Vinay Heavy Equipments & Foundation Pvt. Ltd. v. Oriental Structural Engineers Pvt. Ltd. & Anr.
Factual and Procedural Background
This petition under Section 34 challenged an arbitral award dated 28th June 2010 passed by the learned Sole Arbitrator (the Executive Director (Retd.) of the Airport Authority of India). The petitioner is Vinay Heavy Equipments & Foundation Pvt. Ltd. and the respondents are Oriental Structural Engineers Pvt. Ltd. & anr. The petitioner had been awarded piling work at Chidambaram Bypass (sites 301–304) by the respondent, under a work order dated 29th February 2008 with a contract value of Rs.1,42,25,000/-. The contract commencement date was 10th March 2008. Disputes arose between the parties, the respondent invoked arbitration and a sole arbitrator was appointed. The arbitral award determined multiple claims and counterclaims between the parties and fixed amounts payable and receivable, together with interest.
Legal Issues Presented
- Whether the calculation(s) in the arbitral award concerning mobilisation payments, recoveries and net dues contained errors warranting interference under Section 34.
- Whether the 5% retention under Clause 6.05 (retention/retention money) should be treated as an adjustment/credit to the contractor.
- Whether the Tax Deducted at Source (TDS) and the description "PRW" in the work order affect the calculation of amounts treated as paid to the contractor.
- Whether the arbitral award should be upheld, modified or set aside in light of the above accounting/contentions.
Arguments of the Parties
Petitioner's Arguments
- The petitioner (through Mr. Thomas Franklin Caesar) submitted that the arbitral award contained calculation errors.
- First, the petitioner argued that entire mobilisation charges were not paid to the contractor because under Clause 6.05 five per cent of the gross value of the work was deducted; that deducted amount ought to have been credited to the contractor.
- Second, the petitioner argued that the TDS was to be deducted in respect of "PRW" (as described in the work order) and not the contractor, implying the TDS should not have been treated as part of amounts paid to the contractor.
Respondents' Arguments
- The respondents (through Mr. Anil Airi) submitted that the retention (5%) should be considered as having been advanced and, because the contractor abandoned the work, no adjustment/credit was due to the contractor for that retention.
- The respondents further explained that "PRW" is merely the description of the contractor (Piling Related Work) as defined in Clause 1.03 of the Sub Contract Work Order and is not a separate entity; therefore deductions described as TDS in respect of PRW were effectively deductions from amounts paid to the contractor and must be included in the recoveries considered by the Arbitrator.
- The respondents also contended that the arbitrator had correctly calculated recoveries and payments and that the TDS and other recoveries were properly included in the arbitrator's computation.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Court summarized the arbitral findings and the parties' submissions and addressed the two principal accounting/contention points raised by the petitioner.
- The Court noted the arbitrator's findings: mobilisation free charge of Rs.10,00,000 and mobilisation advance of Rs.7,11,250 (total Rs.17,11,250) were paid; the contractor did not remain on site even for four days and thus was liable to refund mobilisation amounts after deduction of work actually done. The arbitrator allowed a partial claim for bentonite material (Rs.99,968 plus 10% pursuant to clause 6.06, totaling Rs.1,09,964.80) and rejected most other claims while awarding interest at 12% for relevant claims. On counterclaims, the arbitrator determined the contractor was due a net amount of Rs.4,33,178 after applying rates and recoveries.
- On the petitioner's contention regarding TDS and the meaning of "PRW", the Court accepted the respondents' explanation that PRW is a description of the subcontractor (the contractor) and not a separate entity; accordingly the TDS/deductions described in the work order are to be treated as part of the recoveries effected and included in the amounts considered as paid to the contractor. The Court therefore rejected the petitioner's submission that TDS should not be treated as an amount paid to the contractor.
