Sumit Chemicals Pvt. Ltd. v. Commissioner of C. Ex., Kanpur
Summary of Tribunal Order — M/s. Sumit Chemicals Pvt. Ltd. (Pronounced 16-12-2015)
Factual and Procedural Background
The appellant, M/s. Sumit Chemicals Pvt. Ltd., appealed against an order-in-original dated 2-1-2014 which denied remission claimed in respect of duty involved in goods destroyed in a fire. The claimed duty amount totalling Rs. 46,19,123/- comprised duty on raw material (Rs. 26,31,955/-), finished goods (Rs. 22,29,617/-) and semi-finished products (Rs. 3,72,325/-). The appellant later dropped the claim of Rs. 26,31,955/- towards raw materials.
The fire occurred in the early morning of 17-1-2012. The fire was reported to the Fire Department at about 6:00–6:17 am; the Fire Department reached the location at 6:23 am. The Fire Department's report attributed the fire to a short circuit and recorded that no foul play was found; it also recorded that some staff were injured and moved to hospital. The appellant notified the Superintendent by letter dated 17-1-2012 of the fire and losses (finished goods, semi-finished products, raw materials and plant & machinery).
On receipt of the remission claim the Department issued a show cause notice dated 15-1-2013 alleging that the fire was due to an electric short circuit that could have been avoided by proper monitoring of electric wiring and fittings, suggesting negligence on the part of the appellant and non-compliance with Electricity Safety Rules. The Department also recorded that no documentary proof was submitted showing that the loss had been claimed from an insurance company. The adjudicating authority rejected the remission claim in entirety and appropriated Rs. 26,31,955/- already deposited by the appellant towards reversal of Cenvat credit on raw material lying in stock. The appellant challenged those findings before the Tribunal.
Legal Issues Presented
- Whether the appellant is entitled to remission of duty in respect of loss by fire of finished goods and semi-finished goods (work-in-progress), where the Fire Department's report attributes the cause to short circuit and records no foul play.
- Whether findings of negligence by the Department (including alleged non‑compliance with Electricity Safety Rules and lack of mitigation or training) justify denial of remission.
- What is the evidentiary burden (onus) on the assessee seeking remission for goods lost/destroyed by fire — specifically whether the onus lies on the assessee to prove goods were destroyed by unavoidable accident/natural causes.
Arguments of the Parties
Appellant's Arguments
- The appellant contested the finding of negligence and the finding that staff were not trained, pointing to the Fire Department's conclusive report which recorded the cause as short circuit and no foul play.
- The appellant said it had been regularly obtaining safety/consent certificates from the Fire Department; the last consent was dated 17-6-2011 (within one year of the fire), which demonstrates safety compliance.
- On mitigation, the appellant relied on the Fire Department report noting that the report of fire was received within 20 minutes of the incident and that employees were injured while dousing the fire, implying reasonable mitigation efforts were made.
- The appellant relied on Tribunal and Supreme Court authorities: (i) Sanskriti Packaging Pvt. Ltd. v. C.C.E. & S. Tax (Tri.-Ahmd.), where remission was allowed where the fire was held accidental and insurance had settled the claim; and (ii) C.C.E. v. Indchem Electronics (S.C.), holding that an assessee is entitled to claim in respect of work-in-progress or semi-finished goods and that claims are only deniable with respect to raw materials lying in stock.
- Accordingly, the appellant sought setting aside of the rejection and allowance of the remission claim (as to finished goods and semi-finished goods / WIP).
Revenue's Arguments
- The Revenue relied upon the impugned order and its findings of negligence and non-compliance with safety rules to deny remission.
