. 400 kV bays 244/365X66.51X4 =177.84 68.71X4 =274.84

400 kV D/C Kishenpur-New Wampoh line 244/365x0.780x135.02 =70.40 0.806x135.02 =108.82 Total calculated 248.24 383.66 *pro-rata has been calculated from 31.7.2017 to 31.3.2018=244 days. Interest on Working Capital (IWC) Rate of interest on working capital

50. As per proviso 3 of Regulation 28 of the 2014 Tariff Regulation, SBI Base Rate Plus 350 bps as on 1.04.2017 (i.e.12.60%) has been considered for the instant asset, as the rate of interest on working capital.

51. Accordingly, the interest on working capital is summarized as under:- (` in lakh) Particulars Asset-I 2017-18 (Pro-rata) 2018-19 Maintenance Spares 55.71 57.55 Page 32 of 33 Order in Petition No. 62/TT/2018 O&M expenses 30.95 31.97 Receivables 1591.87 1618.96 Total 1,678.53 1,708.48 Interest 141.38 215.27 Annual Transmission charges

52. In view of the above, the annual transmission charges being allowed for the instant asset is summarized hereunder:- (` in lakh) Particulars Asset-I 2017-18 (pro-rata) 2018-19 Depreciation 1848.34 2874.12 Interest on Loan 2068.60 3008.60 Return on Equity 2078.31 3232.10 Interest on Working Capital 141.38 215.27 O&MExpenses 248.28 383.66 Total 6384.91 9713.75 Filing fee and the publication expenses

53. The petitioner has sought reimbursement of fee paid by it for filing the petition and publication expenses, in terms of Regulation 52 of the 2014 Tariff Regulations. The petitioner shall be entitled for reimbursement of the filing fees and publication expenses in connection with the present petition, directly from the beneficiaries on pro-rata basis in accordance with clause (1) of Regulation 52 of the 2014 Tariff Regulations. License fee and RLDC Fees and Charges

54. The petitioner has requested to allow the petitioner to bill and recover License fee and RLDC fees and charges, separately from the respondents. Page 33 of 33 Order in Petition No. 62/TT/2018 We are of the view that the petitioner shall be entitled for reimbursement of licence fee and RLDC fees and charges in accordance with Clause (2)(b) and (2)(a), respectively, of Regulation 52 of the 2014 Tariff Regulations. Service Tax

55. The petitioner has sought to recover Service Tax on transmission charges separately from the respondents, if at any time service tax on transmission is withdrawn from negative list in future. We have considered the submission of the petitioner. Service tax is not levied on transmission. Further, service tax is subsumed by GST and hence petitioners prayer is infructuous. Goods and Services Tax

56. The petitioner has prayed for reimbursement of tax, if any, on account of implementation of GST. GST is not levied on transmission service at present and we are of the view that petitioners prayer is premature. Sharing of Transmission Charges

57. The transmission charges shall be recovered on monthly basis in accordance with Regulation 43 of the 2014 Tariff Regulations and shall be shared by the beneficiaries and long term transmission customers in Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010 as amended from time to time.

58. This order disposes of Petition No. 62/TT/2018. Page 34 of 33 Order in Petition No. 62/TT/2018 Sd/- Sd/- Sd/- (I.S.Jha) (Dr. M. K. Iyer) (P. K. Pujari) Member Member Chairperson