- On the petitioner's contention regarding the 5% retention under Clause 6.05, the Court observed that Rs.50,000 had been retained by the respondent and not released to the petitioner; because the retention had been retained and not paid out, the Court held that the adjustment in respect of that Rs.50,000 deserved to be granted to the petitioner.
- Accordingly, the Court upheld the arbitral award subject to the adjustment for the retained Rs.50,000, arriving at a modified amount due from the contractor to the respondent. The Court applied the arbitrator's interest determination (simple interest at 12% per annum) up to the date of the Court's order and imposed a higher rate (14% per annum) if payment was not made within three months.
Holding and Implications
FINAL HOLDING: The petition is disposed of and the arbitral award is upheld with a modification for Rs.50,000 retained by the respondent.
Direct effect on the parties:
- The Court held that the amount due to the respondent from the contractor is Rs.12,28,072 (after adjusting Rs.50,000 retained under Clause 6.05).
- Interest: The Arbitrator's grant of simple interest at 12% per annum shall apply until the date of this order. If the payment is not made within three months from the date of the order, interest at 14% per annum shall be payable by the contractor to the respondent.
- The petition under Section 34 is disposed of on the above terms.
No broader precedent or legal principle beyond the application of the arbitral award in the present facts is discussed in the opinion.
$~13 * IN THE HIGH COURT OF DELHI AT NEW DELHI th
Date of Decision: 20 November, 2018 + O.M.P. 696/2010
VINAY HEAVY EQUIPMENTS & FOUNDATION PVT LTD. ..... Petitioner
Through: Mr. Thomas Franklin Caesar, Advocate (M-9818805668).
versus
ORIENTAL STRUCTURAL ENGINEERS PVT LTD
& ANR. ..... Respondents
Through: Mr. Anil Airi, Senior Advocate with Mr. Ravi K. Chandna, Ms. Sadhna Sharma, Ms. Sukanya Lal & Mr.
Satyam Bhatia, Advocates (M-
9711752002).
CORAM:
JUSTICE PRATHIBA M. SINGH
Prathiba M. Singh, J. (Oral)
1. The present petition under Section 34 has been preferred challenging the award dated 28thJune, 2010 passed by the Ld. Sole Arbitrator who was the Executive Director (Retd.) of the Airport Authority of India.
2. The Petitioner - Vinay Heavy Equipments & Foundation Pvt. Ltd. was awarded the work "Piling work at Chidambaram Bypass at 301, 302, 303 & 304" vide Order No.OSE/TNRSP01/PRW-WO/274 dated 29th February, 2008. The contract was awarded by the Respondents - Oriental Structural Engineers Pvt. Ltd. The total value of the work was Rs.1,42,25,000/-. The date of start, as per the contract, was 10thMarch, 2008. The work order was accepted by the contractor, however, disputes arose between the parties. The Respondent invoked arbitration and the Ld. Sole Arbitrator was appointed.
1
3. The Respondent raised various claims and the contractor raised counter claims which are extracted herein below:
"Claim No.1 - for a sum of Rs.17,11,250.00 being the advance payment along with interest @ 18% p.a. to be refunded to OSEPL by M/s Vinay Heavy Equipments & Foundation Pvt. Ltd.
Claim No.2 - for a sum of Rs.1,34,434.00 being the amount on account of Crane and Monkey hammer to be paid to OSEPL by M/s Vinay Heavy Equipments & Foundation Pvt. Ltd.
Claim No.3 - for a sum of Rs.1,99,968.00 being the amount for providing bentonite material & for organizing the mixing & swelling arrangements to be paid to OSEPL by M/s Vinay Heavy Equipments & Foundation Pvt. Ltd.
Claim No.4 - for a sum of Rs.50,000.00 being the amount for scrap fabricating material to be paid to OSEPL by M/s Vinay Heavy Equipments & Foundation Pvt. Ltd.
