M/S ESSAR PROJECTS LTD v. STATE OF RAJ & ORS

Rajasthan High Court
Jul 19, 2017
Smart Summary (Beta)

Factual and Procedural Background

The appellant challenged a judgment and order of the learned Single Judge who declined to interfere with the order in a writ petition filed by the petitioner. The petitioner-appellant sought quashing of impugned orders dated 30.5.2005 and 31.5.2005, which imposed 10% liquidated damages, threatened to take over petitioner’s materials, blacklisting, and issued a fresh notice inviting tender (NIT), along with wrongful deductions and recovery of liquidated damages amounting to Rs. 111.74 lacs. The appellant also sought a declaration that the respondents breached the contract, prevented the petitioner from completing the work, and requested that only the petitioner be allowed to complete the work without re-tendering or other punitive actions.

The Public Health & Engineering Department had issued a tender on 14.12.2001 for execution of a water supply project on a single responsibility turnkey basis. The petitioner submitted a successful bid and was awarded the contract on 15.11.2002, with the execution period of 30 months (ending 25.5.2005) and an operation and maintenance period of 60 months. The petitioner commenced work on 24.11.2002 and executed an agreement on 17.1.2003. The contract encompassed design, survey, implementation, testing, and operation and maintenance of various components of the project.

Legal Issues Presented

  1. Whether the imposition of 10% liquidated damages by the respondents pursuant to the contract was valid and lawful.
  2. Whether the respondents’ actions of threatening to take over materials, blacklisting, and re-tendering were justified or constituted breach of contract.
  3. Whether the petitioner was entitled to complete the awarded work exclusively without re-tendering or awarding the balance work to others.

Arguments of the Parties

Appellant's Arguments

  • The imposition of 10% liquidated damages was illegal and unlawful.
  • The respondents’ actions including blacklisting, taking over materials, and issuing fresh NIT were arbitrary, unfair, unreasonable, unlawful, and unconstitutional.
  • The petitioner was willing and able to complete the work, and the respondents should accept the petitioner’s conditions for extension and allow the petitioner to complete the work without re-tendering.
  • The government cannot act as judge in its own case and impose liquidated damages without proper adjudication.
  • Relied on Supreme Court decisions, including State of Karnataka vs. Shree Rameshwara Rice Mills and Gangotri Enterprises Limited vs. Union of India, to argue that damages cannot be recovered as arrears of land revenue without judicial determination.

Respondents' Arguments

  • The learned Single Judge’s detailed reasoning justified the imposition of liquidated damages and the actions taken as the petitioner failed to fulfill contractual conditions.
  • No relief was warranted for the petitioner given the failure to complete the work within the stipulated period and contractual breaches.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
State of Karnataka vs. Shree Rameshwara Rice Mills, (1987) 2 SCC 160 Damages for breach of contract cannot be recovered as arrears of land revenue unless provided under contract and judicially determined. Held that government cannot unilaterally impose liquidated damages as arrears of land revenue without judicial adjudication; supports quashing of 10% forfeiture.
Gangotri Enterprises Limited vs. Union of India & Ors, (2016) 11 SCC 720 Damages arise only after judicial determination; no pecuniary liability exists before court’s assessment. Reinforced that purchaser cannot appropriate sums due to contractor to satisfy claims for damages; supports appellant’s contention that government cannot act as judge in its own case.
Iron and Hardware (India) Co. v. Firm Shamlal and Bros., AIR 1954 Bom. 423 Damages are compensation awarded by court, not an existing pecuniary liability. Used to explain legal position on damages and liability, supporting appellant’s argument.
Jabed Sheikh v. Taher Mallik, AIR 1941 Cal 639 Consistent judicial view on damages and contract breach. Referenced to support legal principles on damages and breach of contract.
S. Milkha Singh v. N.K. Gopala Krishna Mudaliar, AIR 1956 Punj 174 Consistent judicial view on damages and contract breach. Referenced to support legal principles on damages and breach of contract.

Court's Reasoning and Analysis

The court examined the contractual terms, the timeline of the project, and the conduct of the parties. It noted that the petitioner failed to complete the work within the original and extended timelines despite notices to improve progress. The respondents imposed 10% liquidated damages under the General Conditions of Contract and initiated steps to complete the remaining work through alternative means, including re-tendering.