- The Revenue relied on the Larger Bench decision in C.C.E. v. Gangeshwar Ltd. (All.), where the question put before the Allahabad High Court was whether the onus lies on the assessee to place sufficient evidence that goods were lost or destroyed by natural causes/unavoidable accident; the High Court answered in favour of the Revenue, holding that the onus lies on the assessee.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Sanskriti Packaging Pvt. Ltd. v. C.C.E. & S. Tax (Tri.-Ahmd.) | Where a fire is held accidental by the Fire Department and the insurance company has settled the claim, remission may be allowable even if Revenue originally treated the fire as avoidable/human error. | The appellant relied on this Tribunal ruling to support allowance of remission where the Fire Department's report attributes the fire to accidental causes and there was an insurance settlement. |
| C.C.E. v. Indchem Electronics (Supreme Court) | The assessee is entitled to claim remission in respect of work-in-progress or semi-finished goods; denial of claim is only proper with respect to raw materials lying in stock. | The appellant relied on this Supreme Court authority to argue entitlement to remission for semi-finished goods/WIP and finished goods, while noting raw material claims may be treated differently. |
| C.C.E. v. Gangeshwar Ltd. (Larger Bench; All.) | Onus lies on the assessee seeking remission to place sufficient evidence proving that goods were lost/destroyed by natural causes or unavoidable accident; the onus cannot be shifted to the Department to disprove the claim. | The Revenue relied on this Larger Bench decision to support the proposition that the appellant bears the burden of proof in seeking remission; the Tribunal considered this contention in its analysis. |
Court's Reasoning and Analysis
The Tribunal considered the rival contentions of the parties and the material before it. The Tribunal found that the adjudicating authority (the Commissioner) had rejected the remission claim based on extraneous considerations, including findings of negligence and inadequate mitigation, despite material from the competent authority — the Fire Department — which (a) attributed the fire to a short circuit, (b) recorded no foul play, and (c) had granted consent to operate the plant (last obtained on 17-6-2011).
The Tribunal gave weight to the Fire Department's report and the consent to operate issued by that competent authority. The Tribunal observed that the Fire Department had recorded that the report of the fire was received within 20 minutes and that employees were injured while attempting to douse the fire — facts that undercut the Department's conclusions about lack of mitigation or training. The Tribunal also took into account the authorities cited by the appellant concerning entitlement to remission for semi-finished goods/WIP and the evidentiary posture in remission claims.
Balancing the material and legal authorities, the Tribunal concluded that the Commissioner had erred in denying remission for finished goods and semi-finished goods (WIP) where the competent authority had certified the fire as accidental and beyond the appellant's control. Accordingly, the Tribunal set aside the impugned order insofar as it denied remission in respect of finished goods and semi-finished goods.
Holding and Implications
HOLDING: The Tribunal set aside the impugned order insofar as remission had been denied in respect of finished goods and semi-finished goods (work-in-progress), and held that the appellant is entitled to remission on the loss of finished goods and semi-finished goods.
Implications and immediate consequences:
- The Tribunal's order provides the appellant with entitlement to remission on the destroyed finished goods and semi-finished goods; the appellant will be entitled to consequential relief(s), if any, in accordance with law.
- As recorded in the adjudication history, the appellant had already dropped the claim in respect of raw materials (Rs. 26,31,955/-) and the adjudicating authority had appropriated that amount towards reversal of Cenvat credit; the Tribunal's order, as expressed in the opinion, addresses remission only for finished goods and semi-finished goods.
- The opinion does not purport to lay down a new general precedent; it resolves the appeal on the particular facts and evidence before the Tribunal, giving decisive weight to the Fire Department's certification of cause and absence of foul play.
Pronounced in open Court on 16-12-2015 (Order per: Anil Choudhary, Member (J)).
[Order per : Anil Choudhary, Member (J)]. - The appellant, M/s. Sumit Chemicals Pvt. Ltd. is in appeal against the order-in-original dated 2-1-2014 by which remission claim arising out of loss by fire have been denied on raw materials, finished goods and work in progress.
