- Bookmark
- Share
- CaseIQ
Mr. Samir Narain Bhojwani v. M/S. Aurora Properties & Investments
Factual and Procedural Background
This appeal arises from a dispute concerning development rights and obligations under several interlinked agreements relating to a property situated at Versova Link Road, Taluka Andheri. The original development agreement dated 6th October 1996 was between Andheri Kamgar Nagar Co-operative Housing Society Ltd. ("Society") and respondent no.1, M/s. Aurora Properties and Investments, appointing respondent no.1 as the developer. A Lease Deed dated 31st March 1993 covered the property with obligations to construct tenements including for Project Affected Persons and to develop and dispose of remaining Floor Space Index (FSI).
Subsequent agreements included a sub-development agreement dated 22nd September 1999 between respondent no.1 and respondent no.2, Bombay Slum Redevelopment Corporation Ltd. (BSRC Ltd.), transferring development rights with obligations to construct buildings and allocate certain areas.
On 10th March 2003, respondent no.2 and the appellant entered into a registered development agreement, entitling the appellant to 55% of the free sale area and respondent no.2 to 45%, under the Slum Rehabilitation Authority (SRA) scheme which was subsequently converted under later agreements.
Respondent no.1 terminated the 1999 agreement with respondent no.2 in 2005. In 2009, a tripartite agreement involving appellant, respondent no.1, and respondent no.2 was executed referring to earlier agreements. Occupation Certificates for certain wings of the building "Bay View" were obtained in 2012, and the appellant offered possession of identified flats to respondent no.2.
Respondent no.1 filed Suit No. 62/2013 against respondent no.2 seeking declarations of validity of agreements and specific performance. Interim orders restrained the appellant and respondent no.2 from alienating certain flats. An arbitration proceeding resulted in an interim award directing the appellant to deliver possession of 16 flats to respondent no.2. The appellant challenged this order but the High Court and Supreme Court dismissed the appeals.
In 2017, respondent no.1 and respondent no.2 filed consent terms resulting in a consent decree whereby respondent no.2 agreed to deliver 8 flats to respondent no.1. The learned Single Judge directed the appellant to deliver possession of these 8 flats to respondent no.1, which led to the present appeal.
Legal Issues Presented
- Whether the learned Single Judge erred in granting interim relief directing the appellant to deliver possession of 8 flats to respondent no.1 under the consent decree.
- Whether respondent no.1 is entitled to possession of the flats despite alleged non-performance by respondent no.2 of obligations to construct certain wings under the development agreements.
- Whether the interim order granting possession effectively disposes of the suit and prejudices the appellant's rights if the suit is ultimately decided against respondent no.1.
Arguments of the Parties
Appellant's Arguments
- Respondents 1 and 2 obtained the consent decree to defeat the appellant's claim.
- Initially, the claim was for flats in Wings A, B, and C, but respondent no.1 restricted the claim to Wings A and B which are already constructed.
- Respondent no.1 should not be entitled to possession of flats unless respondent no.2 fulfills the obligation to construct Wing C as per the SRA scheme.
- The learned Single Judge erred in granting final relief by way of an interim order.
- If possession is handed over to respondent no.1, it would be difficult for the appellant to recover flats if the suit is decided against respondent no.1.
- Respondent no.2 failed to perform obligations under the agreement with the appellant.
- The confirmation of the arbitrator's order allotting 16 flats to respondent no.2 does not affect the suit proceedings.
Respondent no.1's Arguments
- The real dispute is between appellant and respondent no.2; respondent no.1's rights are independent and should not suffer due to disputes between the other parties.
- Respondent no.2 did not perform obligations to construct Wing C, but respondent no.1's entitlement to 8 flats is distinct and valid.
- The appellant has utilized and sold his 55% share, while respondent no.1 is entitled to his share of 15,000 sq. ft. area from respondent no.2's 45% share.
- The flats in question are constructed and ready for possession.