The court analyzed the binding Supreme Court precedents which held that damages for breach of contract do not constitute a presently due pecuniary liability until judicially determined, and that the government cannot act as judge in its own case to impose liquidated damages as arrears of land revenue. Based on these principles, the court found the imposition of 10% liquidated damages by the respondents to be invalid and quashed the same.

The court also observed that many of the appellant’s other prayers had become academic given the scale and cost of the project. It left open the possibility for the parties to initiate appropriate proceedings in accordance with law for other reliefs.

Holding and Implications

The appeal is allowed to the extent of quashing and setting aside the imposition of 10% liquidated damages by the respondents. The court held that the government could not unilaterally impose such forfeiture without judicial determination in accordance with established legal principles.

The direct effect of this decision is that the petitioner is relieved from the 10% liquidated damages imposed by the respondents. No new precedent was set beyond affirming the application of existing Supreme Court rulings on the invalidity of unilateral imposition of damages as arrears of land revenue. Both parties are at liberty to initiate further appropriate proceedings for other reliefs in accordance with law.

Show all summary ...

HON'BLE MR. JUSTICE INDERJEET SINGH Order 19/07/2017

1. By way of this appeal, the appellant has assailed the judgment and order of the learned Single Judge whereby the learned Single Judge has declined to interfere in the order in writ (2 of 9) [SAW-143/2006] petition filed by the petitioner.

2. The prayer which are claimed by the petitioner-appellant reads as under:-

i) By a writ of certiorari of any other appropriate writ, order or direction the impugned orders/letters dated 30.5.2005 (Annexure-P9) imposing 10% liquidated damages, threatening to take over the material of the petitioners and getting the work done from outside agency and blacklisting etc. and letter dated 31.5.2005 (Annexure-P11) and the fresh NIT (Annexures- P13) and wrongful deductions and recovery of LD in the interregnum of Rs. 111.74 lacs may kindly be quashed and set aside and the petitioners company should be allow all the consequential benefits arising of it: ii) By a writ of Mandamus or any other appropriate writ order or direction declare that the respondents by their conduct have committed breach of the contract and thereby prevented, precluded or made it impossible for the petitioners to complete the awarded work and that the conditions put forth by the petitioners for accepting the extension are reasonable and command the respondents to accept the said conditions and to allow only the petitioners to complete the work awarded and not to re-tender for completing the balance work and/or award the same to anyone else and further declare that under the circumstances the respondents are not entitled to impose any liquidated damages and take any other action like of re-tendering, blacklisting, taking over the material of petitioners etc and that such actions of the respondents shall and will be irrational, unfair, unreasonable, unlawful, arbitrary and unconstitutional and against public interest.

3. Counsel for the appellant has argued that when this matter was earlier listed on 12th January, 2017, following order was passed:-

This court while observed in page No.105 which reads as under:- The petitioner now shown his willingness to complete the work but it is for the respondent to (3 of 9) [SAW-143/2006] consider the proposal of the petitioner and this court do not want to issue any writ order or direction to this effect. I am not convinced with the submission made on behalf of the petitioner and even the alternative efficacious remedy is available to the petitioner and as the writ involves several disputed facts and questions, this court refrain to entertain such writ petition arising out of the contractual obligations in view of the ratio decided by Honble the Supreme Court in the cases; a) 1994 (6) SCC 651; b) 1991 (1) SCC 492; c) 2000 (2) SCC 617;

d) 2000 (8) SCC 806; e) 1979 (3) SCC 489; f) 1981 (1) SCC 586; g) SBCWP No.3657/05 Nagarjun Construction Company Vs. State decided on 11.7.2005. As discussed and observed here in above, the order dated 30.5.2005 and 31.05.2005 (fresh NIT) requires no interference whatsoever is required by this court. Consequently, the writ petition fails and is hereby dismissed being devoid of merit and the respondents are at liberty to proceed with the fresh NIT. However, it is for the respondents to negotiate with the petitioner if the proposals of the petitioner to complete the remaining work is found to the satisfaction of the respondents. However, counsel for the appellant after arguing at some length, he requests for time to enable to go through the matter.