2. The appellant suffered fire accident in the early morning on 17-1-2012 and the fire was reported to the Fire Department at 6 am/6.17 am and the fire department reached the place of occurrence at 6.23 am. As per report of the fire department, the reason for fire is short circuit and no foul play has been found. Further as is evident from the report of fire department some staff of the appellant got injured and severely burnt and were moved to hospital/nursing home. The appellant vide letter 17-1-2012 informed the Superintendent about fire incident and loss of finished goods, semi-finished products and raw materials as well as loss of plant & machinery. Pursuant to the receipt of the remission claim, show cause notice dated 15-1-2013 was issued wherein at para 4 of the SCN it is mentioned that it is apparent that incident of fire took place due to electric short circuit which could have been avoided if the appellant had taken proper monitoring of electric wires and fittings thereof. It appears to Revenue that there was negligence on the part of the appellant resulting in loss due to fire. It was further observed that the appellant have not followed the Electricity Safety Rules and further no documentary proof was submitted by the appellant showing total value of loss, inclusive of value of excisable goods destroyed in the said fire accident, having been claimed from any insurance company. Accordingly, SCN proposed to deny remission sought for Rs. 46,19,123/- of duty involved in the goods destroyed in fire comprising of raw material Rs. 26,31,955/-, finished goods Rs. 22,29,617/-, semi-finished product Rs. 3,72,325/-. The appellant dropped the claim of Rs. 26,31,955/- towards raw materials.
3. The appellant contested the SCN and the same was adjudicated by the impugned order rejecting the appellant’s claim in totality and appropriating the amount of Rs. 26,31,955/- already deposited by the appellant towards reversal of Cenvat credit on raw material lying in stock. The appellant has challenged the findings of the ld. Commissioner that there was negligence on their part either in running the factory or in taking measure for mitigating loss. The appellant has demonstrated that they were regularly obtaining safety certificate from fire department for running their plant and the last consent was taken on 17-6-2011 which is within one year of the date of loss. So far finding of the ld. Commissioner, the staff in the factory, it appears, were not given training on regular interval to face such emergent situation like fire. It is stated that there is no basis for such finding in view of the conclusive report of the fire department. So far finding as to lack of effort on the part of the appellant to mitigate loss or reduce loss, the ld. Consultant states that the same is without any basis which is apparent from the report of the fire department which states that report of fire starting was received by the fire department within 20 minutes of the incidence and further some persons/employees of the appellant suffered injury in dousing fire and as such said finding is fit to be set aside. Further, the ld. Consultant for the appellant relies on the ruling of this Tribunal in Sanskriti Packaging Pvt. Ltd. v. C.C.E. & S. Tax, Surat - (Tri.-Ahmd.) wherein it was held that remission claim was rejected by Revenue on the finding that fire accident was due to human error and was avoidable. In view of the report of the fire department that fire was accidental and insurance company has settled the claim, the finding was set aside and the claim was held allowable by this Tribunal. Further it is stated that the issue is settled by the Hon’ble Supreme Court in the case of C.C.E. v. Indchem Electronics - (S.C.) wherein it has been held that assessee is also entitled to claim in respect of work in progress or semi-finished goods and the claim is only deniable on the raw materials lying and destroyed in stock. Accordingly, in view of the above fact that there is no dispute on the quantum of claim, the ld. Consultant prays for setting aside the finding for rejection and allowing the appeal.
4. Ld. AR for Revenue relies on the impugned order. He further relies on the ruling of the Larger Bench of this Tribunal in the case of C.C.E. v. Gangeshwar Ltd. - (All.) wherein the question before Allahabad High Court was whether onus on the assessee to place sufficient evidence and prove that goods were lost or destroyed by natural causes, was by unavoidable accident, the appellant/assessee seeking remission of duty and/or such onus cannot be shifted on the Department to prove otherwise. The Hon’ble High Court answered the question in favour of Revenue thus holding that onus lies on the assessee.
5. Having considered rival contentions, we hold that the ld. Commissioner have erred in rejecting the claim on extraneous considerations, in view of the consent to operate granted by the ‘Fire Department’. Further, the Fire Department (Competent Authority) have certified that there is no foul play, and fire is due to reasons beyond control. In this view of the matter, we set aside the impugned order so far remission have been denied on semi-finished goods or work in progress and the finished goods. The appellant, it is held, is entitled to remission on loss of finished goods and semi-finished goods. The appellant will be entitled to consequential relief(s), if any, in accordance with law.
(Pronounced in the open Court on 16-12-2015)