Abdul Qayoom Sheikh v. Union of India and others
Honble Mr. Justice Sanjeev Kumar, Judge Appearing Counsel: For Petitioner(s)/Appellant(s): Mr. M. M. Iqbal, Adv. For Respondent(s): Mr. T. M. Shamsi, ASGI for 1 Mr. Irshad Ahmad, Adv. vice Mr. G. N. Monga, Adv. for 2 and 3.
1. The petitioner in this petition has prayed for the following relief: issue a Writ of Mandamus commanding the respondents to make good the payment to the tune of Rs. 10,60,000/- as was due to the petitioner till 31.12.2007 from the Respondents without any further more delay and also make further payment @Rs. 3,000/- per day till the floating boats provided by the petitioner are retained by the respondents in their possession and use.
2. The short grievance projected by the petitioner is that he being a Contractor was invited by the respondents to provide and launch suitable floating platform at Dam axis of Rattle HE project with all arrangement to hold good to fix the drilling machine for core drilling at Kishtwar.
3. The work aforesaid was allotted to the petitioner pursuant to the negotiation between the parties in which it was agreed that the petitioner will be entitled to the payment for the execution of the aforesaid work on the estimated rates and terms and conditions agreed by the petitioner. It is submitted that in pursuant to the aforesaid agreement, the petitioner executed the aforesaid work and therefore, became entitled to the payment to the tune of Rs. 10,60,000/-. It appears that there was some dispute with OWP No. 208/2008 Page 2 of 3 regard to the rates on which payment of the petitioner was to be worked out. In that view of the matter, the genuine payment which was otherwise payable to the petitioner was also not released by the respondents.
4. The petitioner approached this Court through the medium of instant writ petition and this Court while taking into consideration the pleadings and the reply affidavit filed by the respondents, directed the respondents to release a sum of Rs. 1,58,116/- being admitted amount vide order dated 22nd September, 2007. It is submitted that in compliance to the aforesaid direction, the payment which the respondents had admitted to be payable to the petitioner for Rs, 1,58,116/- has been released in favour of the petitioner. Rest of the amount, however, is disputed by the respondents.
5. In view of the fact that the admitted amount has since been paid to the petitioner, this petition has been rendered infructuous. However, claim of the petitioner for some more amount which he claims is still payable is based on disputed question of facts and cannot be gone into these writ proceedings.
6. This petition is disposed of by providing that the petitioner, if still aggrieved of non-payment or short payment, shall be at liberty to work out his remedy including filing of civil suit to establish his claim.
7. In case, petitioner choses to file civil suit, the period spent by the petitioner in this Court in prosecuting this petition shall be eschewed for the purpose of limitation.
8. Disposed of alongwith connected MP(s). (Sanjeev Kumar) Judge Srinagar 03.05.2018 OWP No. 208/2008 Page 3 of 3 Imtiyaz