- The order of the learned Single Judge is reasonable, equitable, and should not be interfered with.
Respondent no.2's Arguments
- Supports respondent no.1's contentions.
- The plaintiff (respondent no.1) is entitled to 8 flats in Wings A and B as per the consent decree.
- There is no illegality or prejudice in allotting these flats to respondent no.1.
- The appellant has already enjoyed and sold his 55% share.
- The appeal is meritless and should be dismissed.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Progressive Education Society Through Chairman Dr. Gajanan R. Ekbote & anr. v. Shri Laxmikant Mahadev Shekhane & ors. (2017 SCC Online Bom 6593) | General principles on interim relief and contractual obligations. | Considered in evaluating the appellant's challenge to interim relief. |
| The State of Orissa v. Madan Gopal Rungta (AIR 1952 SC 12) | Principles of equity and interim relief. | Referenced for the proposition that courts may mould relief according to changed circumstances. |
| U.P. Junior Doctors' Action Committee & ors. v. Dr. B. Sheetal Nandwani & ors. (1992 Supp (1) SCC 680) | Interim relief and balancing equities. | Used to support the reasonableness of the interim order. |
| Vishnu Babu Tambe v. Apurva Vishnu Tambe ((2017) 2 SCC 454) | Interim relief and contractual rights. | Applied in assessing the entitlement to interim possession. |
| Dorab Cawasji Warden v. Coomi Sorab Warden & Ors. (1990) 2 SCC 117 | Principles of possession and equitable relief. | Relied upon by respondent no.1 to support entitlement to possession. |
| Indian Cable Company Ltd. v. Smt. Sumitra Chakraborty (1985 SCC Online Cal 31) | Equitable relief and contractual interpretation. | Considered in the context of entitlement to property rights under agreements. |
| South Eastern Coalfields Ltd. v. State of MP & Ors. (2003) 8 SCC 648 | Principles of contractual performance and relief. | Referenced in submissions regarding obligations under agreements. |
| Industrial Credit Investment Corp. of India Ltd. & Ors. v. Karnataka Ball Bearing Corpn. Ltd. & ors. (1999) 7 SCC 488 | Interim relief and contractual rights. | Used to support the reasonableness of the order. |
| Deoraj v. State of Maharashtra & Ors. (2004) 4 SCC 697 | Equity and interim possession. | Considered in balancing interests of parties. |
| Om Prakash Gupta v. Ranbir B. Goyal (2002) 2 SCC 256 | Interim relief and contractual obligations. | Applied in the context of interim possession orders. |
| Gaiv Dinshwa Irani & Ors. v. Tehmtan Irani & Ors. (2014 8 SCC 294) | Moulding of relief by courts in changed circumstances. | Relied upon by the learned Single Judge and upheld by this Court for moulding interim relief. |
Court's Reasoning and Analysis
The Court carefully examined the series of agreements and the factual matrix, including the development agreement of 1996, the sub-development agreement of 1999, and the 2003 agreement between respondent no.2 and the appellant. It noted the obligations of BSRC Ltd. to construct the Slum Rehabilitation Component and to provide 15,000 sq. ft. area to respondent no.1 out of its 45% share.
The Court observed that despite disputes between respondent no.1 and respondent no.2, the rights of respondent no.1 to 8 flats and parking spaces are paramount and are not to be prejudiced by disputes between the other parties. The Court relied on the learned Single Judge’s reasoning that respondent no.2 cannot deny respondent no.1’s rights on the ground of any inter se disputes.
The Court found no error or perversity in the learned Single Judge’s order moulding the interim relief to direct possession of 8 flats to respondent no.1. It accepted that the relief was granted in view of the peculiar facts and circumstances, including the readiness of the flats and the equitable considerations involved.
The Court also noted that even if the suit ultimately succeeds against respondent no.1, the appellant has remedies available to recover possession of the flats, thus no irreparable prejudice would be caused.
