Nicholas H. Almeida v. Lenzing Modi Fibres India Pvt. Ltd. & Ors.
We have heard Learned Counsel for the parties. Mr. Ratnaparkhi, K.D Learned Counsel for the Respondent Nos. 2 and 4, submits that he has sent draft affidavit to the office of Respondent No. 2, on 10 October, 2013, for approval and further action. He further submits that he has not received any response from the Respondent No. 2. He has shown us, the copy of draft affidavit, as well as the copy of communication dated 3rd October, 2013, issued by Mr. V.P Upadhyay, the Director of MoEF (IA Division). It appears that the communication is addressed to Shri. Lakhwinder Singh, Additional Principal Chief Conservator of Forests (Central), Bhopal, with a request to approve the affidavit and inform to the MoEF regarding progress of the matter. It is difficult to understand as to why the Director addressed the communication to the Additional Principal Chief Conservator of Forests (Central), Bhopal, for approval of the affidavit, of the fact that it was sent to him by the Counsel, and the remarks were later on received. In fact, the MoEF, is a party to the Application being Respondent No. 2. The MoEF has granted Environment Clearance (EC), subject to the condition that necessary permission shall be obtained from the National Board for Wild Life (NBWL). The EC also indicates that it is subject to CRZ clearance.
Considering the nature of conditions put while granting the EC, it is essential to determine as to whether the EC can be granted, without prior satisfaction of the conditions, which are required to be obtained and same can be granted subject to the conditions, which should be obtained later on. For, there are internal instructions of the MoEF, in this behalf. The Counsel for Respondent No. 2, shall take instructions and place on record OM, pertaining to internal instructions, as regards the procedure for grant of EC and particularly, in respect of necessity to obtain the permission/necessary clearances before grant of EC by the MoEF, or whether it is permissible to allow the Project Proponent to get the permissions/clearances needed after grant of EC by the MoEF.
Item No. 13 October, 24, 2013 Order No. 15
We had called for the relevant information and the file/record from the Respondent No. 2, by deputing any authorised officer. We desired to verify the material, which was considered while granting the EC, in favour of the Respondent No. 1 (Project Proponent). It is unfortunate that the Respondent No. 2, has not taken care to depute any responsible officer, nor has taken care to file any reply affidavit and particularly inspite of communication of the order by the Counsel. We had made it clear by order dated 7 October, 2013, that in case of failure to comply with such directions, we will be constrained to take coercive steps. In view of this peculiar situation, we have no option but to issue Bailable Warrant for Rs. 20,000/- to the satisfaction of the arresting Officer, in exercise of our powers and in terms of the provision of Section 19(4)(a) of the National Green Tribunal Act, 2010 read with Order XVI Rule 10(3) and Section 151 of the Code of Civil Procedure, 1908, against Mr. V.P Upadhyay, the Director of MoEF, or if he is transferred, then his successor or the person incharge, to appear on next date.
We have received Inspection Report from the Committee. The Learned Counsel for the Project Proponent, submits that he desires to go through the report and may file his response. The other Counsels also require to go through the Report of Inspection. If any of the party requires copy of the Report, the same may be sought from the Collectorate, Raigadh (Alibagh), by making Application for certified copy and copy may be provided on payment of required costs. The Parties will have liberty to file their responses to the Report prior to next date. We, however, make it clear that the party shall make no personal comments against any Member of the Committee and shall avoid any disparaging remarks, in as much as the Members of the Committee were appointed by this Tribunal, to exercise the public function. So also, the parties shall not make any comments on the merits of the matter outside the Tribunal, so as to avoid any kind of adverse publicity against each other.
We also make it clear that if above directions are violated, then defaulter party will be liable to face penal consequences of any nature as this Tribunal may deem it proper.
Item No. 13 October, 24, 2013 Order No. 15
The Learned Counsel appearing for the Applicant submits that he has already made representation to the NBWL, but so far no hearing has Item No. 13 been given to him. The Counsel for the Respondent No. 1, makes statement that the Application for grant of permission is yet pending before the NBWL. The NBWL, is requested to expedite hearing of such Application, in order to get things more clarified and for such purpose the Counsel for the Applicant shall also provide a certified copy of the Inspection Report to the NBWL. The NBWL, shall hear both the parties including the Project Proponent. We direct the Collector of Raigadh (Alibagh), to expeditiously issue certified copies of the Inspection Report, within a period of three (3) days after the payment of costs is received by the office of the Collectorate by giving preference, even if other Applications are pending.
Stand over to 12th November, 2013.