4. Today also adjournment was sought by counsel for the appellant which is refused.

5. The facts of the case are that the Public Health & Engineering Department issued a tender on 14.12.2001 inviting bids for Execution of transmission part of Chambal-Dholpur- Bharatpur Water Supply Project on Single Responsibility Basis

i.e. Design (Selected Part) Build, Operation and Maintenance. The petitioner company submitted its bids and was found to be successful bidder and vide letter dated 15.11.2002, the respondent no. 1 accepted bid of the petitioner company and (4 of 9) [SAW-143/2006] awarded the work to the petitioner company. As per acceptance letter and work order, the time of completion of the project was to reckon from 10th day of the issuance thereof i.e. 24.11.2002 and the execution period was 30 months i.e. up to 25.5.2005 and operation and maintenance period was 60 months. The petitioner no. 1 commenced the work with effect from 24.11.2002 and started mobilization, survey, engineering etc. Then the work order dated 5.12.2002 was issued by the respondent no. 3 in favour of the petitioner and agreement was also executed on 17.1.2003 between the petitioner and respondent no. 3. The petitioner submitted that the work was a single responsibility turnkey job and the contractor/supplier is responsible for entire survey, soil survey, site reconnaissance, design, drawing, implementation, testing and commencing operation and maintenance of the work which envisaged the intake well and approach bridge, intake pumping station, raw water pipeline, raw water reservoir at intermediate pumping station, draw water (Raw) of take point, raw water reservoir and raw water pumping station at Mallah treatment plant all components of power sub station of protection equipment, devices, alarms, meters, material plans, equipment or components thereof and all structures from intake well to Mallah terminal points rates etc. and include any addition modification alterations, replacement, repair as may be made thereto from time to time during operation and maintenance period. (5 of 9) [SAW-143/2006]

6. The main contention of Mr. Mehta is that order of imposition 10% liquidated forfeiture is illegal. The order reads as under:-

1. That the dates of commencement and completion of the above work is 24.11.2002 and the extended date of completion 28.2.2007.

2. That despite of the notices issued to you vide this office notice No. 1337 Dt. 30.04.2005 and NO. 1722 dt. 10.05.2005 for improving the progress & restarting the work as per clause 2 of contract agreement but you have failed to make any improvement in the progress & restarting of the work to complete the work within agreement period. Therefore, I hereby impose full compensation @ 10% on the total cost of the contract as on stipulated date of completion under clause 2 of the GCC of the agreement.

3. In exercise to the powers given in clause 3 of the General Conditions of Contract, I hereby order that the remaining work would be completed by adopting the course as mentioned in clause 3 (c). 6.1 He has also relied upon the decision of the Supreme Court in the case of State of Karnataka vs. Shree Rameshwara Rice Mills, Thirthahalli reported in (1987) 2 SCC 160 wherein it has been held as under:-

9. The further question requiring consideration is regarding the power of the State to recover damages as arrears of land revenue under the Revenue Recovery Act. The Full Bench has taken the view that the State is not entitled to recover damages as arrears of land revenue because damages for breach of conditions will not amount to "money due under the contract". The Full Bench has relied upon a decision of this Court in Divisional Forest Officer v. Mool Chand: [1971]3SCR298 in support of its view. This decision cannot be an authority for the view taken by the Full Bench because it has been rendered with reference to facts which are entirely different. What fell for consideration in that case was whether a tender amount could be recovered from a defaulting forest contractor as arrears of land revenue when Section 75 of the Forest Regulation and Rule 10 of the Rules made thereunder did not provide for such realisation. We are, however, concerned with cases where the agreement entered into between the (6 of 9) [SAW-143/2006] Government and the private persons specifically provides for recovery of damages as arrears of land revenue. What the Full Bench has failed to notice is that even though the damages become payable on account of breach of conditions of the contract, the liability to pay damages does not fall outside the terms of the contract but within the terms of the contract. The words "any amount that may become due or payable by the first party to the second party under any part of this agreement" have to be read in conjunction with the earlier portion of the clause stipulating liability on the party contracting with the State to pay damages for breach of conditions. Therefore, it follows that though damages become payable on account of breach of conditions of the agreement they nevertheless constitute amounts payable under the contract i.e. under one of the terms of the contract imposing liability to pay damages for breach of conditions. To illustrate the position if the agreement provides for a liquidated sum being paid as damages for breach of conditions instead of a sum to be assessed by the Deputy Commissioner, it cannot be said that the specified damages will not be money due under the contract and hence the damages cannot be recovered under the Revenue Recovery Act. What applies to specified damages will likewise apply to damages which are quantified after assessment. We, therefore, hold that the opinion of the Full Bench in so far as the recovery of damages and arrears of land revenue is concerned is not in accordance with law.