In sum, the Court upheld the principle that courts may mould interim relief to suit changed circumstances and that the rights of a party entitled under a development agreement cannot be frustrated by disputes between other parties.
Holding and Implications
The Court DISMISSED the Commercial Appeal No. 173 of 2017 and upheld the impugned order directing the appellant to deliver possession of 8 flats to respondent no.1.
The direct effect of this decision is that respondent no.1 is entitled to immediate possession of the specified flats in Wings A and B as per the consent decree and the interim order. The appellant is bound to comply with this direction. No costs were awarded.
No new legal precedent was established; rather, the Court applied settled principles regarding interim relief, contractual rights, and equitable considerations in the context of development agreements and complex multi-party disputes.
1/20 comap173.17.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
COMMERCIAL APPEAL NO. 173 OF 2017
IN
NOTICE OF MOTION NO. 147 OF 2013
IN
COMMERCIAL SUIT NO. 62 OF 2013
Mr. Samir Narain Bhojwani ... Appellant V/s.
1. M/s. Aurora Properties & Investments
2. Bombay Slum Redevelopment Corporation Ltd. ... Respondents
Mr. P.K.Dhakephalkar, Senior Advocate a/w. Mr. Parimal Shroff, Mr. D.V. Deokar,Mr.Dhruvesh Parikh, Mr. Sachin Pandey and Ms. Ankita Roy I/b. M/s. Parimal K. Shroff & co. for appellant.
Mr.Pravin Samdani, Sr. Advocate a/w Mr. Satyen Vora, Ms. Deepti Panda, Mr.Sanmish Gala and Mr. Jigar Shah I/b. M/s. Markand Gandhi & co. for respondent no.1.
Mr. V.K.Ramabhadran, Sr. advocate a/w. Mr Atman Mehta, Mr. Mahendra Ghelani I/b. Law Charter for respondent no.2.
CORAM : NARESH H. PATIL AND
G.S. KULKARNI, JJ.
RESERVED ON : 28th June, 2018.
PRONOUNCED ON : 09th July, 2018.
1
JUDGMENT [ Per Naresh H. Patil, J.] :
This appeal is directed against the impugned order passed by learned Single Judge of this Court in Notice of Motion No.147/2013 dated 9thOctober, 2017. The parties have presented synopsis of relevant dates and events.
2. On 6thOctober, 1996 by development agreement made between Andheri Kamgar Nagar Co-operative Housing Society Ltd. ("Society") of the one part and respondent no.1-M/s. Aurora Properties and Investments of the other part, the said Society appointed respondent no.1 as developer of the property situated at Versova Link Road, Taluka Andheri as described in detail in the plaint. A Lease Deed dated 31stMarch, 1993 was executed in respect of 9402 sq. meters with obligation to construct 243 tenements and 40 tenements for Project Affected Persons free of charge and to develop and dispose of balance F.S.I. as per terms set out in the Development Agreement dated 6thOctober, 1996. On 22ndSeptember, 1999 by an agreement for sub-development made between respondent no.1 and respondent no.2
2
herein-Bombay Slum Redevelopment Corporation Ltd. (hereinafter referred to as "BSRC Ltd." for short), the respondent no.1 with the consent of Society transferred benefits of development rights in respect of said property under the development agreement dated 6th October, 1996 with the said Society with an obligation to construct buildings consisting of 240 tenements and also construct buildings by utilising F.S.I. after deducting 15000 sq. feet area retained by the respondent no.1 as set out in the agreement.
3. By an agreement dated 10thMarch, 2003 respondent no.2 and appellant entered into an agreement for development which was registered in the Sub-Registrar's office. Under the said agreement the respondent no.2 herein confirmed that the appellant herein will be entitled to 55% of the total area available for free sale buildings, car parkings and respondent no.2 will be entitled to 45% of the total area available for construction of free sale buildings, car parking under the SRA scheme. Earlier the agreements were executed between the parties keeping in view SRD scheme but later on under the
3
subsequent agreements the parties converted the scheme under SRA.