Claim No.5 - for losses and damages on account of delay towards loss of Head Office overheads and profits (Rs.13,65,600.00) and loss of site office overheads (Rs.34,14,000.00)
Claim No.6 - for interest at 18% p.a. from 19.06.2008 until date of payment
Claim No.7 - for a sum of Rs.2,22,46,643.00 being the penalty levied along with interest @ 18% p.a. from 23.08.08 till date of payment to be paid to OSEPL by M/s Vinay Heavy Equipments & Foundation Pvt. Ltd. Claim No.8 - for cost of Arbitration. Counter Claims of Respondents
2
Counter Claim No.1 - for payment of Rs.10,97,000/- for the work done between 02.04.2008 and 09.06.2008. Counter Claim No.2 - for payment of Rs.17,40,000/- towards idle charges for the machineries kept idle at site for want of clearance from Claimant's consultant to erect liner up to depth of refusal level. Counter Claim No.3 - for payment of Rs.28,25,600/- as damages.
Counter Claim No.4 - for payment towards interest on payments due at the rate of 18% per annum. Counter Claim No.5 - for cost of Arbitration proceedings."
4. The Ld. Sole Arbitrator, under Claim No.1, records the fact that the contractor had been paid mobilisation charges and mobilisation advance to the tune of Rs.10,00,000/- and Rs.7,11,250/- respectively, constituting a total amount of Rs.17,11,250/-. The case of the Respondent was that the contractor had failed to mobilise the equipment required for completion of the work and in fact it is the admitted position on record that the contractor did not stay even for a period of four days at site despite the mobilisation charges and advance having been paid by the Respondent. Considering this position, the Ld. Arbitrator came to the conclusion that the contractor is liable to pay back the mobilisation charges and the mobilisation advance paid to him after deducting the amount of work actually done by the contractor.
5. Claim No.2 of Respondent was rejected. In Claim No.3, the Respondent had claimed a sum of Rs.1,99,968/-. The Arbitrator records as
3
under:
"4.02 The Respondents, on its part, has admitted (Exh C-12 dated 04.11.2008) their liability for a sum of Rs.99,968.00 on account of cost of bentonite material but have denied their liability to the charges for mixing and swelling as they claimed to have done the operation themselves. During the oral hearing, I had directed the Claimant to submit detailed analysis of their claim of Rs.1,99,968/-. The Claimants could not submit a detailed analysis but orally stated that a lump sum (Emphasis supplied) of Rs.1,00,000/- was charged towards organizing, mixing and swelling arrangement of bentonite material."
6. In view of the fact that the Respondent could not place evidence supporting the claim of Rs. 1,99,968/-, but the contractor had admitted the liability for the sum of Rs. 99,968/-, this claim was allowed by the Arbitrator in the following terms:
"4.03 I have carefully examined the documents and have heard the Learned Counsels for the parties at length. There is absence of any detailed analysis of the claim. In view of the facts and circumstances of the case, and keeping in view the liability admitted by the Respondent for the cost of the material, I allow this claim to the extent of the cost of material supplied i.e. Rs.99,968/- together with 10% thereupon pursuant to clause 6.06 of the Work Order. This Claim is thus admitted for Rs.1,09,964.80P only."
7. The remaining claims of the Respondent were all rejected except claim for interest where interest @12% was awarded.
8. In respect of the counter claims, the Arbitrator held that a net amount of Rs.4,33,178/- is liable to be paid to the contractor in view of the work done by them. In respect of this claim, the contractor had sought a sum of
4
Rs.10,97,000/-, but the Arbitrator went by the figures given by the Claimant and not refuted by the Respondent. The Arbitrator then applied the rates mentioned in the work order and arrived at a sum of Rs.7,28,000/- as per the said rates as being payable to the contractor.
9. Since the contractor had already made recoveries towards a sum of Rs.2,94,822/- net amount payable to the contractor was held to be Rs.4,33,178/-. The remaining counter claims related to interest and cost.