10. As it is not disputed that in all the three cases the Officers acting on behalf of the State have not only assessed the damages but have also acted as arbiters in the dispute regarding the alleged breach of contract, the High Court was justified in dismissing the Second Appeal preferred by the State in R.S.A. No. 311 of 1969 and in allowing the writ petitions filed by the two contractors. All the appeals, therefore, have to fail and will accordingly stand dismissed. The parties will pay and bear their respective costs. 6.2 He has also relied upon the decision in the case of Gangotri Enterprises Limited vs. Union of India & Ors. reported in (2016)

11 SCC 720 wherein it has been held as under:-

37. Their Lordships approved the view taken by Chagla C.J. in the case of Iron and Hardware (India) Co. v. Firm Shamlal and Bros.: AIR 1954 Bom. 423 by observing in para 11 as under. (7 of 9) [SAW-143/2006]

11. ..........................................................The same view has also been taken consistently by different High Courts in India. We may mention only a few of the decisions, namely, Jabed Sheikh v. Taher Mallik: AIR 1941 Cal 639 S. Milkha Singh v. N.K. Gopala Krishna Mudaliar: AIR 1956 Punj 174 and Iron and Hardware (India) Co. v. Firm Shamlal and Bros: AIR 1954 Bom 423. Chagla, C.J. in the last mentioned case, stated the law in these terms: (at pp. 425-26) In my opinion it would not be true to say that a person who commits a breach of the contract incurs any pecuniary liability, nor would it be true to say that the other party to the contract who complains of the breach has any amount due to him from the other party. As already stated, the only right which he has is the right to go to a Court of law and recover damages. Now, damages are the compensation which a Court of law gives to a party for the injury which he has sustained. But, and this is most important to note, he does not get damages or compensation by reason of any existing obligation on the part of the person who has committed the breach. He gets compensation as a result of the fiat of the Court. Therefore, no pecuniary liability arises till the Court has determined that the party complaining of the breach is entitled to damages. Therefore, when damages are assessed, it would not be true to say that what the Court is doing is ascertaining a pecuniary liability which already existed. The Court in the first place must decide that the Defendant is liable and then it proceeds to assess what that liability is. But till that determination there is no liability at all upon the Defendant. This statement in our view represents the correct legal position and has our full concurrence. A claim for damages for breach of contract is, therefore, not a claim for a sum presently due and payable and the purchaser is not entitled, in exercise of the right conferred upon it under Clause 18, to recover the amount of such claim by appropriating other sums due to the contractor. On this view, it is not necessary for us to consider the other contention raised on behalf of the Respondent, namely, that on a proper construction of Clause 18, the purchaser is entitled to exercise the right conferred under that Clause only where the claim for payment of a sum of money is either admitted by the contractor, or in case of dispute, adjudicated upon by a court or other adjudicatory authority. We must, therefore, hold that the Appellant had no right or authority under Clause 18 to appropriate the amounts of other pending bills of the Respondent in or towards satisfaction of its claim for damages against the Respondent and the learned Judge was justified in issuing an interim injunction restraining the Appellant from doing (8 of 9) [SAW-143/2006]

12. We accordingly dismiss the appeals. The Appellant in each appeal will pay the costs of the Respondent all throughout.

6.3 He contended that in view of the aforesaid decisions government cannot be judge in their own case.

7. However Mr. Saxena, AAG has taken us to the order of learned Single Judge and contended that in view of the observations made by the learned Single Judge and detail reasoning where the petitioner-appellant failed to fulfill the condition of contract, the action of the respondents is justified and no relief is required to be granted.

8. We have heard counsel for both the sides. 8.1 Out of the prayers which are claimed by the petitioner- appellant, majority of them have now become academic in view of the fact that for the complete project, original cost was Rs. 137.00 crores. In view of the principle laid down by the Supreme Court and the High Court in exercise of jurisdiction under Article

226 where question was to be considered whether the imposition by State Government of 10% forfeiture pursuant to the agreement between the parties is valid or not. 8.2 In our considered opinion, in view of the observations made by the Supreme Court in case of State of Karnataka (supra), the government could not impose the 10% forfeiture of the total cost of compensation. Therefore, imposition of 10% forfeiture is quashed and set aside. (9 of 9) [SAW-143/2006]

9. The appeal is allowed to the aforesaid extent. It will be open for both the sides to initiate appropriate proceedings for other relief in accordance with law. (INDERJEET SINGH)J. (K.S.JHAVERI)J. A.Sharma/91