4. On 28thDecember, 2005 the respondent no.1 by their Advocate's letter addressed to respondent no.2 terminated the said agreement dated 22ndSeptember, 1999 with the respondent no.2. On 11th September, 2009 respondent no.2 and respondent no.1 by a tripartite agreement executed with the appellant referred the said development agreement dated 6thOctober, 1996 with the said Society and agreement dated 22ndSeptember, 1999.
5. On 9thJanuary, 2012 an Occupation Certificate was obtained by respondent no.2 in respect of Wing A and B of the building "Bay View"
constructed on the said property. By a letter dated 16thJune, 2012 addressed by the appellant to respondent no.2 and duly confirmed by respondent no.2, the 45% area and car parkings in the said Wings "A"
and "B" was identified. The appellant by his letter dated 14thAugust, 2012 offered to hand over respondent no.2 possession of premises in Wing "A" and "B".
4
6. The respondent no.1 in the meanwhile filed a Suit on 21st November, 2012 bearing Suit No.62/2013 ("said Suit") in the High Court at Bombay against respondent no.2 seeking declaration of the agreement for development dated 22ndSeptember, 1999 read with tripartite agreement dated 11thSeptember, 2009 are valid, subsisting and binding upon the parties therein. He claimed specific performance of the said agreement.
7. A Notice of Motion No.147/2013 was taken out on the same day by the respondent no.1 herein in the said Suit. On nomination an Arbitrator was appointed by the appellant on 28thNovember, 2012. By an order dated 3rdDecember, 2012 the learned Single Judge of this Court passed order in Notice of Motion No.147/2013 restraining appellant and respondent no.2 from selling, disposing of, alienating, encumbering, parting with possession and/or creating third party rights in respect of four flats in Wing "A" and 4 flats in Wing "B".
5
8. By an order dated 17thDecember, 2012 the High Court modified its order. By an order dated 30thSeptember, 2014 a Notice of Motion No.540/2013 in Suit No.62/2013, an Arbitration Application No.86/2013 came to be dismissed.
9. On 12thOctober, 2016 the Sole Arbitrator passed an order on an application filed by respondent no.2 under Section 17 of the Arbitration and Conciliation Act, 1996 (for short 'Act of 1996') passing interim award by directing appellant to deliver physical possession of 16 flats together with car parking places.
10. On 15thOctober, 2016 the appellant filed an appeal under Section 37 of the Act of 1996 challenging the order of the Arbitrator. By an order dated 21stNovember, 2016 High Court dismissed the Commercial Arbitration Petition No.118/2016. A SLP filed by the appellant being SLP Nos.7743-7744/2018 challenging the judgment and order came to be dismissed on 16thApril, 2018.
6
11. On 27thSeptember, 2017 respondent no.1 and respondent no.2 filed Consent Terms between them. Based on the said Consent Terms a consent decree came to be passed whereunder respondent no.2 agreed to deliver respondent no.1, 8 flats alongwith car parking places. The Court directed the appellant by impugned judgment and order dated 9thOctober, 2017 to deliver 8 flats to respondent no.1. This appeal arises in these circumstances.