10. In conclusion, therefore, the Arbitrator awarded a sum of Rs.1,27,872/- calculated in the following manner:
"10.01 The Claimants shall be paid by M/s Vinay Heavy Equipments & Foundation Private Limited (Respondent), under Claim no.1, an amount of
Rs.12,78,072/- as per statement given below, along with simple interest @ 12% per annum w.e.f. 19.06.2008 until the date of realization. A. Total payments made to M/s Vinay Heavy Equipments & Foundation Private Limited (Respondents)
(i) Free Mobilization charge for Rs.10,00,000 Transportation of all necessary plants, equipments, piling rigs, materials, etc. at site and
demobilization on
completion of work.
(ii) Mobilization Advance Rs.17,11,250.00 (@ 5% of value of work)
Total amount Rs.17,11,250.00 B. Dues for M/s Vinay Heavy Equipments & Foundation Private Limited (Respondents)
(i) Work done as per Work Order Rs.7,28,000.00
Rates from March 2008 to June 2008
(ii) Recoveries
5
(a) Diesel issued and other material Debits (i/c pile driving hammers) Rs.2,13,490.63
(b) Crane, Transit mixer and JCB Rs.53,694.18
Charges
(c) Any other expenses incurred Rs.27,637.00
By OSE (TDS 1,113%) Total Recoveries Rs.2,94,821.81 Say .................................... Rs.2,94,822.00 C. Net Amount due B(i) - B(ii) Rs.4,33,178.00 D. Payment due to Claimant Rs.12,78,072.00 From Respondent (A-C) along
with simple Interest @ 12% p.a."
11. The Ld. Counsel for the Petitioner - Mr. Thomas Franklin Caesar submits that there are calculation errors made by the Arbitrator. The first submission is that the entire mobilisation charges were not paid to the contractor. As under Clause 6.05, 5% of the gross value of the work was deducted. Thus, this amount ought to have been given credit for. The second submission is that the TDS was to be deducted in respect of PRW and not the contractor.
12. Mr. Anil Airi, Ld. Senior Counsel for the Respondents submits that insofar as the retention money of 5% is concerned, it should be considered as having been advanced and since the contractor had abandoned, the adjustment is not liable to be given. Insofar as the TDS is concerned, the Ld. Counsel for the Respondents submits that PRW is only a description of the contractor who was supposed to execute the `Piling Related Work (PRW)'. The explanation of the term PRW is mentioned in Clause 1.03 of the Sub Contract Work Order (General Terms and Conditions). The PRW is not another entity but the contractor itself, who is referred as PRW. It is submitted by Mr. Thomas that the TDS was not paid in respect of the
6
expenses which were deducted., The arbitrator has held that the recoveries have been effected to the extent as calculated. This obviously has to include the TDS amount towards the said recoveries. Thus, the TDS amount cannot be removed and is rightly considered as being part of the amount paid to the contractor.
13. The Court has heard the counsels for the parties. Insofar as TDS is concerned, this Court accepts the explanation given by the counsel for the Respondent inasmuch as the work order refers to the sub-contractor as PRW, who is the contractor - Vinay Heavy Equipments & Foundation Pvt. Ltd. The Petitioner is described as a sub-contractor because the Respondent - Oriental Structural Engineers Pvt. Ltd. was the main contractor from the Tamil Nadu Road Sector Project 01.
14. Insofar as the amount of Rs.50,000/-, which was deducted under Clause 6.05 is concerned, as the same was retained by the Respondent and was not released to the Petitioner, the adjustment deserves to be granted. Accordingly, the award is upheld holding that the amount due to the Respondent from the contractor is Rs.12,28,072/-. The Arbitrator has granted interest @ 12% per annum which shall be applicable till date of this order. If the payment is not made within three months, interest @ 14% per annum would be liable to be paid by the contractor to the Respondent.
15. The petition is disposed of with the above terms.
PRATHIBA M. SINGH
JUDGE
NOVEMBER 20, 2018/Rahul