12. Mr.Dhakephalkar, the learned Senior Counsel appearing for the appellant also submits that respondents 1 and 2 obtained consent decree to defeat the claim of the appellant. Earlier they had agreed for four flats each in A, B and C Wing but later on respondent no.1 restricted his claim in A and B Wings which are already constructed. The thrust of the submissions of the learned Counsel is that unless the respondent no.2 carries on his obligation to construct C wing as per SRA scheme, the respondent no.1 shall not be entitled to his part of 15000 sq. feet area or 8 flats as agreed under the consent decree. The submission of the Counsel is that the learned Single Judge
7
committed a serious error in passing interim order by which final relief has been granted in favour of the respondent no.1 which is not permissible in law. In case the possession of 8 flats is handed over to respondent no.1, nothing remains in the suit to be decided finally and in case the suit is decided against the respondent no.1 then it would be very difficult for the appellant to get back the possession of the 8 flats which under the impugned order are directed to be handed over to the respondent no.1. The Counsel has taken us to various clauses of agreements placed on record in support of the submissions that the claim of the plaintiff-respondent no.1 herein cannot be considered and granted under interim order. The respondent no.2 has failed to discharge his obligation under the agreement executed between the appellant and respondent no.2 herein. In the submissions of the Counsel the confirmation of the order passed by the Arbitrator allotting 16 flats to respondent no.2 herein which is confirmed in Apex Court shall not have any adverse effect on the proceedings of the present Suit. Reliance was placed on the order passed by the Apex Court in this regard which we have perused. The entitlement of
8
respondent no.2 to the extent of 45% was subject to fulfilling his obligation to construct 'C' Wing which he has failed to construct for reasons best known to him. The learned Counsel placed reliance on the following judgments:-
i) Progressive Education Society Through Chairman Dr. Gajanan R. Ekbote & anr. V/s Shri Laxmikant Mahadev Shekhane & ors.1
ii) The State of Orissa Vs. Madan Gopal Rungta2
iii) U.P. Junior Doctors' Action Committee & ors. V/s. Dr.B.Sheetal Nandwani & ors.3
iv) Vishnu Babu Tambe Vs. Apurva Vishnu Tambe4
13. The learned Counsel appearing for the plaintiff-respondent no.1 herein Mr.Samdani submits that the real dispute and conflict is between appellant and respondent no.2-original defendants 1 and 2 as according to Counsel it is alleged that the respondent no.2 BSRC Ltd.
1 201 7 SCC Online Bom 6593
2 AIR (39) 1952 Supreme Court 12
3 1992 Supp (1) Supreme Court Cases 680
4 (2017) 2 SCC 4 54
9
did not perform his part of obligation in respect of 45% share as he failed to construct the 'C' wing. The learned Counsel submitted that unnecessary the plaintiff is made to suffer as other 2 parties are litigating. The Counsel submitted that 55% share has already been utilised and sold by the appellant Samir Bhojwani. Under the Arbitration Award the respondent no.2 BSRC got 16 flats which he has already utilised against his share. The plaintiff's share is part of 15,000/- sq. feet area out of part of 45% share of the respondents BSRC. These flats were already constructed and are ready, therefore, considering the peculiar facts and circumstances, the learned Single Judge moulded the relief by directing the appellant to hand over keys of 8 flats to respondent no.1. The Counsel submitted that order passed by the learned Single Judge is reasonable, sound and based on the principles of equity and justice. There is no reason to interfere into the order. The appellants have failed to make out any case for Court's intervention in the impugned order. The learned Counsel too took us through various clauses of the agreement, award passed by the Arbitrator by the Civil Court. The learned Counsel further
10
submitted that under the SRA scheme as agreed between the parties, the respondent no.2- BSRC, the appellant and respondent no.2 had entered into an agreement and in case the respondent no.2-BSRC fail to perform certain obligations as alleged by the appellant herein, the plaintiff need not suffer. The source of power derived by the other two parties is the main lease agreement. The basic agreement was executed between the Society and the plaintiff-respondent no.1 Aurora Properties and Investments. Both the appellant and the respondent no.2 have to a large extent enjoyed and utilised their share of property leaving behind the plaintiff.
14. It is submitted by learned Sr. Counsel Mr.Samdani that respondent no.1 has paid 75 lacs against 15000 sq. feet area. The Counsel placed reliance on these judgments:
i) Dorab Cawasji Warden Vs. Coomi Sorab Warden & Ors.5
ii) Indian Cable Company Ltd. Vs. Smt. Sumitra Chakraborty6
iii) South Eastern Coalfields Ltd. Vs. State of MP & Ors.7
iv) Industrial Credit Investment Corp. of India Ltd. & Ors. Vs.
11
Karnataka Ball Bearing Corprn. Ltd. & ors.8
v) Deoraj Vs. State of Maharashtra & Ors.9
vi) Om Prakash Gupta Vs. Ranbir B. Goyal10
15. The learned Counsel appearing for respondent no.2 BSRC supported the contentions of learned Counsel Mr.Samdani. It is submitted that out of the share of 45% the plaintiff is entitled to his share which is now restricted under the consent decree to 8 flats in 'A' and 'B' wings. There is absolutely no embargo and illegality in allotting 8 flats to the share of the plaintiff even under the order. The Counsel submitted that learned Single Judge passed a reasoned order in the peculiar facts of the case. There is no question of any prejudice being caused to the appellant herein. He had already enjoyed and sold his 55% share. The learned Counsel, therefore, submitted that appeal is merit-less and deserves to be dismissed.
16. We have extensively heard the parties finally by consent. Perused the various clauses of the agreement, award passed by the
12
learned Arbitrator and order passed by the Apex Court. We have carefully gone through the judgment of the learned Single Judge of this Court which is impugned herein. We find that the basic development agreement executed between the Society and the respondent no.1 was executed in 1996. A further agreement was executed for development between respondent no.1 and respondent no.2 in the year 1999 wherein the parties agree that 15000 sq. feet area shall be retained by the respondent no.1. This area has been retained throughout for the benefit of respondent no.1 though parties entered into various subsequent agreements. Even in the agreement for development made on 10thMarch, 2003 between BSRC and Samir Bhojwani agreed in the following terms in clause-6 as under:-
(i) BSRCL shall be liable to construct and complete the Slum Rehabilitation Component at their own costs and house the 237 eligible members as per Annexure-II of the said Society in the said Slum Rehabilitation Component at their own costs without any delay or default.
13
(ii) BSRCL shall be liable to give the 15,000 Sq. Ft. (Built up area) agreed to be provided by BSRCL under the said Agreement for Sub-development to the said Aurora Properties. The said area of 15,000 sqft. (built up area) shall be given to the said Aurora Properties by BSRCL from and out of the 45% share of BSRCL being the BSRCL's area in the said Fee Sale Component Area.
17. In a communication dated 11thSeptember, 2009 issued by the respondent no.1 addressed to appellant and the respondent no.2, it was averred in Paragraph-2 clause (i) and (v) as under:
"(i) As mutually agreed between us and BSRCL, we will be now entitled to 22,500 square feet constructed area instead of 15,000 square feet constructed area as set out in the Agreement for Grant of Sub-Development Rights dated 22ndSeptember, 1999. The said 22,500 square feet constructed area and proportionate car parking areas will be provided out of 45% coming to the share of
BSRCL.
14
(v) We shall otherwise be entitled to all our rights under the Agreement dated 22ndSeptember 1999 in respect of our area from BSRCL."
18. The learned Counsel for the appellant submitted that in the subject Notice of Motion prayer (b) was made for appointment of Receiver including the power to take possession of premises coming to the share of the plaintiff and hand over the same to the plaintiff in the form of 12 flats in Wings "A" and "B" which claim was restricted under the consent decree to 8 flats. Reliance was placed on affidavit filed by Samir N. Bhojwani in Notice of Motion wherein the appellant herein stated in clause (viii) as under:-
"(viii) By letter dated 14thAugust, 2012 and addressed by me to the Defendant No.1 I offered possession of the said 45% area and Car Parking Spaces tot he Defendant No.1 as per the said letter dated 16thJune 2012 and Defendant No.1 has not taken possession of the said areas till today.
15
I have dealt with my 55% area and Car Parking Spaces to the knowledge of the Plaintiffs and Defendant No.1 and third parties are entitled to the same."
19. The learned Single Judge has in detail addressed the issue raised and recorded findings. The suit is filed by the plaintiff to enforce rights under their agreements dated 22nd September, 1999 vis- a-vis defendants no.1 and under the tripartite agreement dated 11th September, 2009 between plaintiff, defendant no.1 and defendant no.2. In Paragraph-33 the learned Single Judge observed as under:-
" The rights of Plaintiff to the 8 flats and 16 car parking spaces finally agreed as between Plaintiff and Defendant No.1 are paramount to the rights of either of Defendants. Rights of Defendant No.2 to the development are derivative rights derived through Defendant No.1 from Plaintiff. Consideration for the grant of such rights by Plaintiff, inter alia, is entitlement of Plaintiff to 8 flats and 16 car parking spaces. Defendant No.2 cannot claim or enjoy any rights or benefits to the development if
16
Defendant No.2 denies consideration to Plaintiff for the grant thereof by Plaintiff. Each of Defendants are contractually obliged to discharge their obligations towards Plaintiffs under the said Development Agreement and the Supplemental Development Agreement and provide to Plaintiff the flats and parking spaces agreed to be provided as and by way of consideration and cannot dispute or deny the same on the pretext of any dispute inter se between themselves with which plaintiff is not concerned in any way. Disputes as between Defendants inter se and the result thereof cannot in any event prejudice the rights or entitlement of plaintiff acquired in lieu of grant of Development Rights enjoyed by Defendant No.2."
Adopting the said reasoning the learned Single Judge declared that the plaintiff was entitled to 8 flats in the said property. The Single Judge observed that it is settled law that relief is otherwise awardable on the date of commencement of the suit would become inappropriate in view of changed circumstances, the Courts may mould the relief
17
accordingly. Reliance is placed on the judgment in the case of Gaiv Dinshwa Irani & Ors. Vs. Tehmtan Irani & Ors. {2014 8 SCC 294}.
20. After perusing the record and considering the submissions in detail, we do not find that the Single Judge committed an error in moulding the reliefs. We even do not notice any perversity in the impugned order passed by the learned Single Judge. A reasonable and balance view has been adopted by the Single Judge in the facts and circumstances of the case. The question raised by the Counsel appearing for the appellant is that what if the plaintiff fails in the Suit.
21. We have perused the judgments cited supra by the learned Counsel for the parties.
22. The learned Counsel Shri Samdani while replying the same has referred to judgments cited supra and provisions of Section 144 of CPC. But in our view considering the agreements executed between
18
the parties even at the interim stage such a relief could be moulded and granted in favour of the plaintiff.
23. The learned Counsel appearing for the respondent no.1 has placed on record a chart showing distribution of flats in A and B wing which is reproduced as under:
WING TOTAL 55% share 45% share of SAMIR of BSRCL
A 44 24.4 20
B 44 24.4 19.6
88 48.4 39.6
(Constructed and O.C.
received) Less: 8 =15,000 sq.ft.area
retained by Aurora.
Less: 31.6 Balance flats available
16 Flats released as per Section 17 order to BSRCL NET 15.6 Flats Balance
24. Even after distribution of 8 flats in favour of respondent no.1
19
15.6 balance flats would remain. In case the plaintiff fails in the suit, we do not find that appellant would be remedy-less. His remedies are kept open.
25. The Commercial Appeal stands dismissed. No order as to costs.
(G.S. KULKARNI, J) (NARESH H. PATIL, J.)
26. After pronouncement of the judgment, the learned Senior Counsel appearing for the appellant prays for stay of the order for a period of 8 weeks. The learned Senior Counsel appearing for respondents opposed the prayer.
27. In the facts of the case, prayer for stay of the order stands rejected.
(G.S. KULKARNI, J) (NARESH H. PATIL, J.)
L.S. Panjwani, P.S.
20
Alert